Hvws System Commissioning Report: Status (Yes/No)
Hvws System Commissioning Report: Status (Yes/No)
REPORT NO:- 01
3. Quartz bulb Detection line is pressurized from main line. Yes No leakages found in QBD line.
HVWS system is in Normal
position.
4. Deluge valve is in working postion. Yes No leakages found in Deluge
valve assembly.
5. Inlet Gate valve and Butterfliy valve is in open state. Yes
6. Outlet Gate valve of HVWS system is in open position. Yes
7. Emergency By-pass line is in close postion. Yes
8. Pressure switch and solenoid valve are in working condition. Yes
9. Control panel activation checked for working operations. Yes
Company Name Douse Fire System (P) Ltd Bharat Bijlee Ltd BARC- Tarapur
Date 13/10/2021