Value of Works 879,290,000.00 : Total
Value of Works 879,290,000.00 : Total
Value of Works 879,290,000.00 : Total
00
Weightage in % %
Item Stage for Payment Amount in INR
to contract price Weightage
1 2 3 4 5
Road Works 75.93% A- Widening and strengthening of existing road
(1)Site clearance and Dismantling 1.53% ₹ 13,417,965.40
(2)Earthwork in shoulder/embankment 6.43% ₹ 56,511,968.30
(3) Non Bituminous sub base/base work(GSB+WMM) 25.05% ₹ 220,244,559.20
(4)Bituminous base course (DBM ,prime coat &tack coat) 26.25% ₹ 230,848,796.60
(5) Wearing coat (BC) 16.67% ₹ 146,577,643.00
Total 75.93% ₹ 667,600,932.50
Culvert 6.44% (A)Reconstruction and widening of Culverts (length <6m) 6.44% ₹ 56,608,690.20
Electrical Utility shifting 2.05% Electrical Utility shifting with all complete job 2.05% ₹ 18,016,652.10
Miscellaneous 1.25% Diversion, Repairs and Rehabilitation and Vehicle etc. 1.25% ₹ 10,991,125.00