Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

WEEKLY PERFORMANCE REPORT 008

CLIENT: SREPL PMC: PROMAC Advisors Pvt. Ltd. Architect:ANMA

WPR-Report: 008_18.11.13 to 24.11.13


TECHNICAL STAFF - PMC
S. NO. NAME DESIGNATION REMARKS VISITOR'S NAME & COMPANY
1 Mr. G.D.Garg Sr. PM Mr. Amit (SREPL)
2 Mr. Ajay Kumar Tiwari PM Mr. Vinod Garg (PROMAC)
3 Mr. Sanjeev Kumar PM Mr. Sumer Chaudhary (PROMAC)
4 Mr. Amir Khan Engineer
5 Mr. Himanshu Kaushik Engineer
MAJOR ACTIVITIES LAST WEEK (11-11-13 To 17-11-13)
S.NO. DESCRIPTION UNIT TARGET ACHIEVED VARIANCE REMARKS
(%) (%)
1 Steel Work TON 10.00 34% 64%
2 Concrete Work CUM 200.00 48% 52%
3 Shuttering Work SQM 200.00 52% 48%
ASSUMPTIONS/CONSTRAINTS FOR PLANNING
S.NO. DESCRIPTION REMARKS
1 Availability of Manpower as per requirement.
2 Availability of Concrete and Steel as per requirement.
MAJOR ACTIVITY TARGET NEXT WEEK (25-11-13 to 01-12-13)
S. NO. DESCRIPTION UNIT TOTAL QTY ACHIEVED TILL LAST REMAINING TARGET REMARKS
QTY PERIOD QTY NEXT
PERIOD
1 Steel Work MT 125 100.71 24 10
2 Concrete Work CUM 800 540 260 100
3 Shuttering Work SQM 2500 1211 1289 80
MAJOR MILESTONES PLANNED/ACHIEVED LAST WEEK (18-11-13 To 24-11-13)
S.NO. DESCRIPTION PLANNED DATE ACHIEVED DATE/STATUS REMARKS
1 Plinth beam completion. 18.11.2013 20.11.2013
2 Padestal work will be completed up to Anchor bolt level. 20.11.2013 20.11.2013 For part 1
3 Brick work will be completed above Plinth beam on outer 25.11.2013 25.11.2013
4 periphery.
RCC work in plinth beam started 19.11.2013 22.11.2013
For part 2
5 RCC in pedestal upto anchor bolt level 21.11.2013 23.11.2013
MAJOR MILESTONES TARGET NEXT WEEK (25-11-13 to 01-12-13)
S.NO. DESCRIPTION DATE REMARKS
1 Earth filling and compaction will be start in warehouse area 12/10/2013
2 complete
RCC in Column and Tie beam above anchor bolt level to tie 12/1/2012 FOR PART -01
beam level will start on
3 RCC work in plinth beam completion 12/8/2013
4 RCC in pedestal upto anchor bolt level 12/10/2013 FOR PART -02
5 Brick work above Plinth beam will be start on 11/25/2013
QUALITY REPORT
S.NO. DESCRIPTION PLANNED ACTUAL REMARKS
1 Reinforcement of Isolated Footings As per BBS As per BBS check and found ok
2 Layout work of Column As per drawing As per drawing check and found ok
3 Concrete grade M-25 As per drawing As per drawing Slump and Cubes were taken
4 RCC work of column & Plinth Beam As per drawing As per drawing Line size & plumb checked, Found
5 Brick masonary As per drawing As per drawing ok size & plumb checked, Found
Line
KEY DECISIONS REQUIRED ok
1 Vendor finalisation for services
2 Finalisation of Flooring details in Warehouse Area
PM's COMMENT
1
2
SITE PHOTOGRAPHS

SITE VIST COMPACTION WORK

EARTH FILLING INSIDE PLASTER OVER BRICK MASONARY

You might also like