000-ZA-E-M09406 - B MS For Lighting & Power Outlet
000-ZA-E-M09406 - B MS For Lighting & Power Outlet
1: Approved
CONTRACTOR review result by 2: Approved with comments
3: Rejected
Technical Discipline 1 2 3
HSE Dept. 1 2 3
QA/QC Dept. 1 2 3
1: Approved
2: Approved with comments
3: Rejected
COMPANY
review result by Date Name Signature
1 2 3
SIVA
B 07/28/19 SAVAD ALI G.PANDIYAN
SUBRAMANIAN
A 07/03/19 SAVAD ALI G.PANDIYAN FARRUKH RASHEED
Table of Contents
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 2 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
1. GENERAL.............................................................................................................................................. 3
1.1. Purpose..................................................................................................................................3
1.2. Personnel Duties and Responsibilities...................................................................................3
1.3. Reference Standards and Codes............................................................................................4
1.4. List of Drawings and Documents............................................................................................8
2. SCOPE OF WORK................................................................................................................................. 10
5.2. Manpower...........................................................................................................................19
1. GENERAL
1.1.Purpose
The scope of this Method Statement is to establish, detail and explains the plan and
methodologies involved during all operations activities in order to get a satisfactory result.
The contractor reserves his right to adapt his methods for Installation, Testing of Lighting
and Power Outlet System in accordance with the guide line provided by project
Specifications, Saudi Aramco Standards and procedures with enumerate the safety
requirements and work procedure.
DE - Discipline Engineer E/I - will ensure that the works are performed safely as per the latest
approved drawings and specifications.
DF - Discipline Foreman E/I - will ensure that his crew has to follow the safe work procedure
and works are carried out as per the latest approved drawings. Attend Safety Tool Box
Talks with HSE Department and construction crews.
CO - Crane operator – (ARAMCO certified) shall be responsible for the safe as well as efficient
operations of the crane.
R1 - Rigger 1 – (ARAMCO certified) shall be responsible for the all safe lifting and rigging
throughout the critical lift process activities, he will ensure that his crew will perform a
safe work supporting the crane operator during the whole activities.
QCI - Quality Control Inspector - will ensure that all the work is executed according to the PQP
and that the requirement of quality dossier is fulfilled. The RFI is issued in advance as
per the QCP. All previous activities related to this is covered with RFI, inspected
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 4 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
accepted and signed off by all parties. Latest revision of the IFC drawings, lighting,
power outlet layout and copy of approved MOS are available at site.
Scaffold Supervisor (Aramco Certified) - will ensure that all the scaffolding activities
performed as per Aramco standard by his crew and he is also responsible to release the
safe working scaffold to the working team with proper tagging system and record.
HSE Supervision - will ensure that the works are performed safely as per the latest Company
requirements.
Construction Supervision - will ensure that the works are performed as per the latest
approved method statement in a safe and efficient manners.
IR : INSULATION RESISTANCE
SAES-P-111 : GROUNDING
SAES-P-123 : LIGHTING
IEC 62504 : GENERAL LIGHTING – LEDS AND LED MODULES – TERMS AND
DEFINITIONS
Document Client
Name Number Title
B39-EC-A- BA-
047853 668716.001 B39-USI-LP-003- AREA LIGHTING PANEL SOUTH UTILITIES
B39-EC-A- BA-
047854 668716.010 B39-USI-LP-003- AREA LIGHTING PANEL SOUTH UTILITIES
B39-EC-A- BA-
047855 670528.FS1 B39-USI-LP-003- AREA LIGHTING PANEL SOUTH UTILITIES
B39-EC-A- BA-
047856 670528.003 B39-USI-LP-006- NORMAL AREA LIGHTING PANEL SOUTH UTILITIES
B39-EC-A- BA-
047857 670529.FS1 B39-USI-LP-006- NORMAL AREA LIGHTING PANEL SOUTH UTILITIES
B39-EC-A- BA-
047858 670529.003 B39-USI-LP-007- NORMAL AREA LIGHTING PANEL SOUTH UTILITIES
B39-EC-A- BA-
047859 670530.FS1 B39-USI-LP-008- NORMAL AREA LIGHTING PANEL SOUTH UTILITIES
B39-EC-A- BA-
047860 670530.004 B39-USI-LP-008- NORMAL AREA LIGHTING PANEL SOUTH UTILITIES
B39-EC-A- BA-
047862 670531.002 B39-USI-LP-009- EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047863 670531.003 B39-USI-LP-009- EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047864 670533.001 B39-USI-LP-011- EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047865 670534.004 B39-USI-PP-004- SMALL POWER PANEL SOUTH UTILITIES
B39-EC-A- BA-
047866 289586.001 B39-ROS-LP-001- NORMAL LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047867 289587.001 B39-ROS-LP-003 - EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047868 289596.001 B39-ROS-LP-003 - EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047869 289597.001 B39-ROS-LP-002 - AREA LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047872 809780.001 B39-USI-LP-020 - EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047873 670808.001 B39-USI-LP-018 - EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047874 670808.004 B39-USI-LP-018 - EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047875 809780.004 B39-USI-LP-020- NORMAL LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047876 809778.001 B39-USI-LP-019- EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA-
047877 809778.004 B39-USI-LP-019- EMERGENCY LIGHT PANEL SOUTH UTILITIES
B39-EC-A- BA- B39-USI-LP-021- NORMAL LIGHT PANEL SOUTH UTILITIES
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 9 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
047878 809781.004
B40-EC-A- BA-
041774 668721.007 B40-WS2-LP-016- AREA LIGHTING WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042416 668764.002 B40-WS1-LP-011- EMERGENCY LIGHT. WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042417 668764.005 B40-WS1-LP-011- EMERGENCY LIGHT. WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042418 668796.005 B40-WS1-LP-012- NORMAL LIGHT.PANEL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042419 668796.006 B40-WS2-LP-012- NORMAL LIGHT.WATER INJECTION PUMP STATION & NORTH
B40-EC-A- BA-
042420 668766.FS1 B40-WS2-PP-033- SMALL POWER PANEL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042421 668766.005 B40-WS2-PP-033- SMALL POWER PANEL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042422 669129.004 B40-WS2-LP-013- NORMAL LIGHTING PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042423 669129.005 B40-WS2-LP-013- NORMAL LIGHTING PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042424 289613.FS1 B40-WS1-NLP-101- NORMAL LIGHTING PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042425 289613.001 B40-WS1-ELP-101- EMERG LIGHTING PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042426 289613.002 B40-WS1-ELP-101- EMERG LIGHTING PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042427 289613.003 B40-WS1-ELP-101- EMERG LIGHTING PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA- B40-WS1-ELP-101- EMERG LIGHTING PNL WATER INJECTION PUMP STATION &
042428 289613.004 NORTH
B40-EC-A- BA-
042429 289614.FS1 B40-WS1-NPL-101- NORMAL LIGHTING PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042430 289614.001 B40-WS1-NPL-101- NORMAL LIGHTING PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA-
042431 289614.002 B40-WS1-NPL-101- NORMAL LIGHTING PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA- DISINVEST B40-WS2-LP-012- NORMAL LIGHTING PNL WIP STATION & NORTH
042636 668796.003 UTILITIES
B40-EC-A- BA- DISINVEST B40-WS2-LP-012- NORMAL LIGHTING PNL WIP STATION & NORTH
043283 668796.001 UTILITIES
B40-EC-A- BA- DISINVEST B40-WS2-LP-012- NORMAL LIGHTING PNL WIP STATION & NORTH
043284 668796.005 UTILITIES
B40-EC-A- BA-
043287 668766.001 DISINVEST B40-WS2-PP-033- SMALL POWER PNL WIP STATION & NORTH UTILITIES
B40-EC-A- BA- DISINVEST B40-WS1-LP-011- EMERGENCY LIGHT PNL WIP STATION & NORTH
043289 668764.001 UTILITIES
B40-EC-A- BA- B40-WS1-LP-011- EMERGENCY LIGHT.PNL-DISINVEST WIP STATION & NORTH
043317 668764.002 UTILITIES
B40-EC-A- BA- B40-WS1-LP-011- EMERGENCY LIGHT.PNL-DISINVEST WIP STATION & NORTH
043318 668764.003 UTILITIES
B40-EC-A- BA-
043319 668796.002 B40-WS2-LP-012- NORMAL LIGHT PNL DISINVEST
B40-EC-A- BA- B40-WS2-LP-013- NORMAL LIGHTING PNL DISINVEST WIP STATION & NORTH
043342 669129.FS1 UTILITIES
B40-EC-A- BA- B40-WS1-NLP-101- NORMAL LIGHTING PNL DISINVEST WIP STATION & NORTH
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 10 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
2. SCOPE OF WORK
2.1.General Requirements
1. Confirm correct circuit connections and configurations for all lighting and power branch
circuits.
2. Mounting method of fixtures shall be based on the best arrangement for illuminance, as well
as easy and safe access during installation and maintenance.
4. SAES-J-902 minimum separation requirements between Electrical and Instrument cables shall
be complied.
5. Wires and cables identification at termination for lighting and power outlet systems shall
follow SAES-P-104 Section 6.11.
6. The lighting fixture and power outlets will be identified with suitable approved label provision
and checked against the data sheet for classification.
7. Where fixtures are to be installed in hazardous areas, particular attention shall be paid to the
certification to ensure they are suitable for installation in the classified area.
8. Where industrial or vapor-proof fittings are specified, their NEMA/IP rating will be checked to
confirm the correct protection degree is being applied.
9. Equipment such as floodlight columns, which are supplied in sections, or have accessories
supplied loose, will be checked against the particular inventory.
10. Unless otherwise stated, all tests shall be conducted by the Electrical Testing Engineer and pre-
commissioning department.
11. Lighting fixtures installation shall follow the IFC drawing and typical installation standards.
1. Support brackets, posts and stanchions will be checked against the detailed drawings and
located in accordance with the layout drawings.
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 12 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
2. Particular attention will be paid to interference with access ways, handrails and possible
sources of vibration.
3. Accessibility for maintenance will be checked and it will be ensured that fixtures are not
installed above equipment with moving parts.
4. Upon installation, the support will be checked to ensure rigidly and fixture-fixing points are
available.
6. Prior to installing the supports, the fixing points and foundations will be checked to ensure
their line and level is correct. Cable entries will be checked to ensure they are clear of debris.
2.3.Lighting Fixtures
1. Lighting fixture will be inspected to ensure they are installed in the manner shown on the
detailed drawings, all accessories are installed and where applicable, protection guards have
been fitted.
3. The orientation will be checked to ensure the correction area is illuminated and not obscured
by pipes and/or structures.
4. All exposed conduits for lighting system shall be rigid steel conduits.
5. For cables/wiring termination refer to panel board schedule. Ensure that continuity and
megger value is recorded.
2.4.Power Outlets
1. Receptacles will be checked against the Project data sheets prior to installing.
2. Receptacles installed in Hazardous areas will be checked to ensure their suitability and rating
for that area.
4. Power sockets installed at outdoor areas shall be checked to ensure the correct NEMA/IP and
protection degree.
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 13 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
5. Polarity testing for power outlets shall be performed at energization time to verify right
installation, connection and phasing. Polarity test to be done with approved polarity tester.
1. The emergency lighting system shall be verified and functionally tested with minimum
duration of one-and-one-half hours in the event of normal power failure.
2. Ensure that fixtures required for exit illumination/emergency egress lighting shall be supplied
from separate sources of power for Control Rooms, Process Areas, Switchgear Rooms and
where required by SAES-M-100.
3. Ensure that prior to connection to fixture and energization, the insulation resistance of lighting
cables shall be tested, using an adequate Megger equipment, to ensure no leakage between
phases and to earth.
4. Before energization the correct lighting system shall be checked to ensure the right installation
as per IFC drawing, all conduits shall be secured and rigid and all support correctly fixed and
tighten.
5. Ensure that the lighting system will be energized and the illumination levels checked against
those specified, using a Lumens or Lux meter. The initial field measurement after installation
shall be no less than the specified illuminance divides~ by the light loss factor (LLF) from Table
1 of SAES-P-123 and other factors utilized in the design. The illumination levels outlined in
Table 4 of SAES-P-123 are the required maintained minimum lighting levels at the specified
work plane for each location.
6. The test will be conducted and recorded on S. Aramco Pre-Commissioning Form for process
and Plant Areas and for Open and Indoor Areas.
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 14 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
3.9. JSA for Installation, Testing of Lighting and Power Outlet System (000-ZA-E-K-09717)
1. All the work force shall have completed their Saipem and Aramco safety induction
training before commencement of work.
2. All personnel shall wear the correct and appropriate and approved PPE at all times
when engaged at the job site location.
3. Perimeter of work area(s) will be safety taped or barricaded and appropriate signage
displayed, (e i: Authorized Person Only) other signage appropriate to the task being
undertaken shall also be displayed, flashing lights shall be provided at night at trench
locations.
4. Aramco certified Work Permit Receivers shall be engaged for permit work
requirements and will be present at the job site location for the duration of activities.
5. Aramco certificated Crane/Fork Lift Operator and Riggers will be used, at all times for
the duration of the work activities.
6. All lifting tools shall be load tested and certificated prior to start any activities.
7. Original Permit to Work, Method Statement and Risk Assessment and/ or JSA shall be
displayed at worksite in visible locations.
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 15 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
8. Job Specific Tool Box Meetings shall be conducted before starting any activity.
9. Gas testing shall be done before starting the work and at interval recommended or
required by Saudi ARAMCO for the complete duration of associated work.
10. All electrical equipment, lifting tools and tackles, etc., shall be inspected and tagged the
monthly color code every month.
11. Crane shall be inspected and certified in accord with the ARAMCO standard
requirements.
12. Trailer shall be inspected and certified in accord with the ARAMCO standard
requirements.
13. Boom truck shall be inspected and certified in accord with the ARAMCO standard
requirements.
14. Fork Lift shall be inspected and certified in accord with the ARAMCO standard
requirements.
15. All Permit to Work will be closed after the completion of the activities, or the end of
each shift unless otherwise extend by special consent of foreman. Work Permit will
automatically close during any accident happens in the plant and a new permit will be
applying for the same activities when the area is cleared.
16. Closure of associated permits shall be ensured for works such as de-isolations, box-up
of confined spaces etc.,
17. Maintain the necessary standards of cleanliness and tidiness within the workplace, at
all times for the duration of the work activities.
18. Contractor Site Safety Officer shall be present at the job site at all times while workers
are performing, their work activities and associated responsibilities.
19. Contractor Safety Officers shall be assigned to monitor safety condition of the work
area, and are authorized to stop any activities if the conditions at the site changed to
such an extent that continuing of working would be determined to be unsafe.
A plentiful allocation of cooling water shall be provided in the cooling water cans.
Cooling water cans shall be placed in the easy accessible location to all.
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 16 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
Heat stress protection shall be inducted in the tool box meeting regularly
4. QA / QC DOCUMENTATION
QC inspector shall be ensuring all Lighting and Power outlet conform to the
applicable Projects Standards and material receiving inspection has been
conducted, covered with RFI and accepted.
The QC inspector shall use the relevant SAIC checklist to record his inspection
findings. Any deficiencies noted shall be logged into the Logbook (QEIL System)
and issued to Construction and ensure the comments are rectified before issuing
RFI.
Prior to installation on site, the lighting fixtures will be identified and checked
against the data sheet.
Where fixtures are to be installed in hazardous areas, particular attention shall
be paid to the certification to ensure they are suitable for installation in the
classified area.
Where industrial or vapor-proof fittings are specified, their I.P. rating will be
checked for suitability.
Equipment such as floodlight columns, which are supplied in sections, or have
accessories supplied loose, will be checked against the particular inventory.
Unless otherwise stated, all tests shall be conducted by the Electrical Testing
Engineering.
Support brackets, posts and stanchions will be checked against the detailed
drawings and located in accordance with the layout drawings.
Particular attention will be paid interference with access ways, handrails and
possible sources of vibration.
Accessibility for maintenance will be checked and it will be ensured that fixtures
are not installed above equipment with moving parts.
Upon installation, the support will be checked to ensure rigidly and fixture-fixing
points are available.
Concrete foundations shall be installed as required.
Prior to installing the supports, the fixing points and bases will be checked to
ensure their line and level is correct. Cable entries will be checked to ensure they
are clear of debris.
Lighting fixture will be inspected to ensure they are installed in the manner
shown on the detailed drawings, all accessories are installed and where
applicable, protection guards have been fitted.
The fixture and support assembly will be checked to ensure stability.
The orientation will be checked to ensure the correction area is illuminated and
not obscured by pipes and/or structures.
All exposed conduits for lighting system shall be rigid steel conduits.
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 19 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
5. RESOURCES
Item Qty
Crane As required
Fork Lift As required
Trailer Truck As required
Man Lift As required
Boom Truck As required
Lifting Gears As required
Rigging Material As required
Electrical Tool Box with complete tools As required
Fire Extinguisher As required
Fire Blanket As required
Electrical Hammer As required
Drilling Machine(120V) As required
Grinding Machine(120V) As required
Welding Machine(120V) As required
Cutting Machine As required
Measuring tape As required
Wrenches As required
Galvanized Spray As required
Bending Machine(120V) As required
Threading Machine(120V) As required
Bench Vise As required
PROJECT / UNIT JOB No.
Khurais Area Facilities Expansion & 032184
Satellite GOSP Project
PLANT LOCATION Sheet DOC. No.
Khurais - SAUDI ARABIA 20 of 20 000-ZA-E-M09406
TITLE: Revision: DATE:
METHOD STATEMENT FOR BROWN / GREEN FIELD B 07/28/2019
INSTALLATION, TESTING OF LIGHTING AND
POWER OUTLET SYSTEM
5.2. Manpower
Item Qty
HSE Officer 2
Crane Operator 1
Fork Lift Operator 1
Trailer Truck Operator 1
Man Lift Operator 1
Boom Truck Operator 1
Rigger 2
Fitters 4
Scaffolders 8
Helpers 8
Flagmen 4
Fire Watchers 2
Scaffolder Foremen 2
Scaffolder Supervisor 1
Scaffolder Inspector 1
Electrical Supervisor 1
Electrical Foremen 2
Electrical Skilled Technician 10
E/I Superintendent 1