CONSTRUCTION OF PAVING BRICK AND CONCRETE BEAM AT EDGE OF APRON

BILL OF QUANTITIES AND RESOURCES INPUT COSTS `


Item No. Description Unit QTY Rate UGX Amount UGX Executed QTY
Paving bricks -
a) prepare excavated loose base compacted
m³ 14 65000 910,000
murram
b) Concrete edge beam as protection along the
m³ 1.26 590,000.00 743,400
edge of and
provide asphalt .
lay Double-T pavers 60mm on
m² 70 45,500.00 3,185,000
compacted
b) Concrete edgebase
sand beam as protection along the
m³ 4.2 590,000.00 2,478,000
edge of open drain stone pitching.
compacted sand base for receiving pavers m³ 7.00 65,000.00 455,000
TOTAL 7,771,400
comments Certified Amount