APT ESTIMATES

Project:
Location: Dasmarinas Cavite
Subject: Partial Estimates
Date: August 2013

Quantity
Item Description Total Qty Units
Road 1 Road 2 Road 3 Road 4 Road 5 Road 6 Road 7
Phase 1
CIVIL/ROAD WORKS
Class A mixture:
A Cement 381.00 423.00 489.00 917.00 610.00 1,142.00 3,962.00 bags
B Sand 21.05 23.41 27.01 50.79 33.75 63.32 219.32 m³
C Gravel 42.09 46.82 54.03 101.57 67.50 126.64 438.64 m³
Forms:(3 uses)
D 2" x 6" x10' 26.00 31.00 35.00 65.00 44.00 57.00 258.00 pcs
E 2" x 4" x10' 11.00 13.00 14.00 26.00 18.00 23.00 105.00 pcs
F 2" x 2" x10' 51.00 61.00 69.00 124.00 87.00 112.00 504.00 pcs

DRAINAGE

Reinforced Concrete Pipe:

for Pipe Size


G 12" 28.00 37.00 38.00 68.00 62.00 30.00 263.00 pcs
H 15" 37.00 36.00 47.00 37.00 26.00 183.00 pcs
I 18" 37.00 22.00 96.00 155.00 pcs
J 21" pcs
K 24" pcs

L for Sand Bedding 100mm thk 4.46 4.46 4.71 7.25 7.87 10.76 39.50 m³

for Pipe Collar Class B mixture:


M Cement 36.00 36.00 36.00 54.00 60.00 88.00 310.00 bags
N Sand 2.36 2.36 2.35 3.58 3.99 5.84 20.48 m³

Manholes:

for cover and slab Class B Mixture:


O Cement 8.00 8.00 8.00 12.00 12.00 12.00 60.00 bags
P Sand 0.42 3.17 0.48 0.69 0.74 0.74 6.22 m³
Q Gravel 0.83 6.33 0.95 1.38 1.47 1.47 12.44 m³

for CHB mortar Class C Mixture


R Cement 9.00 10.00 10.00 14.00 13.00 16.00 72.00 bags
S Sand 0.90 1.07 1.10 1.49 1.40 1.74 7.71 m³

for wall sides of manholes


T 4" CHB 258.00 306.00 314.00 427.00 401.00 498.00 2,204.00 pcs

Phase 2
CIVIL/ROAD WORKS
Class A mixture:
A Cement 480.00 1,007.00 358.00 4,245.00 1,009.00 669.00 585.00 8,353.00 bags
B Sand 26.61 55.84 19.77 235.80 56.01 37.07 32.38 463.49 m³
C Gravel 53.22 111.69 39.53 471.61 112.02 74.15 64.76 926.98 m³
Forms:(3 uses)
D 2" x 6" x10' 19.00 44.00 15.00 108.00 46.00 46.00 33.00 311.00 pcs
E 2" x 4" x10' 10.00 22.00 8.00 54.00 23.00 19.00 14.00 150.00 pcs
F 2" x 2" x10' 47.00 109.00 38.00 270.00 113.00 91.00 66.00 734.00 pcs

DRAINAGE

Reinforced Concrete Pipe:

for Pipe Size


G 12" 55.00 140.00 22.00 114.00 35.00 26.00 24.00 416.00 pcs
H 15" 15.00 42.00 62.00 17.00 33.00 169.00 pcs
I 18" 30.00 91.00 54.00 47.00 13.00 235.00 pcs
J 21" 34.00 25.00 59.00 pcs
K 24" 61.00 8.00 69.00 pcs

L for Sand Bedding 100mm thk 4.31 13.49 4.13 23.34 8.93 6.23 4.64 65.07 m³

for Pipe Collar Class B mixture:


M Cement 32.00 101.00 35.00 191.00 75.00 50.00 36.00 520.00 bags

1 of 2
APT ESTIMATES

Quantity
Item Description Total Qty Units
Road 1 Road 2 Road 3 Road 4 Road 5 Road 6 Road 7
Phase 2 Phase
Cont'd1
for Pipe Collar Class B mixture cont'd:
N Sand 2.09 6.72 2.30 12.72 4.97 3.33 2.40 34.52 m³

Manholes:

for cover and slab Class B Mixture:


O Cement 6.00 12.00 6.00 24.00 12.00 12.00 8.00 80.00 bags
P Sand 0.35 0.74 0.37 1.60 0.74 0.68 0.52 4.99 m³
Q Gravel 0.71 1.47 0.73 3.19 1.48 1.35 1.04 9.98 m³

for CHB mortar Class C Mixture


R Cement 9.00 15.00 9.00 39.00 17.00 14.00 13.00 116.00 bags
S Sand 0.96 1.57 0.93 4.25 1.85 1.52 1.34 12.42 m³

for wall sides of manholes


T 4" CHB 274.00 449.00 267.00 1,214.00 528.00 433.00 384.00 3,549.00 pcs

Fencing
Total Units
Walls:

for CHB mortar Class C Mixture


A Cement 241.00 bags
B Sand 26.72 m³

for wall sides of manholes


C 4" CHB 7,635.00 pcs

To Follow:

1. Nails/Reinforcements/Tie Wires - no details


2. Plumbing/Waterline - for clarification of Pipe sizes
3. Columns and Footings on Fence - no details
4. Structural Steel of EWT - no details
5. Cistern Tanks - no details