Professional Documents
Culture Documents
Iet-Rpg 2015 0542
Iet-Rpg 2015 0542
Research Article
Yongxi Zhang1, Zhao Yang Dong1, Fengji Luo2 , Yu Zheng3, Ke Meng1, Kit Po Wong4
1School of Electrical and Information Engineering, University of Sydney, NSW 2006, Australia
2Centre for Intelligent Electrical Networks, University of Newcastle, Newcastle, NSW 2384, Australia
3Electric Power Research Institute, China Southern Power Grid Company, Guangzhou 510080, People's Republic of China
4School of Electrical, Electronic, and Computer Engineering, University of Western Australia, Perth, WA, Australia
E-mail: fengji.luo@newcastle.edu.au
Abstract: In recent years, the battery energy storage system (BESS) has been considered as a promising solution for mitigating
renewable power generation intermittencies. This study proposes a stochastic planning framework for the BESS in distribution
networks with high wind power penetrations, aiming to maximise wind power utilisation while minimise the investment and
operation costs. In the proposed framework, the uncertainties in wind power output and system load are modelled by the
Monte–Carlo simulation, and a chance-constrained stochastic optimisation model is formulated to optimally determine the
location and capacity of BESS while ensuring wind power utilisation level. Then, the Monte–Carlo simulation embedded
differential evolution algorithm is used to solve the problem. Simulation studies performed on a 15-bus radial distribution system
prove the efficiency of the proposed method.
2.2 Load forecast error modelling The first item indicates BESS investment cost which is decided by
the energy capacity, shown as (5). The second item denotes the
The load forecast errors are assumed to follow the Gaussian daily operation and maintenance cost which is proportional to the
cumulative distribution shown as (3), where, σL and μL are energy capacity of BESS, shown as (6). The capital factor A is
statistical mean and standard deviation of load demand; lc and uc introduced to convert the initial payments into annual terms. For
are the minimum and maximum value of load levels, respectively. consistency, the annual BESS energy capacity cost is also
normalised in daily basis.
��
� − ��
�� � = exp − (3) �
��� ��� �inv = ���bat max (5)
��
The curve fitting, maximum likelihood estimation method is �opm = ∑ �bat max��
, (6)
applied to estimate the distribution parameters for simulating the
system wind power output and load demand. ��
� +�
�= �� + (7)
2.3 Micro turbine units availability +� −
The unit availabilities of the MT units are taken into consideration. where d denotes the real interest rate and Nr is the time span of the
Random outage rates of generation units are often presented using BESS project. The BESS allocation problem is constraint by BESS
the binomial distribution [16]. Outage rate and availability rate of investment budget constraint and the location constraint,
the mth MT unit are represents as qm and 1 − qm, respectively. A
two state continuous Markov model is used in this paper to ���bat max ≤ CAP (8)
simulate the transitions between the operative and outage states
during the daily scheduling period [17]. The scheme diagram is �bat ∈ Φ (9)
shown in Fig. 2, where L states are represented and the transition
intensity from state i to j is denoted as Aij.
The third item Qop shown in (10) is a daily scheduling problem
aiming to minimise the expected daily operation cost under
IET Renew. Power Gener., 2016, Vol. 10 Iss. 8, pp. 1105-1113 1107
© The Institution of Engineering and Technology 2016
different scenario. Once the energy capacity and location of BESS BESS integration will reduce the power generation from MT units
is determined, the charging/discharging power of BESS, MT units hence decrease the emission. The emission cost function can be
output power, power bought from substation and wind power expressed as (17), where CO2, NOx and SO2 are the equivalent
curtailment are optimised at hourly time interval. The system emission cost functions.
operational costs are consists of six terms: the MT generation cost, The daily scheduling problem is subjected to following
system power loss cost, wind curtailment penalty cost, energy constraints:
purchase cost from the substation, BESS life cycle depression cost,
and emission cost of the MT units, the above cost functions can be i. System operation constraints
formulated by (11)–(17):
(a) Load balance equations
�op = Exp ∑ ��gen + ��loss + ��pen + ��grid + ��depre + ��emi (10)
�∈Ω The total electrical energy generation should satisfy load
consumption and power loss at each time period t:
• MT generation costs
� � �
The MT generation cost is expressed with cost coefficients ai and ∑ ����, � + �loss
�
,� = ∑ �
��� �
, � − �cur, � + ∑ ��� �,
�= �= �=
bi: (18)
�
+ �ch / dis, �
� �
��gen = ∑ ∑ ������, � + �� (11)
�= �= (b) Power flow equations:
For clarity, we assume the wind power has the priority to serve where Gij and Bij are the real and imaginary parts of the bus
system load. When the total system generation exceeds load admittance matrix, and ij is angle difference between the ith and
demand, the excess wind power will be absorbed by the BESS. the jth buses. For calculation simplicity, in this work, the reactive
Once BESS reached its maximum capacity, the excess wind power power injection/consumption of BESS units and wind turbine units
has to be curtailed. are ignored.
� (c) Line current constraint
��pen = ∑ ��cur ��cur , (13)
�= The current magnitude of each branch must lie within their
allowable range to maintain system stability:
• Energy purchase cost from the substation
�min ≤ ����, � ≤ �max (21)
�
��grid = ∑ �
�buy , ��buy (14)
(d) Bus voltage constraint
�=
• BESS life cycle cost
The voltage magnitude of each node must lie within their allowable
The life cycle is defined as the number of total charge/discharge range:
cycles of BESS. The life cycle depression cost is in this work is
calculated based on the total energy usage, which is the total �min ≤ ����, � ≤ �max (22)
charging/discharging power of BESS. According to the impacts of
discharge rate on battery life in [18], the total energy charging/ (e) Reverse power flow constraint
discharging capability of battery is remained stable within the
reason depth of discharge, e.g. 70%. The cost coefficient factor δ of Reverse power flow would increase system loss while leading
the battery life cycle depression is calculated as overheat of feeders, hence there is strict restrict on the reverse
power flow export limitation. This constraint guarantee that no
CAP reverse power flow through the substation transformer:
�= (15)
�bat max ⋅ Lifecycle
≤ ��� ≤ ��max (23)
�
��depre = ∑ �ch �, �dis �
, , ⋅� (16)
ii. Micro turbine constraints
�=
• Pollution emission cost The active/reactive power output of ith MT units is constrained by
the generation capacity, expressed as:
� �
�emi = ∑ ∑ �
CO ��� �
, � + NO� ���, � ���, min ≤ ����, � ≤ ���, max (24)
�= �=
(17)
�
+ SO ����, � ���, min ≤ ���, � ≤ ���, max (25)
Table 2 Emission factors for micro-turbine generation units decreased to some extent.
Fuel consumption coefficients for MT units, g/kWh
SO2 NOx CO2
0.000928 0.6188 184.0829
1110 IET Renew. Power Gener., 2016, Vol. 10 Iss. 8, pp. 1105-1113
© The Institution of Engineering and Technology 2016
Fig. 6 Comparison of generator output power with/without BESS (Case I)
level βi decreases, BESS capacity goes up due to the fact that the
larger BESS has to be installed to accommodate the excess wind
energy. Consequently, the total costs are increase. Generally
speaking, there is no known to all optimal allocation plan scheme
in an uncertain situation. The investors need to make a trade-off
between wind power utilisation level and investment cost. The
different planning schemes are provided with different confidence
levels for the investors to make the decision (Table 5).
Table 4 Bess allocation optimisation results (confidence level: 80%, scenarios: 1000)
BESS Type LA Zn/Br
elapse time 16 Hour
case I II I II
battery location 11 9 11 4 11 9 11 9
energy capacity, MWh 1.68 0.68 1.78 0.91 1.68 0.68 1.78 0.89
power loss, MW 0.91 1.15 0.89 1.06
battery cost, $/day 1444.9 1645.91 2054.1 2323.8
emission cost, $/day 210.35 208.35 210.35 208.35
thermal power generation cost, $/day 6596.83 6444.6 6583.15 6428.5
power purchase cost, $day 2089 2043 2016 1972
wind power curtailment cost ($/day) 45.897 41.35 45.35 41.37
battery life cycle depression cost, $/day 10.9 10.9 10.7 10.7
total cost, $/day 10489 10509 11008 11091
wind power utilisation level 83.96% 87.96% 82.65% 86.75%
IET Renew. Power Gener., 2016, Vol. 10 Iss. 8, pp. 1105-1113 1111
© The Institution of Engineering and Technology 2016
Table 5 Computational results with different confidence
level (wind utilisation level: 80%, BESS type: L/A)
Confidence Investment Expected Energy
level βi, % costs per day, operation capacity, MWh
$ costs per day,
$
0 1832.5 11,026 1.78 0.78
10 1644.7 10,626 0.99 1.39
20 1444.9 10,485 0.73 0.91
30 1104.5 9945 0.38 0.78
7 Acknowledgments
This work was supported in part by the China Scholarship Council,
in part by the National Natural Science Foundation of China under
grant nos. 71331001, 71401017, and 71420107027, in part by
China Southern Power Grid Funding under grant WYKJ00000027,
and in part by State Key Laboratory of Alternate Electrical Power
System with Renewable Energy Sources (grant no. LAPS14002).
8 References
[1] Opathella, C., Venkatesh, B.: ‘Managing uncertainty of wind energy with
wind generators cooperative’, IEEE Trans. Power Syst., 2013, 28, (3), pp.
2918–2928
[2] Gyuk, I.P., Eckroad, S.: ‘Energy storage for grid connected wind generation
Fig. 9 Impacts of BESS integration on operation cost (Case I) applications’ (US Department of Energy, Washington, DC, 2004), EPRI-DOE
Handbook Supplement, vol. 1008703
[3] Clayton, M.: ‘How enormous batteries could safeguard the power grid’,
Christ. Sci. Monit. Mar, 2009, 22
[4] Luo, F., Meng, K., Dong, Z.Y., et al.: ‘Coordinated operational planning for
wind farm with battery energy storage system’, IEEE Trans. Sustain. Energy,
2015, 6, (1), pp. 253–262
[5] Chakraborty, S., Senjyu, T., Toyama, H., et al.: ‘Determination methodology
for optimising the energy storage size for power system’, IET Gener. Transm.
Distrib., 2009, 3, (11), pp. 987–999
[6] Abbey, C., Joos, G.: ‘A stochastic optimization approach to rating of energy
storage systems in wind-diesel isolated grids’, IEEE Trans. Power Syst., 2009,
24, (1), pp. 418–426
[7] Bahramirad, S., Reder, W., Khodaei, A.: ‘Reliability-constrained optimal
sizing of energy storage system in a microgrid’, IEEE Trans. Smart Grid,
2012, 3, (4), pp. 2056–2062
[8] Changsong, C., Shanxu, D., Tao, C., et al.: ‘Optimal allocation and economic
analysis of energy storage system in microgrids’, IEEE Trans. Power
Electron., 2011, 26, (10), pp. 2762–2773
[9] Ghofrani, M., Arabali, A., Etezadi-Amoli, M., et al.: ‘A framework for
optimal placement of energy storage units within a power system with high
wind penetration’, IEEE Trans. Sustain. Energy, 2013, 4, (2), pp. 434–442
[10] Xiong, P., Singh, C.: ‘Optimal planning of storage capacity in power systems
integrated with pind power gGeneration’, IEEE Trans. Sustain. Energy, 2016,
7, (1), pp. 232–240
[11] Atwa, Y.M., El-Saadany, E.: ‘Optimal allocation of ESS in distribution
systems with a high penetration of wind energy’, IEEE Trans. Sustain.
Fig. 10 Optimisation process of different algorithm Energy, 2010, 25, (4), pp. 1815–1822
[12] Awad, A.S.A., El-Fouly, T.H.M., Salama, M.M.A.: ‘Optimal ESS allocation
for load management application’, IEEE Trans. Power Syst., 2014, 30, (1), pp.
PSO. All above three algorithms are repeated by 10 trails and the 327–336
averaged fitness values are plotted. The maximum deviation [13] Awad, A.S., El-Fouly, T.H., Salama, M.M.: ‘Optimal ESS allocation and load
between the optimal solutions was founded to be less than 5%. The shedding for improving distribution system reliability’, IEEE Trans. Smart
Grid, 2014, 5, (5), pp. 2339–2449
results show that comparing with other algorithms, DE shows [14] Zheng, Y., Dong, Z.Y., Luo, F.J., et al.: ‘Optimal allocation of energy storage
superior performance in terms of rapid convergence rate and system for risk mitigation of DISCOs with high renewable penetrations’,
robustness. IEEE Trans. Power Syst., 2014, 29, (1), pp. 212–220
[15] Gill, S., Premier, G.C., Guwy, A.J., et al.: ‘Energy storage for active network
management on electricity distribution network with wind power’, IET
6 Conclusion Renew. Power Gener., 2014, 8, (3), pp. 249–259
[16] Leite, A.P., Borges, C.L., Falcao, D.M.: ‘Probabilistic wind farms generation
In this paper, a stochastic optimisation method was proposed to model for reliability studies applied to Brazilian sites’, IEEE Trans. Power
find the optimal siting and sizing of BESS in the DN, with the aim Syst., 2006, 21, (4), pp. 1493–1501
1112 IET Renew. Power Gener., 2016, Vol. 10 Iss. 8, pp. 1105-1113
© The Institution of Engineering and Technology 2016
[17] Billinton, R., Allan, R.N., Allan, R.N.: ‘Reliability evaluation of power [25] Wong, K.P., Dong, Z.Y.: ‘Differential evolution, an alternative approach to
systems’ (Plenum press, New York, USA, 1984) evolutionary algorithm, invited book chapter’, in Lee, K., EI-Sharkawi, M.
[18] ‘Battery and electric vehicle report’ July 2010. Available at http://bit.ly/ (Eds): ‘Modern heuristic optimization: theory and applications to power
fGaZPB systems’ (Wiley, New York, 2008)
[19] Charnes, A., Cooper, W.W.: ‘Chance constrained programming’, Manage. [26] MATPOWER, ed, 2006. Available at http://www.pserc.cornell.edu/matpower/
Sci., 1959, 6, (1), pp. 73–79 [27] Strachan, N.D., Farrell, A.E.: ‘Emissions from distributed generation’. CEIC
[20] Ahmed, S., Shapiro, A., Shapiro, E.: ‘The sample average approximation working paper, Carnegie Mellon, 2002
method for stochastic programs with integer recourse’. Technical Report, [28] Greene, N., Hammerschlag, R.: ‘Small and clean is beautiful: exploring the
ISyE Georgia Institute of Technology, 2002 emissions of distributed generation and pollution prevention policies’, Electr.
[21] Liu, Z.P., Wen, F.S., Ledwich, G.: ‘Optimal siting and sizing of distributed J., 2000, 13, (5), pp. 50–60
generators considering uncertainties’, IEEE Trans. Power Deliv., 2011, 26, [29] NREL. Wind integration dataset. Available at http://www.nrel.gov/electricity/
(4), pp. 2541–2551 transmission/eastern_wind_methodology.html
[22] Yang, N., Yu, C.W., Wen, F., et al.: ‘An investigation of reactive power [30] Grigg, C., Wong, P., Albrecht, P., et al.: ‘The IEEE reliability test
planning based on chance constrained programming’, Int. J. Electr. Power system-1996. A report prepared by the reliability test system task force of the
Energy Syst., 2007, 32, (6), pp. 650–656 application of probability methods subcommittee’, IEEE Trans. Power Syst.,
[23] Yang, N., Wen, F.: ‘A chance constrained programming approach to 1999, 14, (3), pp. 1010–1020
transmission system expansion planning’, Elect. Power Syst. Res., 2005, 75,
(2–3), pp. 171–177
[24] Sum-Im, T., Taylor, G.A., Irving, M.R., et al.: ‘Differential evolution
algorithm for static and multistage transmission expansion planning’, IET
Gener. Transm. Distrib., 2009, 3, (4), pp. 365–384
IET Renew. Power Gener., 2016, Vol. 10 Iss. 8, pp. 1105-1113 1113
© The Institution of Engineering and Technology 2016