Professional Documents
Culture Documents
Buoyancy Calculation Report: Tanap Trans Anatolian Natural Gas Pipeline Project
Buoyancy Calculation Report: Tanap Trans Anatolian Natural Gas Pipeline Project
BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
TANAP
TRANS ANATOLIAN NATURAL GAS
PIPELINE PROJECT
SECURITY LEVEL 2
TANAP DOĞALGAZ İLETİM A.Ş. (TANAP) 2014. ALL RIGHTS RESERVED. TANAP CONFIDENTIAL. CONTAINS INFORMATION THAT IS CONFIDENTIAL AND PROPRIETARY TO TANAP OR ITS
AFFILIATES, CONTRACTORS, SUPPLIERS, AND MAY NOT BE USED, REPRODUCED OR DISCLOSED WITHOUT TANAP’S PRIOR WRITTEN PERMISSION.
ELECTRONIC DOCUMENTS ARE CONTROLLED. ANY PRINTED COPY WILL BE UNCONTROLLED AND MAY BECOME OUTDATED
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
Revision
Rev. Date Issued Update / Amendment Details
Description
PROJECT CONFIDENTIAL
Page 2 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
4.2 Basis
4.1.1 Line Pipe Properties (Dia, grade, WT, PE
thickness, etc.)
4.1.2 Soil / Media Properties (densities)
4.3 Calculations - Weighting Methods
4.3.1 Weighting Properties
4.3.2 Weight Calculations
4.3.2.1 PE Coated Pipe
4.3.2.2 Concrete Coated Pipe
4.3.2.3 Pipe with Concrete Saddles
4.3.2.4 Pipe with Saddle Bags
4.3.3 Buoyancy Calculations
4.3.3.1 PE Coated Pipe
4.3.3.2 Concrete Coated Pipe
4.3.3.3 Pipe with Concrete Saddles
4.3.3.4 Pipe with Saddle Bags
4.4 Calculations - Screw Anchors
4.4.1 Anchor Properties
4.4.2 Assumptions
4.4.3 Definitions
4.4.4 Buoyancy Calculations
4.4.4.1 Pipeline Weight
4.4.4.2 Anchor Loading
4.4.4.3 Deflection
4.4.4.4 Stress
PROJECT CONFIDENTIAL
Page 3 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
PROJECT CONFIDENTIAL
Page 4 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
HOLDS
Input Planned
No. Section Description
From Date
PROJECT CONFIDENTIAL
Page 5 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
TABLE OF CONTENTS
1 PURPOSE OF DOCUMENT..................................................................7
2 SCOPE OF DOCUMENT.......................................................................7
3 REFERENCE DOCUMENTS AND DEFINITIONS....................................8
3.1 Project Documents.........................................................................8
3.2 Codes & Standards.........................................................................8
3.3 Definitions.....................................................................................9
3.4 Abbreviations...............................................................................10
3.5 Unit Abbreviations........................................................................11
4 NEGATIVE BUOYANCY MEASURES...................................................12
4.1 Continuous Concrete Coating.........................................................12
4.2 Saddle Bags.................................................................................13
4.3 Concrete Saddle Weight................................................................14
4.4 Screw Anchor...............................................................................14
4.5 Comparison of Buoyancy Methods.....................................................16
5 BASIS OF CALCULATIONS AND FORMULAS.....................................18
5.1 Inputs for Concrete Coating, Saddle Bags and Concrete Saddle:.........18
5.2 The following formulas are used in the calculations for Concrete Coating,
Saddle Bag, and Concrete Saddle:..........................................................19
5.3 Inputs Screw Anchor:...................................................................23
5.4 Calculation Basis and Assumptions for Screw Anchor.........................24
5.5 Basis of Design for Screw Anchor....................................................25
5.6 The following formulas are used in the calculations for Screw Anchor...26
5.6.1 Pipeline.......................................................................................26
5.6.2 Anchor Loading Calculation............................................................26
5.6.3 Deflection Calculation....................................................................26
5.6.4 Stress Calculation.........................................................................27
6 CONCLUSION..................................................................................28
7 ATTACHEMENTS (CALCULATION TABLES).....................................31
PROJECT CONFIDENTIAL
Page 6 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
PURPOSE OF DOCUMENT
The cause of flotation is an uplift force which is weight per unit length of pipe
of displaced liquid. If the buoyancy force exceeds the weight of the pipe and
its content, the pipe floats upward.
SCOPE OF DOCUMENT
In all areas with ground water level and potential ground water level (in flood
and swamp areas) above the pipe bottom and organic soil, the buoyancy
control is carried out.
The calculation bases, feasible measures as well as input and output data for
buoyancy control are included to this document. The Stress calculation will
carry out in the detail design face.
The natural gas pipeline crosses the rivers, flood and swamp areas along
pipeline alignment. Anti-buoyancy measures such as concrete coating, saddle
bags, concrete saddle weight and screw anchor have to be provided after
assessment of their applicability.
In the scope of this document the aforesaid measures are taken into
consideration and assessed.
PROJECT CONFIDENTIAL
Page 7 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
The following codes and standards (latest edition) shall apply unless other
edition specified.
PROJECT CONFIDENTIAL
Page 8 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
3.3 Definitions
Definition Meaning
PROJECT CONFIDENTIAL
Page 9 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
3.4 Abbreviations
Abbreviation Meaning
PROJECT CONFIDENTIAL
Page 10 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
Abbreviation Meaning
°C Degrees Celsius
bNcmy Billion Normal Cubic Meters per Year
cm Centimeter
g Gram
in Inch
kg Kilogram
kN Kilo Newton
km Kilometer
m Meter
mm millimeter
°C Degrees Celsius
cm Centimeter
PROJECT CONFIDENTIAL
Page 11 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
The measures will be applied to provide negative buoyancy and prevent pipe
movement due to flotation, in swampy/marshy lands with high water tables
and also underwater pipelines.
Areas of clay and/or rock require special consideration since trenches in low
laying areas have a tendency to act as large land drains and fill with water. If
dry laying techniques are impractical or impossible for river crossings some
form of negative buoyancy measures are required. In areas of little or no soil
cohesion such as marshy/swampy lands or granular soil with a high water
table the negative buoyancy measures are also required.
It is costly method to apply to the pipe and transport the extra weight and
diameter but it is used offshore as well as river crossings and the
transportation can be eliminated by bringing the "factory" to site. Pipe can be
coated on site, adjacent to the trench, if required. Continuously coated pipes
give a dense homogenous concrete with a lower porosity and finish which
assists in protecting not only the pipe, but also against corrosion and erosion
of the primary coating system. Concrete coating may also be used to provide
mechanical protection to the pipeline for the backfilling process – with
concrete coating, natural coarse river bed material may be used rather than
needing to produce and import select material for bedding and padding.
Calculations are presented comprehensively in attachments with name 48”
Concrete Coating and 56” Concrete Coating.
PROJECT CONFIDENTIAL
Page 12 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
PROJECT CONFIDENTIAL
Page 13 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
These are used in soils with little or no cohesive strength. Saddle weight
weights are designed primarily for wetlands applications as might be
encountered in a flood plain or an approach to a river crossing. Weights are
balanced so that most weight is distributed to the legs, below the center line of
the pipe which provides a more secure fit. Sizes are ranging from 2" through
large size diameter pipe. Calculations are presented comprehensively in
attachments with name 48” Concrete Saddle and 56” Concrete Saddle.
PROJECT CONFIDENTIAL
Page 14 of 31
BUOYANCY CALCULATION REPORT Client No. BCH-CAL-PPL-PLG-002
Revision: P2-1 Status: IFA Date: 24.04.2014 Bechtel No. 25853-100-R5C-R000-00200
down force within the assumed allowable screw anchor design force and not
to exceed allowable deflection of 75% SMYS or 4” whichever less.
The design is complied with all assumption and calculation. Areas requiring
buoyancy control are specified in the design basis manual and alignment
sheets.
PROJECT CONFIDENTIAL
Page 15 of 31
4.5 Comparison of Buoyancy Methods
Saddle Bag Weights Concrete Saddle weight Weights Concrete Coated Pipe Screw Anchor
Generally used for wetland applications Primarily used for wetland Obligatory used in river crossings Used in potential liquefaction
applications, then areas where soils areas where ground
Environmentally clean – bag fabric is non- have little or no cohesive strength Concrete coated pipe is heavier conditions are suitable
biodegradable and fill ballast is local, (directly influencing overall project
natural gravel Curing of concrete often requires costs) Screw anchor is preferable
chemicals not natural to the method for liquefaction as
Short lead time surrounding environment Trucking costs are higher compare with others in terms
of installation, cost, time,
No trench dewatering required Longer lead time for weights to form Equipment costs are higher man power etc.
and cure
Saddle bag weights are a ‘soft’ weight Welding costs increase (many- Environmentally clean it is
requiring no extra depth Trench must be dewatered prior to more in trench welds) manufacture process and
installation no extra requirement at site.
No men required in trench to place saddle Whole construction process is
bag weights Extra trench depth is required to slowed-down. Mob/Demob is very easy
protect against 3rd party damage
Designed to sit on ANY trench bottom Expensive option for the pipeline No trench dewatering
Men required in trench creating industry
Saddle bag weight’s low center of gravity potential safety concern Designed to fix on ANY
prevents the risk of tipping Obligatory used in river crossings trench bottom if ground is
Designed to sit on flat trench bottom suitable
No gap between saddle bag weights and only to prevent tipping Concrete coated pipe is heavier
pipe (directly influencing overall project No damage and extra
Top heavy concrete weights can tip costs) protection material between
With a natural, local stone used as off pipe connection pipe and strap.
ballast, no chemical leaching to damage
the pipeline coating During installation, gaps between
weight and top of pipe common
Porous fabric and ballast allows easy
path to cathodic protection currents Have been known to leach chemicals
that can attack the pipeline coating
PROJECT CONFIDENTIAL
Page 16 of 31
Left-over saddle bag weights easily folded and groundwater
and stored or returned for refund
Cathodic protection systems can be
Easy to remove with straps if shielded
maintenance is required
Any left-over weights are difficult and
Lower installation cost than equivalent costly to accommodate
concrete based system.
Lift hooks rust, can be difficult to
remove if necessary
PROJECT CONFIDENTIAL
Page 17 of 31
BASIS OF CALCULATIONS AND FORMULAS
5.1 Inputs for Concrete Coating, Saddle Bags and Concrete Saddle:
Density of water at river crossings – 1000 kg/m3 only for water logging areas
PROJECT CONFIDENTIAL
Page 18 of 31
Thickness of PE coating – 3.5 mm
Volume of the Concrete Saddle 1.22 m3 for 56” and 0.92 m3 for 48”.
In order to ensure static equilibrium firstly, the weight of pipe and buoyant
force occurred on the pipe are evaluated.
The specific gravity of pipeline against buoyancy must be higher than or equal
to stability safe mass specific gravity (SAFE S.G.).
SAFE S.G. must be 10% greater than Mass Specific Gravity of Medium
(M.S.G.).
M.S.G. must be 1.0 for water crossings with concrete weight coatings and
1.80 for lying in swampy ground in accordance with BoD (Hold).
SAFE S.G. must be 1.10 for water crossings with concrete weight coatings
and 1.98 for Liquefaction areas.
5.2 The following formulas are used in the calculations for Concrete
Coating, Saddle Bag, and Concrete Saddle:
W = Wp + Wc
Where:
In order to investigate the worst case, Wc will be assumed as “0” for an empty
pipe.
PROJECT CONFIDENTIAL
Page 19 of 31
For static equilibrium, the buoyant force must not exceed pipe weight reduced
by safety factor (SF).
W
S=
B S > SF
Where:
B : Buoyant force
γ =ρ⋅g
ρ : Density (kg/m3)
π
W p=(D a 2 −D i ) γ p
2
Where:
PROJECT CONFIDENTIAL
Page 20 of 31
π
W PE=( D 2 −D 2 ) γ PE
PE a 4
Where:
W S =DPE⋅h⋅(γ S −γ w )
Where:
π
W Con=( D −D ) γ
4 Con
2 2
Con Rock
Where:
PROJECT CONFIDENTIAL
Page 21 of 31
γ Con : Specific weight of concrete coating (N/m3)
Where:
W SB=V SB⋅γ SB
Where:
π
B PE =D2PE⋅ ⋅γ w
4
Where:
π
B Con=D 2Con⋅ ⋅γ w
4
PROJECT CONFIDENTIAL
Page 22 of 31
Where:
B FS =V FS⋅γ w
Where:
B SB =V SB⋅γ w
Where:
PROJECT CONFIDENTIAL
Page 23 of 31
b Density of Saturated Soil 14.416 (kN/m3)
s Steel Density 78 (kN/m3)
Pipe Coefficient of Thermal Expansion 1.22E-05 (1/°C)
In location where the highest water table is less than 2.5m below the
natural grade.
PROJECT CONFIDENTIAL
Page 24 of 31
5.5 Basis of Design for Screw Anchor
The anchor locations are selected based on the anchor design capacity limit
for all the applications. The anchor spacing was selected to be less than
allowable maximum unsupported span.
The pipe maximum deflection and the deflection angle are calculated on the
base of the selected anchors spacing.
PROJECT CONFIDENTIAL
Page 25 of 31
5.6 The following formulas are used in the calculations for Screw Anchor
5.6.1 Pipeline
πρs ( OD 2 −ID 2 )
W p=
4
The uniform buoyancy force of the pipeline is considered only the pipeline is
installed by open cut method in saturated soil characteristic which is more
conservative and effective than in high water table area.
πρ b ( OD 2 )
F B=
4
πρ b OD 2 πρ s ( OD 2 − ID 2 )
w b= −
4 4
The load generated by the net buoyancy force for the given anchor spacing is;
F L=wb L
As design basis manual specified safety factor = 2, so safe load of screw
anchor is;
F S =2 F L
4 4 4
wL by where π ( OD −ID )
Δ max = |Δ|≤0.1m.
PROJECT CONFIDENTIAL I=
185 EI 64
Page 26 of 31
5.6.4 Stress Calculation
S p =0 . 3 S H
SH is the net resultant hoop stress determined by;
S H =S Hi + SC
SHi is the hoop stress produced by the internal pressure of the fluid in a pipe
determined by Barlow’s formula is;
Sc is the contact stress induced in the pipe wall produced by the screw
anchor loading force determined by Roark and Young’s Formulas is;
P . OD
S Hi=
2t
KF L
SC=
t 2
ln ( OD
2t )
when K= 0. 02− 0. 00012( β−90 )
The nominal bending stress in straight pipe or large radius bends due to
weight or other external load is;
M
SB =
Z
The bending moment across the pipe cross section is calculated base on a
uniform loaded over entire span as pipeline continuous supported – two equal
spans is;
2
wL
M=
8
PROJECT CONFIDENTIAL
Page 27 of 31
π ( OD 4 − ID 4 )
Z=
32OD
The net longitudinal stresses in restrained pipe is;
S L= S P + S T +S B
|S L|≤0. 9 ST
The maximum permitted value for combined biaxial stress state of the pipeline
in operation is;
|S H −S L|≤kST
6 CONCLUSION
Based on calculations results and past experienced which were gained from
site experiences and international standards, the concrete coating method is
desirable method for river crossing due to the requirement for both
mechanical protection and DSI provisions. Concrete coating will be executed
for river’s set back (bank to bank), it was outcome of site surveys and
statutory meeting requirements. Screw anchor is more suitable and preferable
buoyancy method for water logging, liquefaction and swamp & marshy areas
in terms of applicability at site, cost-effective, time and constructability in
addition screw anchor can be used for small rivers where buoyancy control is
required. Saddle bad and concrete saddle options are not preferable method
for river and water logging areas due to negative buoyancy quality and
construction difficulties. Liquefaction and swampy/marchland areas have high
density of medium, therefore saddle bag and concrete saddle are not
applicable for both areas in terms of required big size of saddle volumes and
very short spacing between bags/saddles. All buoyancy methods have been
evaluated in the calculation tables in order to have all calculations results for
comparison between different buoyancy protection types. Result and
outcomes of calculation tables as well as applicable buoyancy methods and
areas are summarized in Table 2.
PROJECT CONFIDENTIAL
Page 28 of 31
n Logging Marshy Crossings
Concrete Coating X X X √
Screw Anchor √ √ √ √
Saddle Bag X √ X √
Concrete Saddle X √ X √
X: Not Applicable
√: Applicable
PROJECT CONFIDENTIAL
Page 29 of 31
Line size 36 inch 30 inch
Design factor 0.72 0.6 0.5 0.72 0.6 0.5
Screw Anchor
21 m 24 m 26 m 30.2 m 32.2 m 34 m
Spacing 1,8 MSG
PROJECT CONFIDENTIAL
Page 30 of 31
7 ATTACHEMENTS (CALCULATION TABLES)
PROJECT CONFIDENTIAL
Page 31 of 31