DIRECTORATE GENERAL ELECTRICITY AND ENERGY UTILIZATION

MINISTRY OF ENERGY AND MINERAL RESOURCES

Utilizing PPP Framework


To Accelerate Energy Infrastructure
(Power Sector)

Presented by
Director General for Electricity and Energy Utilization

Presented at
Asia Pacific Ministerial Conference on Public Private Partnership
for Infrastructure Development (APMC PPP) and Infrastructure Asia (IA) 2010
Jakarta, 15 April 2010
OVERVIEW OF
INDONESIA ELECTRICITY
Total installed capacity 30,941 MW (PLN 83%, IPP 14%, and PPU 3%).
Electrification ratio 66%.
Some areas are facing crisis condition.
Composition of primary energy for power generation utilization: Coal 39%,
Gas 28%, Oil 23%, Hydro 7%, and Geothermal 3%.
Under construction: PLN 8,133 MW and IPP: 2,252 MW.
WHY WE NEED PRIVATE SECTOR
PARTICIPATION
Growth rate of demand for electricity is still
high (9.2% p.a up to 2027).
Electrification ratio is still low (66% in 2009).
Lack of electricity supply in some areas
areas.

NEED A HUGE OF ADDITIONAL CAPACITY (estimated of


3,000 – 5,000 MW p.a during 10 years), approx. 6 billion p.a)

BUT

PLN’s investment capability is limited (around 20%)


The Government budget for infrastructure is very
limited.
THEREFORE
Privates sector participation are required:
Engineering, Procurement and Construction (EPC) Project
Independent Power Producer (IPP) Project
Public Private Partnership (PPP) Project
PPP PROJECT

The government will provide “the government support” or “the government


guarantee”.
If private as the initiator of the project, the government will provide some
compensation.
ti
List of PPP Projects:
CFPP Jawa Tengah 2 x 1,000 MW (tender process)
CFPP Jambi 2 x 400 MW
CFPP Kalimantan Timur 2 x 100 MW
Proposed list of PPP Book of 2010
CFPP Minahasa 2 x 55 MW, South Sulawesi (need the approval of Bappenas)

CFPP Sumatera Selatan 2 x 600 MW (Minemouth)


CONCLUSION

Indonesia electricity demand is still high thus need a huge additional


capacity of generation, transmission and distribution.
The government encourages participation of private sector to cooperate
with PLN through EPC project, IPP project and PPP project.
The government is committed to maintain the PLN’s financial viability in
order to meet its obligations to other parties.
Thank You
PLN Projects Under Construction Stage
Java-Madura-Bali Outside Java-Madura-Bali
CFPP Suralaya 1 x 625 MW CFPP Pulang Pisau 2 x 60 MW
CFPP Lontar/Teluk Naga 3 x 315 MW CFPP Asam – Asam 2 x 65 MW
CFPP Indramayu 3 x 330 MW CFPP Amurang 2 x 25 MW
CFPP Pelabuhan Ratu 3 x 350 MW CFPP Gorontalo 2 x 25 MW
CFPP Rembang 2 x 315 MW CFPP Barru 2 x 50 MW
CFPP Pacitan 2 x 315 MW CFPP Nii Tanasa 2 x 10 MW
CFPP Paiton 1 x 660 MW CFPP Bima 2 x 10 MW
CFPP T
Tanjung
j A
Awar-Awar
A 2 x 350 M CFPP Lombok
L b k 2 x 25 MW
Sub Total : 6,230 MW CFPP Ende 2 x 7 MW
CFPP Kupang 2 x 16,5 MW
Outside Java-Madura-Bali
CFPP Tidore 2 x 8 MW
CFPP Nagan Raya 2 x 110 MW
CFPP Jayapura 2 x 10 MW
CFPP Pangkalan Susu 2 x 220 MW
Sub Total : 1,903 MW
CFPP Teluk Sirih 2 x 112 MW
CFPP Bengkalis 2 x 10 MW
TOTAL : 8,133 MW
CFPP Selat Panjang 2 x 7 MW
CFPP Tanjung Balai Karimun 2 x 7 MW
CFPP Bangka 2 x 30 MW
CFPP Belitung 2 x 16,5 MW
CFPP Tarahan Baru 2 x 100 MW
CFPP Bengkayan 2 x 27,5 MW
IPP Projects Under Construction Stage
Sumatera
HPP Asahan 1 2 x 90 MW
CFPP Tanjung Pinang 2 x 10.8 MW
CFPP Tanjung Balai Karimun 2 x 6 MW
CFPP Bangka 2 x 10 MW
MHPP Parlilitan 3 x 2.5 MW
MHPP Parluasan 2 x 2.1 MW
CFPP Lampung Tengah 2 x 6 MW
MHPP Hutaraja 2 x 2
2.25
25 MW
Kalimantan
CFPP Tanah Grogot 2 x 7 MW
CFPP Ketapang 2 x 7 MW
CFPP Pontianak 2 x 25 MW
Java-Madura-Bali
CFPP Celukan Bawang 380 MW
CFPP Tanjung Jati B 2 x 660 MW
Sulawesi
CFPP Gorontalo 2 x 6 MW
HPP Poso 3 x 65 MW
HPP Manipi 1 x 10 MW
HPP Rantabela 2 x 1.2 MW
TOTAL : 2,252 MW
LOCATION OF FAST TRACK 10,000 MW PHASE II

TOTAL

HEPP : 1.174 MW
GeoPP : 3.583 MW
SUMATERA
CFPP : 4.164 MW
KALIMANTAN CCPP : 1.626 MW
HEPP : 174 MW SULAWESI TOTAL : 10.
10 547 MW
GeoPP : 1.825 MW CFPP : 706 MW
CFPP : 1.014 MW GeoPP : 125 MW
CCPP : 120 MW
CCPP : 66 MW CFPP : 198 MW
Subtotal : 826 MW
Subtotal : 3.079 MW CCPP : 240 MW
Subtotal : 563 MW
PAPUA
CFPP : 114 MW
Subtotal : 114 MW

JAWA MALUKU
HEPP : 1.000 MW GeoPP : 37 MW
GeoPP : 1.525 MW CFPP : 32 MW
CFPP : 2.000 MW Subtotal : 69 MW
CCPP : 1.200 MW NTB NTT
Subtotal : 5 725 MW
5.725
GeoPP : 40 MW
GeoPP : 31 MW
CFPP : 70 MW
CFPP : 30 MW
Subtotal : 110 MW
Subtotal : 61 MW