Project progress report

Project to install a biscuit line


Granada Food Sidi Sayeh Tripoli / Libya

Period: 19-02-2021  26-02-2021

Participants:
• Mr. Ghali Mahdi
• Mr. Celeste Bettani
• Mr. Mohammed Louhichi
• Mr. Nafaa Ismail
Achievement:
1. Define the rooms of the different compartments (Zone 1, Zone2, Zone3, Zone4) and
organization of the equipment.
2. Specify the final position of the line (See pdf file)
3. Check the position of the chimneys in order to avoid crossing with the beams.
4. Determine the level of each support leg of the oven
1 2 3 4 5 6 7 8 9 10
2.7 2.4 2.5 2.6 2.5 2.5 2.2 2.3 2.8 2.7
11 12 13 14 15 16 17 18 19 20
Côté 2.3 2 2 1.9 1.5 1.8 2 2.6 2.9 2.9
Droite 21 22 23 24 25 26 27 28 29 30
2.3 1.8 2.3 2.1 2.1 2.5 1.9 1.0 0.3 0.2
31 32 33 34 35
0.1 0.3 0 0.2 0.7

1 2 3 4 5 6 7 8 9 10
1.1 0.7 0.7 1.2 1.3 1.3 1.8 1.8 1.8 0.9
11 12 13 14 15 16 17 18 19 20
Côté 1.1 0.8 0.8 0.7 0.6 0.8 1.1 0.8 0.9 1.2
Gauche 21 22 23 24 25 26 27 28 29 30
0.9 0.8 1.0 1.2 1.3 1.2 0.7 0.7 0.4 0.2
31 32 33 34 35
0.2 0.3 0.9 0 0.1
5. Identify the different types of joints (fiberglass braid) and try to recover them by
looking in the different outlets of the local market
-Seal 20 * 20 (Sealing of the cooking chambers)
-Seal 12 * 12 (Tightness of the air blowing pipes inside the cooking chambers)
-Joint 6 * 6 (Sealing and expansion between the flue tubes)
-Joint 98 * 98 (Sealing of the smoke tubes and the sending and return manifolds)
6. Identify the different types of bolts and collect them.
7. Repair of damaged equipment and put in good condition before putting it in position.
8- Visit to the site of the old damaged line (Janzour) in order to recover missing critical
parts and identify the final list of parts to order.

Recommendations:
Depending on the condition of the site and the equipment, the installation of the biscuit
line oven will be carried out in two phases:

1st phase: Before and during the order


-Mounting of the entire metal structure and the different areas including the combustion
chamber and the blower fans, the air ducts.
-Fixing of the two conveyor rollers (motor roller, receiving roller)
so that we can install the REHON line and the EUROSICMA line.
-During this phase we must identify a final order list of missing and damaged parts

2nd Phase: After the order has arrived


-Mounting the upper and lower rollers of the oven (25 upper rollers, 25 internal rollers)
- Carpet assembly.
- thermal insulation of the structure and put the panels.
-Electrical Installation
- getting started