Professional Documents
Culture Documents
Case Study - Improving System Performance Using Distribution Network Automation
Case Study - Improving System Performance Using Distribution Network Automation
Case Study - Improving System Performance Using Distribution Network Automation
Published in
Wide-Area Protection and Control Systems: A Collection of
Technical Papers Representing Modern Solutions, 2017
Abstract—After receiving a U.S. Department of Energy electronic devices (IEDs) because the system was primarily
co-funded Smart Grid Investment Grant, Westar Energy deployed for system restoration and voltage control, which do
implemented an economical and powerful distribution not require high-speed communications.
automation (DA) system that includes fully automated fault
location, isolation, and service restoration (FLISR) functionality
While Lawrence customers are the first to benefit from
and volt/VAR control. The system described in this paper uses a these new capabilities, experiencing fewer outages and a
centralized distribution automation controller (DAC) for reduction in outage durations, the company plans to install
automated feeder voltage profile optimization that remains fully similar equipment throughout its service territory. Application
functional alongside an FLISR system, which can change the of a centralized distribution automation controller (DAC) and
power system topology. Additionally, the DA system provides security gateway hardware at Westar Energy has opened the
intelligence and mitigation for miscoordination detection and
overload avoidance.
door to the secure, system-wide deployment of
One of the unique aspects of the DA system is that it is able to communications devices across the entire Westar territory.
translate between various communications protocols. It also The DA system was designed to maximize system
interfaces with the existing energy management system and effectiveness, allow for improved system awareness, and
integrates some existing Westar legacy equipment with new increase work efficiencies across the company, namely as a
equipment and controls. Cellular modems and a secure Ethernet result of the new remote access capabilities. The SmartStar
gateway provide secure wireless access to the distributed controls
Lawrence DA project was a success and has provided valuable
throughout the distribution system. Engineers use this remote
access along with event collection to improve settings and system experience that will be leveraged as Westar Energy continues
operation. to expand DA to other parts of their system.
This paper describes the objectives of implementing the new
Westar DA system, characteristics and capabilities of the system, II. DISTRIBUTION AUTOMATION SYSTEM OBJECTIVES
system implementation, system performance during real-world
events, and implications for future implementations throughout
Westar Energy identified the following objectives that they
the Westar territory. wanted to achieve through implementing a pilot DA system:
• Increase system reliability [1].
I. INTRODUCTION • Reduce outage restoration times.
In 2010, Westar Energy was awarded a U.S. Department of • Minimize distribution system losses.
Energy (DOE) co-funded Smart Grid Investment Grant for the • Reduce system loading during peak conditions.
SmartStar Lawrence project. The three-year project consisted • Improve system operation and understanding.
of installing advanced metering infrastructure, a meter data • Improve service to customers.
management system, and distribution automation (DA). To minimize the impact on the distribution system
Westar Energy is an investor-owned electric utility founded in operators, Westar Energy also wanted to pass information
1910 that serves approximately 690,000 customers in the from the DA system to the existing EMS so that a separate
eastern portion of Kansas. The company chose Lawrence, interface would not be needed. The operators could then use
Kansas, as the initial location for implementing this the same system that they were already intimately familiar
technology because of its size and customer base, which with operating.
includes many student residents, commercial and industrial
customers, and educational institutions. III. PILOT DA SYSTEM
This paper describes how Westar Energy implemented a The DA system was implemented on 24 of the
cost-effective DA system that is now providing a very capable 1,227 circuits across the Westar distribution network. The
and fully automated fault location, isolation, and service feeder circuits used reclosers at normally open tie points to
restoration (FLISR) and volt/VAR distribution solution. The interconnect two or more power sources. Additional reclosers
system translates between various communications protocols were installed throughout the feeder circuits to allow
and interfaces with the existing Westar energy management sectionalizing capabilities in the event that permanent faults
system (EMS). The implemented DA system also integrates occur on a line section. Fig. 1 shows some of the distribution
some existing Westar legacy equipment. Cellular modems circuits, the interconnection switches, and three different
were used for communications to the remote intelligent substations that can be used as sources for the feeders.
2
Fig. 1. EMS one-line diagram showing normally open (NO) and normally closed (NC) switch points
The equipment used in the DA system included the operators change the state of the switches in the OMS, this
following: information is also passed to the DAC.
• Thirty-three new recloser controls and satellite-
A. Protocol Conversion
synchronized clocks paired with the new reclosers.
Several communications protocols were implemented
• One legacy recloser and recloser control.
across the DA system, including DNP3, Modbus®, and other
• Fifty-three capacitor bank controls retrofitted to
open protocols. The protocols were selected either because of
existing capacitor banks.
legacy equipment limitations or to provide the desired IED
• Ten substation transformer load tap changer (LTC)
functionality. In turn, the DAC acts as a multiprotocol
controls (six of which needed to be upgraded).
interface to all of the IEDs, allowing them to participate as
• Thirty-nine existing nontelemetered switches. peers in a unified, holistic system. Additionally, the DAC
• Eighty-seven 3G and 4G LTE cellular modems for provides port routing functionality for remote access
feeder IED communications and control. capabilities using various proprietary software interfaces. This
• One DAC, providing centralized system intelligence. allows a mix of new and legacy IEDs as well as controllers
• One Ethernet security gateway, providing from different equipment manufacturers to be used, thus
comprehensive security measures including automated minimizing the installation time and the cost associated with
password management of the IEDs. implementing the system.
Leveraging existing communications and controls, the
DAC communicates with the substation transformer LTC B. Wireless Communications
controls and protective relays via messages transmitted Westar Energy chose to leverage cellular technology for a
through the EMS to the substation remote terminal units number of reasons. Because the automation system was
(RTUs). In order to maintain an awareness of the system primarily deployed for system restoration and voltage control,
configuration and of abnormal system operating conditions, a high-speed communications were not required. All protection
server-based software solution monitors the Westar outage functions are performed locally within the IEDs, so the loss of
management system (OMS) and provides the status of the communications is acceptable, although not desirable. It was
nontelemetered switches in the system to the DAC. Whenever also recognized that the design, deployment, and
3
maintainability of a company-owned communications system integration. The initial DAC programming was provided by
would require a significant capital investment and would the DAC manufacturer. FLISR and volt/VAR programming
result in long-term operation and maintenance expenses. were included by creating a system model and configuring
However, there would be the advantage of no recurring carrier standard DA libraries for the Westar distribution system.
charges. This type of deployment would also stress the Human-machine interface (HMI) displays were also
technical workforce at Westar Energy, both in the present and developed for use during commissioning and testing.
in the future. Planned obsolescence would also need to be Cellular GPS
factored into the system and would require another capital- Antenna Antenna
intense system upgrade of the communications network in the
future. Moreover, performance of cellular communications has Cellular Compact
DNP3 Via Ethernet
Modem GPS Clock
been evaluated by Westar Energy and others (refer to [2]) and Engineering Access
Via Serial
was found to be adequate for the new DA system.
IRIG-B
The initial setup of the cellular modems and antennas
proved to be a challenge. However, making an adjustment to Recloser Control