The Federal Democratic Republic of Ethiopia
The Federal Democratic Republic of Ethiopia
The Federal Democratic Republic of Ethiopia
METHODOLOGY OF SCHEDULING
FEBRUARY 2019
ZELALEM, HAYAT & FRIENDSHIP SME Master Work Schedule
TABLE OF CONTENTS
CHAPTER ONE:
Mio Health Centre Staff Residence Construction Projects located the south eastern part of Bale
in the Dawe Kachen district and 135 Km from Robe town. The Employer of this project is Bale
Zone Health office. The project price is estimated to ETB 3,939,437.77 including all local taxes.
The whole project consist construction of 3 blocks (10 rooms) of residence room and 1
traditional kitchen with shower and toilets.
1.2 SCOPE
This part covers all the processes, techniques and methodologies to develop the project
construction plan which aims at the execution and completion of the Construction Mio Health
Centre Staff Residence Construction Projects in Bale Zone works within 120 working days.
1.3 SUMMARY OF INPUT DATA FOR PLANNING
This part covers the collection and formulation of data / information which is used to prepare the
work programs and schedules.
Available Working Days
CHAPTER TWO:
This is to explain the arrangements and methods proposed to adopt for the
execution of Mio Health Centre Staff Residence Construction Project on the basis of
the scope of work outlined in the bill of quantities, contract drawings and
specification thereof. Accordingly, the work program consists of a detail work
method statement of each particular construction activities by their category or
type and the requirements of different resources for each of particular activities
i.e., manpower, equipment and machineries, materials, etc. to achieve the
completion of the construction in accordance with the given contractual
obligations. To make it compatible with actual changing circumstances, delays or
amendments to the work ordered by the Engineer, this method statement is
subjected to be reviewed in due course of time.
The main operations included in this part of the project phase, but not limited, are
staffing and mobilizing Contractor’s key personnel to the site which have been
organized as Mio Health Centre Staff Residence Construction Project Team and
backed with experienced personnel. The investigation and assessment of the
availability of the required quantity and quality of the necessary labor and local
construction materials i.e., sand, water, stones, gravels etc., will be undertaken
during this stage. As usual, all material to be incorporated in works and
workmanship will be strictly of the respective kinds described in the contract and
in accordance with the Engineer’s instructions. In order to produce work which
conforms in quality and accuracy of dimensions to the requirements of
specification and drawings, a Quality control system with experienced staff,
together with all necessary facilities to ensure adequate supervision and positive
control of the works at all times ,will be implemented at site
We also study the duration and intensity of the rainfall by collecting data from
local villagers, work schedule reflects the prevailing weather condition.
As set out in drawings and BOQ, the principal items of work to be executed under
this contract are likely to include but are not limited to the following:
Construction procedure for each of the above mentioned activity is briefly presented on
following pages:
2.2.1 Mobilization
The mobilization of the project facilities, manpower, and light and heavy duty
equipment’s will be done step by step following the construction work schedule,
which gets earlier approval by the client, from their existing locations in order to
meet the proposed construction schedule. The necessary construction materials
required for the construction contractor’s temporary facilities: - site offices,
material stores, equipment stores, and guard house will be supplied at appropriate
location,
The required equipment for this particular project will be mobilized as per the
proposed equipment mobilization schedule attached here in with.
The necessary skilled and unskilled manpower will be deployed to the project site
as per the proposed schedule. The site organization and the assignment of key
personnel assigned is acquired by the contractor, this will be communicated to the
consultant and the client, and such change will only be effected if and only if
approval is given from the consultant and the client.
High quality cements, reinforcing bars, sand stones, nails, and other construction
materials will be delivered after sample approval of the assigned engineer. Also
Considering the constraint of space within the vicinity of construction site, the
required amounts of bar benders shade and other necessary shades will be
constructed on this stage.
Every of the above step will go through all the necessary test processes and will be
ready for use after the approval is granted by the resident engineer.
Prior to the start of the execution of the works, a survey will be executed arranged
by the contractor showing the condition of the existing and adjacent structures.
The location of any defect found will be determined and described. The result is to
be presented to the Engineer .We will appoint and employ the necessary qualified
and experienced staff to set out the work accurately including all necessary
chainmen. It will set out the works well in advance and in sufficient time to enable
the engineer to inspect and approve prior to commencement of the works.
Topography survey of the site will be performed by a senior surveyor and will
check the accuracy of the levels shown on the drawings or the directions given by
the engineer. This will establish an approved primary bench mark and a base line
on which all subsequent setting out will be based. Following this and prior to
construction activities, job/sit/ layout will be prepared and temporary facilities
construction will be commenced. Setting out will be done at every structural level.
The construction begins first by organizing the necessary work crews and then the
first activity will be to locate exact position of block as per the detail plan and
sections using surveying equipment. After locating the positions, the construction
work starts from earth work.
All excavation will be carried out to the lines, levels, widths, depths and grades shown on the drawings or
as directed by the engineer and as appropriate to the works to be placed in the excavation.
We shall examine the site carefully and will ascertain the nature and kind of
materials to be excavated.
Surplus excavated material will be removed from time to time to the appropriate
dumping ground.
2.3.2.3 Gravel
- Gravel used for concrete works will have a size of 20mm which is prepared and
produced by crusher. The stone for production of gravel will come from
quarries found around Adama city. For testing the stone whether it is basaltic
or not, a prior tests conducted by compressive strength machine will determine
the approval of this material by the engineer.
2.3.2.4 Sand
- Sand (fine and coarse) will be supplied from quarries found around Adama city
which will approve by the engineer, but before supplying, test will be
conducted. The gradation and cleanness will be as per the standards given in
the contract document.
Prior to every concrete activity formwork placing will be performed carefully and
will be prepared for the next day so that concrete will be filled. Before every
concreting step the construction engineer will check for its appropriate erection
and will give an order for the general Forman to proceed. This step is critical for
best concrete results and for structural reasons. Needed materials will be
delivered in bulk to the site during mobilization this includes ply wood, timber,
eucalyptus, nails and other necessary tools. Well Experienced man Power will be
assigned to carry out the work.
Mix design will be prepared at site and given for approval, and then concrete cube
samples will be taken for each class of concrete.
Slump test will be conducted during mixing of concretes and the slump should be
within limits given or supplied by the engineer.
b) Concrete mix
c) Transport of concretes.
One cone consistency (slump) test will be carried out when a test sample for
compressive and or tensile strength is made.
to center. Exposed parts of the wall faces will be cleaned of all mortal by
washing or wire brushing so that appearance of the completed wall will
present an even, tight surface.
At the initial stage of the project, the quarries with acceptable quality of rock for
masonry work and aggregate production will be selected and approved by the
Engineer. The exploitation of quarries shall be commenced as early as possible.
The quality control requirements contained in this section and elsewhere in the
contract technical specifications are in addition to and separate from the
The organizational chart shall identify all quality control staff by name and
function, and shall indicate the total staff required to implement all elements of the
quality control program, including inspection and testing for each item of work. If
necessary, different technicians can be used for specific inspection and testing
functions for different items of work. If an outside organization or independent
testing laboratory is used for implementation of all or part of the quality control
program, the personnel assigned shall be subject to the qualification requirements.
The organizational chart shall indicate which personnel are contractor employees
and which are provided by an outside organization.
The program administrator shall have full authority to institute any and all actions
necessary for the successful implementation of the quality control program to
ensure compliance with the contract plans and technical specifications. The
program administrator shall report directly to a responsible officer of the
construction firm. The program administrator may supervise the quality control
program on more than one project provided that person can be at the job site
within 2 hours after being notified of a problem.
d. Test standard
e. test frequency
f. responsibility
g. Control requirements.
Test results from each day’s work period shall be submitted to the engineer prior
to the start of the next day’s work period. When required by the technical
specifications, the contractor shall maintain statistical quality control charts. The
daily test reports shall be signed by the responsible quality control technical and
the program administrator.
The site organization will have a safety officer and his helpers to monitor the day
to day working style and workmanship of the workers. Proper signs to protect the
workers will be put at the right position by this team. Advices will be also given to
each worker at all times to avoid any dangers to them or other workers. Proper
safety equipment will be provided to staff and the management and supervision
staff that will be used while on site. Any person visiting the site will also be
provided with the same service. A suitable room will be provided and maintained
for first aid/safety matters and will be removed after completion of work.
Temporary fences will be constructed around the site. Temporary guard house at
the entrance gate with reasonable size will be constructed and will be removed
after completion of work. Placement of equipment at their appropriate locations
and working condition will be controlled by the safety crew. Precautionary
measures will be taken to minimize noise and dust. We will take all possible
measures to prevent accidents during the execution of the works. It will also take
care of all works to be performed or already constructed, adjacent buildings or
roads nearby the site.
The safety organizer all together with the gang chief and the guard men will follow
up the movement of each worker with in the vicinity, in order to eliminate
unnecessary movements towards places under secure.
The whole project activities will be evaluated every week by the project
management staffs with going through the weekly report. This weekly report is
prepared in the project office by compiling and analyzing the collected data and
information’s of the activities performed.
The weekly meeting will always be led and handled directly by the project
manager. During his absence, it will be organized by the delegated person, mostly
project office engineer or construction engineer.
Please refer next page for the project work performance controlling system chart
Project
Planning
Master
Monthly Weekly Weekly Collection
Scheduling
Work Work of Data and
Scheduling Scheduling Information
Data Weekly
Finding out
Analysis and Performance
Evaluation by Facts for
Weekly
Corrective
Report the Project
Management Measure
Preparation
Action.
Staff
Revising
Project Work
Monthly
Status Every
Report five Weeks
Preparatio
n
In accordance with the time frame (120 Calendar Days), the allocated contract
budget (3,939,437.77 ETB) and our method statement to cope up with the given
contractual obligation, we have prepared a preliminary work program considering
the detail on the contract documents (please refer to the work schedules).
CHAPTER THREE:
Please refer next page for the project work performance target
CHAPTER FOUR:
WORK SCHEDULE
4.1Bar chart
5.
4.2Gantt Chart
Refer to page ( )
4.3Physical work load Distribution
.
Refer to page ( )
4.4Cash Flow.
Refer to page ( )
4.5Manpower Schedule
.
4.7Equipment Schedule
Refer karoora meeshaalee page ( )
.