Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

CONCURRENT DELAY INTRODUCTION expensive, the owner is likely to

The claiming and granting of want to incurthat expense as close


MaLLesons Stephen Jaques as possible to the date
extensions of time in large
infrastructure projects is often a commissioning is due to
complicated and fractious process. commence. Forthis reason, if the
One common reason forthis is the contractor is in delay the owner is
issue of concurrent delay. likely to further delay incurring the
expense of building the pipeline. In
A concurrent delay occurs when
the absence of a concurrent delay
two or more causes of delay
clause, this action by the owner in
overlap. It is important to note that
response to the contractor's delay
it is the overlapping of the causes of
could entitle the contractor to an
the delays not the overlapping of
extension of time.
the delays themselves. In our
experience, this distinction is often APPROACHES FOR
not made which leads to confusion DEALING WITH
and sometimes disputes. More CONCURRENT DELAYS
problematic is when the contract is The issue of concurrent delay is
silent on the issue of concurrent dealt with differently in the various
delay and the parties assume the international standard forms of
silence operates to their benefit. As contract. Accordingly, it is not
a result of conflicting case law it is possible to argue that one approach
difficult to determine who, in a is definitely right and one is
particular fact scenario, is correct. definitelywrong. Further, the 'right'
This can also lead to protracted approach will depend on which side
disputes and outcomes contrary to of the table you are sitting.
the intention of the parties.
In general, there are three main
This update considers the approaches for dealing with the
significance of addressing the issue issue of concurrent delay. These
of concurrent delay in construction are:
contracts and the various
approaches that may be taken. • option one-contractor has no
entitlement to an extension of time
SIGNIFICANCE OF if a concurrent delay occurs;
CONCURRENT DELAY
• option two-contractor has an
There are a number of different
entitlement to an extension of time
causes of delaywhich may overlap
if a concurrent delay occurs; and
with delay caused by the contractor
The most obvious causes are the • option three-causes of delay are
acts or omissions of an owner. apportioned between the parties
and the contractor receives an
An owner often has obligations to
extension of time equal to the
provide certain materials or
apportionment, for example, if the
infrastructure to enable the
causes of a 10 day delay are
contractor to complete the works.
apportioned 60-40 owner-
The timing forthe provision of that
contractor, the contractorwould
material or infrastructure [and the
receive a six day extension of time.
consequences for failing to provide
it) can be effected by a concurrent Each of these approaches is
delay. discussed in more detail below.

For example, on gas plant projects, Option one-contractor not


an owner often has a contractual entitled to an extension of
obligation to ensure there is a time for concurrent delays
pipeline available to connect to the Acommon,ownerfriendly,
plant by the ti me the contractor is concurrent delay clause forthis
ready to commission the plant. As option one is:
the construction of a pipeline can be

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #92 SEPTEMBER/OCTOBER 2003 35


If more than one event causes Nothing in the clause prevents the For example, if the contractor's
concurrent delays and the cause of contractor from claiming an personnel were on strike and
at least one of those events, but not extension of time pursuant to the during that strike the owner failed
all of them, is a cause of delay general extension of time clause. to approve drawings, in accordance
which would not entitle the contrac- What the clause does do is to with the contractual procedures, the
tor to an extension of time under remove the contractor's entitlement contractorwould not be entitled to
[EDT Clause}, then to the extent of to an extension of time when there an extension of time for the delay
the concurrency, the contractor will are two or more causes of delay caused by the owner's failure to
not be entitled to an extension of and at lease one of those causes approve the drawings. The
time. would not entitle the contractor to operation of this clause is best
an extension of time underthe illustrated diag ra m matica lly usi ng
general extension of time clause. the following examples.

Example 1-Contractor not entitled to an extension of time for owner caused delay

Owner Delay
Contractor Delay 1 1 week
6 weeks
Contractor Delay 2
2 weeks

In this example, the contractor would not be entitled to an extension of time because the Owner Delay and the
Contractor Delay 2 overlap. Under the example clause above, the contractor is not entitled to an extension of
time to the extent of the concurrency. As a result, at the end of the Contractor Delay 2 the contractor would be
in eight weeks delay (assuming the contractor has not, at its own cost and expense accelerated the works).

Example 2-Contractor entitled to an extension of time for owner caused delay

Contractor Delay Event Owner Delay Event I.

'------- 6_w_e_e_k_s --------'---------2-w-e-e-k-s---_ _ -----'I


In this example, the contractorwould be entitled to a two week extension of time for the Owner Delay.
Therefore, at the end of the Owner Delay the contractor will remain in six weeks delay, assuming no
acceleration.

Example 3-Contractor entitled to an extension of time for a portion of the owner caused delay

Contractor Delay 2
Contractor Delay 1 2 weeks
6 weeks Owner Delay
2 weeks

In this example, the contractorwould be entitled to a one week extension of time because the delays overlap
for one week. Therefore, the contractor is entitled to an extension of time for the period when they do not
overlap, i.e. when the extent of the concurrency is zero. As a result, after receiving the one week extension of
time, the contractorwould be in seven weeks delay, assuming no acceleration.

36 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #92 SEPTEMBER/OCTOBER 2003


From an owner's perspective, we Option three-responsibility [a) the delay is split down the
believe, this option one is both for concurrent delays is middle and the contractor receives
logical and fair For example, if, in 50% of the delay as an extension of
apportioned between the
Example 2 the Owner Delaywas a time; or
delay in the approval of drawings parties
Option three is a middle ground [b) the delay is apportioned 100 % to
and the Contractor Delaywas the
position that has been adopted in the owner and therefore the
entire workforce being on strike,
some of the standard form contractor receives 100% of the
what logic is there in the contractor
contracts. For example, the time claimed.
receiving an extension of time? The
delay in approving drawings does Australian Standards construction The delay is unlikely to be
not actually delay the works contract AS4000 adopts the apportioned 100% to the contractor
because the contractor could not apportionment approach. The because a judge or arbitrator will
have used the drawings given its AS4000 clause states: likely feel that that is 'unfair'
workforce was on strike. In this 34.4 Assessment especially if there is a potential for
example, the contractorwould s'ignificant liquidated damages
When both non ?qualifying and liability. We appreciate that the
suffer no detriment from not
qualifying causes of delay overlap, above is not particularly rigorous
receiving an extension of time.
the superintendent shall apportion legal reasoning, however, the
However, if the contractor did
the resulting delay to WUC accord-· clause does not lend itself to
receive an extension of time it
ing to the respective causes' rigorous analysis.
would effectively receive a windfall
contribution. In assessing each EDT
gain. In addition, option three is only
the superintendent shall disregard
The greater number of obligations questions of whether: likely to be suitable if the party
the owner has the more reluctant undertaking the apportionment is
a) WUC can nevertheless reach independent from both the owner
the contractor will likely be to
practical completion without an and the contractor Increasingly, this
accept option one. Therefore, it may
EDT; or is not the case on large scale
not be appropriate for all projects.
b) the contractor can accelerate, infrastructure projects.
Option two-contractor
entitled to an extension of but shall have regard to what CONCLUSION
prevention and mitigation of the A concurrent delay clause should
time for concurrent delays
delay has not been effected by the be included in all construction
Option two is the opposite of option
contractor. contracts. Remaining silent on the
one and is the position in many of
We appreciate the intention behind issue may lead to disputes. Which
the contractor friendly standard
the clause and the desire for both option is adopted will depend on the
forms of contract. These contracts
parities to share responsibility for project and the respective
also commonly include extension of
the delays they cause. However, we bargaining strengths of the parties.
time provisions to the effect that the
contractor is entitled to an have some concerns about this
clause and the practicality of the This article was previously
extension of time for any cause
apportionment approach in published in Mallesons Stephen
beyond its reasonable control
general. It is easiest to demonstrate Jaques' Asian Projects and
which, in effect, means there is no
need for a concurrent delay clause. our concerns with an extreme Construction Update (20 September
example. Forexample, what if the 2003). Reprinted with permission.
The suitability of this option will
qualifying cause of delay was the
obviously depend on which side of
owner's inability to provide access
the table you are sitting. This option
to the site and the non-qualifying
is less common than option one but
cause of delay was the contractor's
is nonetheless sometimes adopted.
inability to commence the works
It is especially common when the
because it had been black banned
contractor has a superior
by the unions. How should the
bargaining position.
causes be apportioned? In this
example, the two causes are both
100 % responsible for the delay.
In ourview, an example like the
above where both parties are at
fault has two possible outcomes.
Either:

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #92 SEPTEMBER/OCTOBER 2003 37

You might also like