PROPINSI
JAWA TENGAH
4.00 KABUPATEN
KENDAL
0.20 KECAMATAN
KALIWUNGU
0.90 1.50 DESA
DENAH PENULANGAN PLAT NOLOKERTO
LOKASI
DENAH GORONG-GORONG
RT 1 RW 1
0.30 PAS BATA MERAH 1:3 0.30 1.50
PAS BATA BELAH1:5 JENIS SARANA
PLAT BETON BERTULANG 1:2:3
0.50
0.20 Gorong-Gorong Plat Beton
0.70
GAMBAR
0.20
POTONGAN
0.30 0.30
DIBUAT OLEH
0.30 0.30
0.40 0.90 0.40 PELAKSANA KEGIATAN
DIPERIKSA OLEH
POTONGAN B - B POTONGAN A - A
CARIK
DIKETAHUI OLEH
KADES
Kabupaten KENDAL Jenis Prasarana Gorong-Gorong Plat Beton
Kecamatan KALIWUNGU Take Off Sheet Lokasi RT 1 RW 1
Desa NOLOKERTO Volume 4 X 0.4 X 0.3
f Volume bekisting
(4 + 0.2 + 0.2) X 0.9 = 3.96 m²
h Perhitungan plesteran
I 0.3 X 0.5 X 2 X 2 = 0.6 m²
II 1.5 X 0.5 X 2 X 2 = 3.0 m²
III 0.3 X 1.5 X 2 = 0.9 m²
Total = 4.5 m²
i Perhitungan acian
I 0.3 X 0.5 X 2 X 2 = 0.6 m²
II 1.5 X 0.5 X 2 X 2 = 3.0 m²
III 0.3 X 1.5 X 2 = 0.9 m²
Total = 4.5 m²
j Langsiran material
Pekerja langsiran (1 m³ = 0,5 HOK)
Bahan = 11.1 m³
Pekerja = 5.5 HOK
IV Beton 1 : 2 : 3 1.2 m³
(SNI 2009, Bab 8, hal 37)
0.8100 Batu pecah ⅔ 1.0 m³ 370,000 359,640
0.5400 Pasir muntilan 0.6 m³ 390,000 252,720
6.7200 Semen 50 Kg 8.1 Zak 90,000 725,760
2.0000 Pekerja 2.4 HOK 55,000 132,000
0.3500 Tukang 0.4 HOK 75,000 31,500
1.0000 Kepala Tukang 1.20 HOK 75,000 90,000
1.0000 Mandor 1.2 HOK 60,000 72,000
Total biaya 1,663,620
Rincian Pendanaan
Alat 216,000
Cetok 1.0 Set 14,000 14,000
Ember plastik (5 liter) 2.0 Buah 10,000 20,000
Sekop 1.0 Buah 91,000 91,000
Cangkul 1.0 Buah 91,000 91,000
JUMLAH 25,765,500
Nolokerto,
...................................... ……………………