Professional Documents
Culture Documents
Successfully Allocating Risk and Negotiating A PPP Contract
Successfully Allocating Risk and Negotiating A PPP Contract
Successfully Allocating Risk and Negotiating A PPP Contract
Consider, for example, the $2.2 • provide the private sector only received when the public
billion Pacific Highway Upgrading with an opportunity to develop services commence following
Program, which has been in innovative solutions which construction completion and
place since 1996, on the Central satisfy the RTA’s output focused continued payment depends upon
and Northern coasts of New requirements for each project. performance against specified
South Wales. These upgrades are performance criteria. Placing
Furthermore, all of the above
being delivered using a Design, the capital cost of the project
value for money drivers are being
Construct and Maintain (DCM) at risk clearly provides a very
achieved without the utilisation of
delivery model.1 The NSW Roads strong incentive for the private
private sector finance.
and Traffic Authority (RTA) enters sector to identify, allocate and
into a single contract with the There is also no reason why manage those risks which are
private sector for the design, a DCM or Design, Construct, allocated to it, and to achieve
construction and, for a 10 year Maintain and Operate (DCMO) the optimal balance between
period, maintenance of the delivery model cannot be applied design and construction costs
upgrade. This delivery model has to many other forms of public on the one hand, and operation
enabled the RTA to: infrastructure in order to facilitate and maintenance costs on the
value for money outcomes other. Indeed, one of the desirable
• transfer most risks associated through whole–of–life costing, features of the private sector
with the design, construction and risk transfer, innovation and, in financing of a project is the
maintenance of the upgrades to appropriate cases, third party due diligence work which the
the private sector, being risks asset utilisation. financiers and equity investors
which the private sector is able carry out on the project. However,
to manage at lower cost than the Of course, a key difference
between a DCM/O and a PFP it is suggested that the same
RTA, thereby reducing the overall incentives can be created, albeit
cost of the projects to the RTA; is that with a DCM/O it is only
the contractor’s operation with less money at risk,2 under
• provide the commercial and/or maintenance fee which a DCM/O model, particularly
motivation (via a lump sum is effectively at risk during the if some of the payments for
maintenance fee) required to operational phase of the project. construction work are ‘back
encourage the private sector to With a PFP, the private sector’s ended’ and made contingent upon
adopt a whole–of–life approach investment in the capital cost of the operational performance of
to the design, construction and the project is also ‘at risk’ during the facility. Also, these outcomes
maintenance of each project; and the operation phase of the project can be achieved under a DCM
since payments are typically without some of the other
Project Contract
Debt Financiers Debt Financing Documents PPP Company Equity Documents Equity Investors
It shows the main players in the Compare, for example, the construction of the project to
transaction, amongst whom the interests of government, the the D&C contractor and which
project risks will be allocated. concessionaire and the equity requires the D&C contractor to
They are: investors on the one hand, and pay sufficient liquidated damages
the financiers on the other hand. to enable PPP Company to meet
• the government agency; its debt service obligations in
Each of government, the
• the PPP company, and as the event construction is not
concessionaire and the equity
a consequence, the equity completed on time.
investors are interested in
investors; delivering the project at the Similarly, whilst the interests
• the debt financiers (or the lowest overall cost and thereby of the D&C contractor, PPP
bondholders and the credit achieving the best value for company and the equity investors
wrapper if the finance is raised money outcome. Accordingly, it is might generally be aligned when
from the capital markets); generally in the interests of these it comes time to negotiating the
parties to allocate risk in the most terms of the project contract with
• the D&C contractor, which will efficient manner possible, which government, the same cannot
typically be a joint venture of two will generally be to the party be said when it comes time to
or more contractors on the larger which is able to manage the risk negotiate the terms of the D&C
PPPs, and their parent company for the least cost. contract (although as mentioned
guarantors; and above, the financier will also have
The debt financier, on the other
• the FM contractor and its parent a significant influence over the
hand, is predominantly interested
company guarantor. terms of that document).
in ensuring that its loan will be
In addition, there will be: repaid, and that the risk of default Accordingly, the answer to
under the financing documents what constitutes the successful
• insurers to whom the
is minimised. It is not particularly allocation of risk in a privately
concessionaire and its contractors
interested in its borrower (PPP financed PPP will depend on who
will transfer certain risks; and
company), taking on more risk you ask. That said, it is in the
• subcontractors, to whom in the pursuit of better value for interests of all parties to devise a
the D&C contractor and FM money outcomes (and thereby a risk allocation which:
contractor will transfer certain lower cost to government and/or • is consistent with market
risks and obligations. a higher return to the equity expectations, and thereby enable
So, the question of how to investors), if this will increase the the transaction to proceed
successfully allocate risk in a PPP risk of PPP company falling into to financial close swiftly and
transaction really applies at many default on its loan repayments. minimises tender and deal
levels, and the outcomes which It is for this reason that we do closure costs;
the different parties are seeking not see, on privately financed
projects, the PPP company • will survive the risk ‘bumps’
to achieve are in many respects
entering into an alliance contract which will inevitably occur during
fundamentally different, such that
with the D&C contractor. Rather, the life of the project; and
what constitutes a successful
allocation of risk for one would the financier will require that PPP • has within it sufficient flexibility
not necessarily be considered a company enter into a lump sum to enable the parties to deal with
successful outcome by the others. D&C contract which allocates external changes and events
most risks associated with the the effects of which cannot be
22 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #113 MARCH/APRIL 2007
predicted with certainty at the few months afterwards and even tables which you can find in the
time the deal is signed (such as the LCT which achieved financial PPP policy documents published
possible changes to the public’s close less than 12 months after by other governments.
service expectations over the life the M7. This resulted in subtle One of the dangers, however,
of the project). differences in the risk allocation in using a ‘checklist’ method to
which the RTA put to the market
In this regard, the ‘centre piece’ risk allocation is that it may lead
in its tender documents for each
of any privately financed PPP, in to a ‘blinkered’ approach to the
project. A good example here is
terms of risk allocation, is the identification of risks. As stated
the additional provisions which
project contract between the above, each project has its own
were included in the M7 Project
government agency and PPP unique set of risks and market
Deed for the future connection
company. The main architect of conditions that must be dealt
of new roads to the M7, and the
this document is, of course, the with. As such, the formulation
possible future provision of public
government agency. Accordingly, of a risk framework must take
transport services (such as light
the balance of this paper will into consideration the unique
rail or dedicated bus lanes) in
generally consider the issue characteristics and risks of
the median between the M7
of how to successfully allocate the project. Thus, although
carriageways; and
risk and negotiate a project precedents and the risk allocation
contract from the perspective of • the public’s desire for tables are useful in drawing
government. continuous improvement. on previous experiences, they
should only be used as a starting
4. DEVELOPING A RISK The benefits of following market
point when developing a risk
FRAMEWORK FOR THE precedents in terms of reducing
framework for the project.
tender and negotiation costs
PROJECT can also be seen on the North Further, for some projects, there
4.1 Risk framework South Bypass Tunnel deal in will not be a close precedent
precedents Brisbane. The speed with which which government can draw
Whilst every project is different, the Brisbane City Council is likely on when developing a risk
there is nothing like market to close the NSBT deal—just framework. A good example here
precedents as a starting point 14.5 months after calling for is the RailCorp Rolling Stock PPP.
for the development of a risk expressions of interest—is a direct On this deal, many of the risks are
framework which will meet the reflection of its decision not to unique and it has been necessary
objectives mentioned above. For ‘reinvent’ the risk allocation and to go back to first principles to
example, there is now a well commercial terms for a privately identify all relevant risks and
established ‘core’ risk allocation financed tollroad deal, but instead devise a risk allocation which will
for privately financed tollroad largely adopt the form of tender achieve all of the key objectives
projects in Australia. That said, and contractual documentation mentioned above and also deliver
with each successive tollroad most recently used by the RTA the best value for money outcome
project the risk allocation has whilst at the same time picking for NSW taxpayers. This has
‘evolved’ around the edges having up some of the latest thinking involved a variety of techniques
regard to: from the EastLink transaction as to ensure all relevant risks are
well as some fresh thinking to identified (such as brainstorming
• lessons learned from previous deal with project specific issues workshops, reviews of previous
projects—both tollroads and (such as the future Airport link) projects, interviews with internal
non–tollroads, in Australia and and lessons learned on the recent and external stakeholders, site
overseas; NSW tollroads. visits and the use of generic risk
• changes in general market matrices and previous rail sector
Similarly, if you are looking at
conditions and the level of and rolling stock procurement
a hospital project, or a school,
competition and market appetite contracts as checklists). A risk
prison or stadium project, then
for these projects; matrix was then developed which
there are plenty of good market
has informed the development
• the unique characteristics precedents which you can draw
of the project contract as
of each project—for example on to develop a risk framework
well as various internal risk
with the Cross City Tunnel had for your project. Indeed, it is these
management plans to assist
some characteristics which precedents which have informed
RailCorp to manage those risks
were quite different to those the Partnerships Victoria
which it will bear. Bidders have
associated with the M7 which Standard Commercial Principles
also been required to prepare
achieved financial close just a and the ‘generic’ risk allocation
risk management plans which
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #113 MARCH/APRIL 2007 23
demonstrate how they will that is not best able to manage the principles of efficient risk
manage risks allocated to the risk in order to assist the allocation. The reality is that
them and which are capable of party responsible for managing sometimes risks will be allocated
interfacing with RailCorp’s risk the risk. There are often many to the party least able to refuse
management plans. ways in which such risk can be the risk rather than the party best
sliced, diced and allocated and able to manage the risk. This is
4.2 Efficient risk hence considerable scope for of course heightened at the time
allocation—principles vs debate and brinkmanship. the government is maintaining
practices maximum competitive tension, i.e.
Difficult Risks
The risk allocation principles just before the announcement of
Similarly, for some risks (such as
of the various PPP policies are preferred proponent (see section
uninsurable force majeure events)
easy to state but more difficult 5.2 below).
neither party is particularly well
to implement. The objective of
placed to manage the risk. In a 4.3 How can the challenge
the policies is efficient/optimal
2001 survey conducted by the of risk allocation be better
risk allocation, that is that risks
Chamber of Commerce and
should be allocated to the party managed?
Industry of Western Australia
that is best able to manage the Measures which government and
and the Institution of Engineers
risk at the least cost. other PPP participants can take
Australia on risk allocation
to better manage the challenge
Whilst the principle of efficient in major West Australian
of risk allocation include the
risk allocation appears to construction projects, 35% of
following:
be generally agreed by both respondents said that risks which
government and the private had been allocated to them were Don’t Lose Sight of the Basic
sector, the proper application ‘impossible to manage’. This Principles
of the principle to specific risks figure rose to 67% of contractor Firstly, government agencies
on various projects continues to respondents (as opposed to need to be careful, when drafting
be the subject of considerable principals or consultants).3 the contractual documentation
negotiation. The reasons for this on which bids will be based, not
Other Influences
include the following: to lose sight of the principles of
The principles of efficient risk
efficient risk allocation. There
Subjective Views allocation do not operate in
is often a strong temptation to
Each party comes to the a vacuum—there are other
start with an aggressive draft and
transaction with its own important influences on risk
see how the market responds
subjective views as to: allocation which are also at play.
before making the difficult calls
• the respective abilities of the In a 1999 survey of participants in
on the difficult risks. The fact
parties to manage various risks; infrastructure projects conducted
that government is often in a
by the Victorian Department
• the likelihood of certain strong bargaining position at
of Treasury and Finance, it
risks occurring and their the start of the tender process
was found that the three most
consequences; and exacerbates this temptation. One
influential factors on risk
of the risks which government
• the costs which the other may allocation were:
agencies run when they adopt
incur in managing risks. • commercial requirements such an approach is that bids will
These subjective views, even if (linking risk and return); incorporate pricing that reflects
reasonably and honestly held, • bargaining power; and the allocation of unmanageable
often differ. risks to the private sector.
• debt financiers’ requirements.4
Complexities Price the Risk
Many risks are not wholly within In the context of PPPs, the risk Where a party considers the
the control of one particular party. allocation underpinning the PSC allocation of a particular risk to it
For some risks the ability of a and the dollar values attributed offends the principles of efficient
particular party to manage the to retained and transferred risks risk allocation it should be
risk, and the costs which it will can also have a bearing on the prepared to separately price the
incur in doing so, will depend to a willingness of government to risk and advise the other party of
large extent upon how the other depart from its preferred risk the price. This would enable the
party conducts itself. In these allocation. other party to make an informed
cases, risks need to be shared, These influences dictate that, value for money assessment.
and obligations or restrictions inevitably, risks will not always Too often it seems that bidders
need to be imposed on the party be allocated in accordance with are unwilling to separately
CCT 9 4 4 10
M7 4 4 7 4
LCT 4 6 9 2
NSBT 3 5.5 5 1
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Months
In the Cross City Tunnel project, An even shorter period of Development and the chairman of
the first in the latest generation negotiation was conducted during the successful Lane Cove Tunnel
of Sydney toll roads, the NSW procurement of the $1.5 billion consortium, Mr Tony Shepherd,
Minister for Roads announced the Westlink M7 project (formerly publicly praising the efforts of the
Cross City Motorway consortium the Western Sydney Orbital). The RTA in tackling ‘deal creep’.
as the preferred proponent in WestLink Motorway Consortium On EastLink, proposals were
February 2002, and negotiations was announced as the preferred received by the State in late April
were concluded by December proponent in October 2002, and 2004 and contract close was
2002. This reasonably short negotiations were concluded in achieved on 14 October 2004,
negotiation period is even more February 2003. resulting in a process comprising
impressive when it is considered Similar processes were adopted evaluation, negotiation and award
that negotiations were conducted in the recent Lane Cove Tunnel lasting just over 6 months in total,
in tandem with a series of project, which led to the Vice with financial close a little over a
changes to the proposed project. President of the Australian month later.
Council for Infrastructure