10 mm dia.

RSB spaced @ PLUMBING NOTES


0.20 m both ways 1. ALL MATERIALS, FIXTURES AND EQUIPMENTS TO BE USED IN THE
1.00 1.00 2.00 PLUMBING INSTALLATION SHALL BE NEW, OF THE APPROVED TYPE AND
SIZE AS TO ITS INTENDED USAGE.
LEGEND
2. ALL THE INSTALLATION BE IN CONFORMANCE WITH THE RULES AND WC WATER CLOSET
REGULATION OF THE PLUMBING CODE OF THE PHILIPPINES.
3. DRAINAGE PIPING SHALL BE PROVIDED WITH APPROVED INLET FITTINGS FD FLOOR DRAIN
FOR FIXTURE CONNECTIONS, CORRECTLY LOCATED ACCORDING TO THE
LAV. LAVATORY
SIZE AND TYPE OF FIXTURE PROPOSED.
4. CHANGE IN DIRECTION IN DRAINAGE PIPING SHALL BE MADE WITH ST SEPTIC TANK
APPROPRIATE USE OF APPROVED FITTINGS AND SHALL BE OF THE CO CLEAN OUT
APPROVED AVAILABLE ANGLES.
5. PROVIDE CLEANOUT FOR EACH CHANGE IN DIRECTION IF THE TOTAL CB CATCH BASIN
0.40 AGGREGATE CHANGE EXCEEDS 135'.
6. HORIZONTAL DRAINAGE PIPING SHALL RUN IN PRACTICAL ALIGNMENT &
CV CHECK VALVE
1.50 A UNIFORM SLOPE OF NOT LESS THAN 41 OF AN INCH OR 2% TOWARD THE WM WATER METER
0.40 POINT OF DISPOSAL.
7. UNLESS PROHIBITED BY STRUCTURAL CONDITIONS, EACH VENT SHALL GV GATE VALVE
RISE VERTICALLY TO A POINT NOT LESS THAN 6" ABOVE THE FLOOD KS KITCHEN SINK
MANHOLE LEVEL RIM OF THE FIXTURE SERVED BEFORE OFFSETTING
HORIZONTALLY. HB HOSE BIBB
8. EACH VENT PIPE OR STACK EXTEND THROUGH ITS FLASHING AND SHALL FC FAUCET
TERMINATE VERTICALLY NOT LESS THAN 6" ABOVE THE ROOF AND 1FT
FROM ANY VERTICAL SURFACE. WASTE LINE
9. PIPING SHALL BE LAID ON A FIRM BED THROUGH OUT ITS ENTIRE WATER LINE
LENGTH. IF ANY SUCH PIPING IS LAID IN MADE OR FILLED GROUND, IT
SHALL BE LAID ON A BED OF APPROVED MATERIALS AND SHALL BE
ADEQUATELY SUPPORTED
P L A N

0.15
0.10 0.44
W.L.
0.23 0.33 0.72
LB8
0.30

0.33
PF1/2
0.41 0.39
32Ø
0.19
0.07
DIGESTIVE CHAMBER
1.50 0.47
LEACHING LEACHING
CHAMBER 1 CHAMBER 2

0.76 0.73
0.56
0.48
0.37
F.L.
0.20 0.20

S E C T I O N WALL HUNG LAVATORY 0.30 F.L.

SEPTIC TANK DETAIL LAVATORY AND WATER CLOSET INSTALLATION DETAIL