This weekly performance report provides updates on construction progress for the client SREPL. It summarizes the technical staff and visitors to the site. Major activities from the past week included 34% of targeted steel work being achieved and 48% of concrete work. Upcoming targets for the next week include completing 10 MT of steel work, 100 cubic meters of concrete work, and 80 square meters of shuttering work. Several milestones from the past week were achieved on or ahead of schedule, and new milestones are planned for the next week. Quality checks found reinforcement, layout work, concrete grade and other work to be as planned or drawing specifications. Key decisions are needed on services vendors and flooring details.
This weekly performance report provides updates on construction progress for the client SREPL. It summarizes the technical staff and visitors to the site. Major activities from the past week included 34% of targeted steel work being achieved and 48% of concrete work. Upcoming targets for the next week include completing 10 MT of steel work, 100 cubic meters of concrete work, and 80 square meters of shuttering work. Several milestones from the past week were achieved on or ahead of schedule, and new milestones are planned for the next week. Quality checks found reinforcement, layout work, concrete grade and other work to be as planned or drawing specifications. Key decisions are needed on services vendors and flooring details.
This weekly performance report provides updates on construction progress for the client SREPL. It summarizes the technical staff and visitors to the site. Major activities from the past week included 34% of targeted steel work being achieved and 48% of concrete work. Upcoming targets for the next week include completing 10 MT of steel work, 100 cubic meters of concrete work, and 80 square meters of shuttering work. Several milestones from the past week were achieved on or ahead of schedule, and new milestones are planned for the next week. Quality checks found reinforcement, layout work, concrete grade and other work to be as planned or drawing specifications. Key decisions are needed on services vendors and flooring details.
TECHNICAL STAFF - PMC S. NO. NAME DESIGNATION REMARKS VISITOR'S NAME & COMPANY 1 Mr. G.D.Garg Sr. PM Mr. Amit (SREPL) 2 Mr. Ajay Kumar Tiwari PM Mr. Vinod Garg (PROMAC) 3 Mr. Sanjeev Kumar PM Mr. Sumer Chaudhary (PROMAC) 4 Mr. Amir Khan Engineer 5 Mr. Himanshu Kaushik Engineer MAJOR ACTIVITIES LAST WEEK (11-11-13 To 17-11-13) S.NO. DESCRIPTION UNIT TARGET ACHIEVED VARIANCE REMARKS (%) (%) 1 Steel Work TON 10.00 34% 64% 2 Concrete Work CUM 200.00 48% 52% 3 Shuttering Work SQM 200.00 52% 48% ASSUMPTIONS/CONSTRAINTS FOR PLANNING S.NO. DESCRIPTION REMARKS 1 Availability of Manpower as per requirement. 2 Availability of Concrete and Steel as per requirement. MAJOR ACTIVITY TARGET NEXT WEEK (25-11-13 to 01-12-13) S. NO. DESCRIPTION UNIT TOTAL QTY ACHIEVED TILL LAST REMAINING TARGET REMARKS QTY PERIOD QTY NEXT PERIOD 1 Steel Work MT 125 100.71 24 10 2 Concrete Work CUM 800 540 260 100 3 Shuttering Work SQM 2500 1211 1289 80 MAJOR MILESTONES PLANNED/ACHIEVED LAST WEEK (18-11-13 To 24-11-13) S.NO. DESCRIPTION PLANNED DATE ACHIEVED DATE/STATUS REMARKS 1 Plinth beam completion. 18.11.2013 20.11.2013 2 Padestal work will be completed up to Anchor bolt level. 20.11.2013 20.11.2013 For part 1 3 Brick work will be completed above Plinth beam on outer 25.11.2013 25.11.2013 4 periphery. RCC work in plinth beam started 19.11.2013 22.11.2013 For part 2 5 RCC in pedestal upto anchor bolt level 21.11.2013 23.11.2013 MAJOR MILESTONES TARGET NEXT WEEK (25-11-13 to 01-12-13) S.NO. DESCRIPTION DATE REMARKS 1 Earth filling and compaction will be start in warehouse area 12/10/2013 2 complete RCC in Column and Tie beam above anchor bolt level to tie 12/1/2012 FOR PART -01 beam level will start on 3 RCC work in plinth beam completion 12/8/2013 4 RCC in pedestal upto anchor bolt level 12/10/2013 FOR PART -02 5 Brick work above Plinth beam will be start on 11/25/2013 QUALITY REPORT S.NO. DESCRIPTION PLANNED ACTUAL REMARKS 1 Reinforcement of Isolated Footings As per BBS As per BBS check and found ok 2 Layout work of Column As per drawing As per drawing check and found ok 3 Concrete grade M-25 As per drawing As per drawing Slump and Cubes were taken 4 RCC work of column & Plinth Beam As per drawing As per drawing Line size & plumb checked, Found 5 Brick masonary As per drawing As per drawing ok size & plumb checked, Found Line KEY DECISIONS REQUIRED ok 1 Vendor finalisation for services 2 Finalisation of Flooring details in Warehouse Area PM's COMMENT 1 2 SITE PHOTOGRAPHS