COLLEGE OF ADMINISTRATIVE AND FINANCIAL SCIENCES

Period: Test 2
Tr Trimester: 3rd, AY 2020-2021
H HOMEWORK/CASELETS/ASSIGNMENT NO.2

COURSE CODE COMP625/BSIS632 COURSE TITLE IS-PROJECT MANAGEMENT


SECTION TIME DAYS ROOM
STUDENT NAME ID NO. DATE

TOPIC PROJECT SCHEDULE MANAGEMENT

ASSIGNMENT 1. Given the table of activities below which represents the project activities of a software
DIRECTION &
development project, draw the networking diagram (05 MARKS), compute CPM
REQUIREMENT/S
(Identify the ILOs to
be assessed at the (05MARKS), ES, EF (05 MARKS), LS, LF (05 MARKS)
end of each
requirement.
Include the rubric or
marking scheme for
each
item/requirement.)

Prepared by : Reviewed / Checked by: Verified by: Approved by:


1
1
Eng. Abdulaziz Al Saadi VISHWAS CHAKRANARAYAN, PhD. VINODH NATARAJAN, PhD. Dr. Marluna. Urbio, PhD.
Course Teacher Programme Head Associate Dean College Dean
:Answers

Compute ES, LS, EF, LF and Slack of each activity as follows Earliest Start (ES) is calculated by forward pass method
as latest of the predecessors Earliest Finish (EF). Latest Finish (LF) is calculated using backward pass method as
earliest of the successors Latest Start (LS). Earliest Finish (EF) = Earliest Start (ES) + Activity's duration Latest Start
(LS) = Latest Finish (LS) - Activity's duration Slack = Latest Finish - Earliest Finish

Activity Immediate Predecessor Duration ES EF LS LF Slack Critical Activity Successo r


A 8 0 8 0 8 0 Yes B,C,D
B A 13 . 8 21 8 21 0 Yes E,F
C A 9 8 17 20 29 12 H,I
D A 12 8 20 10 22 2 G
E B 14 21 35 27 41 6 J
F B 8 21 29 21 29 0 Yes H,I
G D 7 20 27 22 29 2 H,I
H C,F,G 12 29 41 29 41 0 Yes J
I C,F,G 9 29 38 42 51 13 K
J E,H 10 41 51 41 51 0 Yes K
K 1,J 7 51 58 51 58 0 Yes