Name of task Constru Date of Date of 2021 2022

12 12 1/ 1/ 2/ 2/ 3/ 3/ 4/ 4/ 5/ 5/ 5/ 6/ 6/ 7/ 7/ 8/ 8/ 9/ 9/ 10 10 10 11 11 12 12 1/ 1/ 2/ 2/ 3/ 3/ 4/ 4/ 5/ 5/ 5/ 6/ 6/ 7/
1 527 days
Fri 1/1/21 8:00 Sat
AM 6/11/22 5:00 PM 0%
2 120 days
Fri 1/1/21 8:00 Fri
AM 4/30/21 5:00 PM 0%
3 include submit APG and receive advince payment etc 60 days
Fri 1/1/21 8:00 AM
Mon 3/1/21 5:00 PM 0%
4 open LC for offshore, open form M for CIF 60 days
Tue 3/2/21 8:00 Fri
AM 4/30/21 5:00 PM 0%
5 44 days
Tue 3/2/21 8:00 Wed
AM 4/14/21 5:00 PM 0%
6 Preparation(include man power and equipment organisation 7 days
Tue 3/2/21 8:00 AM
Mon 3/8/21 5:00 PM 0%
etc)

7 bush cleaning, acess road 7 days


Tue 3/9/21 8:00 Mon
AM 3/15/21 5:00 PM 0%
8 mobilization water xecavator and construction temporary road 7 days
Sun 3/14/21 8:00 Sat
AM 3/20/21 5:00 PM 0%
for pile foundation

9 soil investgation and submit report for approval 5 days


Sat 3/20/21 8:00 Wed
AM 3/24/21 5:00 PM 0%
10 pile foundation design and submit for approval 7 days
Thu 3/25/21 8:00 Wed
AM 3/31/21 5:00 PM 0%
11 construction of pile foundation 14 days
Thu 4/1/21 8:00 Wed
AM 4/14/21 5:00 PM 0%
12 197 days
Mon 5/31/21 8:00Mon
AM 12/13/21 5:00 PM 0%

13 Material store prepare and office prepare at ALAOJI power 14 days


Mon 5/31/21 8:00 Sun
AM 6/13/21 5:00 PM 0%
plant and owerri SS

14 Material handover and transportation 180 days


Mon 6/14/21 8:00Fri
AM 12/10/21 5:00 PM 0%
15 material sorting 180 days
Thu 6/17/21 8:00Mon
AM 12/13/21 5:00 PM 0%
16 14 days
Mon 6/14/21 8:00 Sun
AM 6/27/21 5:00 PM 0%
17 profile survey including staking/check survey 14 days
Mon 6/14/21 8:00 Sun
AM 6/27/21 5:00 PM 0%
18 80 days
Mon 6/28/21 8:00 Wed
AM 9/15/21 5:00 PM 0%
19 Foundation construction part 20 days
Mon 6/28/21 8:00 Sat
AM 7/17/21 5:00 PM 0%
20 tower erection and string part 60 days
Sun 7/18/21 8:00 Wed
AM 9/15/21 5:00 PM 0%
21 123 days
Sat 5/1/21 8:00 Tue
AM 8/31/21 5:00 PM 0%
22 factory materials of tower prepare 60 days
Sat 5/1/21 8:00 Tue
AM 6/29/21 5:00 PM 0%

23 FAT(four circult tower and cable terminal tower) 7 days


Mon 5/31/21 8:00 AM
Sun 6/6/21 5:00 PM 0%

24 factory manufacture 30 days


Mon 6/7/21 8:00 AM
Tue 7/6/21 5:00 PM 0%
25 Freight,customs clearance and transportation 56 days
Wed 7/7/21 8:00 Tue
AM 8/31/21 5:00 PM 0%

26 303 days
Fri 8/13/21 8:00 Sat
AM 6/11/22 5:00 PM 0%
27 141 days
Fri 9/17/21 8:00 AM
Fri 2/4/22 5:00 PM 0%
28 Excavation of foundation(depend on wayleave) 90 days
Fri 9/17/21 8:00Wed
AM 12/15/21 5:00 PM 0%
29 Foundation of pile(depend on wayleave) 120 days
Fri 9/24/21 8:00 Fri
AM 1/21/22 5:00 PM 0%
30 backfill 120 days
Fri 10/8/21 8:00 AM
Fri 2/4/22 5:00 PM 0%
31 268 days
Fri 8/13/21 8:00 AM
Sat 5/7/22 5:00 PM 0%
32 Erection of towers 180 days
Fri 8/13/21 8:00 AM
Tue 2/8/22 5:00 PM 0%
33 fixing of insulator strings 180 days
Sun 9/12/21 8:00 Thu
AM 3/10/22 5:00 PM 0%
34 stringing of conductors 180 days
Sun 10/3/21 8:00 Thu
AM 3/31/22 5:00 PM 0%
35 earth wires/OPGW along with 180 days
Sun 10/3/21 8:00 Thu
AM 3/31/22 5:00 PM 0%
36 all necessary line accessories 180 days
Sun 10/3/21 8:00 Thu
AM 3/31/22 5:00 PM 0%
37 Linking of the transmission line including all hardware and 180 days
Tue 10/12/21 8:00 AM
Sat 4/9/22 5:00 PM 0%
connectors

38 Check, eliminating defects 28 days


Sun 4/10/22 8:00 AM
Sat 5/7/22 5:00 PM 0%
39 35 days
Sun 5/8/22 8:00 Sat
AM 6/11/22 5:00 PM 0%

40 Testing and pre-commissioning 21 days


Sun 5/8/22 8:00 Sat
AM 5/28/22 5:00 PM 0%
41 Commissioning, inspection, hand-over 14 days
Sun 5/29/22 8:00 Sat
AM 6/11/22 5:00 PM 0%