Project Job no.

10 houses Mullinahone 19149


David Kelly Partnership Calcs for Start page no./Revision
Nelson House, Emmet Place
Attenuation tank - 10 houses 1
Youghal
Calcs by Calcs date Checked by Checked date Approved by Approved date
Co. Cork
GOS 31/10/2019

ATTENUATION DESIGN
In accordance with CIRIA publication C753 - The SUDS Manual
Tedds calculation version 1.0.04

Pre post runoff method


Site characteristics
Location; Other
Hydrological region; 11
Soil type (Wallingford Procedure W.R.A.P map); 3
Standard percentage runoff; SPR = 0.37
Average annual rainfall; SAAR = 1000 mm
5 year return period rainfall of 60 minute duration; M5_60min = 13.8 mm
Ratio 60-minute to 2 day rainfalls of 5 year return; r = 0.45
Rainfall intensity increase due to global warming; pclimate = 10%
Routing coefficient; cr = 1.30
Volumetric runoff coefficient; cv = 0.75
Catchment details
Impermeable.
Subcatchment Name Area (ha) PIMP (%);
area (ha)
1; mullinahone 10 0.40; 57.0; 0.23;
houses;
Total 0.40; 57.0; 0.23;

Greenfield runoff rates


Catchment area; AREA = 50.00 hectare
Greenfield runoff rate (50 hectare site); Qrural = 0.00108m3/s  (AREA/1km2)0.89  (SAAR/1mm)1.17  SPR2.17 =
218.0 l / s
Greenfield runoff rate; Q = Qrural / AREA  A = 1.7 l / s
Greenfield runoff rate per unit area; QA = Q / A = 4.4 l / s / hectare

Estimated site discharges


FSR growth rate (1 year); FSR1yr = 0.88
Discharge (1 year); Q1yr = Q  FSR1yr = 1.5 l/s
FSR growth rate (30 year); FSR30yr = 1.65
Discharge (30 year); Q30yr = Q  FSR30yr = 2.9 l/s
FSR growth rate (100 year); FSR100yr = 1.96
Discharge (100 year); Q100yr = Q  FSR100yr = 3.4 l/s

Table equations
Peak flow; Qpost_imp = cr  Imax  Aimp
Runoff volume; Vpost_imp = Qpost_imp  D / cr
Post development runoff; Qpost = Qpost_imp + Qpost_open
Permitted discharge; Oexist = Q  D
Post development runoff volume; Ipost = Qpost_open  D + Vpost_imp
Storage volume required; Spost = Ipost - Oexist

Required storage for period of 1 year


Discharge per hectare; Q1yr_area = Q1yr / A = 3.8 l/s/hectare
Greenfield runoff rate post development; Q1yr_post_open = Q1yr_area  Aimp = 0.9 l/s
Project Job no.
10 houses Mullinahone 19149
David Kelly Partnership Calcs for Start page no./Revision
Nelson House, Emmet Place
Attenuation tank - 10 houses 2
Youghal
Calcs by Calcs date Checked by Checked date Approved by Approved date
Co. Cork
GOS 31/10/2019

Duration 1 year Rainfall Peak Runoff Post Permit Post Storage


(min) rainfall intensity flow volume dev. dischrge dev. vol. reqd
(mm) (mm/hr) (m3/s) (m3) runoff (m3) runoff (m3)
(m3/s) vol (m3)
5 4.0 47.6 0.04 9.0 0.04 0.46 9.30 8.84
10 5.5 33.1 0.03 12.6 0.03 0.92 13.12 12.20
15 6.7 26.7 0.02 15.2 0.02 1.38 16.02 14.64
30 8.5 17.0 0.01 19.4 0.01 2.76 20.94 18.18
60 10.4 10.4 0.01 23.8 0.01 5.53 26.95 21.43
120 12.5 6.3 0.01 28.6 0.01 11.05 34.86 23.81
240 14.6 3.7 0.00 33.4 0.00 22.10 45.99 23.89
360 16.1 2.7 0.00 36.7 0.00 33.15 55.64 22.49
600 18.1 1.8 0.00 41.2 0.00 55.26 72.68 17.42
1440 22.1 0.9 0.00 50.5 0.00 132.61 126.09 -6.52

Attenuation storage required


Vol. increase due to head-discharge relationship; phydro = 1.25
Maximum attenuation storage required; Vreq_max = Vmax_1yr  phydro = 29.9 m3

Required storage for period of 30 year


Discharge per hectare; Q30yr_area = Q30yr / A = 7.2 l/s/hectare
Greenfield runoff rate post development; Q30yr_post_open = Q30yr_area  Aimp = 1.6 l/s
Duration 30 year Rainfall Peak Runoff Post Permit Post Storage
(min) rainfall intensity flow volume dev. dischrge dev. vol. reqd
(mm) (mm/hr) (m3/s) (m3) runoff (m3) runoff (m3)
(m3/s) vol (m3)
5 8.5 102.6 0.08 19.5 0.09 0.86 19.98 19.12
10 12.0 72.1 0.06 27.4 0.06 1.73 28.39 26.66
15 14.6 58.5 0.05 33.4 0.05 2.59 34.84 32.25
30 18.5 37.0 0.03 42.2 0.03 5.18 45.13 39.95
60 22.6 22.6 0.02 51.5 0.02 10.36 57.39 47.03
120 26.7 13.3 0.01 60.8 0.01 20.72 72.60 51.88
240 30.7 7.7 0.01 70.0 0.01 41.44 93.63 52.18
360 33.5 5.6 0.00 76.3 0.01 62.16 111.76 49.60
600 37.1 3.7 0.00 84.5 0.00 103.61 143.56 39.96
1440 44.3 1.8 0.00 100.9 0.00 248.65 242.62 -6.03

Attenuation storage required


Vol. increase due to head-discharge relationship; phydro = 1.25
Maximum attenuation storage required; Vreq_max = Vmax_30yr  phydro = 65.2 m3

Required storage for period of 100 year


Discharge per hectare; Q100yr_area = Q100yr / A = 8.5 l/s/hectare
Greenfield runoff rate post development; Q100yr_post_open = Q100yr_area  Aimp = 1.9 l/s
Duration 100 year Rainfall Peak Runoff Post Permit Post Storage
(min) rainfall intensity flow volume dev. dischrge dev. vol. reqd
(mm) (mm/hr) (m3/s) (m3) runoff (m3) runoff (m3)
(m3/s) vol (m3)
Project Job no.
10 houses Mullinahone 19149
David Kelly Partnership Calcs for Start page no./Revision
Nelson House, Emmet Place
Attenuation tank - 10 houses 3
Youghal
Calcs by Calcs date Checked by Checked date Approved by Approved date
Co. Cork
GOS 31/10/2019

Duration 100 year Rainfall Peak Runoff Post Permit Post Storage
(min) rainfall intensity flow volume dev. dischrge dev. vol. reqd
(mm) (mm/hr) (m3/s) (m3) runoff (m3) runoff (m3)
(m3/s) vol (m3)
5 11.1 133.1 0.11 25.3 0.11 1.03 25.87 24.84
10 15.8 94.6 0.08 35.9 0.08 2.05 37.10 35.05
15 19.3 77.3 0.06 44.1 0.07 3.08 45.83 42.75
30 24.5 49.0 0.04 55.8 0.04 6.15 59.35 53.20
60 29.9 29.9 0.02 68.2 0.03 12.31 75.25 62.95
120 35.1 17.5 0.01 80.0 0.02 24.61 94.05 69.44
240 40.1 10.0 0.01 91.5 0.01 49.23 119.58 70.35
360 43.6 7.3 0.01 99.3 0.01 73.84 141.41 67.56
600 47.9 4.8 0.00 109.3 0.01 123.07 179.46 56.39
1440 56.6 2.4 0.00 129.1 0.00 295.37 297.47 2.11

Attenuation storage required


Vol. increase due to head-discharge relationship; phydro = 1.25
Maximum attenuation storage required; Vreq_max = Vmax_100yr  phydro = 87.9 m3

Interception storage
Interception rainfall depth; dint = 5 mm
Volume of interception storage required; Vint_req = 0.8  Aimp  dint = 9.12 m3