CIS4603 – Project Management

Case Study – Scope Management

Description

You have been assigned a project manager role for a project to create an application that aims at helping
students to choose the courses to register in for each semester. The project shall make students choice for
course registration easier and more efficient. It also should support the advising tasks by proposing courses
to register in. The director of the college approved the project and assigned a budget of 150,000 Dirhams
for the project.
The application needs be connected to the courses and programs database. It should have a logon page, a
reporting functionality, and it should allow for filtering the courses offered by program and by college. This
is not a registration application it is an advising application that propose courses based on the student GPA,
courses completed, and program of study. The application needs to be ready before the spring semester in
2021. So should be deployed and go live by Dec 2020.
The project manager needs to submit the scope baseline by Jun 2020, submit the interface designs by Jul
2020 and submit a short, student oriented, training video that shows how the application works by Dec
2020.

Questions

1. Give an appropriate name for the project.


Students Advising System
2. What are two constraints in this project?
Project budget is AED150,000
Project should be completed by Dec 2020
3. Identify an assumption.
Programs and courses database will be available to connect to
4. Identify an exclusion.
Course registration is outside the scope of this project
5. List two project deliverables and two product deliverables.
Project deliverables: Project Charter, Project Scope Baseline, Project Progress Reports
Product Deliverables: Logon page, reporting functionality, interface design

RK Jun 2020 1
6. List two milestones.
Interface designs completed by Jul 2020
Application deployed and go live by Dec 2020
7. Who is the project sponsor?
The college director
8. List three project stakeholders
The college director, the students, the teachers, the development team

RK Jun 2020 2