Professional Documents
Culture Documents
Project Management Lec 4 Scheduling
Project Management Lec 4 Scheduling
Project Management
Cairo – August 2021
Lectures Prepared by
Dr. Amr A. Elsharkawy
1
Safety Moment
2
Texting while Driving
4
Project Planning and Scheduling
1 2 3 4
Execute,
Define Develop Integrate
Monitor
Scope WBS /OBS PMCS
& Change
6
Scheduling Situations
Probability of 1 in 100
of a Occurring
Probability
Probability of 1 in 100
of b Occurring
Activity Time
Most Most Most
Optimistic Likely Pessimistic
Time Time Time
(a) (m) (b)
Schedule
- Schedule is a time phased plan for completion
of a project based on a logical arrangement of
activities, resource availability and contractual
requirements; inclusive of Client /project objectives
and constraints.”
- Schedule is converted to
“S-Curve” in order to
Measuring act. Progress vs
Planned progress . 11
Schedule / Progress
12
Schedule Principles
Start Date :
A Start date is a date on which the particular
schedule activity is anticipated to be started.
Early Start Date (ES):
represents the earliest possible point of time at
which the schedule activity can begin.
Late Start Date (LS):
represents the latest point at which the schedule
13
Schedule Principles
activity may be kicked off without causing
delays in the project completion date.
Actual Start Date (AS):
marks the beginning of work on a scheduled
activity.
Finish Date:
Refers to the date in which the particular schedule
activity is anticipated to be completed.
14
Schedule Principles
Early Finish Date (EF):
earliest possible point of time at which the schedule
activity may potentially be completed .
Late Finish Date (LF) :
latest date at which the schedule work activity may
be completed without causing schedule delays
Actual Finish Date (AF) :
marks the completion of work on a scheduled
activity. 15
Activity Identification
16
Activity Identification
17
Total Float , Free Float
Total Float ( slack ) is the number of days an
activity may be delayed without interfering with the
project completion date.
TF = LF date - EF date
19
Activity Identification
Forward Pass is used to determine and calculate
the early start and finish dates by starting at the
project start and working forwards through the
schedule network logic
22
Class exercise :
23
Class exercise :
24
Example , cont.
25
Example , cont.
26
Total Float , Ex.
27
Critical Path
It is a string of activities in the Logical Network
Path that has no flexibility in terms of schedule
slippage.
28
Ex. , Critical Path
29
Critical Path , Ex.2
30
Class Exercise
32
Class Exercise
33
Class Exercise
34
Levels of Schedule
36
Levels of Schedule
Level I schedule
37
Levels of Schedule
Level II schedule
Laddering
39
Planning and Scheduling Tricks
40
Planning and Scheduling Tricks
42