RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : Material Pembongkaran dan Pemasangan Paving kembali


LOKASI : BATANG

HARGA SATUAN JUMLAH HARGA


NO. JENIS PEKERJAAN VOLUME SATUAN ( Rp.) ( Rp.)
(Rp.)
1 2 3.00 4 5 6=(3X4X5)

A MATERIAL PEKERJAAN FISIK


1 Tanah Urugan 20.45 m3 90,000.00 1,840,500.00
2 Pasir 6.82 m3 300,000.00 2,046,000.00
3 Sewa Stamper 2.00 hari 350,000.00 700,000.00
4 Bata + semen + Cat 1.00 ls 500,000.00 500,000.00
5 Semen+Pasir+kricak 1.73 m3 850,000.00 1,468,800.00
6 Laker Roda Pagar 24.00 bh 80,000.00 1,920,000.00
SUB TOTAL A 8,475,300.00
B TENAGA PEKERJAAN FISIK
1 Tenaga Bongkar Paving Lama 136.30 m2 5,000.00 681,500.00
2 Tenaga Urugan Tanah 20.45 m3 25,000.00 511,250.00
3 Tenaga Pelapisan Pasir 136.30 m2 3,000.00 408,900.00
4 Tenaga Bongkar Kanstin Taman 1.00 ls 350,000.00 350,000.00
5 Tenaga Stamper pemadatan 136.30 m2 5,000.00 681,500.00
6 Tenaga Pemasangan Bata+plesteran+acian+dinding bibir tempat torn 1.00 ls 400,000.00 400,000.00
7 Tenaga Pemasangan kembali Paving 136.30 m2 20,000.00 2,726,000.00
8 Tenaga Pelur area masuk mobil 14.40 m2 50,000.00 720,000.00
9 Tenaga Pemasangan kanstin taman kembali 1.00 ls 450,000.00 450,000.00
10 Tenaga bongkar Pasang roda pagar 1.00 ls 1,000,000.00 1,000,000.00
SUB TOTAL B 7,929,150.00
TOTAL PEKERJAAN 16,404,450.00

Note : RAB yang tertera tidak termasuk biaya keamanan, perijinan, IMB, biaya2 ormas, LSM (apabila ada)

Semarang, 1 OKTOBER 2021


Hormat kami,

Victorius H. Saputro, ST
Direktur