Professional Documents
Culture Documents
Here Are Your Results: The PM
Here Are Your Results: The PM
(file:///D:/Downloads/Free%20PMP%20Practice%20Exam%20Questions%20-%20120%20Sample%20Test%
20Questions.html#offcanvas) (https://www.project-
The PM
management-prepcast.com/)
Question 1 - Qid 6113151, Risk Management, 2. Process, 11.7 Monitor Risks Click the red
button at the
The project management plan specifies that a predictive development approach has bottom of the
been selected to produce the project deliverables. page to end the
exam and see
Where in the project life cycle will the overall project risk be the lowest?
your results.
(Please note that on the real PMP exam you may be asked to provide your answer by
clicking the correct area in the image. But here in the simulator, we are asking you to
select the answer below.)
Restart
the Exam
A
B
C
D
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 2 of 89
Restart
Explanation: (https://www.project-
61%
Please note that on this page we only show a general You answered
explanation for the 120 questions. 73 out of 120
The PMP Exam Simulator (http://www.pm-exam- questions
simulator.com/pmp), however, will give you a much correctly.
richer experience because you also receive an You have 47
explanation of why each of the answer choices is incorrect, 0 of
correct or incorrect, as well as a reference that allows which were
you to read up on the subject and learn from any unanswered.
mistakes. 0 questions
marked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 3 of 89
Get PM Exam
Hint Unmarked
Simulator
(http://www.pm-
Your answer is incorrect
Explanation: exam-
simulator.com/pmp)
Opportunity cost is regarded as the value of the alternative that is not
chosen. If the decision is made to select project Alpha and forego the $45
million in potential profit from project Beta, the opportunity cost of this
decision is $45 million, the value of project Beta.
The topic of this question is not covered in the PMBOK® Guide. However,
the Project Management Professional (PMP)® Examination Content Outline
(ECO) indicates that while there are some commonalities between the
PMBOK® Guide and the ECO, the exam is not bound by the PMBOK® Guide.
The list of enablers specified in the tasks of the ECO domains is not
exhaustive either. The ECO assumes that prospective PMP aspirants are
familiar with other sources of information/preparation, including but not
limited to PMI Code of Ethics and Professional Conduct, PMI?s Practice
Standards (e.g., Scheduling, Earned Value Management, etc.);
organizational behavior theories such as Tuckman?s Ladder, Theory X and
Theory Y, Maslow's hierarchy of needs; commonly frowned upon project
management practices, such as gold plating; and others. We intentionally
have these questions in our simulator so that you would be better
prepared for the real exam. PMP aspirants are encouraged to explore
additional sources of information and/or to be familiar with them from
their project management experience.
You are managing a project to build five bridges. The project consists of five sequential
phases with each phase delivering one bridge.
After the first phase of the project is complete, which process group of the second phase
should follow?
Initiating
Planning
Executing
Closing
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 4 of 89
In the scenario described, you are about to start a new project phase.
Therefore, you should start with the Develop Project Charter process. It
does not necessarily mean you would develop a new project charter for
each consecutive project phase, but it means that you will perform the
processes of the Initiating Process Group starting with the Develop Project
Charter process. You will review the project charter to see if the high-level
assumptions and constraints made during project initiation are still valid,
and whether or not the market conditions are still favorable for the project.
Performing this process may result in an update of the charter or an
addendum to the project charter. In an extreme scenario, this process may
result in project termination.
While the PMBOK® Guide does not explicitly mention going back to the
Initiating Process Group to look at the project charter, it does provide
several examples implying that the project team may choose to go with
each new phase as a separate, stand-alone project. Undertaking a stand-
alone project means performing all its processes, starting with the Develop
Project Charter. The same logic applies to the next process in the Initiating
Process Group, the Identify Stakeholders process. It is possible that new
stakeholders became involved in the project, or some of the previous
stakeholders left, or the level of engagement of the existing stakeholders
have changed. Even if nothing has changed, the Develop Project Charter
and the Identify Stakeholders processes should be performed. Otherwise,
how would you be able to conclude that nothing has changed? Therefore,
starting the new phase of the project with the processes of the Initiating
Process Group is the best answer to the question asked.
The project aims to investigate the feasibility of constructing a hydroelectric dam from a
technical, economic, and social point of view. The project charter created by the project
manager on behalf of the project sponsor is now approved.
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 5 of 89
Identify Risks
Identify Stakeholders
Develop Project Charter
Hint Unmarked
You are managing a software upgrade project for your company. Your project sponsor
has a great deal of authority regarding project decisions, but you recently discovered
that he doesn't have much interest in your project. To complete the project
successfully, you need your project sponsor's continuous support.
What stakeholder management strategy should you use with your project sponsor?
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 6 of 89
The project sponsor asks for a copy of the document that contains the description,
owner, source, priority, and status of product requirements.
Hint Unmarked
You are facing problems decomposing the testing work package into the final activities
required to complete the work package. Detailed testing plans and activities cannot be
determined until the system is at least 50% developed and more details become
available. The system development work package will take at least three months to
complete.
Use product analysis techniques such as product breakdown and systems analysis
to decompose the system testing work package
Decompose the system development work package now and decompose the
b c g f
system testing work package later
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 7 of 89
Break down the project into multiple phases so that the system testing work
package goes into the second project phase
Consult the project management plan to determine what to do in this situation
Hint Unmarked
Delaying the decomposition of the system testing work package until later
in the project is an example of rolling wave planning. Rolling wave planning
is an iterative planning technique in which the work to be accomplished in
the near term is planned in detail, while the work in the future is planned at
a higher level. Decomposition may not be possible for a deliverable or
subcomponent that will be accomplished far into the future. The project
management team usually waits until the deliverable or subcomponent is
agreed on, so the details of the work breakdown structure (WBS) can be
developed. Therefore, the best approach is to use rolling wave planning
and decompose the system development work package now, and then
decompose the system testing work package later, when more project
information becomes available.
You are about to start planning for a large and complex project. Due to the size of the
project along with the regulatory and environmental considerations, the development
of a detailed project management plan will be critical.
As a starting point for initial project planning, what is the first thing you should do?
Conduct a project kick-off meeting to inform and engage stakeholders and gain
commitment
Review the project charter to understand the high-level information about the
project
Share the project scope statement with the project team for a common
understanding of project deliverables
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 8 of 89
The question states that project planning is about to begin which suggests
that project initiation has been completed. The project charter is created
during the Develop Project Charter process as part of project initiation. The
project team uses the project charter as a starting point for initial project
planning. The type and amount of information in the project charter varies
depending on the complexity of the project and the information known at
the time of its creation. At a minimum, the project charter should define
the high-level information about the project that will be elaborated in the
various components of the project management plan.
As you are monitoring the cost baseline for your project, you notice that project
expenses are higher than expected at this point in the project.
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 9 of 89
Recently, you promoted your star programmer, Sam, to lead the agile development
team. Sam was a fantastic software coder, and you thought the promotion would mean
that he could now share his expertise with the other development team members.
However, you are surprised to learn that the performance of Sam in his new role is not
meeting your expectations.
Which empirical rule did you forget while considering the promotion of Sam?
Expectancy theory
Halo effect
Pareto concept
Murphy's law
Hint Unmarked
The halo effect (also known as the Peter principle) states "In a hierarchy,
every employee tends to rise to his/her level of incompetence." Most
project team members are motivated by an opportunity to grow,
accomplish, and apply their professional skills to meet new challenges.
Their achievements continuously promote them within an organization to
a certain level until they are unable to perform. Sam might have risen to his
incompetency level, which is what you have likely forgotten to consider
while promoting him to lead the development team.
The topic of this question is only briefly mentioned in the PMBOK® Guide.
However, the Project Management Professional (PMP)® Examination
Content Outline (ECO) indicates that while there are some commonalities
between the PMBOK® Guide and the ECO, the exam is not bound by the
PMBOK® Guide. The list of enablers specified in the tasks of the ECO
domains is not exhaustive either. The ECO assumes that prospective PMP
aspirants are familiar with other sources of information/preparation,
including but not limited to PMI Code of Ethics and Professional Conduct,
PMI?s Practice Standards (e.g., Scheduling, Earned Value Management,
etc.); organizational behavior theories such as Tuckman's Ladder, Theory X
and Theory Y, Maslow's hierarchy of needs; commonly frowned upon
project management practices, such as gold plating; and others. We
intentionally have these questions in our simulator so that you would be
better prepared for the real exam. PMP aspirants are encouraged to
explore additional sources of information and/or to be familiar with them
from their project management experience. The PMBOK® Guide is provided
as a reference to indicate that the scenario refers the Develop Team
process.
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 10 of 89
You have just taken over a project in execution. During your first week, you determine
that the project team members spend a lot of time responding to unexpected requests
for information from different project stakeholders. Because of these interruptions, the
team cannot focus on their project activities, and as a result, the project is behind
schedule.
Tell the team members to stop responding to unexpected requests since it is not the
responsibility of the team
Push the team to respond to all the requests faster so that they can perform their
assigned project activities on time
Ask the team to forward all stakeholder inquiries to you so that the team members
can focus on their assigned tasks
Hint Unmarked
A team member submits a draft of the requirements management plan to the project
manager for a review. The project manager notices that one of the components
included in the plan does not belong there.
Which of the following components did the project manager most likely notice?
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 11 of 89
Hint Unmarked
Question 13 - Qid 6110038, Scope Management, 2. Process, 4.5 Monitor and Control
Project Work
While reviewing your project's performance, you discover a significant variance. If the
issue is not fixed before the next customer inspection, your project might be canceled.
However, after a further review conducted by the project team, you are glad to hear that
bringing the project back on track requires only a minor correction to a configuration
element.
Hint Unmarked
All of the available answers seem like possible options in this scenario, but
the question is specifically asking what you should do 'first'. Although you
have already analyzed the situation and you know what corrective actions
are required, you must follow the proper change control procedure. A
configuration element is a project artifact that has been placed under
configuration control. Any change to a configuration element should be
formally controlled and will require a change request. Since the question
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 12 of 89
Which of the following activities might be carried out during this process?
Hint Unmarked
Monitor and Control Project Work is the process of tracking, reviewing, and
reporting overall progress to meet the performance objectives defined in
the project management plan. Of the available choices, only comparing
actual project performance against the project management plan is
performed during the Monitor and Control Project Work process.
An organization has a policy that a change control board (CCB) must review all change
requests for every project in the organization, and that the CCB follows the
recommended activities outlined in the PMBOK® Guide. Project managers and the
project team do not serve as members of the CCB.
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 13 of 89
A company has authorized a dedicated change control board (CCB) to review and
evaluate all change requests that are submitted for any project.
If the project sponsor is a member of the CCB, which of the following best describes an
individual or group that can request a change on a project?
Project manager
Project sponsor
Project team
Any stakeholder
Hint Unmarked
One of your contractors is not performing to the agreed-upon standards. You want to
terminate the contract and engage another contractor for the same job. You need to
determine the specific legal procedure for the early termination of the contract.
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 14 of 89
Hint Unmarked
The contract is the document you would refer to in order to understand the
early termination procedure. A contract is a mutually binding agreement
that obligates the seller to provide the specified deliverable. It constitutes
a legal relationship. The early termination of a contract is a special case of
the Control Procurements process that can result from an agreement by
both parties, from the default of one party, or for the convenience of the
buyer if provided for in the contract. The rights and responsibilities of the
parties in the event of an early termination are contained in the
termination clause of the contract.
A project is divided into four sequential phases. The second phase of the project has just
been completed, and the third phase is about to begin.
Hint Unmarked
The process of identifying project stakeholders occurs for the first time in a
project either before or at the same time the project charter is developed
and approved. It is repeated as necessary but should be performed at the
start of each phase and when a significant change in the project or
organization occurs. Each time the identification process is repeated, the
project management plan components and project documents should be
consulted to identify relevant project stakeholders.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 15 of 89
An organization has a project management office (PMO) that ensures all relevant
project documents are created, and all project management processes are followed
according to established best practices.
What should the project manager review first to identify stakeholders for a newly
started project?
Hint Unmarked
The business documents include the business case and the benefits
management plan. Both of these documents are created during pre-
project work and are available as sources of information about the
project's stakeholders during the first iteration of the Identify Stakeholders
process. The business case identifies an initial list of stakeholders affected
by the project. The benefits management plan may identify the individuals
and groups that will benefit from the delivery of the outcomes of the
project and are thus considered as stakeholders. Among the available
options, only the business documents are available as sources of relevant
information during the first iteration of the Identify Stakeholders process.
The following table is an activity list that includes the duration and predecessor for a
series of project activities.
11
14
9
13
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 16 of 89
Hint Unmarked
Using the critical path method may require drawing a project schedule
network diagram, or listing all the possible the sequences of paths with the
given activities, then adding up the durations, and knowing which path
constitutes the critical path.
The resulting list of paths with their aggregated durations is below. The
critical path is Start-E-B-D-End, and the duration of the critical path with
the data given is 14.
A project manager is in the process of developing the stakeholder register. As the first
step in this process, she needs to create a list of potential stakeholders and decides to
use a data gathering technique called brain writing.
Consult the stakeholder engagement plan to understand how the stakeholders are
to be identified
Hint Unmarked
Your
b answer is incorrect c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 17 of 89
Explanation:
Data gathering techniques that can be used for the Identify Stakeholders
process include questionnaires and surveys, brainstorming, and brain
writing. Brain writing is a refinement of brainstorming that allows
individual participants time to consider the questions individually before
the group creativity session is held. Therefore, the first step of brain writing
is providing the participants with the questions before the creativity
session. This process will allow the participants to be better prepared
which will make the meeting more effective than a traditional
brainstorming session.
A project manager does most of her communicating with team members, internal
project stakeholders, and external project stakeholders via email. The project manager
incorporates specific techniques when composing her emails to reduce any
misunderstandings.
Concise expression
Clear purpose directed to the needs of the reader
Controlled flow of words and ideas
Communications register
Hint Unmarked
The scenario describes the use of techniques that will aid in the reduction
of misunderstandings in written communication specifically. These
techniques are known as the 5Cs of written communication:
However, the question asks which answer is 'not' a technique that will aid
in the reduction of misunderstandings in written communication, or in
other words, which answer is not one of the 5Cs of written communication.
'Communications register' is not one of the 5Cs components. Actually,
'communications register' is a made-up term.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 18 of 89
Note, the term 'tools and techniques' used in this question to describe the
5Cs does not refer to the traditional meaning of tools and techniques of the
project management processes. We are using this term as we consider it to
be a reasonable description of the components comprising the 5Cs.
As the project manager, you are leading a brainstorming session with key stakeholders
to identify project risks. Once the project risks are determined, you immediately
proceed to nominate different team members as risk owners and assign them the task
of developing individual risk response plans.
No, you should be the one developing the risk response plans as you are ultimately
responsible for the outcomes of the project.
Yes, the risk response plans are an output of the Identify Risks process and should
be developed right after the risks have been identified.
No, before assigning risk responsibility to team members, you need to assess each
risk's probability of occurrence and its impact.
Yes, the team members should be assigned responsibility for a risk as soon as
possible and tasked with creating a risk response plan.
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 19 of 89
order to properly identify the risks on which to focus and plan. Only then
should team members be assigned risk ownership. Assigning risk
ownership to team members before determining which risks are the most
likely to occur and impact the project is not an efficient use of resources
and is not the proper protocol outlined in the PMBOK® Guide.
You are managing a project to build a database and need to acquire information from
the stakeholders of the project. The team is using brainstorming, focus groups,
interviews, questionnaires, and benchmarking to understand and document the
stakeholders' needs.
The methods the team is using are representative of which tool and technique?
Data gathering
Data analysis
Decision making
Data representation
Hint Unmarked
The project is in execution, but your project team is unable to stop arguing about the
project milestones and the specific risks associated with them. This on-going conflict
puts the project at risk of running behind schedule.
What would likely have helped avoid this conflict had it been properly created first?
A project charter
Physical resource assignments
Quality metrics
A work breakdown structure
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 20 of 89
Question 26 - Qid 6110075, Scope Management, 2. Process, 4.5 Monitor and Control
Project Work
During project execution, the team discovers that some of the buttons on the remote
control developed by the project for a new product do not work according to the
specifications. A change request is submitted and approved to replace the buttons.
Corrective action
Preventive action
Defect repair
Gold plating
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 21 of 89
A project manager meets with a customer for initial discussions about an upcoming
project. At the end of the meeting, the customer asks the project manager for a rough
estimate of the project duration. Based on her experience with three similar projects,
the project manager provides an estimate of 8-10 months.
Expert judgment
Three-point estimating
Analogous estimating
Bottom-up estimating
Hint Unmarked
Design for X (DfX) where the X in DfX represents the quality aspect of the product
Design of experiments (DOE) as a quality improvement methodology
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 22 of 89
The question implies that the Manage Quality process, sometimes referred
to as quality assurance, is underway. Design for X (DfX) is one of the tools
and techniques which may be used during the Manage Quality process. DfX
is a set of technical guidelines that may be applied during the design of a
product for the optimization of a specific aspect of the design. DfX can
control or even improve the product's final characteristics. The X in DfX can
be different aspects of product development which can include but are not
limited to quality improvement.
You have compiled a list of potential stakeholders for your project, and now you are
classifying the stakeholders with regard to the direction of their influence. As you work
through your way down the list of stakeholders, you have come to the project sponsor.
Downward
Sideward
Outward
Upward
Hint Unmarked
According to the scenario, you are carrying out the Identify Stakeholders
process. Directions of influence is an example of a data representation
technique that can be used as part of this process. This technique classifies
stakeholders according to their influence on the work of the project or the
project team itself. Stakeholders can be classified as upward, downward,
outward, or sideward. The upward classification includes senior
management of the performing organization or customer organization,
sponsor, and steering committee. Therefore, the project sponsor should be
classified as upward.
Question 30 - Qid 6110083, Scope Management, 2. Process, 4.5 Monitor and Control
Project Work
During project planning, the project team rigorously defined the project scope. During
project execution, a senior engineer calls the project manager and suggests a simpler
and more efficient design which could benefit the project.
Nothing, no changes are needed since the project scope was rigorously defined
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 23 of 89
Hint Unmarked
One may argue that evaluating the change should come before submitting
the change request. We had an extensive debate on the subject of change
requests in general and on this question in particular. The reason being is
that the PMBOK® Guide does not do a good job in explaining the exact
process in detail. We have discussed this process among our team of
certified project management professionals and have concluded that the
first thing that should be done when a change is requested on a project is
the physical creation of the change request, a document if you wish, filling
out a form. Otherwise, on what basis would a project manager and the
project team spend time evaluating a request that is not even
documented?
You are working with a team to estimate how much time is required for each activity.
You are using a document that contains information on the categories of labor,
material, and equipment required to complete the project. You are also interested in
the skill levels, required certifications, and the grade levels for supplies.
Which of the following documents would you primarily refer to for this purpose?
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 24 of 89
While performing project work, a team member notices that there is a potential new
risk, which could impact the project's critical path.
Recommend the project be placed on hold for a day to avoid the risk
Document the risk in the risk register
Draft an emergency fallback plan since the critical path is in jeopardy
Generate a risk report using quantitative and quantitative analysis of the identified
risk to alert the team of the schedule impacts
Hint Unmarked
By recording identified risks in the risk register, the project manager and
team are able to keep track of all potential threats and opportunities.
Furthermore, once a risk has been analyzed using qualitative and or
quantitative risk analysis methods, the risk register serves as the central
repository for planned risk responses and lists risk owners. As such, any
time a new risk emerges on a project, the first step to take is to
immediately document it in the risk register.
You are managing a project that is nearing its end and planning to settle all pending
claims with the vendors. In one case, you are not satisfied with the delivery of their final
product. All conversations with the vendor have ended in an impasse.
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 25 of 89
Hint Unmarked
Contested charges where the buyer and seller cannot reach an agreement
are called claims. The contract usually has terms to handle claims
administration. If the parties cannot resolve the claim, it should be handled
by alternative dispute resolution (ADR), typically following procedures
established in the contract. There are two types of ADR, arbitration and
mediation. Direct negotiation between the parties is the preferred method.
Litigation in the courts is the last option that a project manager should
choose. Based on the scenario described, the project manager has
negotiated directly with the seller. However, all conversations have ended
in an impasse. In this situation, the next step for the project manager to
take is to identify some form of alternative dispute resolution.
Your company was awarded a contract that includes a 10% bonus payment if the
project is completed two months early. You consider several options to exploit this
opportunity.
What is the best course of action for you to increase the chances of receiving the bonus?
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 26 of 89
The quality management plan specifies the use of a data representation technique to
show the strength of relationships between four factors.
Which of the following tools or techniques should be used to comply with the plan?
Affinity diagram
Matrix diagram
Scatter diagram
Quality diagram
Hint Unmarked
You have just taken over a project in which some of the deliverables will be produced by
external vendors. You want to familiarize yourself with those who are involved in the
project from the sellers' side.
Bid documents
Stakeholder register
Seller proposals
Stakeholder engagement plan
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 27 of 89
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 28 of 89
In the design phase, external experts verified that the team's blueprints for a new crane
complied with requirements. During the build phase, the customer performed a
walkthrough and found that some welding joints on the crane were defective. The crane
needs to be reworked to ensure it can be operated safely.
Hint Unmarked
For an upcoming project, a needs assessment and business case have been completed,
and the project management office (PMO) is reviewing a draft of the benefits
management plan. The PMO highlights an element of the benefits management plan
and requests that the element be removed before the document is finalized.
Which of the following was most likely the element the PMO requested to remove?
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 29 of 89
You have been requested to fill in for a project manager who has called in sick midway
into project execution. As you get yourself familiar with the project team, you are
impressed to see how well the team members collaborate and work through issues
smoothly and effectively.
(Please note that on the real PMP exam you may be asked to provide your answer by
clicking the correct area in the image. But here in the simulator, we are asking you to
select the answer below.)
A
B
C
D
Hint Unmarked
The Tuckman ladder is one of the models used to describe stages of team
development. This model is typically referred to by project management
practitioners as part of the Develop Team process. The model includes five
stages: forming, storming, norming, performing, and adjourning. While it is
safe to say that most teams go through all five stages, some may get stuck
in a particular stage or even regress (go back) to an earlier stage. On the
other hand, projects with team members who worked together in the past
might skip a stage. Each stage is distinguished by different dynamics
among the team members resulting in various levels of team effectiveness.
Team effectiveness is at its lowest level during the storming stage as the
environment is characterized by a high degree of conflict and a lack of
collaboration among the team members. As the team members begin to
b c g f
work together and trust each other, in other words, the relationships
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 30 of 89
between the team members normalize (thus the name of the next stage,
norming), the degree of team effectiveness increases. Teams that
successfully go through the norming stage would eventually reach the
performing stage, which is the highest level of team development. In the
performing stage, the team function as a well-organized unit, and the team
effectiveness is at its highest.
To define the product that will be produced by the project, the project team is using a
product analysis technique that helps with breaking down the high-level requirements
into the level of detail needed to design the product.
Which of the following is the product analysis technique used by the team?
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 31 of 89
described, the team breaks down the high-level requirements into the level
of detail needed to design the product, which corresponds to the product
breakdown technique, making it the best answer among the choices given.
A three-phase project to build a prototype is underway. The first phase entails design. In
the second phase, the manufacturing team would produce the parts from the design
specifications. In the third phase, the production team would assemble the parts to
construct the prototype. The project is now at the end of the first phase.
Hint Unmarked
A project is nearing its end when the project manager receives an approved change
request to replace a defective unit.
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 32 of 89
The question suggests that the Direct and Manage Project Work process is
being carried out. Approved change requests are one of the inputs to that
process. The project manager has received an approved change request. It
is now her responsibility to ensure the approved change request is
implemented as specified. Since the change request calls for the
replacement of the defective unit, the next step for the project manager is
to have the defective unit replaced.
A technician has just tested a piece of equipment and found a defect. The technician
has informed the project manager and submitted a change request to repair the defect,
indicating that the repair will require significant rework.
Hint Unmarked
At the end of a design project, a competitor has gained market share with a new
technology that has rendered the project?s deliverable obsolete. The project sponsor is
pleased with the work of the project team who finished within budget and on time but
thinks that the project should have been terminated much sooner.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 33 of 89
What might have the manager of the project done differently in this situation?
Established a change control board (CCB) to review and render decisions for all
submitted change requests
Terminated the project when the new technology was introduced
Scheduled more frequent lessons learned meetings with the project team
Hint Unmarked
Which of the following is the most likely challenge the teams will face while controlling
the schedule?
Stability of requirements
Technology support
Human resource availability
Project importance
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 34 of 89
Each project is unique. Therefore, the project manager may need to tailor
the way Project Schedule Management processes are applied. Technology
support is among the considerations for tailoring that should be kept in
mind while planning the project under the circumstances described in the
scenario. The question presents a situation where a project is being
conducted in a desolate area without any existing infrastructure for
technology support. This circumstance means that there are no cellular
towers or Wi-Fi and no readily available means of communication.
Concerning controlling the schedule, the project manager must consider
how the project management software, including the project schedule, will
be updated and submitted daily to the home office. The project manager
may need to acquire the necessary equipment to use satellite technology
and reconsider the content and frequency of the project status updates.
Therefore, of the available choices, technology support is the best answer
to the question asked.
What conflict resolution technique did you most likely employ in this situation?
Compromise or reconcile
Force or direct
Collaborate or problem solve
Smooth or accommodate
Hint Unmarked
The question states that a temporary solution was suggested that provided
some degree of satisfaction for both managers. The compromise/reconcile
approach to conflict resolution is characterized by searching for solutions
that bring some degree of satisfaction to all parties to temporarily or
partially resolve a conflict. Even though the compromise/reconcile
approach provides a lose-lose solution because both parties have to give
up something, it is the best answer based on the situation described by the
question.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 35 of 89
During a daily stand-up meeting, one of the programmers mentions that she had some
extra time and added functionality, which was not included in the original design. She
believes the customer will appreciate the added functionality.
Remove the added functionality and ensure that the project team builds the
software as designed going forward
Thank the programmer for the extra effort and notify the customer of the new
functionality that has been added
Update the cost baseline since the project will run over budget due to the cost of
adding new functionality
Accept the added functionality, but ask the programmer to build only what has
been designed going forward
Hint Unmarked
The extra code that was written to add the functionality should be
removed from the build, and the project manager should ensure software
is written as designed going forward. Adding unplanned functionality,
sometimes referred to as gold plating, will increase the overall project risk.
For example, there may have been a good reason the client did not want
this added functionality. Perhaps the client's computer system cannot
support more advanced functionality. Additionally, the added code may
interfere with other functionality since it was not integrated with the
original build plan. Of the available choices, the best course of action is to
remove the added functionality and ensure that the design plan is followed
in the future. Note that if the project manager believes that this added
functionality would benefit the customer, then the suggestion can be made
to the customer. The customer can then decide whether or not to add the
functionality and accept any impact on other project constraints. If the
customer approves the added functionality, a change request should be
submitted and processed through the Perform Integrated Change Control
process.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 36 of 89
The project manager is managing the research and development of a new cancer
screening test. The project manager would like to determine whether the processes
currently in use in the project are effective in meeting the quality requirements
specified by the customer.
What does the project manager need to obtain first to make this determination?
Hint Unmarked
The scenario implies that the project manager wants to perform Manage
Quality which is the process of translating the quality management plan
into executable quality activities that incorporate the organization?s
quality policies into the project. Ensuring that the processes used in the
project are effective in meeting the quality requirements needed to satisfy
the customer is one of the goals of the Manage Quality process. However,
to do this, the Manage Quality process uses the quality control
measurements gathered during the Control Quality process. Therefore, to
determine whether the processes currently in use in the project are
effective in meeting the quality requirements needed to satisfy the
customer, the project manager first should obtain the quality control
measurements. Note that typically outputs from the executing processes
become inputs to the monitoring and controlling processes. However, in
this case, quality control measurements are an output from the Control
Quality process, a monitoring and controlling process, and an input to the
Manage Quality, an executing process.
During an inspection of a project deliverable, the team detects the same defect in the
deliverable that has already been identified during a previous inspection. The project
manager is confused about how this could have happened since a change request was
approved to repair the defect. After discussing the issue with the team, the project
manager learns that the team never implemented the approved change request.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 37 of 89
Hint Unmarked
Inspections carried out as part of the Control Quality process may uncover
defects or areas of noncompliance with project requirements, which, in
turn, may generate change requests. It is the responsibility of the project
team to ensure that those approved change requests are implemented and
properly tested, completed, and certified. In this scenario, the project
manager learns that an approved change request was never implemented.
Retrospectives, root cause analysis, and quality reports would not have
prevented this issue but could be used to help the team avoid such a
mistake in the future. An approved change request review would have
provided the project manager and the team a mechanism for verifying that
the approved change request was implemented and is, therefore, the best
answer to the question asked.
The team has just reported to you that they have completed the Plan Quality
Management process. You review their work and see that they have produced the
quality management plan, and made the necessary updates to the project management
plan and project documents.
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 38 of 89
The question suggests that the Plan Quality Management process was
performed, and an element of this process was missed. Quality metrics are
a project document that serves as one of the outputs of the Plan Quality
Management process. This document was not mentioned in the scenario.
All of the other outputs are stated as being completed. A quality metric, an
input to the Manage Quality and Control Quality processes, specifically
describes a project or product attribute and how these processes will verify
compliance with it. Therefore, quality metrics are what was most likely
missed by the project team.
One may argue that quality metrics should be part of the quality
management plan just like the quality roles and responsibilities. While this
may sound counter-intuitive, the PMBOK® Guide describes quality metrics
as a separate standalone document. The complete list of the components
of the project management plan vs. project documents can be found on
page 89, Table 4-1. Project Management Plan and Project Documents.
You are managing a project to build a house for a private client. A few weeks before the
project's planned completion date, the client calls and asks to add an outdoor sauna to
the property. You analyze the project schedule and determine that this change would
be fairly easy to implement without having an impact on the completion date.
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 39 of 89
What if the cost of adding the sauna will exceed the budget the client had
in mind for the project? What if the project does not have enough resources
to implement the change? These and other questions should be asked
when a change request is properly evaluated. Therefore, of the choices
provided, reviewing the requested change against all project constraints is
the best answer to the question asked.
You have been asked to lead a product development project which will use an agile
framework. Currently, you are in the process of drafting the project charter, and you
want to bring together stakeholders and subject matter experts to discuss perceived
project risk, success criteria, and other topics.
Hint Unmarked
The question states that the project charter is being drafted which implies
that the project is in the initiation stage. A focus group is a data-gathering
technique which may be beneficial in the development of the project
charter. Focus groups bring together stakeholders and subject matter
experts to learn about the perceived project risk, success criteria, and
other topics in a more conversational way than a one-on-one interview.
The expectations of the project manager do not change in an adaptive
(agile) environment, but control of the detailed product planning and
delivery is delegated to the team who, in the scenario described, can be
considered the subject matter experts. The incorrect answer choices
represent meetings that would take place after project initiation has been
completed or are not held in a group setting. Therefore, of the available
choices, scheduling a focus group is the best answer.
A multi-phase project has reached a phase gate. The key project stakeholders want to
determine if the phase has met its success criteria and if the project should proceed to
the next phase.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 40 of 89
Hint Unmarked
You are in the process of establishing a knowledge management system for your
project.
Which of the following actions will be the least beneficial in this process?
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 41 of 89
You are leading a large project that involves many stakeholders. You want to get two
new team members up to speed with the overall dynamics of the project and engage
effectively with the project stakeholders.
Ask the team members to record any issues they encounter into the issue log
Review the stakeholder register with the new team members
Schedule a meeting with the new team members and all project stakeholders
Submit a change request to update the stakeholder engagement plan
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 42 of 89
You are facilitating a meeting with your project team to develop the team charter. At the
start of the meeting, a team member states, "I don't understand the importance of this
meeting. We are all professionals, and this isn't our first project working together.
Wouldn't our time be better spent getting an early start on project execution?" The
body language of the other team members suggests that they agree with the
comments.
As long as everyone is in agreement, then let's skip the team charter and get ahead
of schedule
Let's use the team charter from our last project as a starting point and then update
it as necessary
The team charter is required by the project management office (PMO) for all projects
The team charter will eliminate any potential conflicts which will improve our
productivity
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 43 of 89
You are leading a project to build an oil pipeline in a foreign country. You want to
outsource some of the construction work to local contractors and are in the process of
preparing the bid package for prospective sellers.
Which of the following documents would you leave out of the package?
Hint Unmarked
Preparing the bid package for prospective sellers implies you are carrying
out the Plan Procurement Management process. Bid documents along with
the request for proposal (RFP), procurement statement of work (SOW),
source selection criteria, independent cost estimates are among the
outputs of this process. These documents are also among the inputs to the
Conduct Procurements process. However, not all of these documents are
provided by the buyer to the prospective sellers. Sometimes, to benchmark
procurements, the buying organization develops independent cost
estimates either internally or using external resources such as a
professional estimator. Buyers do not usually provide these estimates to
the prospective sellers since a benchmark range may prejudice the sellers
into proposing prices that do not work well with their business model and
resources. The buyer uses these benchmark estimates principally to verify
if bids are reasonable, or if a large number of outliers indicate an issue with
procurement processes or communications. Thus, of the choices provided,
leaving the independent cost estimates out of the bid package makes the
most sense and is, therefore, the best answer to the question asked.
You are developing the communications management plan for a construction project.
You want to determine the information needs of the project stakeholders, specifically
focusing on the type and the format of information that will be required to
communicateb with the stakeholders. c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 44 of 89
Hint Unmarked
The question implies that you are performing the Plan Communications
Management process with the development of the communications
management plan. Communication requirements analysis is one of the
tools and techniques that may be used in this process. Analysis of
communication requirements determines the information needs of the
project stakeholders. These requirements are defined by combining the
type and format of information needed with an analysis of the value of that
information. Therefore, of the available answer choices, conducting a
communication requirements analysis is the best course of action in this
scenario.
The following Gantt chart displays the schedule for a software upgrade project. The
system analysis was completed on August 12th, but the system design and development
activities are still in process as of October 3rd. Once the product is developed, the
project team will need to test and deploy it, which must be completed by October 17th.
The method used to determine the earned value is based on percent complete.
-$650
$3,750
$650
$3,100
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 45 of 89
Cost variance (CV) is the earned value (EV) minus the actual costs (AC). The
current earned value is the sum of the earned values for every activity that
has either been completed or is in progress. Thus, the earned value can be
calculated by multiplying the activity's percent complete by the activity's
planned value. The actual costs are the total costs of individual activities.
Note, since the scenario mentions that the method used to determine the
earned value is based on percent complete, the earned value of a partially
completed work package is calculated by multiplying the planned value of
the work package by its the percent complete.
Therefore, the cost variance (CV) in this scenario is $650. Since the CV is a
positive value, the project is running under planned costs. Note, the
information about testing and deployment that must be completed by
October 17th is irrelevant for selecting the correct answer.
A servant leader has just been assigned to an upcoming product development project
and believes that the project is well-suited to Kanban. However, the development team
is unfamiliar with this approach.
Hint Unmarked
The scenario implies that the servant leader wants to use a project
management approach with which the development team is unfamiliar. If
the servant leader believes that the Kanban approach is the best
methodology for the project, then the servant leader has the responsibility
to ensure that the development team has the appropriate training to
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 46 of 89
You are developing the project scope statement. You have specified the deliverables for
the project, included the requirements under which the deliverables will be accepted,
and explicitly stated what is out of project scope.
Project exclusions
Acceptance criteria
Project approval requirements
Product scope description
Hint Unmarked
According to the scenario, of the four elements listed above, three have
already been specified in the project scope statement. The only missing
element is the product scope description.
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 47 of 89
Hint Unmarked
The scenario implies that the project manager is about to start one of the
iterations of the Acquire Resources process and needs to understand the
availability of the project team members. The project documents include
the resource calendars which serve as an input to the Acquire Resources
process. A resource calendar identifies the working days, shifts, start and
end of normal business hours, weekends, and public holidays when each
specific resource is available. Information on which resources are
potentially available during a planned activity period is used for estimating
resource utilization. Resource calendars also specify when and for how
long the identified team and physical resources will be available during the
project. Of the available choices, looking at the resource calendars
provides the best source of information for the project manager about the
availability of the team members to perform project work.
Which of the following would be the most beneficial for this project?
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 48 of 89
Hint Unmarked
The question implies that the project manager is carrying the Manage
Quality process. Quality improvements can occur based on findings and
recommendations from the quality control processes, the findings of the
quality audits, or problem-solving in the Manage Quality process. Plan-do-
check-act and Six Sigma are two of the most common quality
improvement tools used to analyze and evaluation opportunities for
improvement. A person with the Six Sigma Black Belt certification is an
individual that has been trained to apply Six Sigma tools and techniques
for process improvement. Six Sigma improves quality by identifying and
eliminating the causes of defects and minimizing the variability in a
manufacturing process. A Six Sigma process is one in which 99.99966% of
the products of the process are free of defects. Of the available choices,
only consulting with a certified Six Sigma Black Belt expert would be
beneficial in reducing the defect rate of a manufacturing process.
During project planning of a large, complex project, project management best practices
were rigorously and thoroughly followed. During project execution, the project
experienced several critical risks, which were foreseen and previously identified.
Despite the meticulous planning, the project failed to achieve the established objectives
due to these realized risks.
The realized risks had not been identified earlier in the project
The risk responses were poorly devised
The qualitative risk analysis was inadequate
There was little or no action taken to manage the known risks
Hint Unmarked
Proper attention to the Implement Risk Responses process will ensure that
the agreed-upon risk responses are actually executed. A common problem
with Project Risk Management is that project teams spend effort in
identifying
b and analyzing risks andcdeveloping risk responses, theng risk f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 49 of 89
responses are agreed upon and documented in the risk register and risk
report, but no action is taken to manage the risk. The incorrect answer
choices all represent activities that occurred during project planning,
which according to the scenario, was meticulous and followed all project
management best practices. Therefore, the most likely reason for the
project failing to meet objectives is the result of inadequate attention to
the Implement Risk Responses process during project execution. Thus,
among the available choices, taking little or no action to manage the
known risks is the best answer to the question asked.
What is the best way for the project manager to address this situation with the team
member?
Hint Unmarked
Note, the correct answer choice, "discuss the issue with the team
member", does not specify whether the discussion is formal or informal.
However, it is reasonable to assume that such a discussion would be
informal. Regardless, whether the discussion is formal or informal, of the
choices provided, discussing the issue with the team member is the best
answer to the question asked.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 50 of 89
Which of the following actions is the project manager least likely to perform in this
situation?
Hint Unmarked
You are leading a software development project where the developers are colocated
within rented office space. Writing the code is taking longer than anticipated, and you
have contacted the landlord requesting to rent the office for another week.
Unfortunately, the landlord tells you that the office is already booked. You capture the
problem in the project documents.
Record
b the issue in the issue log c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 51 of 89
Hint Unmarked
During a bidder conference, a supplier asks why a section is missing from the request
for quotation (RFQ). Upon realizing that the section is indeed missing, the project
manager becomes flustered and stumbles through a brief reply. When the seller
responses were received, all but three prospective suppliers fail to address the missing
section.
Hold the bidder conference again, and explain the importance of the point that was
initially missed
Select from the three vendors that submitted complete proposals
Send a revised RFQ to all prospective suppliers and allow them the opportunity to
resubmit their proposals
Extend the deadline and allow all of the vendors to resubmit their proposals
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 52 of 89
In this scenario, sending the new RFQ to all suppliers, clarifying the critical
point that was previously missing, and receiving updated responses to the
RFQ would be fair to all suppliers. It may not be practical or cost-effective
to conduct another bidder conference, especially as other aspects of the
project have already been covered in the prior bidding conference. Apart
from fairness, re-issuing the RFQ ensures that requirements are
understood. Another benefit of sending out a revised RFQ would be
receiving more viable bids from other vendors. Therefore, among the
available options, the best course of action for the project manager is to
send a revised RFQ containing the new information to all prospective
suppliers and allow them the opportunity to resubmit their proposals.
You are leading a project to develop a new web application. Together with your project
team you reprioritize the product backlog, determine velocity for the past iterations,
and adapt your work plans accordingly. Additionally, you facilitate retrospectives every
two weeks.
Which of the following processes describes the work you are performing?
Monitor Risks
Manage Quality
Control Schedule
Develop Schedule
Hint Unmarked
Adaptive life cycles, such as the agile approach, use short cycles to
undertake work, review the results, and adapt as necessary. These cycles
provide rapid feedback on the work approaches and suitability of
deliverables, and generally involve iterative scheduling. The project
described in the scenario is using an agile approach as evidenced by the
use of the retrospectives, backlog, and iterations. When an agile approach
is used, Control Schedule is concerned with conducting retrospectives to
correct and improve processes, reprioritizing the backlog, determining the
velocity in each iteration, and adjusting the plans accordingly. Therefore,
of the choices provided, the work you are performing is best described by
the Control Schedule process.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 53 of 89
Which of the following components of the template are you likely to tailor the most?
The rules of performance measurement, the summary milestones, and the key
deliverables
The organizational procedures links, the units of measure, and the project
organization charts
The schedule model development, the release and iteration length, and the
reporting formats
The project schedule model maintenance, the level of accuracy, and the level of
precision
Hint Unmarked
The question suggests you are carrying out the Plan Schedule Management
process. The schedule management plan is the primary output of this
process. The schedule management plan establishes the criteria and the
activities for developing, monitoring, and controlling the schedule. Of the
choices presented, only the schedule model development, the release and
iteration length, and the reporting formats are components of the schedule
management plan. All three of these components would merit significant
tailoring to reflect an adaptive approach to project management. The
project schedule model development specifies the scheduling
methodology and the scheduling tool used to develop the schedule model.
For an adaptive approach, the schedule model will be a selected series of
activities needed to complete a high-priority subset of the project scope
that can deliver value quickly. The release and iteration length determine
the time-boxed events that must be completed and how long it will take to
release the iteration. The reporting formats will be driven by the adaptive
schedule model and the iteration length.
The other answer choices contain components that are not part of the
schedule management plan.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 54 of 89
A project team performs monthly risk audits for a project, where a large number of
identified risks have been realized. So far, the risk responses have been appropriate,
and the reserves sufficient. An executive for the requesting organization criticizes the
project manager improper risk audits, stating that only independent, external resources
should perform risk audits.
Explain that risk audits can be performed either internally or externally as long as
they follow the project management plan
Agree with the executive and submit a change request to update the project
management plan to have the audits conducted externally
Follow the guidance provided by the executive and hire a team of external auditors
to conduct the risk audits going forward
Explain that if the current risk audits are not sufficient, then a comprehensive
project audit should be carried out
Hint Unmarked
Risk audits are among the tools and techniques of the Monitor Risks
process. Risk audits are used to consider the effectiveness of the risk
management process. The project manager is responsible for ensuring that
risk audits are performed at an appropriate frequency as defined in the
project's risk management plan. Risk audits are typically performed by the
project team and may be included during routine project review meetings
or may form part of a risk review meeting, or the team may choose to hold
separate risk audit meetings. In this scenario, since conducting risk audits
internally is not contrary to project management best practices, and the
current risk audit process has proven to be effective, there is no reason to
agree with the executive. Therefore, among the available options, the best
course of action is to explain to the executive that risk audits can be
performed either internally or externally as long as they follow the project
management plan.
Note that any stakeholder can request a change to the project. It is not
clear from the question if the executive's comment constitutes a change
request. If, after explaining the rationale for continuing with the current
internal risk audits, the executive still wants external auditors performing
the risk audits, the project manager should follow the change control
process established for the project. However, in this situation, the change
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 55 of 89
request would likely be rejected since there is no reason to believe that the
project would benefit from hiring external auditors to perform the risk
audits.
Question 73 - Qid 6112819, Risk Management, 2. Process, 11.1 Plan Risk Management
You are developing the risk management plan for your project. In support of this
process, you need to determine the acceptable level of overall project risk exposure.
Develop a set of responses to individual project risks to mitigate overall project risk
Hint Unmarked
You meet with your team to determine the life cycle for your project. After analyzing the
best way to define and manage requirements, develop deliverables, handle changes,
control risk and cost, and engage key stakeholders, the decision is made to select a
hybrid life cycle.
With the project life cycle selected, how will the product be delivered?
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 56 of 89
Hint Unmarked
Predictive and agile project life cycles differ from one another in several
aspects. One of them is the way the project product, service, or result is
delivered. Predictive projects develop plans up-front and deliver only a
single final product (service or result) at the end of the project. Agile
projects, on the other hand, deliver working product increments as
frequently as possible based on the highest value to the customer.
Everything in between is defined as a hybrid delivery. With hybrid project
life cycles, the product can be divided into subsets, which are delivered at
either pre-defined intervals or as soon as the subsets are completed.
Therefore, of the choices provided, with the hybrid life cycle selected,
delivering the result of the project as subsets of the final product
constitutes the best answer to the question asked.
As a project manager, you are in the process of estimating the team resources that will
be required for your project. The challenge you are having is that, due to the nature of
the project and the selected development approach, only a few of the top levels of the
WBS have been identified with the remainder to be progressively elaborated
throughout the project.
What is the best approach to determine the team resource requirements for the
project?
Check the organizational process assets for similar projects and use analogous
estimating
Apply bottom-up estimating using the work breakdown structure (WBS) as a guide
Utilize parametric estimating for the individual work packages within the existing
WBS
Decompose the WBS down to the work package level during initial project planning
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 57 of 89
The question suggests that you, as the project manager, are performing the
Estimate Activity Resources process and that a hybrid development
approach is being utilized. When incorporating agile practices within an
overarching traditional waterfall approach, the project scope may be
progressively elaborated throughout the project, and the work breakdown
structure (WBS) may not be fully decomposed during initial project
planning. Under such circumstances, one viable approach to estimating
team resource requirements would be to utilize the analogous estimating
technique. If there are past similar projects, the organizational process
assets (OPAs) should contain detailed information that could be used for
analogous estimating.
You are part of a project team designing a new type of a vehicle. You are about to begin
work on a work package for the braking system of the vehicle and want to review the
acceptance criteria before starting the work.
Hint Unmarked
A work package is the lowest level of the WBS and provides a general
description of the work to be completed by this work package. The WBS
dictionary supplements the WBS by including more detailed information
for each work package or other WBS components. The WBS dictionary is an
output of the Create WBS process and provides information such as the
description of work, schedule milestones, quality requirements, and
acceptance criteria for each work package. Therefore, the acceptance
criteria for the work package to be completed are described in the WBS
dictionary.
Note, the wording of the question, "You are about to begin work on a work
package...", suggests that project execution has already begun, thus
implying the project management plan including all its components (such
as the scope baseline that includes the WBS dictionary) has been finalized
and approved.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 58 of 89
A project to construct an assembly line is nearly complete. The project manager closes
procurements, shares the final project report, updates the lessons learned repository,
and obtains feedback from the relevant stakeholders.
Send formal written notice to the vendors that the contracts have been completed
Hint Unmarked
The question implies that the Close Project or Phase process is underway.
Actions and activities necessary to transfer the project's products, services,
or results to the next phase or production and/or operations is one aspect
of project closure. Correctly answering this question is an exercise in the
process of elimination. The incorrect answer choices represent activities
that have already been completed by the project manager in this scenario.
Among the available choices, only transferring the completed assembly
line to operations represents a closing activity which has yet to be
completed, making it the best response to the question asked.
Question 78 - Qid 6113034, Risk Management, 2. Process, 11.5 Plan Risk Responses
A project team is mulling over two risk responses for inclusion in the risk register. The
first risk response has two criteria that must be met and costs $5,000. The second risk
response has four criteria that must be met, but only costs $2,000.
What action is the project team least likely to take in selecting the best risk response?
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 59 of 89
In this scenario, the project team is deciding between two different risk
responses for inclusion in the risk register, which suggests that the project
team is currently performing the Plan Risk Responses process. Alternatives
analysis, cost-benefit analysis, and multicriteria decision analysis are all
techniques which are commonly used during the Plan Risk Responses
process to select risk responses. Note, the question is asking for the action
that the project team is 'least' likely to take in selecting the risk response. A
Monte Carlo simulation is a data analysis technique where a computer
model is iterated many times, with the input values chosen at random for
each iteration driven by the input data, including probability distributions
and probabilistic branches. Outputs are generated to represent the range
of possible outcomes for the project. However, in this case, there are only
two options under consideration which can serve as inputs for the
simulation. Thus, a Monte Carlo simulation would only be able to perform
two unique iterations rather than the many iterations required to produce
a probability distribution. Using a Monte Carlo simulation is not
appropriate when only a small, finite number of options are under
consideration. Since there are only two options under consideration, in
this case, a Monte Carlo simulation is not the appropriate tool for the
project team to use in selecting the best risk response.
To acquire resources for the project, the project manager consults the resource
management plan. The plan calls for the scrum master to be assigned to the team.
However, the only individual in the company qualified to serve as a scrum master has
already started working on another project, and her functional manager does not
cooperate on a potential resolution.
The project manager should have checked the project's resource calendars for the
availability of the scrum master.
The project sponsor should have directed the project manager to serve as both the
project manager and the scrum master.
The scrum master should have refused to work on the other project knowing that
she is the only qualified resource in the company.
The availability of the scrum master should have been negotiated between the
functional manager and the project manager during project initiation.
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 60 of 89
The question implies that the project manager is carrying out the Acquire
Resources process. In situations where a key resource is required for the
success of the project, that resource can be-preassigned to the project in
the project charter or during initial project planning. In the scenario, the
scrum master was assigned to a different project, and the functional leader
is refusing to find a suitable resolution. Had the project manager
negotiated with the foundational manager for the resource ahead of time,
the resource might have still been available. Note that it might be a little
unusual for a project to have a project manager and a scrum master, but it
might be necessary for a complex project that will utilize a hybrid project
framework.
A project team is using the Stacey Complexity Model to map the degree of uncertainty in
the project and select the appropriate project life cycle. As the meeting progresses, it
becomes evident that while the requirements are well-known, the team is unfamiliar
with the technology required to implement them. As a result, the team selects an
adaptive project life cycle.
Where on the Stacey Complexity Model did the team most likely map the project?
(Please note that on the real PMP exam you may be asked to provide your answer by
clicking the correct area in the image. But here in the simulator, we are asking you to
select the answer below.)
A
B
C
D
Hint Unmarked
A project life cycle is the series of phases that a project passes through
from its start to its completion. (Note, the word "phase" in this context is
used differently from how it's used in multi-phase projects). The project life
cycle provides the basic framework for managing the project. Predictive,
iterative, incremental, adaptive, hybrid are examples of a project life cycle.
The selection of the life cycle depends on project characteristics. There are
various models that can be used to describe project characteristics. One of
them is the Stacey Complexity Model. The model addresses the degree of
uncertainty as it relates to the project requirements on the one hand and
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 61 of 89
Your project team members are writing software code together as a pair and reviewing
each other's work to determine if the code conforms to the requirements
documentation.
Accepted deliverable
Acceptance criteria
Work performance data
Verified
b deliverable c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 62 of 89
Hint Unmarked
Writing software code together as a pair and reviewing each other's work is
known as pair programming. This practice is often used on agile projects.
As far as traditional project management is concerned, the scenario
suggests the team is in the Control Quality process and is using the tool of
inspection, such as peer reviews, to determine if the software conforms to
documented standards. The goal of the Control Quality process and the
inspection is to verify the correctness of deliverables thereby producing the
output of verified deliverables. The verified deliverables then become an
input to the Validate Scope process to determine if the deliverables meet
the acceptance criteria for formal acceptance by the customer or sponsor.
Formal acceptance of the verified deliverables produces an output from
the Validate Scope process called accepted deliverables. Since the team is
conducting a code review to determine the correctness of the software, the
result of their efforts will be a verified deliverable.
As part of the Direct and Manage Project Work process, the project manager conducts
an iteration planning meeting. The meeting is dominated by the most senior developer
who frequently and sharply interrupts the other team members. The project manager
wants to ensure that during the next iteration planning meeting all voices are heard.
Discuss the issue with the senior developer, and for the next meeting allocate equal
amounts of time for each team member to speak
Inform the senior developer's functional manager about this unacceptable behavior
and request that the manager take disciplinary action
Post a copy of the team's social contract in the meeting room and review the
contents at the start of the next iteration planning meeting
Invite the sponsor to the next iteration planning meeting to have the senior
developer be more thoughtful in the presence of the sponsor
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 63 of 89
It should be noted that there are many ways of addressing the issue
described in the question. The project manager probably should have been
more proactive during the meeting to ensure that all voices are heard.
Alternatively, the project manager might have spoken to the senior
developer in private about his behavior to address the issue. Regardless, of
the available options, posting the team charter, and reviewing the contents
before the iteration planning meeting is the 'best' answer.
The scrum master, business analyst, programmers, and testers have been assigned to a
product development project. The performing organization is well-versed with the
traditional waterfall framework but will incorporate scrum for the software
development phase of the project.
What is the best strategy to ensure that all of the scrum roles and responsibilities are
served in the project?
Remove the business analyst from the software development phase since that role
is only associated with waterfall project management
Mentor the business analyst to serve in the role of the product owner during the
software development phase since those roles are closely aligned
Request that one of the programmers serve as the voice-of-the-customer for the
purposes of prioritizing the items in the product backlog
Ask the most experienced tester to approve or reject the deliverables during the
sprint review as testers are typically most familiar with the product
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 64 of 89
The roles typically associated with scrum include the scrum master,
development team, and product owner. In this scenario, the product
owner is the role that is vacant. Although the business analyst is a role that
is typically associated with waterfall projects, the business analyst can also
provide support to the team leader and product owner in an agile
environment. The business analyst typically works with the customer to
determine and refine project requirements and develop the requirements
documentation. When agile methodologies are employed, the business
analyst may also assist with the development and refinement of the
product backlog. With scrum, the product owner is responsible for
managing the product backlog and ensuring that it is prioritized according
to business value. In this case, the business analyst will likely have much of
the necessary skill set to serve as the product owner but will be lacking in
knowledge and experience with agile. Thus, the scrum master should
mentor the business analyst to close any agile knowledge gaps and ensure
that all of the duties related to a product owner are fulfilled.
The construction project has many people and specialized teams at the worksite every
day. Frequent communication between the team leads is critical for safety and
efficiency.
Which agile ceremony can this project incorporate to increase timely cross-functional
communication?
Iteration reviews
Risk-based spikes
Retrospectives
Daily standups
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 65 of 89
the last daily standup, work to be done today, and any impediments to
progress. This daily communication and coordination of activities may help
the project manager, team, and other individuals and groups working on
the construction site maintain safety and efficiency, as requested by the
question.
At times over a project life cycle, the team must adopt a few agile ceremonies. The aim
is to communicate quicker in times of tight deadlines. Unfortunately, team members
are not getting the information needed during the ceremonies.
What is the best option to confirm that the information is received and understood?
Validate with the team that the information was captured and facilitate feedback
discussions
Spread out the ceremonies over months between each event to ensure
comprehension
Mandate that all project team members update the information radiators after each
ceremony
Reduce the number of project team members that attend the ceremonies
Hint Unmarked
Hybrid projects take the best options from the various project
management approaches available. For example, the scenario describes a
traditional project, in which the team is requested to adopt agile
ceremonies to speed up communication cycles during tight deadlines.
Occasionally, especially as teams are first learning the methods, there may
be gaps in communication and action. Project managers can assist in
improving the effectiveness of agile ceremonies by validating with all the
participants that the information shared with them was received and
understood. Confirming that the ceremony is meeting its objectives and
facilitating the necessary feedback loops supports the purpose. Those
feedback actions may be gradually lessened as the ceremonies are
internalized by the team and relevant stakeholders.
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 66 of 89
How might the project manager's role change with respect to integration management?
Act as a servant leader by determining the relative size of the story points of the
items in the product backlog
Delegate the control of the detailed project work planning and product delivery to
the project team members
Ensure that the project team members each have specific tasks assigned to them
and recorded in a Gantt chart
Hint Unmarked
During the upcoming sprint, measure velocity and, if it decreases, discontinue pair
programming and reprimand the team members
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 67 of 89
Invite the project sponsor and other key stakeholders to demonstrate the increased
collaboration between the project team members
Submit a change request to update the communications management plan with the
new agile practice of pair programming
At the end of the upcoming sprint, revise the burndown chart, evaluate the
productivity, and update the lessons learned register
Hint Unmarked
Note, the scenario implies the project is managed using hybrid methods.
Therefore, incorporating pair programming may or may not require an
approved change request. This would depend on how explicit the project
management plan is in this case.
A project manager is leading a daily standup meeting with a scrum team as part of the
Direct and Manage Project Work process. A developer raises an impediment stating that
he is struggling with the software code necessary to authenticate users on the sign-in
page. The developer indicates that the impediment could result in a schedule delay to
the current sprint.
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 68 of 89
Write the software code for the developer since it is the project manager's
responsibility to remove impediments
Submit a change request to update the schedule baseline to reflect the delay
caused by the impediment
Move the user authentication feature back into the project backlog and ask the
product owner to reprioritize it
Recommend that the scrum team members use swarming as a technique to clear
the impediment
Hint Unmarked
Note, when all of the team members leave their current tasks to help one
developer, it is reasonable to assume that their tasks may also be delayed.
While this assumption makes the correct answer arguable, of the choices
provided, suggesting swarming is the project manager's best course of
action.
Collecting requirements for the project and creating the WBS has been a daunting task
because stakeholders' needs are vague and are only expressed in the most general
terms due to the nature of the project. As a result of this uncertainty, the project
manager is concerned about excessive changes, wasted work, and rework anticipated
during project execution.
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 69 of 89
Develop a project scope statement and decompose it down to the work package
level as part of initial project planning
Request that the project team use an iterative and incremental approach to product
development with short feedback loops
Implement a robust change control system to only allow for the most important
changes to be incorporated into the product
Generate an activity list from what is currently known and use the Kanban board to
break the activities down to their tasks
Hint Unmarked
The scenario describes a situation where, due to the nature of the project,
the requirements are not clearly understood and can only be expressed at
a high level. This situation presents an obstacle to collecting project
requirements and creating a fully decomposed work breakdown structure
(WBS) as part of initial project planning. Projects with a high level of
uncertainty in requirements benefit from iterative and incremental
approaches that allow the project scope to evolve over the course of the
project. Demonstrating smaller increments of the product to the relevant
stakeholders allows for short feedback loops to keep the evolving product
or result of the project in alignment with stakeholder needs and
expectations. For example, the project team might use prototypes to gain
early feedback on the requirements. All of the incorrect answer choices
represent strategies that would be unrealistic for a project with a high
degree of uncertainty in the project requirements. Note that incorporating
an agile lifecycle within a project management plan would make this a
hybrid project.
Create a questionnaire and send it out to all of the stakeholders to determine the
project requirements
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 70 of 89
Perform a job shadowing exercise with the intended end-users of the existing
software
Hint Unmarked
The question implies that the project manager is carrying out the Collect
Requirements process for a hybrid project. Workshops can be used to
quickly define cross-functional requirements and reconcile stakeholder
differences. The interactive nature of a workshop can be effective in
helping the project manager build a consensus among the stakeholders.
When agile methodologies are being incorporated into a project, a
requirements gathering workshop may take the form of a story-writing
workshop, where required functionality is captured in the form of a user
story. Of the available choices, only a requirements workshop would meet
the project manager's criteria for being able to 'quickly' gather feedback,
and have the interactivity necessary to reconcile stakeholder differences
and help build a consensus.
Before mandating any agile methods to be used in a project, what should be done first?
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 71 of 89
You are establishing the relative priorities of individual risks identified in the project.
Which of the following tasks is the least likely to impact this prioritization?
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 72 of 89
Team members are frequently changing during the long timeline of a multi-phase
project. The project manager is questioning whether to include agile practices to
accommodate the changes.
Ensure project finances are secured for the next project phase
Reduce the team size to nine people, plus or minus two
Target a smaller project as a proof of concept to test the feasibility
Evaluate the benefits of incorporating agile practices
Hint Unmarked
Midway into project execution, new cybersecurity laws take an immediate effect and
require audits of the system. The project has a well thought out project management
plan. The audits may come at any time throughout the system?s development.
What is the best way for the project manager and team to address the risk of audits
disrupting the project plans?
Hint Unmarked
Plan-driven managed projects can utilize some of the tools and techniques
from agile methodology to support their project management.
Incorporating agile methods with traditional plan-driven methods would
b the overall project management
make c approach hybrid. In the scenario
g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 73 of 89
described, the project team could use the agile technique of a spike. A
spike is a short timeboxed effort established to address a risk, explore
possible solutions, answer a question, or gather information, to name but a
few common examples. While this may sound counter-intuitive, of the
choices provided, addressing the audit as a spike is the best answer to the
question asked.
A plan-driven project has many deliverables planned to be released at the end of the
phase. The project manager wants to ensure that the deliverables are completed as
expected.
Which agile practices can the project manager recommend to the team to make certain
that the deliverables are completed and delivered as expected?
Hint Unmarked
A project manager facilitates a discussion with the team about experimenting with
some agile practices in their plan-driven project. A suggestion of incorporating daily
standups is on the table. The team members, however, are unsure of what is expected
of them.
What can the project manager suggest the project team members do prior to the daily
standup? b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 74 of 89
Hint Unmarked
The project team is undergoing an agile transformation. This requires the team
members to maintain their original project plans in the current management tool, but
also enter performance data in the new tool built around agile practices. The team
identifies that the information in the two tools is out of sync. This risk has been
identified earlier in project planning.
Accept the risk since agile values individuals and interactions over processes and
tools
Recognize that the risk has now become an issue and implement the planned
response
Conduct a probability and impact assessment to determine a risk score
Communicate to the project sponsor that work may be delayed due to clerical
errors
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 75 of 89
Projects in a program are using various project management approaches, such as plan-
driven, agile, hybrid. The project teams are complaining that because of that, the team
members must enter the same work, hours, risks, and other data in multiple tools. The
redundant work is impeding on their productivity time.
Direct the teams to continue entering the data in the various systems
Determine what tools and data provide the appropriate oversight
Switch all projects in the program to the agile project management approach
Pause all data entry until a valuable solution can be determined
Hint Unmarked
Data and metrics are very important to track, monitor, and control any
project. This is true regardless of which project management approach is
used. When teams and organizations shift from one approach to another or
use various approaches for different projects with a program, it is common
for multiple tools and software to be used. The intent of these tools is to
assist the teams, stakeholders, and project organizations in managing their
data and methodology. However, too many or divergent tools may cause
more administration and maintenance. Therefore, project and program
governance must determine which data is most relevant and worth the
teams' time. The balance between collecting and communicating project
data with the resource load to enter and upkeep the data can be difficult,
butbneeded decision. c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 76 of 89
Which project management approach should the project manager select for this
project?
Waterfall
Agile
Hybrid
Phased
Hint Unmarked
Your sponsor has committed to building a high-speed rail from one major inland city,
Azules, to the coast. You have two possible routes, either Brazos or Corazon.
Given the costs, odds, and rewards of high demand and low demand of each route in
this decision tree, what is the expected monetary value of the route to Brazos?
1.6 billion
-2 billion
0.8 billion
10.8 billion
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 77 of 89
The value of each possible outcome is the net path value. Remember:
when you "net" something, you should consider both positive and negative
flows. The formula to compute net path value is to subtract the path
reward minus the cost of its decision.
For building the route to Brazos, here are the steps to compute the
expected monetary value:
EMV = 0.8B
Other answer choices do not properly factor the net path value (the payoff
minus the cost of the decision) and sum the effects.
Below is the completed decision tree with all the net path values and the
resulting expected monetary value of each choice. The EMV for the Brazos
route is 0.8 billion, and the EMV for the Corazon route is -8.8 billion (note
this is a negative number). Since the path with the largest expected
monetary value is the Brazos route at 0.8 billion, that is the best choice.
Question 101 - Qid 6113147, Integration Management, 2. Process, 4.4 Manage Project
Knowledge
Senior leadership has returned from a conference where they have learned about the
agile practice of retrospectives. Even though the organization does not manage any
projects in an agile manner, they mandate that from now on this ceremony is included
in all projects.
How should the outputs from the retrospectives be stored and managed?
Senior leadership determines the location of the outputs and who may access the
contents
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 78 of 89
The project team stores the outputs in a location that the project manager can
control and limit changes
The project team determines a location that is accessible for relevant stakeholders
to view and track
The project manager establishes the location and allows the customer to view and
make recommendations
Hint Unmarked
Question 102 - Qid 6113155, Resource Management, 1. People, 9.0 Project Resource
Management
The resource management plan for an international project calls for a scrum team to be
colocated during the regular workweek. However, after five sprints were completed, the
project manager got a change request approved to cut costs by transitioning the team
to a virtual environment working remotely from their homes with the start of the sixth
sprint.
After the team begins working remotely, what will be the best method to understand
the impact of the change on the team's productivity?
Check the product burndown chart to look for any changes to the trendline
Calculate the CPI at the end of each sprint to determine the change in the team's
productivity
Review the product burnup chart to compare velocity before and after the change
Update the project schedule network diagram to reflect the changes in the team's
environment
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 79 of 89
Hint Unmarked
The scenario describes a hybrid project where a change in the project team
environment might have an impact on the productivity of the team. Burn
charts are one way of visualizing the project's performance over time.
Depending on the information that needs to be understood, different
approaches can be used to build burn charts. Sprint burn charts typically
show the story points completed by day over the course of a single
iteration. Release burn charts document the work completed for each
iteration over the course of a release. Finally, product burn charts typically
display the story points completed for each iteration over the course of the
entire project. Burndown charts record the work remaining (usually in the
form of story points) over time. Burnup charts show the work completed by
the project team over time. Burnup charts are better for understanding
team productivity than burndown charts as they document the work
completed by the project team. Burndown charts can provide a distorted
view of team productivity as an increase/decrease in project scope will
affect the trendline independent of the work actually accomplished.
Therefore, of the available choices, the best way to understand the
productivity impact of the change to the work environment is to review the
product burnup chart.
Question 103 - Qid 6113157, Resource Management, 1. People, 9.1 Plan Resource
Management
As part of the Plan Resource Management process, project team members hold a
brainstorming session to charter working agreements. The team identifies 37
agreements that include communication guidelines, decision-making and conflict
resolution processes, core hours, a definition of a story point, how and when user
stories will move through the Kanban board, etc.
Verify that all of the project team members support the working agreements and
document the agreements in the project charter
Review the team's working agreements at the start of every daily standup and
during the sprint review meetings
Ask the project team members for their top five to ten agreements and document
b
the information in the team charter c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 80 of 89
Hint Unmarked
The question describes a project team that creates the team's working
agreements as part of the Plan Resource Management process. The
working agreements represent the team's social contract and should be
documented in the form of a team charter. The team charter is an output of
the Plan Resource Management process. One best practice for the team
charter is to limit the working agreements to the top five to ten items. A
comprehensive list of 37 agreements will likely be too cumbersome to be
effective, and the really important agreements may get lost among less
important items. Therefore, it would be appropriate to ask the project
team for their top five to ten agreements and then capture them in the
form of a team charter.
Question 104 - Qid 6113159, Resource Management, 1. People, 9.5 Manage Team
Submit a change request to revise the project management plan to eliminate the
requirement for retrospectives
Take a proactive step in improving his own emotional intelligence (EI) to become a
more effective leader
Reduce the story size by splitting user stories and use relative estimation with the
entire team to estimate
Lead a training session with the project team members to help them become
emotionally competent
Hint Unmarked
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 81 of 89
The scenario describes a hybrid project carried out according to the project
management plan with the deliverables developed using sprints. The
question implies that the project manager lacks emotional competence, as
exemplified by his failure to control his emotions during the sprint
retrospectives. The project manager must learn to control his own
emotions and lead by example before he can expect emotional
competence from the project team members. Taking action, such as
investing in training to improve his emotional intelligence (EI), would be
one positive step in addressing the leadership problem. Once the project
manager has addressed his own lack of emotional competence, he can
then work with the project team members to develop the team's EI.
Improving EI will likely have a positive effect on the turnover rate as well.
A project is six months into its nine-month projected duration. The project manager
reports that the project is at least three months behind schedule because certain key
stakeholders were resistant to consequential changes due to the project.
What might have been done differently during project planning to avoid this situation?
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 82 of 89
Two team members are arguing over how to organize the work packages in the work
breakdown structure (WBS). One says the work packages should be arranged in the
order the work is planned to be carried out, while the other insists the order of the work
packages in the WBS does not matter. The two ask the project manager for advice.
Hint Unmarked
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 83 of 89
You are leading a project to design a high-efficiency solar cell. The project needs copper,
silver, and silicon among other materials. You have ordered custom-built
manufacturing equipment, secured permission to install a solar array on the roof for
testing, and reserved a conference room for daily stand-up meetings.
Resource histogram
Resource management plan
Resource assignment matrix
Physical resource assignments
Hint Unmarked
It can be inferred from the question that the process of acquiring resources
is being performed. One of the outputs from the Acquire Resources process
is physical resource assignments. Documentation of the physical resource
assignments records the material, equipment, supplies, locations, and
other physical resources that will be used during the project. Based on the
description provided by the question, the physical resource assignments is
what has been accomplished.
Question 108 - Qid 6113733, Cost Management, 2. Process, 7.3 Determine Budget
During project execution, several unexpected issues have developed and are now
threatening the project schedule and budget.
What is the best course of action for the project manager to address the issues?
Hint Unmarked
The total project budget includes the cost baseline plus the management
reserves. The cost baseline is comprised of the work package estimates
andb contingency reserves. The contingency
c reserves are allocatedgfor f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 84 of 89
Note, the scenario describes issues, while the explanation refers to risks.
Prospective PMP aspirants should keep in mind that the questions on the
real PMP exam may have such discrepancy in their wording.
Question 109 - Qid 6113755, Risk Management, 2. Process, 11.2 Identify Risks
To produce the deliverables, the project will procure goods and services from outside
the organization. The project manager has instructed the team to develop a
comprehensive list of individual project risks related to those procurements.
Hint Unmarked
Question 110 - Qid 6113796, Cost Management, 2. Process, 7.4 Control Costs
How much bmore will it cost to complete thecproject if the cost performanceg remains f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 85 of 89
unchanged?
$160,000
$149,254
$120,000
$89,254
Hint Unmarked
Understanding what exactly the question asks is the key to answering the
question correctly. The last sentence of the question starts with "How
much more will it cost to complete the project...", implying we are
requested to find the estimate to complete (ETC). The ETC can be
calculated as follows:
Selecting the correct formual for the EAC is another key to answering this
question correctly. The last sentence ofthe question ends with "...if the cost
performance remains unchanged?", implying that the formula for the EAC
should consider the cost performance index (CPI), i.e.:
A major dispute arises with a vendor on a project. The project manager claims that the
vendor has failed to perform its contractual obligations, while the vendor complains
that the project is behind on payments.
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 86 of 89
Hint Unmarked
Question 112 - Qid 6125216, Resource Management, 1. People, 9.5 Manage Team
You want to recognize the contributions of some of the high-performing team members
so far in the project.
Which of the following do you need to guide you through this process?
Hint Unmarked
The scenario implies you are carrying out the Manage Team process.
Manage Team is the process of tracking team member performance,
providing feedback, resolving issues, and managing team changes.
Organizational process assets (OPAs) are an input to this process.
Examples of the OPAs associated with the Manage Team process include
certificates of appreciation, corporate apparel, and other organizational
perquisites. Recognizing the contributions of the high-performing team
members is part of the Manage Team process. The project manager can
use the relevant OPAs to guide her through this process and provide the
team
b members with the appropriate c rewards and recognition. g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 87 of 89
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 88 of 89
(http://twitter.com/pmexamtips)
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner
(PMI-ACP)®, and Certified Associate in Project Management (CAPM)®
(https://www.facebook.com/PrepCast)
(http://www.pinterest.com/pmexamtips/)
Group Discounts
(https://www.project-
management-
prepcast.com/group-
discounts)
PM PrepCast Discount
Coupon
b c
(https://www.project- g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020
Free PMP Practice Exam Questions - 120 Sample Test Questions Page 89 of 89
management-
prepcast.com/discount-
coupon)
Scholarships
(https://www.project-
management-
prepcast.com/scholarships)
b c g f
mhtml:file://D:\Downloads\Free PMP Practice Exam Questions - 120 Sample Test Questio... 12/2/2020