Determination of Critical Path
Determination of Critical Path
For critical path we look the connection of the flow activities by referring to Expected time
Top+ 4 Tml+Tpe
Exp. Time =
6
1. A C F H= 2+2+3+2 = 9 weeks
2. A C E G H = 2+2+4+5+2= 15weeks
3. B D G H = 3+4+5+2= 14 weeks
Slack is the length of time an activity can be delayed without delaying the whole project( free
time, that each activity has).
Tpe−Top 2
Variance = ( ¿ and standard deviation is the root square of variance
6
Ŏ=√ variance . If the activity times are statistically independent, the project variance is computed
by summing the variances of the critical activities (A C E G H).
Tpe−Top 2
Project Variance = ( ¿ of the activities which are on critical path
6
4 4 36 64 4 112
∑ var=¿ 36 + 36 + 36 ¿+ 36 + 36 = 36 =3.311
Standard deviation =√ var =¿ ¿ √ 3.311=1.76
Such information helps to answer questions regarding the probability of finishing project time.
Example:
Find the probability that project will be finished before 16 weeks deadline, we need to determine
the appropriate are under the normal curve. The standard normal equation can be applied as
follow:
Where Z is the number of standard deviation the due date or target date lie from the mean or
expected date. Referring to the normal distribution table shows that there is a 71.6% chance that
air filter system can put in place 16 weeks or less as shown below;
15 weeks
16 weeks Time
In the controlling of the process of monitoring and controlling of the project PERT has been able
to provide fair construction with several valuable pieces of management information, which
include;