MCQ Bhima

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 8

S.

N
Calculate the cost of the plastering required for a wall of 4 m long, 3.5 m high and 300 mm thick, if the rate of
1 plastering is Rs. 12 per square meter.
101 168 336
2 What is the actual size (mm) of the standard modular brick as per Indian Standards?
190 x 90 x 90 200 x 90 x 90 200 x 100 x 100
3 Concrete mainly consists of
Cement Aggregates Admixture

4 Keeping concrete wet to enable it to attain full strength is known as


Curing Wetting Drenching

5 Segregation is responsible for …………


honey-combed concrete Porous layers in concrete Surface scaling in concrete

6 The process of hardening the concrete by keeping its surface moist is known ………
 Placing Wetting Curing

7 Minimum grade of concrete for Plain Cement Concrete work as per IS


M-5 M-7.5 M-10

8 Minimum grade of concrete required for Reinforced Cement Concrtete work as per IS
25 20 15

9 Deshuttering period for Column and RCC retaining wall as per IS


12 to 20 Hrs 16 to 24 Hrs 20 to 24 Hrs

10 Deshuttering period for beam bottom span - 9 m


7 Days 14 Days 21 Days

11 Wetting of coarse aggregate shall be carried out for cast in situ concrete
6 Hrs
12 Hrs
18 Hrs
24 Hrs

12 Slump reading should not be exceed for designed workcablity


±10
±15
±20
±25

13 Tamping required for cube casting on site


20 Nos.
35 Nos.
30 Nos.
25 Nos.

14 Timber props only used only where height of structure less than
3m
3.5 m
2.4 m
2m

15 Locking pin (Share Pin) for telescoping adjustible props


8 mm
12 mm
10 mm
6 mm

16 Telescopic adjustiblae props should be braced (Bracing provide) when height


Less than 3 m
Exceeds 3.6 m
Less than 3.6 m
Exceeds 3 m

17 Weight of 12 mm FE 500 TMT Steel Bar


9.55 Kg
10.66 Kg
11.65 Kg
12.66 Kg

18 Minimum Diameter of Pin provided in beam reinforcement


12 mm
16 mm
20 mm
25 mm

19 Silt content of sand should not exceed


8%
5%
10%
7%
20 Avarage Water absorption of brick not more than
10%
15%
20%
25%

21 Raking of joints – minimum ….....mm deep.


15 mm
10 mm
20 mm
05 mm

22 Minimum gap …... days shall be maintained between completion of brick masonry and commencement of internal plaste
10 Days
5 Days
7 Days
15 Days

23 Level pads of size not less than ……….. shall be made on the walls and distance between level pads shall not exceed…...
2'' x 2'' , 5'
3'' x 3'' , 5'
2'' x 2'' , 6'
' 4'' x 4'' , 5'

24 Hacking on concrete surface per sq.ft


50 to 55 Nos
60 to 65 Nos
45 to 50 Nos
40 to 45 Nos

25 internal plaster, average thickness of plaster shall not be less than …... mm and not more than ……..mm
12 mm and 15 mm
10 mm and 15 mm
15 mm and 20 mm
10 mm and 12 mm

26 Gypsum plaster thickness shall be….. to ….. mm thick


10 to 12 mm
12 to 15 mm
05 to 10 mm
10 to 15 mm

27 In external plaster , time gap between application of first coat and second coat not exceeds
2 Days
3 Days
5 Days
7 Days

28 Pani Patti shall be at …. mm thickness and ….. mm in width


10 mm and 20 mm
05 mm and 35 mm
15 mm and 25 mm
05 mm and 20 mm

29 Which Is code required on site for RCC and PCC


IS 457 : 2000
IS 458 : 2000
IS 456 : 2000
IS 455 : 2000

30 Side cover required for Footing, Column, Beam and Slab respectively
40,45,30,20
50,45,25,20
45,40,25,20
50,40,20,20

31 A days work, brick/block work should not be constructed more than………... height
0.9 m
01 m
1.2 m
1.5 m

32 For Primary safety on site what is most important


Safety Belt
Safety Shoes
Safety Helmet
Safety Goggles

33 What is very Important on site


Execution
Monitoring
Safety
Procedure
nd 300 mm thick, if the rate of

423 336

ards?
229 x 114 x 76 190 x 90 x 90

All option are correct All option are correct

Quenching curing

All option are correct All option are correct

……
Compacting Curing

M-15 M-15

per IS
30 20

24 to 30 Hrs 16 to 24 Hrs

21 Days
28 Days

24 Hrs
±25

35 Nos.

3.5 m

12 mm

Exceeds 3.6 m

10.66 Kg

25 mm

8%
20%

10 mm

commencement of internal plaster application.

7 Days

n level pads shall not exceed…...

2'' x 2'' , 6'

60 to 65 Nos

re than ……..mm

12 mm and 15 mm

05 to 10 mm
5 Days

05 mm and 35 mm

IS 456 : 2000

50,40,20,20

1.2 m

Safety Helmet

Safety

You might also like