Value of Works 879,290,000.00 : Total

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Value of Works ₹ 879,290,000.

00
Weightage in % %
Item Stage for Payment Amount in INR
to contract price Weightage
1 2 3 4 5
Road Works 75.93% A- Widening and strengthening of existing road
(1)Site clearance and Dismantling 1.53% ₹ 13,417,965.40
(2)Earthwork in shoulder/embankment 6.43% ₹ 56,511,968.30
(3) Non Bituminous sub base/base work(GSB+WMM) 25.05% ₹ 220,244,559.20
(4)Bituminous base course (DBM ,prime coat &tack coat) 26.25% ₹ 230,848,796.60
(5) Wearing coat (BC) 16.67% ₹ 146,577,643.00
Total 75.93% ₹ 667,600,932.50

Culvert 6.44% (A)Reconstruction and widening of Culverts (length <6m) 6.44% ₹ 56,608,690.20

A.1- Widening and Repair of Minor Bridges


Minor Bridges 2.18% (length > 6m and <60m)
A.2- New Minor Bridges (length > 6m and <60m)
(1) Foundation 0.45% ₹ 3,912,840.50
(2) Sub structure 0.65% ₹ 5,750,556.60
(3) Suer structure 0.21% ₹ 1,855,301.90
(4) Approach 0.87% ₹ 7,676,201.70
Total 2.18% ₹ 19,194,900.70

Drainage and Protection


Work 9.50% Drainage and Protection Work with all complete job 9.50% ₹ 83,488,585.50

Traffic Signs, Marking


and other Road Traffic Signs, Marking and other Road Appurtenances with all
Appurtenances 2.66% complete job 2.66% ₹ 23,389,114.00

Electrical Utility shifting 2.05% Electrical Utility shifting with all complete job 2.05% ₹ 18,016,652.10

Miscellaneous 1.25% Diversion, Repairs and Rehabilitation and Vehicle etc. 1.25% ₹ 10,991,125.00

Grand Total 100% ₹ 879,290,000.00