II Activity Time (Days) Immediate Predecessors: A+B+E+G+I
II Activity Time (Days) Immediate Predecessors: A+B+E+G+I
II Activity Time (Days) Immediate Predecessors: A+B+E+G+I
(a)
B(4)
A(1)
1 22
D(7)
A+C+F+G+I = 17 NO
A+D+F+G+I = 21 NO
A+B+E+G+I = 22 YES(critical path)
As A+B+E+G+I has longest duration in comparison to other so it will be the critical path.
(c )
3 weeks and 1 day it will take to complete the task
(d)
Activities Slack:-
Activities Time Activity Nodes ES EF LS
C 3 2-4 1 4 6
D 7 2-5 1 8 2
F 2 4-6 8 10 9
H 9 5-7 8 17 9
3
6
F(2)
C(3) G(7)
4
d
5 H(9) 7 I(4) 8
LF Slack = LF-EF or it can be written as LS-ES
9 5
9 1
11 1
18 1
huh
Items purchased from a vendor cost $20 each, and the forecast for next year’s demand is 1,000
units. If it costs $5 every time an order is placed for more units and the storage cost is $4 per unit per year
a) What quantity should be ordered each time?
b) What is the total ordering cost for a year?
c) What is the total storage cost for a year?
Q=
EOQ = 2500
50
100
100
QUESTION 4
Job (In Order of Arrival) Processing Time (Days)
A 3
B 4
C 2
D 6
E 1
SOLUTION
Utilization metric= Total job work processing time/sum of total flow time
32.00%
Utilization metric= Total job work processing time/sum of total flow time
44.44%
Utilization metric= Total job work processing time/sum of total flow time
41.03%
Utilization metric= Total job work processing time/sum of total flow time
26.67%
ys/number of jobs
days
ys/number of jobs
days
ys/number of jobs
days
ys/number of jobs
days
Given
Plant Coordinate Volume
Plant A (150, 75) 6000
Plant B (100, 300) 8200
Plant C (275, 380) 7000
Answer
To determine the location for Plant D using the centroid method (COG)
200
150
0
50 100 150 200 250 300
X axis