Project start date and holidays:

2
WBS outline
1.0 Conveyor Belt Project

1.1 Hardware 1.2 Operating System 1.3 Utilities 1.4 System integration

1.1.1 Hardware 1.2.1 Kernel 1.3.1 Utilities 1.4.1 Architectural


Specification specification Specifications decisions

1.2.2 Memory 1.4.2 Integration first


1.1.2 Hardware design 1.3.2 Routine utilities
management phase

1.1.3 Hardware 1.2.3 Operating system 1.4.3 System


1.3.3 Complex Utilities
documentation documentation hard/software test

1.3.4 Utilities 1.4.4 Project


1.1.4 Prototypes 1.2.4 Network interface
documentation documentation

1.1.5 Order circuit 1.4.5 Integration


1.2.5 Drivers 1.3.5 Shell
boards acceptance test

1.1.6 Assemble
1.2.5.1 Disk drivers
preproduction models

1.2.5.2 Serial I/O


drivers

3
When this project estimated to be completed?
It is estimated to be completed on 20th Jan 2012

How long the project will take?


It will take 530 days

What is the critical path(s) for the project?

4
Which activity has the greatest amount of slack?

It is utilities documentation which has 115 days of slack