Professional Documents
Culture Documents
205 - Guide To Quick Die Changes - 2016
205 - Guide To Quick Die Changes - 2016
Guide to Quick
Die Changes
Publication # 205
Although great care has been taken to provide accurate and current information, neither the author(s)
nor the publisher, nor anyone else associated with this publication, shall be liable for any loss, damage
or liability directly or indirectly caused or alleged to be caused by this book. The material contained
herein is not intended to provide specific advice or recommendations for any specific situation.
Any opinions expressed by the author(s) are not necessarily those of NADCA.
Trademark notice: Product or corporate names may be trademarks or registered trademarks and are used
only for identification and explanation without intent to infringe nor endorse the product or corporation.
© 2016 by North American Die Casting Association, Wheeling, Illinois. All Rights Reserved.
Neither this book nor any parts may be reproduced or transmitted in any form or by any means,
electronic or mechanical, including photocopying, microfilming, and recording, or by any information
storage and retrieval system, without permission in writing from the publisher.
Quick Die Change
Table of Contents
Sustain
5S & Visual Controls This means making a habit of properly maintaining correct proce-
dures. Employees must be committed to maintaining 5S condi-
tions. This will require hourly, daily, weekly and yearly efforts.
5S is Consists of five activities that all start with the letter “s.”
These 5 S’s are:
Often a 6th “S” is added as the word “Safety.” Initially, this
might seem like a wasted “S,” but it is important to always re-
Sort
member that the other steps should be pursued in a safe manner.
Set in Order It is not hard to imagine a scenario where safety doors may be
Shine removed or modified in an effort to make it easier to clean. Be-
havior like this which increases the risk in the die casting plant
Standardize
should never be encouraged or tolerated.
Sustain
If your plant has already implemented the 5S discipline, intro-
ducing and implementing SMED should be fairly straight-
Sort forward. This is because many of the disciplines and cultural
This means that you remove from the workplace all items that changes required for 5S are also requirements for SMED.
are not needed for current production. Toolboxes are a perfect One more thought in this chapter on perspective. We should
example of an area that can be sorted. Most tasks in die casting recognize the contributions of Dr. Shigeo Shingo. Dr. Shigeo
require a limited set of tools, but a quick survey of toolboxes will was an international consultant with the greatest impact on
reveal wrenches that have never been used because they do not fit manufacturing with his teachings in three concepts:
any bolts on the die casting machine. Also, while looking at your
toolboxes do not forget to look at machines as well. Equipment • Just in time ( JIT)
that is not used/needed should be removed from the workplace. • Single Minute Exchange of Dies (SMED)
• Zero Quality Control
There is an exercise that works well for sorting. Simply remove
everything from the work cell to an inconvenient yet accessible
As part of JIT, Dr. Shigeo pioneered the concept of SMED.
area. For example, all the non-essential items from a die casting
SMED was developed in order to reduce the fixed cost associ-
cell could be moved to the die storage warehouse. Over the fol-
ated with the setup and changeover of dies. The basic elements
lowing 2-4 weeks the workers should be allowed to go get what-
driving the SMED concept are to reduce the setup time of dies,
ever they need for their job and return it to the cell when it is
which directly result in smaller batch sizes of parts. A smaller
needed. After the 2-4 week period is over anything that has not
batch size translates as lower cost associated with work in process
returned to the work cell is clearly not needed for production.
(wip) inventory storage, as well as raw material and finished goods
inventories. This concept is especially beneficial as it allows the
manufacturing system to quickly adjust to engineering design
Set in Order changes with very little costs. In addition, SMED allows higher
This is arranging needed items so they are as close to the point machine utilization and in turn results in higher productivity.
of use as possible and identifying them so they are easy to find
and put away. Most people have seen examples of this “s” in the Dr. Shigeo’s approach to developing the SMED concept was
form of shadow boards. These boards are located at the point of to isolate and identify the setup time as two entities: internal
Function Checklist
CstgDie: 3000
Operation: Function check
Date: Jun-05
Employees trained for function check
John B. Ted A.
Visual check
Cover cavity: cores and mounting screws tight
Eject. Cavity: cores, ejector pins, mounting
screws tight
Ejector plate: Pins free and lubed, mounting
screws tight
Ejector plate: Insert spacer block, check heights of
all ejector. Pins in cavity to spec.
Tools required
3/4 Allen key Figure 4.3: A portable preheating station.
1/2 Allen key
1215 master ejector spacer block
Standard Operating Procedure
SOP F3000 (Function check)
Figure 4.2: Example Function check D/N 3000.
External Activities After the DCM is restarted This completes the die setup. The unit die setup is pretty simple
1. Return portable die preheat station to its designated location. and already contains some of the techniques that are used to re-
2. Return Tool/Cleanup cart to it designated location. duce setup time. For example, the keyway on the mold base that
3. Return impact wrench and drivers to their storage locations. fits into the key slot in the unit die pre-positions the die half in
exactly the correct location and orientation.
Handling:
• Permanent eyebolts are attached to each die half (they could
be tack welded to prevent their loss).
• They are selected at a standard size to fit the hoist hook.
• They are installed in the top of the die to provide orientation.
• They are located to best balance the die.
Alignment:
• The keys in the master mold base and keyways in the unit
die provide alignment and positioning of the unit dies on
their respect mold base halves.
• Additional alignment between the die halve is provided by
leader pins or bushings in each unit die half.
Clamping:
• Two wedge clamps are used to force the die half onto the key-
way and hold it against the clamp plate or support parallel.
• The clamps are standard and interchangeable for this unit
system.
• Clamping heights/die thickness are standard for the unit
die system. Figure 4.7: Die storage using addresses to locate dies.
Figure 4.10: The die is slid into a tapered holder to clamp the die. Figure 4.11: This graduated scale is similar to a vernier used in measurement.
From the list above, all are already being done in die casting. How-
ever, these types of mechanization are typically best left for addi-
tion on new machines. As retrofit technologies they rarely make
sense from a pure dollars and cents calculation. On new machines
these forms of mechanization are like options on a car. For the
minor addition in cost, many of these features can be added.
Figure 4.12: Using V-block used to preposition a work piece.
Least Common Multiple System (LCM) Large Casting Dies
The principle for this system is to leave the machine mechanism For purposes of this publication, large CASTING DIE’s are
alone and only modify its function, and make settings not adjust- CASTING DIE’s run on 2000 ton or larger machines.
ments. For example, there is a tailrod attached to the crosshead of
the DCM. There is a limit switch, when activated by this tailrod, The same SMED principles applied to small dies are used for large
that stops the die opening, in effect controlling the die opening. die. The issue with large dies is they have a large mass and must be
This switch must be adjusted during setup to determine the op- moved and adjusted carefully. A large mass moving at high speed has
timum stroke. In order to eliminate this adjustment, several limit a lot of momentum (mass x velocity = momentum). You do not want
switches are mounted to be activated by the tailrod, and then the the CASTING DIE becoming a pendulum. When moving large
switch closest to the optimum opening stroke is selected for the dies, mechanically aids, as opposed to manpower, are required. If the
particular die being setup. See Figure 4.13. movement can be controlled robotically through programming, that
is even better. Then accelerations and decelerations can be controlled
A selector switch can now be used to select the limit switch closest and the large CASTING DIE mass can be positioned accurately
to the optimum die spacing. Again, this technique avoids having to without impacting the DCM. Keep in mind for safeties sake, there is
adjust the limit switch position. Modern PLC controlled die casting little that you can move or adjust on a large die, manually.
machines can select the correct switch as part of the part program.
This greatly reduces the potential for human error in the setup. Moving dies in and out of large die casting machines is aided by
machines equipped with automatic tie bar pullers. With tie bar(s)
4. Mechanization out of the way the assembled CASTING DIE can be lowered
Mechanization is considered only after the first three techniques have into the die space from above or slid in from the side. One of the
been exhausted. Mechanization does not usually yield large savings in first decisions to be made, when considering SMED for large
time because most of the time saving have already been achieved by dies, is will the DC be installed from the top or a side. This will
the time we get to mechanization. Also, mechanizing an inefficient depend on the CASTING DIE configuration. If there are no ap-
operation is not advantageous. Think of mechanization as a process pendages hanging below the CASTING DIE, it should be slid or
for fine tuning, not quantum leaps in improvement. Mechanization is rolled in from the side. If the CASTING DIE mounts below the
essential for moving large tools including large casting dies. lower tie bars, once it is in the die space, it can be lowered into its
Mechanization techniques include: mounting position by use of an elevator style table or lift. Today,
most large CASTING DIEs and DCMs employ automated
clamping systems.
Exercising the 5 Why’s does not necessarily mean that the root Exercising the 5 Why’s leads to the question of whether the cold
cause is the result of asking, “why?” five literal times. Instead, chamber/gooseneck change on every setup can be eliminated. Of
pull a team together and write down the problem at hand. At- course, a common answer is “no” leading to asking:
tempt to answer the problem as simply as possible. Often this
does not immediately identify the root of the problem. Thus Why not? The stationary die halves vary in thickness.
Why? That’s how the toolmaker builds them.
Why? Because he adds a minimum amount of die steel under-
neath the cavity.
Why? He does not want the die to crack.
Could he make the die thicker? No.
Why not? Because it would cost more.
Figure
5.2: (Left) Standardize Mold Base external sizes. (Right)
Figure 5-1:
Standardize Mold Base dimensions.
Guide to Quick Die Change 23
After listening to this exchange, do you think it might be assigned the task. It is necessary that the stationary die half be
feasible to have a standard stationary die thickness? Or may constructed with a setup ring to locate the half at the nozzle
it be feasible to have a standard stationary die thickness for a hole in the stationary platen. The setup ring is a collar at the
particular machine size? If this is feasible, you could incorporate sprue bushing that pilots into the hole in the stationary platen,
into your CD Engineering Standards specific stationary die locating the die.
thicknesses for given DCM sizes.
Recognize that the streamlining must be done as part of a cross
This standardization of stationary die thicknesses could functional team. There are a number of pitfalls in streamlining.
eliminate the need for adjustment of the DCM injection For example preassembling the chamber to the stationary half
stroke. For hot chamber, this standardization of stationary may cause die fit issues. In this case the setup person may have
die thicknesses would also lead to standardization of nozzle to disassemble the stationary half prior to die setting. This is
lengths. Existing dies could be retrofit with clamp plates of clearly not optimal. Similarly, the weight of the chamber may
various thicknesses’ that would be attached to the dies as an throw off the balance of the stationary half making it impos-
external setup activity. sible to set with the chamber installed. These items and similar
concerns will result from a cross functional team meeting on the
Answering the above question leads to another question and proposed streamlining plans.
that is whether the cold chamber/gooseneck size be standard-
ized? No.
2. Clamp the Stationary Die Half to the Stationary DCM Platen
Why not? Some castings are large and some are small. This operation can be mechanized or done manually. Several
Can you use a large cold chamber/gooseneck for small castings? No. examples of mechanization are shown in the Appendix. For
Why not? The metal will get cold. mechanized clamping, die standardization will be required for
Why not? The metal pressure will be too low. the particular clamping devices. For manual die clamping opera-
tions there are a number of alternatives that can improve the
Can a standard size chamber/gooseneck be used on a certain
current condition, depending on the current condition.
machine sizes? Maybe.
The objectives with manual clamping are to have the clamps
It may be possible to use a standard chamber/gooseneck size
readily available, no loose pieces, easy to positively position and
for specific machine sizes. This will depend on the casting
without need for judgment as to placement and fastened with
size (shot size) and quality requirements (static metal pres-
a minimum of turns to a predetermined tightness. One of the
sure requirement). Standardizing the chamber/gooseneck size
biggest barriers to this these objectives is dirt. To minimize the
will eliminate the need to change the plunger and cooling
irregularity in clamping it is best to keep the clamps on a con-
line connections.
tinuous preventative maintenance program.
Can plunger lubricant adjustment be eliminated? No. Why
If your current clamps are the tuning fork style with a loose
not? Different shot sizes require different amounts of lubri-
piece spacer, socket head cap screw, washers and tee nuts, or tee
cant. Can lubricant adjustment be done concurrently with
bolts and nuts; these can be replaced reasonably with an inte-
other activities? Yes. Keep in mind that die casting technology
grated clamp and spacer with a hole through it for the tee-bolt
is constantly evolving. There are many shot rod, tip, and cham-
washer and nut. The washer can be replaced with a C-washer as
ber systems now that contain automatic lubrication capability.
shown in Figure ???.??? if a greater release distance is required.
Perhaps a system exists that completely eliminates the need for
With this system the clamps can be released with a quarter to
adjustment.
half turn, slid out of the way, but not removed, and staged for
the next die.
In some cases, this analysis will conclude that the chamber/
gooseneck must be changed. Once this has been determined
Standardization of the casting die for manual clamping it rela-
the task for the SMED team changes. Focus should be put on
tively easy. A clamp slot with standard height and depth should
streamlining that task.
be specified.
If the cold chamber must be changed, it should be pre-
Finally, to tighten the clamp uniformly, a torque wrench or impact
assembled into the stationary die half. It must be fixed into
wrench could be used. To clamp
position to assure the pour hole is properly oriented and
the die in a minimum of time may
that it cannot slip out of the die half during setting. The die
require setup team personnel on
can then be positioned at the platen and the cold chamber
both sides of the DCM.
pushed through the hole in the stationary platen. Installa-
tion of the plunger rod cooling line connections, plunger lube
Figure 5.3: Clamp slot detail. The
adjustments and coupling can be done as an activity parallel
distance to the DCM platen must be
to clamping the die half.
standardized to fix the spacer height.
The depth of the slot is also standard-
If the hot chamber gooseneck and nozzle must be change, this
ized to assure the Tee-bolt can be
should be done as a parallel activity with a setup team member
pushed as close to die as possible.
B. Hydraulic ejection:
For the purposes of this discussion, hydraulic ejection will be
defined as DCM provided ejection cylinder, the rod of which is
directly coupled to the ejector plate of the casting die. The cou-
pling can be achieved in a number of ways. One method, a yoke
is shown in Figure 5.6. Another method could be a ring and
stud with interlocking pins. Whatever method is used, it needs
to simple and positive.
Development of the SMED Team the planning and strategy on new, replacement, redesigned, and
reengineered tooling.
It is important for both the Setup Crew and the SMED Team Development of the SMED team that will in turn provide sup-
to truly interact and perform as a well coached, disciplined and port and resources to the Setup Crew is also very important. This
focused team. Like any sports team, this involves conditioning, group needs to see themselves as the vendor and the changeover
training, watching game tapes and practice. It is very important team as the customer. The role of the SMED team is to meet the
that the right people are playing the right positions that in turn needs of the customer by supplying the right resources, tools and
compliment their skills and enhance the contribution they can equipment at the right time, in the right quantities while adher-
make to the success of the team. This will take some thought and ing to the delivery and terms and conditions of the Setup Crew
discussion. It is also important that the players really want to be customer. Sustainability of improvements in changeover time
on the team. A player that wants to be traded will contaminate the and movement of the SMED project forward is couched in the
culture of a team and negatively impact its ability to be successful. sustainability and quality of this all-important relationship.
Before you start your journey to achieve SMED, determine First convene all project participants, including both the SMED
where you are in terms of baseline changeover times. This should team and the Setup Crew. Make sure your Setup Crew chief;
be done by die, die family, by machine and if possible by shift. project manager or head coach has supreme authority to drive
Also be able to look at historical data by operator and/or the the project relentlessly. Insure that all primary and secondary
current changeover team structure. Review the data from several players and team positions are covered. We are now entering
perspectives, including longest changeover, shortest changeover, the training camp phase of team development. Think of your
average, etc. It is especially valuable to have information on changeover team as a specialty team. They have a specific re-
problems that were encountered and solved or at least addressed sponsibility to actually perform the die change, but they are also
during previous die changes. Don’t forget trim dies, and other part of a larger team that has responsibility to win the game. The
ancillary equipment as part of the complete changeover process. other members of the team are also specialists and will come
from various departments within your organization.
Shot monitoring equipment typically carry a treasure trove of
information to fill out the baseline setup time. Since setup time Even though your Setup Crew or SMED team will likely be
is defined as the time from the last good shot to the next good composed of a changeover specialist and assisted by an operator
shot on a new tool, the shot records implicitly track the setup or lead technician, the additional resources that will contribute to
time. Keep in mind that this setup time is typically excessively the success of your team will come from every department in your
long because it is an unbiased measure. The SMED team should organization. As you develop the composition of your SMED team
resist the temptation to ignore the shot to shot time. Instead, consider this analogy; if the die cast operator is the equivalent of
practice the 5 Why’s discipline as get to the root cause of the the driver on a NASCAR, team, would you also have them serve
excessive times. double duty as part of the pit crew, or would you develop a team of
specialists to perform the changeover while the operator (driver) is
If your measurements do not include these “data points”, it is preparing for casting the next part (getting back in the race)?
important to develop the appropriate methodologies to evalu-
ate the information you will be collecting. Also, don’t forget to When developing composition of the SMED team, include man-
capture information by customer and by toolmaker and tool de- agers and technicians from all departments and functions that can
signer. This is especially important if your customer has respon- impact the relative success of the Setup Crew or SMED team.
sibility for and /or dictates tool design standards. Most thought This will certainly include, but not be limited to representatives
that goes into tool design and tool build focuses on quality part from maintenance, process engineering, scheduling, tool room,
production, tool life and economies that reduce cost. Rarely is engineering, quality, automation technicians, purchasing, informa-
the changeover process a significant discussion point early in the tion technology, finance, and other departments in addition to
tool design process. Standardization is also critical to moving production. Then determine who will serve as head coach or proj-
the SMED process forward and should be an important part of ect manager. This person will have supreme authority and should
have a direct line to top management for reporting purposes and from several perspectives. This means extensive data collection
authority to take out “barriers” and secure support for funding to from several sources and as well as visual documentation of the
sustain changes and move the project forward. current state. Make sure the team has an easy to use camera
that can readily transfer images to a computer for capture and
At this stage it is important to make a comment about smaller delivery to a projector.
companies. Small and medium sized businesses have all the crit-
ical SMED team functions spread across a handful of employ-
ees. Practice judgment when selecting the team. It is important
to have the right team members while also not having everyone
in the front office involved in the SMED team. Development of the SMED Tools
The space(s) required by both the Setup Crew and the sup- In the actual SMED improvement process the SMED team will
port functions represented by the SMED team to meet, require enhanced tools to document and record the changeover
practice and do their work is very important. Insure that a process(s). It is very likely that the team(s) will need Figure 6.2
well equipped training room and appropriate meeting rooms to do their work.
are available to the team(s) when they need them. At a mini-
mum, these facilities should include a computer, color printer,
projector and a screen. Pay careful attention to chairs, tables,
lighting and even room temperature controls. Any deficiency
in these areas serves as a distraction to the team and removes
their focus from the business at hand. It is also important to
Development of the SMED Plan
provide flip charts, white boards, and other means to record
ideas, data, information and progress. The teams will also If you have the commitment of management and that commit-
require clip-boards, paper, pens, pencils, calculators and other ment has been has been verbalized to all of the SMED team
aids to express, validate and measure ideas. One of the key members on your pit crew, you are very near the start of your
precepts in the journey to SMED is to capture good ideas, SMED project.
quantify them and then standardize them into the improve-
ment process. Any tools, techniques or aids in the process Make sure that you have fully established and developed your
should be easily justified. SMED Team . Make sure your SMED team has the proper
tools in place and access to those tools and resources. Insure that
Before moving forward from the current state to the envisioned your team(s) has the appropriate classroom and meeting space
future state, the team(s) must first determine where they are… and that you have the right “lab” space for changeover activities.
Insure that the classroom and changeover resources and spaces Afterword
will support the needs of the team and that they are conducive
to effective meetings, data collection, analysis and success. At- A die casting company in Japan is now changing die casting dies
tention to detail is critical –everything is important. Broadcast (shot to shot) in less than 15 minutes… Other companies have
to everyone that the team’s needs are paramount and that sup- halved their changeover times… Your ability to achieve success
port of the team and their needs is everyone’s job. Also make in the journey toward SMED is related more to your commit-
sure that “ground rules” are established for classroom and project ment than to your challenges.
behaviors, activities and procedures.
Justification
Potential Savings for SMED program at ICG Selecting the Setup Team Participants
Assumptions: 30 Die changes per year
$150.00 Overhead rate Determining the team members for the first demonstration proj-
$2.00 Scrap Cost per part & Average of ect is very important. The team is a cross-functional group with
2 hours of scrap per set up a variety of skills. Initially, not all the detail tasks of the setup are
10% Dross loss for remelt known. For that reason a number of individuals with a variety of
16 hrs Current set up time last good job skills will be trained to deal with any unforeseen circumstances.
piece to 1st piece approval
8 hrs Set up time Team Goal last Some of the skills required are as follows:
good piece to 1st piece approval
@ 50% Reduction • Supervision, initially a team leader is required to coordinate
80 shots per hour with a 2 cavity die the various setup tasks, keep track of timing and deal with
any unanticipated circumstances.
Current Estimated Set Up Cost
Downtime Scrap Cost Cost/Set Up Annual Cost
2,400.00 704.00 3,104.00 93,120.00
Projected Set Up Cost After SMED Program
Downtime Scrap Cost Cost/Set Up Annual Cost
1,200.00 176.00 1,376.00 41,280.00
Not all these persons will be required to participate in the setup once
the SMED technique becomes routine. The Team Leader coordinates
the activities of the set-up team through the various stages of SMED.
Additional leadership is required when the actual set-up takes place.
This leader will be the Crew Chief, in charge of the set-up crew. This
person may currently have a job description such as “lead set-up tech-
nician.” Tooling and maintenance technicians are not required unless
a problem with tooling or the DCM comes up. Their participation on Figure 7.2: Preliminary stage of gathering data for the baseline of
the team is required to establish priorities. When a problem occurs the set-up.
during a setup, it must have the highest priority in the plant.
Stage one – this stage separates internal and external activities.
This means studying each internal step and determining if it
could be external. Common issues such as remote tool storage,
and lack of availability of tools and the hoist must be solved.
Initial Training Stage two – converting internal activities to external activities
is attempted. Why can't the remaining internal activities be
Initial training for the SMED team was 4-6 hours in the class- external activities? Each step is re-examined. Common issues
room to learn the basics of SMED. This is necessary so each such as cold dies, lack of recorded machine settings, and lack of
team member understands the process and will see where their die location aids are resolved.
contribution is in the long term. Stage three – streamline all activities. This stage analyzes the
facts (elements) of each activity, both internal and external.
In this case, five stages of SMED are developed, the three tra- Common issues such as differing fasteners and die dimensions
ditional stages plus the beginning, or “preliminary” stage and a are resolved through standardization.
final “follow-up” or documentation stage.
Documentation – documentation of internal and external
procedures in required. The entire activity must be reviewed to
Preliminary stage – this stage establishes the set-up baseline.
determine what went well, or badly, and what changes must be
This consists of the team members “observing and recording”
completed prior to the next SMED activity.
the set-up in detail.
Preliminary Stage at the DCM. The video cameras are useful in corroborat-
ing the time and activities. Once all the raw data has been
For the first SMED activity, two persons, Scott and Chris were
collected it has to be reduced to a usable form. The data is
assigned to do the actual set-up. The balance of the team was
distilled and placed on a spreadsheet. Two partial examples
assigned activities of “observing and recording” the work as it
are shown below, each depicting the beginning activities of
was being accomplished. In this case Recorders, timers, and
Scott and Chris.
fact collectors were used to follow Scott and Chris’ activities.
In this case the Recorder would describe what change was
Scott’s activities begin at 8:11 AM. His first activity is to re-
made and record what is any equipment was used. The timer
move the safety gate on the Helper side of the DCM. This takes
would record the time for each activity step. The fact collector
10 seconds. His next activity is to move the cold chamber. This
would breakdown each step into actions, with as much detail
takes 40 seconds. This list of 18 activities takes about 32 minutes
as possible.
to complete.
In order not to miss any activity, two video cameras, one on
Scott has a total of 88 activities that are concluded at 12:19 PM.
each side of the DCM were used to document all activities
Total time for set-up was 4 hours 8 minutes.
Chris begins at 8:10 AM. His first activity is to run the sprayer
down and disconnect it. This takes 2 minutes. His next activity is
to close the DCM and loosen tie bar nuts. This takes 5 minutes.
This list of 18 activities takes about 28 minutes to complete.
Duration
Minutes
Name
Tools
Note
11
12
10
Required
Upload or
program process
7 Mark parameters for
0:30:00 8:40:00 AM 9:10:00 AM
new part number
Allen wrench
Change grippers
8 Doyle if needed
0:19:00 8:40:00 AM 8:59:00 AM set, pliers, open
end wrenches
Figure 7.10: After stages 1-3 of SMED, beginning work assignments.
Sledge Hammer
Loosen inner tie
13 Reassign?
bar nuts
0:08:00 8:40:00 AM 8:48:00 AM and Tie bar nut
wrench
Sledge Hammer
Loosen inner tie
14 Rick bar nuts
0:08:00 8:40:00 AM 8:48:00 AM and Tie bar nut
wrench
Sledge Hammer
Loosen Outer tie
15 Reassign?
bar nuts
0:08:00 8:48:00 AM 8:56:00 AM and Tie bar nut
wrench
55 Chris Run in full auto and submit First Place 0:01:00 10:06:00 AM 10:07:00 AM
57 Doyle Pre-stage robot grippers, lube, and all tools prior to shut down TBD All External
Figure 7.12: Activities 47-58 showing last internal activity and completion time of 10:06 AM.
Technical Documentation
Operator Manual
TechnicalTechnical
Documentation
Documentation
Technical Documentation
Operator
Operator
Manual
OperatorManual
Manual
Automatic ejector locking coupler (without hydraulic quick clamping system)
Pneumatic ejector locking coupler for quickly clamping the cen-
tral ejector nail. The
Automatic automatic
ejector ejector (without
locking coupler locking hydraulic
coupler for quicktheclamping system)
Automatic ejector
Automatic ejector locking couplercentral locking
(withoutejector
hydraulic coupler
isquick
depicted (without
below.
clamping hydraulic
In its ejector
system)
Pneumatic quick
depressurized clamping
condition,
locking coupler system)
for quickly clamping the cen-
the coupler canPneumatic
be locked ejector
by tral
meansejectorof
locking cup
nail. springs.
The automaticYou can
ejector locking coupler cen-
for the
Pneumatic ejector locking coupler for quickly clamping the
central centralcoupler
ejector ejector
is depicted
for The
nail. quickly
below. In
clamping
automatic
its ejectorthe
depressurized locking
condition,
retract and advance the
tral ejector
coupler for the central ejector is depicted central
nail.
in Figure A.1 ejector when
The automatic compressed
ejector locking air is
coupler for the
the below.
coupler Incan
its depressurized
be locked condition,
by means of cupthesprings.
coupler can can
You be
locked by meansapplied to theYou
of cup springs. sleeve.
central The
can retract stroke
ejector
and is of the
depicted
advance the sleeve
below.
central isIn
monitored
its
ejector by
depressurized
when compressed condition,
air
retract and advance the central ejector when compressed air is is applied
anstroke
to the sleeve. The initiator.
of the sleeve
the iscoupler
monitored canby an initiator.
be
applied locked by means
to the sleeve. of cup
The stroke of springs.
the sleeveYou can
is monitored by
retract and advance the central ejector when compressed air is
an initiator.
applied to the sleeve. The stroke of the sleeve is monitored by
Coupler
an sleeve under tension
initiator. Coupler sleeve under tension
CouplerEjector
sleevenail
under tension Ejector nail
Ejector nail
!
Only use coupler.
to the ejector nails for automatic
Note: ejectorlock
Before, this automatic locking
was onlycouplers.
tried out with the nail
Only use ejector nails for automatic ejector
Their shape is matched speciallyTheir
locking couplers. to theshape
coupler.
and without the die.
is matched specially
It must be possible to turn the nail when the coupler is
Note: to the coupler.
Before, this automatic lock locked.
was only tried out with the nail
and without the die.
Note: Before,
Note: It mustthis automatic
be possible lock
to this
Before, turn thewas
nailonly
automaticwhen tried
lockthe
out with
wascoupler
thewith
is out
only tried
nailthe
andnail
without
locked. the die.
and without the die.
It must be possible to turn the nail when the coupler is locked.
It must be possible to turn the nail when the coupler is
Edition: 06.07.04
locked.
Guide to Quick Die Change gb-kap-50-f-reihe.fm 14.7.05 395 -
- Chapter 5 - Page
Oskar Frech GmbH + Co. KG, D-73614 Schorndorf
DIE INFORMATION PROFILE Die Number ____________________
Customer: _______________ Date: __________ Revision: ______
Part Number: _______________
DCM Preference: _______________
Alloy: _______________
Die Information: Cover half: _______________ Shut height: _______________
Vertical height: __________ Width: __________ Weight: __________
Fill position: _______________
Cold chamber: _______________ Nozzle: _______________
Length: _______________ Length: _______________
Diameter: _______________ Diameter: _______________
Clamp slot: __________ Width: __________ Height: __________
Cooling System: Eyebolt size: __________
Water: _______________
Oil: _______________
Stationary cores: _____________________________________
_____________________________________
Die Information: Ejector half
Vertical height: __________ Width: __________ Weight: __________
Ejector rod position
Ejector type: __________ Bumper pin length: __________ Size: __________
Clamp slot Width: __________ Height: __________
Cooling System: Eyebolt size: __________
Water: _______________
Oil: _______________
Movable cores: _____________________________________
_____________________________________
40 Guide to Quick Die Change
Exterior Operation Checklist 1
1. Check necessary materials & determine if there has been any change:
Maintain both a physical and written inventory of materials.
Revise inventories to reflect ant changes.
4. Check die:
Determine die is at latest engineering change.
Determine if all repairs are complete.
Check for broken ejector pins.
Check for leaks in cooling lines and manifolds.
Check condition sprue/cold chamber.
Check that all bolts are tight.
Check the last shot from previous production run.
Plunger Tip & Rod Assemble moveable core & related parts
Hydraulic Hoses
"T" Bolts
Wire Rope/Chain
Ladle
Tools
Impact wrench
Allen Wrench
Prybar
The ejector plate is part of the die, and carries the ejector pins,
not shown in Figure A.2.
1. Slide the first die block, complete with adapter plate and
ejector plate assembly, into the front of the crosshead,
ensuring that: (i) the “horseshoe” on the back of the ejector
plate assembly mates with the “ring” on the face of ejector
hub (these slide together – no tools are required); and that
(ii) the lug (tongue) of the adapter plate mates with the slot
in the retaining bar which is bolted to the face of the shank. .
Figure A.2: Techmire Quick Die Change System for Model 88NTX
Again, no tools are required – the lug slides into the clamp.
multi-slide DCM
Figure A-2. Techmire Quick Die Change System for Model
88NTX multi-slide DCM.
Appendix T 1