Predictive Maintenance Program Implementation Experience
Predictive Maintenance Program Implementation Experience
Implementation Experience
TR-111915
Effective December 6, 2006, this report has been made publicly available
in accordance with Section 734.3(b)(3) and published in accordance with
Section 734.7 of the U.S. Export Administration Regulations. As a result
of this publication, this report is subject to only copyright protection and does
not require any license agreement from EPRI. This notice supersedes the
export control restrictions and any proprietary licensed material notices
embedded in the document prior to publication.
Project Manager
R. Pflasterer
EPRIGEN • 3412 Hillview Avenue, Palo Alto, California 94304 • PO Box 10416, Palo Alto, California 94303 USA
800.313.3774 • 650.855.2121 • askepri@epri.com • www.epri.com
11667179
DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
THIS REPORT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS AN ACCOUNT OF WORK
SPONSORED OR COSPONSORED BY EPRIGEN, INC. NEITHER EPRIGEN, THE ELECTRIC POWER
RESEARCH INSTITUTE, INC. (EPRI), ANY COSPONSOR, THE ORGANIZATION(S) NAMED BELOW, NOR
ANY PERSON ACTING ON BEHALF OF ANY OF THEM:
(A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I) WITH
RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM
DISCLOSED IN THIS REPORT, INCLUDING MERCHANTABILITY AND FITNESS FOR A PARTICULAR
PURPOSE, OR (II) THAT SUCH USE DOES NOT INFRINGE ON OR INTERFERE WITH PRIVATELY OWNED
RIGHTS, INCLUDING ANY PARTY'S INTELLECTUAL PROPERTY, OR (III) THAT THIS PACKAGE IS
SUITABLE TO ANY PARTICULAR USER'S CIRCUMSTANCE; OR
(B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER (INCLUDING
ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRIGEN OR ANY EPRIGEN REPRESENTATIVE HAS BEEN
ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOUR SELECTION OR USE OF
THIS REPORT OR ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM
DISCLOSED IN THIS REPORT.
ORDERING INFORMATION
Requests for copies of this package should be directed to the EPRI Distribution Center, 207 Coggins Drive, P.O.
Box 23205, Pleasant Hill, CA 94523, (925) 934-4212.
EPRI is a registered service mark of the Electric Power Research Institute, Inc.
11667179
CITATION
Principal Investigator
W. Woyshner
The report is a corporate document that should be cited in the literature in the
following manner:
iii
11667179
11667179
REPORT SUMMARY
Background
In October 1995 ComEd of Chicago, Illinois, and the EPRI’s Maintenance and
Diagnostic (M&D) Center of Eddystone, Pennsylvania, joined together to develop and
implement a PDM Program within the fossil division of the ComEd system. The
implementation involved 10 generating stations, and it included the Fossil Operations
Availability Systems Team and ComEd's System Material Analysis Department
(SMAD). In order for a PDM program to be successful, it is very important that all staff
levels at the plant and at the central office have an awareness of the program. This is
especially important when a program that employs a new approach to maintenance
decision making is being implemented. Typically, any significant change in working
habits is many times resisted initially, unless “Buy-In” of those affected by the changes
occurs.
This report is part of EPRIGEN’s development efforts under the Plant Maintenance
Optimization (PMO) Target, number 54 in 1998 and 75 in 1999. The PMO mission is to
lead the industry by developing and demonstrating products and services that will
improve utilization of power plant maintenance resources and increase profitability for
generation business units/companies.
Objectives
To implement predictive maintenance programs at 10 ComEd generating stations; to
achieve ComEd’s aggressive cost improvement goals through the use of predictive
maintenance; to change from a corrective maintenance strategy to a predictive
maintenance strategy.
Approach
The PDM Implementation Program comprised four major initiatives: 1) PDM Program
Implementation Support, 2) Level-of-Awareness (LOA) Training, 3) Technology
Implementation, and 4) PDM Program Follow-Up Reviews and Meetings. The project
v
11667179
team worked with ComEd’s Fossil Operations Availability Systems Team, PDM
Specialists from the 10 generating stations, and selected SMAD personnel to implement
PDM programs at each station. The team subsequently described the details of each
initiative and the tasks within them for this report. In addition, they wrote a section
dedicated to Cost Benefit Analyses.
Results
PDM programs were implemented at 10 ComEd fossil generating stations. ComEd’s
aggressive cost reduction goals were exceeded, and substantial progress was achieved
moving from a corrective maintenance strategy to a predictive maintenance strategy.
The program’s success can be measured by the cost-effective identification and
correction of potential equipment failures at the 10 generating stations with cost
benefits calculated at over $10.6 million in the first two years of the project. These
savings are an excellent indicator that a level of awareness and “Buy-In” of the PDM
Programs now exists at most of the stations.
EPRI Perspective
Predictive maintenance has become the dominant theme for the M&D Center at
Eddystone, Pennsylvania. That Center is operated in cooperation with PECO Energy
(PECO). Over 40 diagnostic systems are installed and operating at PECO's Eddystone
station. The M&D Center provides the utility industry a broad range of products and
services related to predictive maintenance. These include PDM Assessment services,
PDM Program Implementation services, training courses on PDM technologies, PDM
automation tools such as the O&M Workstation, and specific PDM services such as
thermography surveys. Over the past 11 years, the EPRI M&D Center has gained a
wealth of experience implementing PDM Programs at various utilities. The techniques
and experiences described in this report will be very beneficial to all EPRI members
that are implementing PDM into multi-station organizations.
TR-111915
Interest Categories
Fossil Steam Plant Performance Optimization
Fossil Steam Plant O&M Cost Reduction
Combustion Turbine/Combined Cycle Plants
Assessment & Optimization
Keywords
Diagnostic monitoring
Maintenance practices
Reliability/availability
Maintenance optimization
Performance
Predictive maintenance
vi
11667179
EPRIGEN Licensed Material
ABSTRACT
This report is part of EPRIGEN’s development efforts under the Plant Maintenance
Optimization (PMO) Target, number 54 in 1998 and 75 in 1999. The PMO mission is to
lead the industry by developing and demonstrating products and services that will
improve utilization of power plant maintenance resources and increase profitability for
generation business units/companies. This report describes the experience
implementing predictive maintenance (PDM) programs at Commonwealth Edison’s
(ComEd’s) fossil power plants.
This report describes the process and results of implementing predictive maintenance
programs. The implementation process was broken down into four major initiatives:
implementation support, Level Of Awareness (LOA) training, technology
implementation, and follow-up. Specific results from this implementation includes the
project schedule, the mini-assessment, the PDM plan, and the opportunities for further
improvement. The PDM plan includes: key findings, plant equipment assessment,
establishing the technologies, setting up the organization, establishing cost benefit
worksheets, and training. The PDM technologies implemented include: vibration,
lubrication, infrared thermography, ultrasonic, and motor current analysis.
vii
11667179
11667179
EPRIGEN Licensed Material
CONTENTS
ix
11667179
EPRIGEN Licensed Material
6 SUMMATION....................................................................................................................... 6-1
x
11667179
EPRIGEN Licensed Material
xi
11667179
EPRIGEN Licensed Material
Resource Requirements............................................................................................C-18
Training Requirements ..............................................................................................C-18
Miscellaneous Requirements ....................................................................................C-19
Lubrication TAD ............................................................................................................C-19
Technology Application .............................................................................................C-19
Activities ....................................................................................................................C-19
Responsibilities .........................................................................................................C-19
Resource Requirements............................................................................................C-20
Training Requirements ..............................................................................................C-20
Miscellaneous Requirements ....................................................................................C-20
IR Thermography TAD ..................................................................................................C-21
Technology Application .............................................................................................C-21
Activities ....................................................................................................................C-21
Responsibilities .........................................................................................................C-21
Resource Requirements............................................................................................C-21
Training Requirements ..............................................................................................C-22
Miscellaneous Requirements ....................................................................................C-22
Ultrasonic TAD ..............................................................................................................C-22
Technology Application .............................................................................................C-22
Activities ....................................................................................................................C-22
Responsibilities .........................................................................................................C-23
Resource Requirements............................................................................................C-23
Training Requirements ..............................................................................................C-23
Miscellaneous Requirements ....................................................................................C-23
Motor Current Analysis..................................................................................................C-23
Technology Application .............................................................................................C-23
Activities ....................................................................................................................C-24
Responsibilities .........................................................................................................C-24
Resource Requirements............................................................................................C-24
Training Requirements ..............................................................................................C-24
Miscellaneous Requirements ....................................................................................C-25
Organization..................................................................................................................C-25
Communication Formats and Description..................................................................C-25
Standard Reports ......................................................................................................C-26
xii
11667179
EPRIGEN Licensed Material
xiii
11667179
11667179
EPRIGEN Licensed Material
LIST OF FIGURES
xv
11667179
11667179
EPRIGEN Licensed Material
LIST OF TABLES
xvii
11667179
11667179
EPRIGEN Licensed Material
1
INTRODUCTION AND OVERVIEW
1. Consider why you are implementing a PDM Program, and get an understanding of
how PDM supports your goals (for example financial, reliability, safety, regulatory).
2. Establish or modify a formal PDM program which is focused on the PDM goals in
mind, including programmatic issues (e.g., your Organizational readiness), and
technical issues (for example identify components and applied technologies).
3. Formulate a detailed action plan, by creating task lists & schedules for all
technologies and PDM process activities.
4. Execute the plan, by having the discipline to perform the planned tasks according to
the schedule, such as:
— Procuring Equipment,
1-1
11667179
EPRIGEN Licensed Material
Introduction and Overview
Most utilities begin the PDM Program implementation at Step 4; thereby missing the
most important steps in the implementation process. The project, discussed in this
report, systematically applied the Six Steps listed above, and focused on providing the
awareness of the new maintenance program and achieving the formal "Buy-In" from all
staff levels, which are both necessary to create and implement a successful PDM
Program.
ComEd of Chicago, Illinois and the EPRI M&D Center, of Eddystone, Pennsylvania,
joined together to develop and implement a Predictive Maintenance Program (PDM).
The implementation involved ten (10) generating stations, the Operations Availability
Systems Team (AST), and the System Material Analysis Department (SMAD).
Implementing this program at ComEd was recognized as a difficult task and required
significant commitment from the ComEd team members. The experience of the AST
with implementing programs and/or initiatives within the utility organization and
culture, coupled with the expertise from EPRI M&D Center personnel with condition
monitoring tools and PDM program implementation, were instrumental to the project
success.
The motivation of the entire staff at ComEd to change the way maintenance decisions
would be made to lower O&M costs, as part of a competitive action plan, added fuel to
the fire for accomplishing the PDM program implementation.
The PDM Program was successfully initiated and developed via these four (4) major
initiatives of the project. The techniques and experiences consolidated in these four
initiatives will be very beneficial to all EPRI members that are implementing PDM into
multi-station organizations. The program's success was measured by the cost-effective
identification and correction of potential equipment failures at the ten (10) generating
stations. This is evidence that a level of awareness and "Buy-In" of the PDM Programs
exists at most stations. The program's success also resulted in over $10.8 million
calculated in cost benefits over the first two years of the project. As mentioned
previously, this initial "Buy-In" of the PDM Program is an important first step toward
changing the work culture and the process in which maintenance decisions are made at
all of ComEd's Fossil Generating Stations.
1-2
11667179
EPRIGEN Licensed Material
Introduction and Overview
1-3
11667179
11667179
EPRIGEN Licensed Material
2
PDM PROGRAM IMPLEMENTATION
Appendix A of this report includes an overall schedule showing the sequence of events
explained in this report; and, it links the explanation of each event to the time that the
event occurred. The schedule also displays the time of occurrence of the financial
benefits gained throughout the implementation process of the PDM Program.
The goals of the course were: 1) To understand technical, organizational, and financial
issues surrounding the implementation of PDM; 2) Raise the level of awareness of the
effectiveness and limitations of PDM technologies as applied power plant equipment;
and, 3) Show how a PDM Program can be implemented at ComEd. The topics
discussed during the first day included Planning, Design, Implementation, Evaluation,
and Automation of a PDM Program. The second day discussions involved Technology
Reviews of the different technologies used in a PDM Program. These technologies
included both Periodic and On-Line Systems such as: Vibration Monitoring; Lube Oil
Sampling and Analysis; Infrared Thermography; Acoustic Valve Leak Detection; On-
Line Water Chemistry Analysis; and, On-Line Performance Monitoring.
Coaching Sessions
The most significant portion of the PDM Program Implementation Support was the
coaching sessions. These sessions were divided into five different meetings at various
ComEd selected locations, and they were spaced approximately three months apart.
The purpose of the sessions was to ensure program consistency and program cost
minimization through economics of scale across the ten plants. The specific topics of
each session were somewhat different; however, the intent was to present, discuss, and
2-1
11667179
EPRIGEN Licensed Material
PDM Program Implementation
review the PDM Program with the Operations Availability Systems Team and the PDM
specialists from each station.
Coaching Session # 1
The EPRI M&D Center provided two engineers for the initial coaching session held at
the Joliet 29 Generating Station training facility, approximately seven months after the
initial PDM course.
The focus of the first coaching session was PDM equipment selection, technology
applications, and programmatic issues such as organization and communications.
Equipment selection included: Infrared Thermography equipment; Vibration Analysis
equipment; Lube Oil Analysis equipment; and the software applicable to each of the
technologies for the reporting of the respective data gathered. Suggestions from the
M&D Center were made as to what was required to do the job; however, vendor
selection was made by ComEd. The application of which of the different PDM
technologies should be applied to the selected station equipment, and how often they
should be surveyed, was discussed. The programmatic issues discussed were: how to
organize each individual station's PDM group; how to establish communications
between the individual groups at each station and the Fossil Operations Availability
Systems Team; and, how to organize all the data from all the plants into a central
database so that all plants could share information. The highlights of the formal
presentation of the first coaching session were as follows:
2-2
11667179
EPRIGEN Licensed Material
PDM Program Implementation
The ComEd PDM Manager and PDM Leader, and the EPRI M&D Center project
manager, presented a PDM Program progress update at the Senior Leadership Team
meeting held at ComEd's Fossil Division headquarters. Topics discussed for upper
management buy-in to the PDM Program included the six steps required when
implementing a PDM Program, as stated previously.
The ensuing PDM Program Progress and Results discussions of the presentation
included:
• Completion of ten (10) of the forty (40) total weeks of LOA Training, with the after-
test scores indicating a 20% to 30% increase over the before-test scores.
• Completion of the first five (5) coaching sessions where the positive and negative
aspects of the PDM Program Implementation Plan, along with critical personnel
concerns, were being worked out.
Coaching Session #2
The EPRI M&D Center provided an engineer for the second coaching session held at
the ComEd's Central Testing, Engineering and Material (C-TEAM) training facility,
approximately three months after the first coaching session. The focus of the second
coaching session was a Review of the Homework Assignments, via Presentations by
each Plant's PDM Specialist, and the Introduction of the 14 Key Elements of a PDM
Program Implementation Plan. Prior to beginning the second coaching session, some
initial program implementation questions were fielded. Some of those questions and
their responses were as follows:
2-3
11667179
EPRIGEN Licensed Material
PDM Program Implementation
• Question: Why create a PDM Implementation Plan if the M&D Center is working
with the PDM Specialist, shouldn't they know what to do?
— The plan also gives plant Management the necessary "Yard Stick" to measure the
progress and success of the PDM Program.
The homework assignment was for the PDM Specialist to gather the required
information, identified on the first coaching session's "Homework Assignment" to help
develop the PDM Program Implementation Plan. The most consequential portion of
the Homework Assignment was how to select which pieces of plant equipment would
be the most beneficial for inclusion in the PDM Program. The process for determining
how to select those pieces of equipment is by listing the most likely candidates, as
shown in Table 2-1 below.
The next step is to apply corresponding numbers adjacent to each piece of equipment
that represents its importance in the two categories outlined (1 having the most effect,
and 10, etc. having the least). The two numbers entered for each category are added
together and the equipment that is determined to have the smallest accumulative
number is the first piece of equipment that should be monitored in the PDM program.
Therefore, based on the above example, the pulverizers and boiler feedpumps are the
two pieces of equipment that the initial PDM program's attention should be focused on.
2-4
11667179
EPRIGEN Licensed Material
PDM Program Implementation
Table 2-1
Equipment Selection Process
Pulverizers 1 4 5
Condensate Pumps 13 1 14
Air Compressors 10 7 17
Etc.
The introduction of the 14 Key Elements of a PDM Program Implementation Plan was
also presented during the second coaching session. The following is a list of these
items:
2-5
11667179
EPRIGEN Licensed Material
PDM Program Implementation
3. Equipment and Condition Indicators (E&CI) Matrix - is a matrix list of the plant's
essential equipment to be included in the PDM Program. Also, included in the
E&CI matrix is each available parameter measured, or equipment condition
indicators used, for each piece of equipment included in the listing. Some
equipment condition indicators include:
— Visual Inspections/Indicators
— (This E&CI matrix should also indicate the "Owner " of each piece of equipment
on the list, or the person responsible for the long term maintenance/performance
of the equipment.)
5. Planning and Estimating Guides - are cost estimates for implementing the specific
technologies described in the Technology Application Descriptions.
8. PDM Report Format - is a document that summarizes all the condition indicators
for a piece of equipment, and documents all maintenance actions required for that
piece of equipment. This report is the primary deliverable of a PDM Program. This
document is also referred to as the Equipment Condition Report.
2-6
11667179
EPRIGEN Licensed Material
PDM Program Implementation
10. Work Flow Diagrams - depicting and understanding the actual process of how
maintenance work is executed and closed-out once the need for the tasks has been
identified (i.e. as a result of PM work order or equipment failure) is critical when
implementing PDM. The actual existing work flow process must be adjusted
properly to receive the information regarding equipment condition, so that
maintenance tasks are re-evaluated, re-scheduled, or eliminated prior to the work
being performed. The PDM process of collecting data, converting it to information,
and taking the respective corrective action, must be 'built-in' to the current
maintenance process, not 'added-on'.
— (These work flow diagrams depict the 'as found' work process and clearly define
the desired process with the PDM process integrated.)
11. Schedule - is a Gantt chart that depicts all key activities and milestones of the PDM
Program. The program schedule is critical for monitoring program progress.
12. Training Matrix - is a matrix that identifies each person involved with the PDM
Program that is to be trained, and what type of training they are to receive.
The progress meeting with all of the stations' Operations, Maintenance, and Technical
leaders was held at the Joliet 29 Generating Station training facility. This meeting was
used as a forum for accomplishing goals similar to those achieved at the presentation to
senior management; and, to gauge the level of understanding by these plant
management personnel as to the current PDM Program status and their "Buy-In". Their
understanding of the activities and progress was weak, with the exception of a few.
This realization reinforced the need for each plant's PDM Specialist to create and/or
complete a formal plan, and to present these plans for review and approval by this
management group. This approach would provide answers to their questions and
further stimulate future support.
2-7
11667179
EPRIGEN Licensed Material
PDM Program Implementation
The EPRI M&D Center provided two (2) engineers for the mini Plant Assessments held
at Waukegan & Crawford Generating Stations. The focus of the mini Plant
Assessments was to examine ways to integrate existing programs or processes to meet
the PDM goals. Some of the basic assumptions made in the Plant Assessment process
are that:
• Participation by all Plant Personnel is Critical for the Success of the PDM Program
Coaching Session #3
The EPRI M&D Center then provided an engineer for the third coaching session held at
the Joliet 29 Generating Station training facility, approximately three months after the
second coaching session. The focal points of the third coaching session were on:
1)Reviewing the 14 Key Elements of a PDM Program Implementation Plan; 2) Review
of the PDM Program Implementation Plan from Waukegan & Crawford Generating
Stations; 3) Presentations from each of the ten (10) Stations on Actual Cost Benefits
Gained from their Programs; and, 4) Summarization of All Cost Benefits &
Occurrences.
The review of the 14 Key elements of a PDM Program Implementation Plan was
performed so that everyone in attendance could properly critique the PDM Program
Implementation Plans to be presented.
Presentations were given for Waukegan Station's PDM Program Implementation Plan
(see Appendix C), by the respective station's PDM Specialist. Also presented were two
(2) individual Cost Benefit Analyses from each station's PDM Specialist. In addition,
the PDM Coordinators presented a summary of all PDM Occurrences to-date and their
associated total Cost Benefit Analyses values.
2-8
11667179
EPRIGEN Licensed Material
PDM Program Implementation
2nd Progress Meeting with All Station's Operations, Maintenance, & Technical
Leaders
The EPRI M&D Center provided one (1) engineer for the 2nd progress meeting with all
of the stations' Operations, Maintenance, & Technical leaders which was held at the
Central Testing, Engineering and Material (C-TEAM) training facility. The focus points
of the second progress meeting were: 1) Maintenance Strategy Optimization Overview;
2) Review the Progress of the PDM Plan Implementation at the Waukegan & Crawford
Generating Stations; and, 3) Review the Cost Benefit Analyses Methodology. Some of
the management personnel had realized the value of having a formal PDM Program
Implementation Plan to ensure success prior to this meeting; however, the general
consensus arrived at in this meeting was that each plant must have a formal plan to be
successful.
Coaching Session #4
The EPRI M&D Center provided an engineer for the fourth coaching session held at the
Operations Availability Systems Team's facility, approximately four (4) months after
the third coaching session. The agenda consisted of: 1) The Design & Discussion of
Equipment Condition Assessment Meetings, including setting goals and determining
deliverables; 2) Review Inter-Organizational Communications for Standardized
Equipment Condition Reports (Table 2-2), Cost Benefit Calculations, Standardized
Lesson Plans; 3) assimilation of an Equipment Condition Assessment Meeting; and, 4) a
Detailed Demonstration of the O&M Workstation.
These meetings were attended by the applicable plant Operations Dept., plant
Maintenance Dept., and the plant Technical Staff personnel, in an effort to communicate
all equipment condition information for PDM Program equipment, and making the
"Best" possible decision on current maintenance requirements. The data typically
reviewed was:
2-9
11667179
EPRIGEN Licensed Material
PDM Program Implementation
• Maintenance Costs
• Operation Logs
2-10
11667179
EPRIGEN Licensed Material
PDM Program Implementation
Figure 2-1
Example of Monthly Equipment Condition Assessment Report
Coaching Session #5
The EPRI M&D Center provided an engineer for the fifth coaching session held at the
Joliet 29 Generating Station training facility, approximately five (5) months after the
fourth coaching session. This last coaching session's agenda was as follows:
• Open Discussion (i.e. Brainstorming) of Major Issues Regarding the PDM Program
• Implementation
2-11
11667179
EPRIGEN Licensed Material
PDM Program Implementation
The most significant portion of Coaching Session 5 was the Open Discussion or
"Brainstorming" of the major issues regarding the PDM Program Implementation at
ComEd. The process of "Brainstorming" involved all PDM Specialists and the
Availability System Team members present at the meeting and their concerns with the
implementation process. The brainstorming process was to list every issue from
everyone involved. The next step was to prioritize those issues.
This was done by giving everyone involved a fictitious $100 to spend, in any amounts
and on however many issues they desire. The dollar values are added up for each
issue, and the top five dollar amounts are the five issues that are attacked first, to help
resolve open issues in a prioritized manner. Included in Table 2-3 are the results of this
prioritization process.
The EPRI M&D Center provided an engineer for the second Senior Leadership Team
meeting. The ComEd PDM Program Manager and the Availability Systems Team
Leader presented the accomplishments for each plant's PDM program, shared various
case history examples of Return On Investment (cost benefits), and explained that the
initial goal of $2 million annually in net savings per plant was well on it's way after the
first 16 months. However, to attain or exceed this goal, the following issues must be
prioritized and addressed by this leadership team and each station.
Table 2-2
Major PDM Program Issues
Priority Issues
$255 Union agreement negotiations must be completed (It's holding back work
force and causing inconsistencies).
$70 "No time made available to get coaches, planners, specialists, and
operations personnel together for Equipment Condition Assessment
meeting."
2-12
11667179
EPRIGEN Licensed Material
PDM Program Implementation
agreement."
$13 "Too many people doing data collection, not enough response time
allowed."
$75 Establish station-wide Rules and Responsibilities (#3 also affects this).
$105 PDM information not fully integrated with existing work flow process.
$87 "Do not have total ""Buy-In"" from coaches, planners, and shift advisors."
$100 PDM specialists are not paid enough (overtime pay was cut out).
2-13
11667179
11667179
EPRIGEN Licensed Material
3
LEVEL OF AWARENESS (LOA) TRAINING
• How will the program or technology benefit you and your company?
The following are the four (4) LOA training modules performed for ComEd.
• Predictive Maintenance
• Infrared Thermography
• Vibration Analysis
Each module was performed in a 3 1/2 - hour session, twice a day, for a five-day
period at each generating station. Each session was limited to 10 - 20 persons;
therefore, approximately 100 to 150 persons at each station received the LOA Training
(See Section 3 PDM Program for exact numbers). The sessions were targeted for each
station's Management, Operations, engineering, and Maintenance personnel. The
Operations Availability Systems Team personnel received exposure to each LOA
training module, by rotating their involvement into different LOA training sessions
conducted at each generating station. The following is a detailed description of the
content of each of the LOA Training modules.
3-1
11667179
EPRIGEN Licensed Material
Level of Awareness (LOA) Training
• What is PDM
• Maintenance Strategies
• PDM Technologies
• PDM Analysis
• PDM Challenges
• PDM Goals
This module assisted ComEd personnel in implementing the IRT Program at each
station, because of the overall exposure it afforded to all station personnel regarding
the many applications of this technology in a station environment. With the knowledge
gained from participating in this LOA Training course, station personnel can now assist
and/or call on the PDM Group to use IRT to troubleshoot problems identified within
the station. The course content discussions covered the following IRT topics:
• Theoretical Overview
• Instrument Classifications
3-2
11667179
EPRIGEN Licensed Material
Level of Awareness (LOA) Training
• Advantages
• Measurement Methods
• Field Applications
This module discussed the proper use of vibration monitoring as a valuable tool to
detect and diagnose machinery problems before serious failure occurs. The course
content discussions covered the following topics:
• Analysis Techniques
• Condition Monitoring
This module discussed the basics of lube oil analysis as part of the PDM Program. The
course content discussions covered the following topics:
• Basic tests
3-3
11667179
EPRIGEN Licensed Material
Level of Awareness (LOA) Training
• Failure progression
• Case histories
3-4
11667179
EPRIGEN Licensed Material
4
TECHNOLOGY IMPLEMENTATION
The Technology Implementation activities of this project were a result of the PDM
Program Implementation Support initiative of the project. The four (4) technologies
chosen to be implemented at ComEd were: 1) Infrared thermography (IRT); 2) Electric
Motor Predictive Maintenance (EMPM); 3) Vibration Analysis; and, 4) Lube Oil
Analysis. The vibration and lube oil analysis programs were somewhat already in
existence at most of the ComEd's plants; therefore, ComEd took the responsibility for
ensuring that the changes and training requirements developed from the PDM Program
implementation plans would take place for those technologies. The EPRI M&D Center
provided assistance in the development and initial implementation of the IRT and the
EMPM Programs.
IRT Program
The approach for the development and implementation of the IRT Program was
divided into five separate tasks, which were performed for all 10 generating stations.
These tasks were as follows:
The EPRI M&D Center conducted a two-day IRT Report Generation training course at
ComEd's Joliet 29 Generating Station training facility. The course provided each of the
selected PDM Specialists from the ten (10) generating stations with the necessary
training to generate an IRT report from the data gathered during field surveys. The
4-1
11667179
EPRIGEN Licensed Material
Technology Implementation
software used was EPRI's Infrared Report - Software Integration Program (IR-SIP),
which was developed by the M&D Center. The three off-the-shelf software products
necessary to operate IR-SIP were provided by ComEd; and, the IR-SIP program
diskettes, operating procedures, and example reports, were provided by the M&D
Center. The success of the training was somewhat limited due to the significant time
lag from when the training was given to the time the IRT equipment and the off-the-
shelf software became available to the PDM Specialist. However, follow-up training
was provided at later dates. The lesson learned was not to provide report generation
training until all of the necessary equipment and software is in place at all locations.
The EPRI M&D Center conducted a five (5)- day IR survey on the selected mechanical,
electrical, and switch yard components, on one unit, at each of the ten (10) stations. The
surveys were performed in the following manner:
An IRT Field Survey entrance meeting was held with plant management, planning,
engineering, electrical/mechanical maintenance supervisors, and PDM personnel to
discuss:
• Plant personnel assistance during the survey (e.g. Performance Eng., System Eng.,
Electricians, etc.)
• Informal, hands-on, IRT field survey training for applicable plant personnel
An IRT Field Survey exit meeting was held, with the same personnel as the entrance
meeting, to discuss:
4-2
11667179
EPRIGEN Licensed Material
Technology Implementation
The EPRI M&D Center generated a formal, comprehensive report from the survey data,
using the IR-SIP software developed by the M&D Center for all ten (10) generating
stations. This report serves as an equipment status document, and as a guide to be
used as the foundation of the IRT Program.
• Data sheets containing thermal and visual images, with arrows identifying the areas
of interest
The report for each station was provided in hard copy and disk copy formats. The
initial IR-SIP training (Task 1) provided each station with the information necessary to
integrate the M&D Center's constructed report with the station's IR-SIP program.
Subsequent surveys on the units that the M&D Center surveyed, and other units, will
only require an update to the delivered database, which is a minimum effort as
compared to the initial database development.
The EPRI M&D Center re-visited each station during one of the subsequent surveys to
review the overall IRT Program progress. The IRT Program Follow-Up and Reviews
consisted of reviewing two (2) station per week to evaluate each station's progress in
developing the following IRT PDM tasks:
• Creation of an "equipment to be surveyed list" for units other than the units
surveyed during the initial IRT training session
4-3
11667179
EPRIGEN Licensed Material
Technology Implementation
Technology Transfer
4-4
11667179
EPRIGEN Licensed Material
Technology Implementation
• Heater testing
In addition, various new condition monitoring technologies are applied, such as:
• Vibration analysis
The approach for the development and implementation of an Electric Motor Predictive
Maintenance (EMPM) Program at ComEd was divided into four (4) major tasks which
were as follows:
2. Presentation of the EMPM Project at the other nine (9) generating stations
4. EMPM Project Review and Follow-Up Meetings at the Other Nine (9) Generating
Station
ComEd picked the Joliet Generating Station as the station to fully participate in EPRI's
Tailored Collaboration project for EMPM. The following topics were discussed in the
initial implementation meetings, and then in the initial field survey that followed:
4-5
11667179
EPRIGEN Licensed Material
Technology Implementation
Task 2: Presentation of the EMPM Project at the Other Nine (9) Generating
Stations
The remaining ComEd generating stations were presented with an overview of the
EMPM Project. Also reviewed at the remaining stations were the existing motor
programs to determine what is working well and what is not. Also, as part of the
overview, the different technologies used in the program, and how to implement and
review the data was discussed. Further program discussions took place over the next
several months, via Telnet (e.g. telephone, fax, Internet e-mail, etc.) communications.
Task 3: Continuation of the Full EMPM Project at the Joliet 29 Generating Station
The data collection and analysis for the EMPM Project at the Joliet 29 Generating
Station will continue for a period of three (3) years from the date of the initial kick-off
meetings and field surveys.
Task 4: EMPM Project Review and Follow-Up Meetings at the Other Nine (9)
Generating Stations
Subsequent site visits at the other nine (9) generating stations were made to assist
ComEd personnel with monitoring the EMPM program, calculating cost benefits, and
creating case histories that depict specific cost savings at each plant (e.g. reduction of
PMs, avoidance of catastrophic failures, and individual increases in component
availability.
The responsibility of the existing Vibration Program at the ComEd plants was given to
each plant's PDM Specialist, with integrated support and guidance from SMAD. The
PDM Specialist was to develop and implement the necessary changes to the Vibration
Analysis Program, that resulted from the implementation of CAP (Competitive Action
Plan) and the PDM Program Implementation plan. These changes included dividing
the equipment in the established routes into individual process Team areas of
responsibility. This allows the Process Teams themselves to be responsible for the
collection and analysis of the vibration data. In order to prepare them for this
responsibility, a sequence of training was planned for the Team members. In addition
to the Vibration Analysis LOA training, the Team members were exposed to
approximately 40 hours of hands-on basic vibration training, provided by the PDM
Specialist, as well as advanced classes in vibration analysis, balancing, and vibration
hardware, developed especially for ComEd and provided by an outside contractor.
4-6
11667179
EPRIGEN Licensed Material
Technology Implementation
The PDM Specialist also has acquired some of the responsibilities of the Lube Oil
Analysis Coordinator; by establishing the frequency found on the Equipment and
Technology (E&T) Matrix of the PDM Program Implementation plan, coordinating the
lube oil sampling, the sending off of samples for analysis, and reviewing and trending
the analyzed data. The sampling of the lube oil was done by plant Operating
personnel. The majority of the lube oil analysis is performed at ComEd's Central
Testing, Engineering and Material (C-TEAM) Facility by SMAD. One station is
utilizing a particle counter to screen samples for particle contamination; thereby,
reducing the amount of samples actually being sent to SMAD for analysis. In addition
to the Lube Oil Analysis LOA training, SMAD also provided, by an outside contractor,
training for the PDM Specialist and other selected Operating personnel on the proper
handling and taking of samples, to make sure meaningful samples are being taken
from the correct locations on the equipment. This ensures that accurate data is being
collected, which is needed to better assess the actual equipment and lubricant
conditions.
The Plant PDM/PD Program Review sessions were conducted with and EPRI M&D
Center engineer and ComEd's Fossil Operations Availability Systems Team personnel
at all ten plants. During each plant's visit, individual interviews were conducted with
plant management, maintenance supervisors, and various craft personnel to capture the
current strengths, weaknesses, and corresponding opportunities for PDM Program
improvement (see Appendix D). The results of these sessions are discussed in the
"PDM Program Results" section of this report.
4-7
11667179
11667179
EPRIGEN Licensed Material
5
PDM PROGRAM RESULTS
The PDM Program conducted at ComEd showed significant cost benefits. This section
explains the procedures for estimating cost benefits in detail, provides examples of cost
benefit calculations, and covers other aspects of the benefits of PDM.
Basic Assumptions
With any cost benefit analysis procedure, some assumptions and suppositions are
needed to simplify the process. Some of the basic assumptions of this procedure are:
1. There are two areas where a predictive (or condition based) analysis of plant
equipment has an impact on plant Operations and Maintenance. The first area deals
with the loss of generating revenue associated with the detected fault. The second
area deals with the maintenance savings associated with early detection of the fault.
4. There are three possible outcomes for any detected plant equipment fault:
— Moderate Failure - Includes only the costs of replacing the failed component
parts and the impact of the failure on generating capability. These types of
failures are given a higher probability of occurrence than the catastrophic
occurrence.
— Loss of Performance - Includes the costs associated with the resulting loss of
service of the faulty equipment if the fault had gone undetected. This category
could also be considered a "Minor Failure", and often mirrors the "actual" costs
5-1
11667179
EPRIGEN Licensed Material
PDM Program Results
5. There are costs associated with the actions taken as a result of a detection. These
costs are not always known when the cost benefit analysis is done, so they must be
estimated. These costs are subtracted from the estimated total benefit to yield a net
benefit differential. The benefits associated with the detection of the fault, as
defined in this procedure, is actually this benefit differential. Therefore, the
reported benefit is the actual net savings experienced by the utility, not the gross
costs avoided.
LOA Training
The following two questions regarding LOA training were proposed by the EPRI M&D
Center to several of the ComEd station personnel:
1. Would you recommend LOA type training to another multi-station type utility?
Please provide reasons why you would or would not.
2. Does LOA Training help eliminate PDM barriers and provide better "Buy-In" from
station personnel? Please provide reasons why or why not.
1. Yes, I feel that whether it is a single or multi-unit station, the benefits of the LOA
Training are well worth the efforts. You can reach all the people necessary to make
the program successful. The information learned can be shared from site to site
(which is important considering he way personnel move in the industry today).
2. Absolutely, the structured presentations used for the LOA Training are simple, easy
to understand, and do not rely on personnel having a maintenance background to
realize the advantages of the PDM Program. It shows all personnel that everyone,
no matter the discipline they have, play an important role in the success of the PDM
Program.
1. Yes, I would recommend LOA type training for other multi-station organizations. It
benefited our station because it gave everyone a broad look of the "big picture" of
PDM in general. Then the technology-specific LOAs gave everyone their first taste
5-2
11667179
EPRIGEN Licensed Material
PDM Program Results
of the objectives of the program without going into so much detail that would have
put people to sleep.
2. We may have had barriers without the LOA Training, but we will never know. I do
feel, however, that we had great response if not eager response when it came time to
find the personnel to become involved. We actually had more people interested
that I could handle. I do not think we would have had the same response without
the LOAs.
The majority of the Powerton employees that attended the LOA courses took something
from the courses that helped them understand the concept of a PDM Program and its
technologies.
The station operators really took an interest in the Oil Analysis LOA course. At this
time, operators are responsible for gathering all lube and oil sampling. After taking the
course, for just a few days, I had operators interested in making sure they took good
samples.
Contents of the initial Oil Analysis classes were too complex for the participants. LOA
Training was somewhat out of sequence, due to making site personnel aware of a
program that was not yet fully functional.
5-3
11667179
EPRIGEN Licensed Material
PDM Program Results
Courses had over 90% of all plant personnel in attendance. Plant personnel were very
interested in course materials. Instructors were impressed with the many responses
from the class attendees.
Table 5-1 shows the average % improvement that students reported from LOA training.
In the four training subjects, students reported a 12% to 22% improvement in the
understanding of that subject.
5-4
11667179
EPRIGEN Licensed Material
PDM Program Results
Table 5-1
ComEd Level Of Awareness Training Overall Averages
LOA % Average Collins Crawford Fisk Joliet 9 Joliet 29 Kincaid Powerton Stateline Waukeg. Will Co. Overall
Improvement Station Station Station Station Station Station Station Station Station Station Average
PDM Program 14% 17% 8% 13% 13% 4% 1% 19% 12% 12% 12%
Infrared Thermog. 27% 19% 23% 23% 17% 25% 22% 21% 16% 22% 22%
Vibration Analysis 16% 12% 19% 22% 22% 19% 16% 19% 29% 15% 19%
Oil Analysis 10% 24% 15% 12% 11% 25% 19% 17% 5% 7% 15%
5-5
11667179
11667179
EPRIGEN Licensed Material
6
SUMMATION
6-1
11667179
11667179
EPRIGEN Licensed Material
7
REFERENCES
1. Implementing Predictive Maintenance Across the Fossil Division Saves ComEd Over 7
Million Dollars in 18 Months, Electric Power Research Institute, IN-111104, September
1998.
7. Techniques For Achieving CBM Program Buy-In, Nochera, J , paper given at EPRI
Fossil Plant Maintenance Conference, Baltimore, MD August 1996.
10. Benefits of Predictive Maintenance Program in a Power Plant Environment, Colsher et al,
EPRI 5th Predictive Maintenance Conference, Knoxville, TN, July 1992.
11. Beyond Detection - Realizing the Value in a PDM Program, VanDerHorn, G.,
Matusheski, R., MARCON Conference, Knoxville, TN, May 1997.
7-1
11667179
11667179
EPRIGEN Licensed Material
A
PLANNING SCHEDULE
When planning a Predictive Maintenance program, all of the key tasks should be laid
out on a time schedule to indicate what events will occur when, how they interact, and
the total length of the project. From the time schedule the required man-hour and
material resources can then be summarized. The schedule included here is only one of
many computer generated time schedules that are available today, and it was selected
for scheduling the ComEd PDM Implementation activities.
Table A-1
Schedule for Events
First Program Meeting with Fossil Div. Sr. Mgmt. 1d 5/21/96 5/21/96
A-1
11667179
EPRIGEN Licensed Material
Planning Schedule
Oil Analysis LOA Training (Typical for all Sta.) 5d 5/20/96 5/24/96
A-2
11667179
EPRIGEN Licensed Material
B
PDM MINI-ASSESSMENT QUESTIONNAIRE
General Questions
Personal
3. What is your background? (Emphasize your work with this company) This helps us
to understand where he or she came from and gives us good perspective of what the person
feels is important. People tend to believe in things they do, or did in the past.
2. Are there any existing procedures or processed that you consider to be highly
efficient and cost effective? (i.e. quality program, equipment reliability initiatives,
etc.).
3. Are there any old processes or procedures that should be brought back?
4. In your opinion, are current resources (personnel and materials) adequate for
maintaining the facility?
5. Is your company planning to reorganize or down-size anytime soon? Only ask the
following if the response to 5 is positive.
B-1
11667179
EPRIGEN Licensed Material
PDM Mini-Assessment Questionnaire
— Are you aware of any other programs for cost reductions, either at the plant level
or at the corporate level?
Preventive Maintenance
1. What types of preventive activities are carried out on a regular basis? Describe your
predictive maintenance activities.
3. Do the maintenance crews capture the "as found" condition of the components that
were repaired or replaced during these preventive procedures?
Predictive Maintenance
1. What is your definition of Predictive Maintenance? Ask for his or her definition as
they understand it. This is important to know what the person perceives as the
definition. Take time here to encourage the person interviewed. It may help to
show the guidelines definition of PDM, CM, PM, PAM, RCM.
3. What, if any, monitoring or diagnostics have been applied to these systems? Does
the culture at the facility support monitoring as a solution for equipment problems?
This will give clues as to the reception and "buy-in" of monitoring solutions.
B-2
11667179
EPRIGEN Licensed Material
PDM Mini-Assessment Questionnaire
— Are there any contracted services that have been conducted in the past or present
that were effective? If applicable.
Communications
1. On a scale of 1 to 10 (10 being perfect) how well does your organization, within the
facility, communicate information regarding diagnostic testing or special testing
related to a specific equipment problem? We are trying to establish how well the
personnel communicate and use operations, maintenance and engineering to help diagnose
problems.
2. Explain how the conversion of data to information and corrective action works. Use
the Data Information, Corrective Action presentation slide
On a scale of 1 to 10
DATA INFORMATION ACTION
Explain any reasons for low scores.
Training
1. Is the current training program adequate to the needs of the facilities maintenance
personnel? What other courses should be offered?
2. Do you feel you need training? If so, in what areas? (Either maintenance
philosophy, PDM program training or special condition monitoring technology
training).
B-3
11667179
EPRIGEN Licensed Material
PDM Mini-Assessment Questionnaire
3. Do you have any experience using personal computers? Would training in this area
be helpful?
4. Do you feel confident in crafts in which you had some previous training or would
some refreshers help? Craft personnel only.
3. Do you know your typical costs for maintenance activities (labor and parts)? We
want to know their level of awareness of this business issue.
4. Are you aware of any sort of equipment trouble list? Who keeps it?
B-4
11667179
EPRIGEN Licensed Material
C
WAUKEGAN STATION PDM PLAN
Attached is the PDM Assessment report for the ComEd Waukegan plant which will
serve as the PDM Implementation plan. The M&D Center also assisted ComEd in the
Assessment and the Implementation Plan for the Crawford station. With these road
maps, ComEd will prepare their own Assessment reports for implementing PDM at the
remaining stations.
Overview
Introduction
The new economic environment will require that maintenance strategies be put in place
to help us be effective in a competitive market. This will require all employees
involved in the daily operation and maintenance of Waukegan Station to increase their
awareness of each individual's responsibilities in reducing costs and maintaining
availability.
Predictive Maintenance (PDM) represents a new and permanent way of doing business
in a competitive environment. Predictive Maintenance is an approach to plant
maintenance that relies on condition-based maintenance. This approach evaluates the
condition of various equipment in the plant in order to determine an appropriate
operating or maintenance action. The Predictive Maintenance process applies new and
existing technologies with plant know-how to increase the capability of this assessment
process based on equipment condition.
Fossil Senior Leadership and Station Leadership are committed to supporting the
development and implementation of a PDM Program for Waukegan Station. This has
helped to stimulate personnel involvement in Predictive Maintenance at all of our
plants. However, in order for PDM to be successful, it will require the support and
commitment of all the employees of Fossil Operations.
C-1
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Scope
The information contained in this report is to be used as an action plan to formalize the
development and implementation a PDM Program at Waukegan Station. The
information given will provide a method for introducing and utilizing available
technologies at our plants in order to assist plant personnel in maximizing the
effectiveness of the plant maintenance and operational processes.
• Integration of the PDM Program into the Station Organizational Work Flow
Recommendation #1
Process Specialists and Team Coaches will be trained on all PDM technologies, in order
to support the PDM program within their Process Areas.
C-2
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Recommendation #2
PDM Specialists will facilitate and coordinate the training needed to implement the
PDM program within the teams. This will include providing support in targeting the
proficiencies needed by the Process Specialists and Team Coaches, plus providing
hands-on training for all team members. The PDM Specialist will also provide training
and support to the Process Specialists and Team Coaches in the applications and
software currently being used for reporting.
Recommendation #3
Operations information is critical to the PDM program. Shift turnover and logging of
equipment condition in the Operations Logs will be improved. The station is currently
investigating several options in this area.
Recommendation #4
Root cause analysis will be performed on all equipment designated as station assets.
Recommendation #5
Recommendation #6
PDM Level of Awareness training will be conducted for the operators. In addition, any
applicable application training on the various technologies must be attended. This is a
crucial step in obtaining operations participation.
Recommendation #7
The new Asset Management System for Waukegan under design by the FBI team
should contain the following capabilities:
C-3
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Recommendation #8
The general practice at Waukegan Station is to write work requests for equipment
problems. However, in some cases this does not occur. It is recognized that this can
result in the loss of captured costs and history on assets in the plant. Therefore, work
requests will be written for all work done to assets in the Equipment Technology
matrix at Waukegan Station. By capturing work performed to an asset, Waukegan will
better be able to determine what type of predictive maintenance technology to use,
track all costs including lost revenue, and identify failure trends.
Note: Any station employee can initiate a work request using TJM. In the first quarter
of 1997 all TJM files will be transferred into an Asset Management System called
MAXIMO. This Asset Management System will provide more capabilities for tracking
asset costs and for trending asset performance.
Recommendation #9
1.0
0.9 S avings ($M)
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0.0
1 3 5 7 9 11
M o n th s
Figure C-1
Expected Heat Rate Benefits
C-4
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Waukegan Station
O&M Cost Reductions from PDM Program
1
0.9
Savings ($M)
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0 Months
Months
Months
Months
Months
1 Month
11
3
9
Note: This would reflect a reduction from $16M to $15M.
Figure C-2
Expected O&M Cost Reductions
Waukegan Station
Cost Savings from EFOR Reductions from PDM Program
8
% 6
5
4
Goal 3%
3
2 (1.2 million)
1
0
5 Months
1 Month
2 Months
3 Months
4 Months
6 Months
7 Months
8 Months
9 Months
10 Months
11 Months
12 Months
Note: A reduction of EFOR to 7-8% would result in increased demand for Waukegan Station and
further reduce $cost per net MWHR. 1% EFOR reduction would result in a savings of $402,336.
Figure C-3
Expected EFOR Reductions
C-5
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Waukegan Station
Ratio of $ Spent PDM/$ Spent CM for Major (Top Ten) Equipment
0.8 80%
0.7
0.6
0.5
0.4
0.3
0.2
0.1 Current Personnel Perception
0
1996 1997 1998 1999
Note: The New Maintenance Management System Should Provide Capabilities to Track this Ratio.
Figure C-4
Ratio of PDM/CM for Major Equipment
15%
5%
● Corrective = 80%
80% ● Preventive = 15%
● Predictive = 5%
Figure C-5
Relative CM, PM and PDM Now
C-6
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Where Do We Want To Be ?
Corrective
Preventive
Predictive
5%
15%
● Predictive = 80%
80%
● Preventive = 15%
● Corrective = 5%
Figure C-6
Expected Future Relative CM, PM and PDM
Implementation
Waukegan Station's Process Teams will work together to improve the reliability and viability of
the Station. PDM is an integral part of this process. Equipment will be operated and maintained
based upon proper collection and analysis of data. Proven technologies, including vibration
analysis, oil analysis, IR/Thermography, motor current analysis, and ultrasound/leak detection
will provide the necessary information needed to make sound, informed decisions of equipment
condition. Root cause analysis and Proactive Maintenance strategies will be utilized to prevent
future failures.
In order for a PDM Program to succeed, we must first increase the level of awareness
in the technologies available for assessing equipment condition. Plant personnel must
C-7
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
be trained in the various technologies so they may begin the process of gathering and
combining all the information available to make timely and informed decisions about
the operating practices and maintenance requirements of the plant equipment. This
information should include; diagnostic and performance data, maintenance histories,
operational logs, and design data. In addition, personnel must be trained in analyzing
the available data, creating reports, and capturing cost/benefit information supporting
their decisions. Finally, the PDM plan must be used as a 'Driver' for the efficient use of
our Asset Management System.
• Establish a formal PDM plan (70% of the issue for success is organizational -
communication)
• Identify the components that will impact the goals set in 1 and 2 if the PDM
program is effective; and, apply the respective technologies
In developing and implementing a PDM Program, the objective is to start with the most
critical components required for generation, and with the equipment that is costing the
most unexpected O&M expenditures and loss of availability. This is necessary in order
to use the limited resources available at the Station in the most effective manner.
C-8
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
• A listing of the severity criteria for the monitored equipment (i.e. alarm limits,
temperature anomalies, etc.)
• A Top 10 list of equipment for O&M cost and availability loss was supplied by the
Availability Systems Team using Station Maintenance Management System records
• The AST provided an equipment listing based on parts and labor costs
When examining Waukegan's Top 10 list for parts and labor costs, there were items not
included in the matrix. One example is Building and Grounds, which cannot be
influenced by PDM technologies. Others, such as Boilers, Sootblowers and
Electronic/Control systems will be included as the program progresses. Therefore,
these have not been included in the evaluation and formation of the Equipment &
Technology list for this plan.
The Equipment & Technologies (E&T) Matrices are included on the following pages of
this plan. A Matrix is included for each Unit (6,7, and 8).
C-9
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Table C-1
Unit #6 Equipment and Technologies
Equipment Vibs Interval Oil Interval IR Interval MtrCur Interval Acoust Interval
C-10
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Notes: Yes* = Fluid Drive Only, Yes** = Motor Control Cabinet, M* = Exhauster only; mill & motor Quarterly,
M = Monthly, Q = Quarterly, S/A = Semi-Annually
C-11
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Table C-2
Unit #7 Equipment and Technologies
Equipment Vibs Interval Oil Interval IR Interval MtrCur Interval Acoust Interval
C-12
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
C-13
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Notes: Yes* = Fluid Drive Only, Yes** = Motor Control Cabinet, M* = Exhauster only; mill & motor Quarterly,
M = Monthly, Q = Quarterly, S/A = Semi-Annually
C-14
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Table C-3
Unit #8 Equipment and Technologies
Equipment Vibs Interval Oil Interval IR Interval MtrCur Interval Acoust Interval
C-15
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Notes: Yes* = Fluid Drive Only, Yes** = Motor Control Cabinet, M* = Exhauster only; mill & motor Quarterly,
M = Monthly, Q = Quarterly, S/A = Semi-Annually
C-16
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
The following section contains Technology Application Descriptions (TADs) for each
technology being applied at Waukegan Station. The TADs will answer the Who, What,
When, and Where questions on the application of each PDM technology at Waukegan
Station. They will serve as outlines for the use of the various technologies by
prescribing guidelines and responsibilities for the implementation and support of each
technology.
Vibration TAD
Technology Application
Activities
Support Steps:
C-17
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Support steps:
Responsibilities
• Station Leads, as the sustaining sponsors, will commit the appropriate resources
such as capital and personnel to become the vibration specialists within each team.
This will be necessary for the collection and analysis of data.
• The Process Specialist will be responsible for coordinating data, assigning problem
severity, initiating action, coordinating post maintenance surveys, documentation
distribution and case closing of any finds.
• The Predictive Specialist will support the PDM efforts of the Process Specialists and
the Process Teams.
Resource Requirements
• Each team will provide one member to be trained; however, all members will
subsequently be trained. Team members will report survey results to the Process
Specialist.
• SMAD will provide technical support as needed, including fast response to special
problem diagnostic testing/analysis.
Training Requirements
C-18
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Miscellaneous Requirements
Lubrication TAD
Technology Application
Lubrication samples will be taken for the purpose of analysis by the appropriate
resource. This technology will be combined with vibration analysis data. One
technology serves as an important backup to the other. Careful coordination of these
two technologies increases the value of both.
Activities
Support Steps:
2. Establish PM routes in the Asset Management System for automatic generation and
scheduling.
Support steps:
Responsibilities
• Station Leads as sustaining sponsors, will jointly commit the appropriate resources,
such as capital and personnel necessary for the collection and analysis of data.
• The location and installation of quality sample points will be the responsibility of
the Process Specialists with assistance from the PDM Specialist and support from
C-19
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
the appropriate teams. This is vital to the program as it ensures quality samples and
repeatability of data.
• The Process Specialist will be responsible for coordinating data, assigning problem
severity, initiating action, coordinating post maintenance surveys, documentation
distribution and case closings for any finds reported.
• The PDM Specialist will support the PDM efforts of the Process Specialists and the
Process Teams.
• The resulting data from surveys will be reviewed by the Process Specialist, SMAD,
and PDM Specialist.
• An outside resource will provide OJT on proper sampling techniques, sample port
locations, as well as basic data interpretation.
Resource Requirements
• SMAD will provide technical support as needed, including fast response to special
problem diagnostic testing.
Training Requirements
• Data interpretation.
Miscellaneous Requirements
C-20
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
IR Thermography TAD
Technology Application
Activities
Support Steps:
2. Establish PM routes in the Asset Management System for automatic generation and
scheduling.
Responsibilities
• Station Leads, as the sustaining sponsors, will commit the appropriate resources
such as capital and personnel to become the IR/Thermography specialists within
each team. This will be necessary for the collection and analysis of data.
• The Process Specialist will be responsible for assigning problem severity, initiating
action, coordinating post maintenance surveys, documentation distribution and case
closings for any finds reported.
• The PDM Specialist will support the PDM efforts of the Process Specialists and the
Process Teams.
Resource Requirements
• Each team will start with one member trained. Subsequently, all members will be
trained. Team members will report survey results to the Process Specialist.
C-21
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
• SMAD will provide technical support as needed, including fast response to special
problem diagnostic testing/analysis.
Training Requirements
Miscellaneous Requirements
• EPRI supplied software (IR-SIP) will be the reporting software of choice. Any
additional software/hardware needed will be provided by the Station or Division.
Ultrasonic TAD
Technology Application
Activities
• Periodic ultrasonic and acoustic leak detection surveys on all critical plant valving,
gearboxes, compressed air and gas systems, and other applicable equipment as
determined by Operations with recommendations by the Process Specialist and
SMAD. These surveys should be identified through an asset management system.
Support Steps:
2. Establish PM routes in the Asset Management System for automatic generation and
scheduling.
C-22
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Responsibilities
• The Operations Leader will determine and provide the appropriate resources such
as capital and Shift Team members necessary for the collection of data. This will be
coordinated by the Process Specialist.
• Operations should establish a survey route and prepare data sheets using ComEd
standard software such as Microsoft Excel spreadsheets. The Process Specialist will
provide support in the formation of the routes in the Asset Management System and
data sheets.
• Operations will report survey results to the Process Specialist. Technical direction
will be provided by the PDM Specialist and SMAD.
• The Process Specialist will be responsible for assigning problem severity, initiating
action, coordinating post maintenance surveys, documentation distribution and case
closings for any finds reported.
• The PDM Specialist will support the PDM efforts of the Process Specialists and the
Process Teams.
Resource Requirements
• SMAD will provide technical support as needed, including fast response to special
problem diagnostic testing/analysis.
Training Requirements
Miscellaneous Requirements
Technology Application
motor condition. This will assist the station in determining which motors need
attention, rather than basing motor repairs on time.
Activities
Periodic surveys on all motors currently included in the Equipment & Technology
matrix. These surveys will be identified through an Asset Management System.
Support Steps:
2. Establish PM routes in the Asset Management System for automatic generation and
scheduling.
Responsibilities
• Station Leads, as the sustaining sponsors, will commit the appropriate resources
such as capital and personnel to become the motor current analysis specialists
within each team. This will be necessary for the collection and analysis of data.
• The Process Specialist will be responsible for coordinating data, assigning problem
severity, initiating action, coordinating post maintenance surveys, documentation
distribution and case closings for any finds reported.
• The PDM Specialist will support the PDM efforts of the Process Specialists and the
Process Teams.
Resource Requirements
• Each team will start with one member trained. Subsequently, all members will be
trained. Team members will report survey results to the Process Specialist.
• SMAD will provide technical support as needed, including fast response to special
problem diagnostic testing/analysis.
Training Requirements
C-24
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Miscellaneous Requirements
Organization
2. The PDM Specialist will attend the current weekly process meetings to address any
equipment condition indications from the PDM program which cannot be shelved
until the bi-monthly meetings.
— Operations Leader.
— Shift Advisor.
— Maintenance Leader.
— Maintenance Coaches.
— Maintenance Planner.
— Process Specialists.
— Plant Manager.
C-25
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
5. A report resulting from the periodic acoustic surveys of plant air systems should be
generated with exceptions requiring corrective action. The report should also be
forwarded to the above-listed personnel.
7. PDM program goals and progress should be posted along with the station O&M,
EFOR, EA, and heat rate performance, quarterly.
8. Tracking of the ratio of dollars spent for maintenance as a result of PDM vs. dollars
spent on corrective maintenance for major equipment.
Standard Reports
• Diagnostic Graphs.
• Performance data.
• by process.
• by systems.
• by monitored equipment.
The following are some of the reports that will be available in the new Asset
Management System:
• Equipment History Graph - Graph showing mean time between failure, total
equipment costs, and total downtime hours.
C-26
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
• Weekly Station Schedule by Process Team and Dates - Schedule showing predictive
and preventive task starts and completions by equipment.
• Summary failure report - Report showing problem description, most recent failure,
number of equipment failures, MTBF, average downtime, and equipment name.
Load
Operations Logs 80 - 85% Dispatch
Data
Operations Shift
Load Critical
Advisors
Work
System of Process 10 - 15% Process Bins Shift Advisor Shift Assistant
Data Process (1 Per Process) Equipment (Permits, Blocks
Coaches & Availability and Schedule)
Mechanics
Diagnostic Data Shift Advisor Review
A, B
(Specialist Informed)
Process Coach
Batch Testing Data Priority Evaluation
All Others
and Assignment
Process Specialists B,C If Top-Ten
Etc.
Maintenance Planners Create Outage
Histories (EWCS) Work Request Backlog Plan
PM Schedule Rework
Work Execution Notification
Permits Cleared
Eng. Ops. Maint. Process Team
Experience Work Order Post Maint. Mechanic Minor PMs
Close Out Test/Check Work Performed (blanket W.OS.)
Coach Ops. & Maint.
A - causes unit der ate
Planners B - within 5 days
History TJM enters work Rework
history C - can be planned
Evaluation
Figure C-7
Current Work Flow at Waukegan For Major Equipment
C-27
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Work Flow at Waukegan for Major Equipment With PDM Program Implementation
Resources Data Analysis Work Planning
Load
Operations Logs 80 - 85%
Data Dispatch
Operations Shift
Load Critical
Advisors
Work
System of Process 10 - 15% Process Bins Shift Advisor Shift Assistant
Data Process (1 Per Process) Equipment (Permits, Blocks
Coaches & Availability and Schedule)
Mechanics
Diagnostic Data Shift Advisor Review
A, B
(Specialist Informed)
Process Coach
Batch Testing Data Priority Evaluation
All Others
and Assignment
Process Specialists B,C If Top-Ten
Etc.
Maintenance Planners Create Outage
Histories (EWCS) Work Request Backlog Plan
PM Schedule Rework
Work Execution Notification
Permits Cleared
Eng. Ops. Maint. Process Team
Experience Work Order Post Maint. Mechanic Minor PMs
Close Out Test/Check Work Performed (blanket W.OS.)
Coach Ops. & Maint.
A - causes unit der ate
Planners B - within 5 days
History TJM enters work Rework
history C - can be planned
Evaluation
Figure C-8
Work Flow at Waukegan for Major Equipment with PDM Implementation
Waukegan Organization
(PDM Program Roles and Responsibilities)
• Review and Approve PDM Implementation Plan
Plant Manager
• Review Cost Benefit Analysis - semi-annual
• Enable the PDM process
Figure C-9
Organizational Charts Including PDM Strategies
C-28
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Process Specialists
Process Specialists will facilitate the PDM activities performed on the assets within their
Process Areas. The Specialists will:
• Be trained in all technologies associated with PDM, and pass this knowledge to the
Teams.
• Ensure that proper operational or maintenance actions are taken based on PDM
recommendations.
• Recommend ways of reducing the frequency, duration, and extent to which any
maintenance activities are performed.
• Review assigned systems for evaluation of any PDM monitoring technologies that
could improve availability and/or reduce O&M costs.
• Coordinate with PDM Specialist for necessary support for the diagnosis and
analysis of data.
PDM combines and uses a variety of data in order to make decisions based on
equipment condition. While PDM requires management support, and in many cases
technical assistance, the Coaches and Process Team members also play an integral part
of this process. Their involvement in the process includes the following:
C-29
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
• Coaches will be trained in all technologies associated with PDM, and pass this
knowledge to the Teams.
• Vibration data collection and analysis, including installation of monitors and taking
hand-held readings on equipment.
The PDM Specialist will support the implementation of the PDM program. They must
be involved in the planning process. They will transfer PDM skills and knowledge to
the Process Team level. The PDM Program should be viewed as a project with plant
maintenance and operations personnel performing PDM functions for the major
components within their areas of responsibility. The roles and responsibilities in this
process are as follows:
• Provide support to the Process Specialists and Team Coaches for PDM program cost
benefit tracking.
• Facilitate the implementation of the PDM program for the identified critical
components using the selected technologies, and integrate this information with the
process teams.
C-30
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
• Assist Process Specialists and Teams in Root Cause Analysis and Proactive
Maintenance applications.
• Provide services to all Process Teams regarding the condition of all major
equipment in the Station.
• Review PDM reports with Process Specialists and make recommendations for
action.
Operations Department
Operations Lead
Operations
• Assist Process Teams in the creation of equipment monitoring routes and data
collection.
C-31
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
• Operations logged data collection reporting run times equipment starts and stops,
etc.
Upper management support of PDM is critical to the success of the program. Top
down commitment and support is necessary in order to instill the philosophy of
condition-based maintenance into the organization as a permanent way of doing
business. To accomplish this, the site leadership is responsible for the following:
• 'Champion' the change - keep it visible and make it part of the 'culture'.
• Review staffing assignments to ensure that the necessary resources are committed to
the program.
C-32
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
I/S Specialist
• Coordinate the EMPM Program in conjunction with the Rotating Machinery group
and the PDM Specialist.
Maintenance Planners
The Maintenance Planners must integrate the PDM strategies with daily, long term,
and outage planning. To accomplish this they should ensure the following:
• Track CM/PM/PDM/Performance/Component.
• Work Requests will be written for all maintenance problems involving equipment
contained in the Equipment and Technologies matrix and/or identified through the
use of PDM technologies.
• Technology routes and surveys will be set up and performed using PM work
requests generated both manually and automatically by the Asset Management
System.
C-33
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Financial
The following Planning and Estimating (P&E) Guides have been developed for the
various technologies to be included in the Station's PDM program. The projected
savings shown demonstrate the potential dollar benefits that can be realized when
implementing the technologies and the PDM program.
As new technologies are added to the program, new cost saving projections will be
prepared. Tracking the actual cost savings can be compared with these projections as
the PDM program matures, to verify real dollars saved.
C-34
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Material Subtotal $46,000 (5) Most program start-up labor costs at Crawford have been
previously spent for equipment selection and route
Labor (5) set up. New software/hardware purchase and further
Engineering 20 man-days $304 (6) $6,080 plant personnel training is still required.
Training - Mechanics 30 man-days $304 (7) $9,120
Secretarial $0 (6) Four Process Specialists attend one-week vibration training.
$2,000,000
Cumulative Cost
$1,500,000
Cumulative Gross Benefit
$1,000,000 Cumulative Net Benefit
Figure C-10
Planning & Estimating Guide, System: Periodic Vibration Monitoring
C-35
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
$600,000
$500,000
$400,000 Cumulative Cost
$300,000 Cumulative Gross Benefit
Cumulative Net Benefit
$200,000
$100,000 Five Year Cumulative
$0 Net Benefit:
1 2 3 4 5 $499,704
Year
Figure C-11
Planning & Estimating Guide, System: Periodic Acoustic Leak Detection
C-36
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Labor Subtotal $12,160 (7) Labor necessary from ICE team and other station personnel.
Annual Operation & Maintenance Costs (9) SMAD support for data analysis and troubleshooting.
O&M Labor 44 man-days $304 (7) $13,376
Training Labor 5 man-days $304 (8) $1,520 (10) Misc. supplies, materials, and annual equipment upgrade.
Training Tuitions 2 course $2,000 (8) $4,000 ($8,500 equip. $2,000 misc.)
SMAD Support 12 man-days $320 (9) $3,840
Misc. Materials & Equip. Misc. Misc. (10) $10,500
$3,000,000
$2,500,000
$2,000,000 Cumulative Cost
Cumulative Gross Benefit
$1,500,000
Cumulative Net Benefit
$1,000,000
$500,000 Five Year Cumulative
$0 Net Benefit:
1 2 3 4 5 $2,459,953
Year
Figure C-12
Planning & Estimating Guide, System: Infrared Thermography (Plant)
C-37
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
1,000,000
800,000
Cumulative Cost
600,000
Cumulative Gross Benefit
400,000 Cumulative Net Benefit
200,000
Five Year Cumulative
0 Net Benefit:
1 2 3 4 5
$636,960
Year
Figure C-13
Planning & Estimating Guide, System: Electric Motor Predictive Maintenance
C-38
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Material Subtotal $2,000 (4) Hands-on training for data collection and
handling of samples by the operators.
Labor
Chemist/Engr. Support 10 man-days $288 (2) $2,880 (5) Miscellaneous supplies/materials.
Maintenance Labor 20 man-days $288 $5,760
Network Support 3 man-days $288 (4) $864 (6) Process Specialist involvement in equpment
Training 10 man-days $288 $2,880 selection.
(7) Coordination of lube oil program will be
Labor Subtotal $12,384 performed by the PDM Specialist (hours are
captured
Figure C-14
Planning & Estimating Guide, System: Lube Oil Monitoring
C-39
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Labor
Engineering $0
Training $0
Planners $0
Secretarial $0
Labor Subtotal $0
Figure C-15
Planning & Estimating Guide, System: Integrated Predictive Maintenance Program
C-40
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Table C-4
Cost Summary
Note: Approximately $150,000 of the $225,436 annual recurring cost is ComEd labor.
A Cost Benefit Analysis (CBA) worksheet should be filled out whenever a predictive
maintenance technology has been used to identify a potential problem with a piece of
equipment, and a corrective action was initiated.
This process will be performed by the Process Specialists, Team members, with support
from the PDM Specialist.
The following section outlines the steps involved in preparing a CBA Worksheet:
C-41
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Only the first sheet of the CBA worksheet will have any information added to it. All
calculations are performed on the second page of the worksheet, based on entries on
the first page.
Starting at the top of the page, the unit-specific fields must be filled in, including
Occurrence number. It is recommended that a standard numbering system be used,
including a station designator, such as CRA for Crawford, J29 for Joliet 29, etc. plus an
Occurrence number as shown on the sample worksheet. Crawford's first Occurrence
for 1996 would be shown as CRA96-001.
This section of the CBA will need to be filled out on a Unit by Unit and Occurrence by
occurrence basis. Enter the potential de-rating caused by loss of or failure of this piece
of equipment in the field marked "Power Reduction", enter the expected number of
hours the de-rating would last, and indicate (with a 1=yes and 0=no) if it will be a
forced outage. This will figure into the EFOR calculation later.
Maintenance Costs
The section relating to Maintenance Costs will require some research, usually through
the Maintenance Management Program, (TJM or EWCS). Costs associated with past
maintenance repairs, including both parts and labor can be found in both TJM and
EWCS and should be used as the basis for the "Cost of Parts" and "Labor Hours" fields
on the worksheet.
This section will require a consensus from a cross-section of personnel from your site.
People familiar with the equipment should be brought together for a brief meeting to
discuss the finds, the actions required and, based on a wide range of operating and
maintenance experience, an agreement on the probability of each scenario actually
occurring should be reached. The combination of probability for all possible scenarios
must equal 100%.
C-42
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
This section of the worksheet shows the values which have been calculated based on
the numbers you enter on the worksheet. The Total Cost Benefit for this Occurrence,
Maintenance Cost Savings, and impact on EFOR will change as the numbers above are
added or modified.
Input Data
The box labeled "Input Data" contains two numbers that the calculations are based
upon, and should not be modified. Any change to the Average Replacement Power
Costs or the Average Labor Rate will change the resulting figures for the CBA and will
hamper efforts to accumulate total saving for the Fossil Division
C-43
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Definitions:
OCCURRENCE - any detected or diagnosed fault which the station takes action, whether the action was proactive or reactive.
When the station schedules repairs or modifies plant operation to minimize the fault's impact, a cost benefit analysis will be conducted.
If maintenance is deferred based on a PDM technology, the CBA, based on the deferral, will be calculated on the time-value of $$$ saved.
CATASTROPHIC - Total equipment failure requiring full repalcement.
MODERATE - System failure resulting in some repairable equipment damage.
LOSS OF PERFORMANCE - Reduction of operating capacity due to fault.
ACTUAL - Actual cost of outage.
Input Data
Calculated Values
Total Cost Benefit - This Occurrence $855,637 Average Replacement Power 9
Maintenance Costs Savings ($): $177,792 Costs ($/MWH)=
Impact on EFOR (%): 4.97
Figure C-16
Occurrence Assumption and Cost Benefit Worksheet
Training Program
Training Matrix
This section contains a training matrix along with training type descriptions of the
suggested classes. Listed also are the suggested recipients of this Predictive
Maintenance training, prerequisites, and possible resources . Specific classes may be
C-44
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
developed in the future to address specific needs of the Teams under the direction of
SMAD and the PM Specialist.
Process
Process PDM Specialist/ Maintenance Station
PDM Activity Training Type* Teams Specialist Coaches Operations Planners Leadership
Figure C-17
Typical Training Matrix
Predictive Maintenance
A. Level of Awareness
Available Resources:
Thermography
A. Level of Awareness
Provides an overview on the use of portable infrared (IR) scanners to record thermal
images and monitor conditions on a variety of equipment in a power plant setting. The
C-45
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
session includes hands-on demonstrations with the IR camera and the presentation of
various case histories.
Available Resources:
• PDM Specialist
• SMAD
• Outside vendor
B. Application
Available Resources:
• PDM Specialist
• SMAD
• Outside vendor
C. Analytical
Covers physics, advanced theory, and application knowledge needed to analyze data
and recommend solutions.
Available Resources:
• Vendor supplied/SMAD
Vibration
A. Level of Awareness
Provides and overview on the use of various sensors to monitor vibration of plant
equipment. Data gathering methods, the analysis of information, and the benefits of
vibration analysis are included in the topics discussed during the session.
Available Resources:
C-46
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
B. Application I
This course covers the basics of vibration monitoring, techniques and the applications
for the diagnosis of machine condition. The course reviews the use, including pitfalls,
of the various diagnostic tools used today.
Available Resources:
• PDM Specialist
• SMAD
C. Application II
This course will cover the basics needed to utilize the equipment and software
currently in use at the Stations, including data collection by routes using the TEC
Smartmeter 1330 and Intellitrend software.
Available Resources:
• Vendor supplied/SMAD
• PDM Specialist
D. Analytical
These courses build on the knowledge from Basic Vibration Testing and Analysis. This
includes Machinery dynamics, instrumentation, use of FFT analyzers for diagnostics,
sources of vibration and other advanced techniques.
Available Resources:
• Vendor supplied/SMAD
C-47
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
Oil
A. Level of Awareness
Provides an overview on the use of oil sampling to perform wear particle analysis.
Also included in the discussions are the proper techniques for obtaining samples from
equipment, and the logistics involved in setting up an oil analysis program.
Available Resources:
B. Application
Available Resources:
• Vendor supplied/SMAD
C. Analytical
Available Resources:
• Vendor supplied/SMAD
Ultrasound/Acoustics
A. Application
This training will teach plant personnel utilization of the instrumentation and practical
application of Acoustic/Ultrasonic Leak Detection as it applies to valves, flanges,
pressure vessels, air and gas systems.
Available Resources:
• Vendor supplied/SMAD
C-48
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
A. Level of Awareness
Available Resources:
• ICE Team
• SMAD
B. Application
This course will cover the basics of determining electric motor condition through
periodic testing of motor currents. Included will be the use of the TEC Smartmeter 1330
as a diagnostic tool for motor current analysis.
Available Resources:
• SMAD
PDM Reporting
A. IR-SIP
Available Resources:
• PDM Specialist
• EPRI M&D
C-49
11667179
EPRIGEN Licensed Material
Waukegan Station PDM Plan
B. PDM ESR
Computer based database reporting system that links Excel and Access functions to
integrate the tasks of organizing and reporting PDM program findings and equipment
conditions.
Available Resources:
• PDM Specialist
• EPRI M&D
A. Asset Management
Courses are being developed to tailor training to individual roles and responsibilities.
Available Resources:
B. Operations Information
Courses are being developed to tailor training to individual roles and responsibilities.
Available Resources:
C. PI Archival System
Available Resources:
• IS Group
• PDM Specialist
C-50
11667179
EPRIGEN Licensed Material
D
STRENGTHS, OPPORTUNITIES, AND
RECOMMENDATIONS EVALUATIONS
As a result of the PDM Assessments, visits to the various ComEd plants to conduct
Level of Awareness (LOA) training sections, and the ensuing discussions, included is a
summary of the Strengths, Opportunities, and Recommendations to be considered by
ComEd in the PDM Implementation process.
Strengths
4. Good knowledge of what is RCA and how to do it, this helps with understanding
how the system works.
5. Good communication:
— Daily huddles
— PDM hotline
— CCmail
— Verbal (phone)
— CETV
— C.B.A.
6. Commitment of the money and available manpower to the PDM program is good
(non-operations).
8. In general, people are aware of PDM and feel it is working and providing value. It
is still in the early stages of implementation.
11. Doing Cost/Benefit analysis for major PDM occurrences is allowing plant personnel
to recognize PDM value and justify program costs (still some opportunities).
12. A substantial amount of training has been done to date and is a major reason for
early success of PDM.
13. Program is doing well with the bargaining unit participation being voluntary.
Opportunities
4. Establish and get input from all departments on a formal PM program and create
measures.
D-2
11667179
EPRIGEN Licensed Material
Strengths, Opportunities, and Recommendations Evaluations
6. Raise awareness and focus of PDM on 5 equipment problems for each process.
8. Provide more detail to all plant personnel regarding how work is prioritized:
— All other
10. Re-instate Ops walk-down checklist - but specifically data that will be used in the
E&T matrix.
15. Continue to work on the bargaining unit agreement for increasing participation of
craft personnel in PDM.
Recommendations
D-3
11667179
EPRIGEN Licensed Material
Strengths, Opportunities, and Recommendations Evaluations
3. Review E&T matrix with Operations specifically for process data points.
5. Process Specialists given responsibility to approve when an RCA will be done, and
they will also follow up on RCA recommendations.
— All other.
10. Reinstate Op's walk-down checklist specifically for data to be included in the E&T
matrix.
14. Continue to work on the bargaining unit agreement for increasing participation of
craft personnel in PDM.
15. Continue to work on the bargaining unit agreement for increasing participation of
craft personnel in the PDM Program.
D-4