Professional Documents
Culture Documents
Cost - Schedule Control in Project
Cost - Schedule Control in Project
A CANADIAN APPROACH
178
subcontractors. By incorporating the WBS elements to the determining whether a contractor's project management
corresponding responsible organisational structures. control system meets project management needs. Contrac-
responsibility for identified manageable work to the appro- tors are allowed to use the specific management prOl:edures
priate. specific organisation elements will be identified. i.e.. of their choice but have to comply with the characteristks
establishment of responsibility for identified work tasks. and capabilities of an effective cost / schedule control
system. A validation process is to be canied Out by a
review team of experienced CS~ client's staff to determine
control system compliance with CS!. System acceptance
and continuous surveillance will also be monitored by the
Planning and Budgeting: Define the authorized work client's review team. The criteria are applicable to any
execution strategy by developing a baseline for planning
types of contracts in excess of approximately $60 millions
and budgeting. i.e.. the establishment of a time-phased
for research and development programs or $250 millions
budget baseline against which contract performance can be
for production ones. except firm. fixed-priced contracts.
measured. This Performance Measurement Baseline (PMB)
integrates time. cost and work performance in timely-
manner baselines through a realistic schedule that identifies In a CS2 environment. earned value technique is used to
the sequence of work. task interdependencies required to
provide cost and schedule performance measurement. It is
meet the development. production and delivery require- based on the measurement of the budgeted value of the
ments of the project. and through budgets for all authorized work actually canied out. its comparison with the budgeted
work compliant with the organizational criteria as well as value of the work that should have been canied Out and
through work authorization that defl11esthe scope of work what it actually costs. The followings are imponant basic
and assigns it to responsible performing program data elements which must be used to determine and plan
organisations. .
for objective evaluation of project's progress and
performance:
179
Although there were concerns with the criteria's application
and implementation. the U.S. approach with its 25 years of
· The standard promotes "Top concerns" variance
analysis reports as opposed to automatic WBS
hard-won experience in industry, is still considered by threshold-based ones. emphasizes the importance of
project managers as one of the most valid concept and graphical. integrated overall program level summary of
approach to assess and control contract performance status Cost and Schedule performance data. highlights
in today's project management environment. However. the cost/schedule issues through key schedule dates
flexibility of the criteria's interpretation relating to its (milestones) generated from appropriate and reliable
application and implementation purposes has resulted in scheduling techniques.
increasing concerns2within Canadian industries and govern-
ments as application experiences were gained on major
Canadian projects. There was also a valid concern that The standard encourages an up-to-date Performance
some of the practices have been question-driven. Measurement Baseline (PMB) to reduce unnecessary
Confidence of project managers in the criteria's cost and variance reportings through client's acceptance and
schedule control processes has been slowly eroded resulting training.
in the need to respond directly to these problems. A
consensus was obtained during an industry/government
exchange conference in 1990 in Ottawa to develop a
Canadian Cost/Schedule policy which. in general. should be
· Basic concepts of the standard are compatible with the
above-mentioned U.S. criteria (000 5000.2) resulting
compatible with the U.S. criteria while minimizes in reciprocating agreement being sought for validation
government bureaucracy and reduces application burdens on and certification purposes.
contractors. It accelerates the push to quickly introduce this
policy on all government's major projects. As a result. the
Canadian government initiated the effort to involve The C/SPMS in Major Projects
government and industry experts in the development of the
Canadian Cost/Schedule Performance Measurement
Standard (C/SPMS). taking into consideration the fact that The objectives of the standard2 are:
in the absence of a Canadian standard. the application of
the U.S. criteria on Canadian projects has culminated in the
following issues: · To provide a timely. accurate and realistic projection
of the integrated workscope. cost and schedule perfor-
mance data of a project in order to provide both
· The criteria approach is a sound and good project
management principle. However. it is too costly and
contractor and customer's management sufficient back-
ground to make appropriate decisions.
complicated for Canadian governments and contractors.
· Implementation requires significant amount of paper
work. reflected through long guidelines. check lists and
. To emphasize uniform criteria used to evaluate a
contractor's project management cost and schedule
significant amount of reports generated. Excessive
control system. provide the baseline requirements for
criteria rules and processes demand such a volume of
an acceptable system as well as encourage and support
findings during demonstration and application reviews
contractor to better its planning and control operations
that project activities are swamped by forms and
by implementing project management systems most
papers.
effective in managing contract cost/schedule
The Performance Measurement Baseline (PMB) performance.
monitoring is too rigid. inflexible. complex and vague.
eg.. the Over Target Baseline (OTB) process.
The intended implementation of the standard for Canadian
projects. basically. should involve the same planning and
Since 1990. government/industry teams have come up with control processes as those required by the U.S. 000
many practical recommendations on how to improve the 5000.2 while trYing to improve performance measurement
U.S. criteria (000 5000.2) for application in the Canadian and reporting requirements. especially those associated with
context. Many of the objectives set out to achieve by the scheduling aspect. An official implementation guide
experts on these teams have been realized. culminating in will be finalized and issued for use in the very near future.
the C/SPMS having the following characteristics: There were. however. differences about reporting specifics.
Apart from significant differences in reporting requirements
180
focussing on cost/schedule issues, implementation of the References
standard should follow the same cycles' as carried out to
comply with the U.S. criteria. The C/SPMS's reporting
requirements include the following formats.1as illustrated by I. Nguyen. Nghi, M., "CSl in High-Tech Program
the attached figures A-E. Management", 1988 Transactions, American Associa-
tion of Cost Engineers (AACE), Morgantown, WV.
USA, pp.U.1.l to U.1.l0.
These formats, in general. promote "Top Concerns" issues
with significant emphasis on evaluations of scheduled
milestones performance as well as forecasts of achievement 2. Nguyen, Nghi. M.. "Cases Impairing C/SCSC Applica-
for these milestones. Le.. reports concentrating on tion in Program Management", 1990 Transactions,
Cost/Schedule Performance Data Integration with resulting Association Fran~aise des Ingenieures et Techniciens
Cost/Schedule issues to be highlighted as well as emphasis d'Estimation de Planification et de Projet (AFITEP).
on contract master schedule's control including Critical Path Paris, France, pp.E.3.l to E.3.10.
monitoring.
181
Contractor Contract Type Contract Report Signature.
& No: Name Period Title & Date
Ceiling Price
-T Risk Range
--'- EAC
ETC~
Graphic MR Target Cost
~ Now Estimated
Time Planned
Completion
~
z
Program Overview
182
Format B
Surnmary Master Schedule (SMS)Status
Contractor: Contract Contract Report Period: Signature, Title and Date:
Type & No: Name:
Calendar - Months
- Statusof "air majormilestones
and deliverable end items
... .... -
-- Schedule window ...
--
A ("x" month)
Bar
Chart
I ". A
.- D
'J
00
VJ
,
J Now ., ,.
I
Performance Data ,
- - i_- -
30 x 0
Overhead
Gen and Admin
Narrative:
· Analysis of major problems including identification of the top "X" ones impacting contract
o'
To "back-up" performance data elements associated with CWBS variance identification
ii'~ """"".
t~ 'rii'
r
'"" '''.'''
~:r~r .~].
,.,.
~3 ttJ, ~~ it b ~~~~~ 1[
:
.. .,,,", .'" ~
D iW~fJa~j;l':1i~~u ,~C~
:.'.'.,.:,~.
. '
. J'
~i\;ltl~.. j~io'~~i~Wi tr".:.:~\~?~,:,.
~e(: d~~u~~~ei..U~
,.:an~& ~.a{Jti:!f~h rJ.~
---
at the "Intermediate" level
.
..
of the Master Schedule ...- Schedulewindow
A ... ("x" month)
00
...
VI Bar ...
Char:t "
" A
A
!Z
Y
NOW
.
A
'\1
.
A
ESI
De8cnptlon
~
~~FF
LS Duration Iu:
-legend:
ES EanyStart
EF EariyFinish
LS Late Start
u: Late Finish
TF TotaJRoat
CPM Precedence Diagram (PDM) -
FF Free Float
Critical Path
Logic Listings
Format E - Network, Critcial Path and Logic Listings
186