Download as pdf
Download as pdf
You are on page 1of 5
yz California State University Northridge Department of Civil Engineering & Construction Management Prof. Ananian: CE315 — Mid Term Exam #la Spring 2015 (1 hour and 30 minute exam, no questions allowed, closed book and notes) Problem 1 A. Inthe Earned Value Analysis we found: BCWP = $32,500; BCWS = $25,400; ACWP = $25,000 (Circle the best result that applies) coup io Cn} CLT a. Behind Schedule and OverBudget SPL=———,-CPL= Ecus AcwP b. Behind Schedule and Under-Budget . stp = #228 21,26 71007 Ahead of Schedule and Over-Budget #25, 400 Abead of Scheduleand Under Budget 4 | #E2SCO 9 Sin) 0% [Show calculations to prove your results] €29)000 . Auenoor Creoure { Uncen Bucaer B. Free float represents: The portion of total float where it is not influenced by preceding activities The portion of total float where it does not influence following activities. c. Botha &b. d. None of the above. then: 4 Z C. Where there is a 3-day lag between the end of activity A and the start of activity of B, a. Activity B has to wait exactly 3 days after the completion of activity A before it can start, Activity B has to wait at least 3 days after the completion of activity A before it can start. c. Activity B has to wait at most 3 days after the completion of activity A before it ccan start, 4. Activity B cannot take more than 3 days in duration. — 4 ] D. Your critical path is 30 days long. The next longest path is 26 days. a. If you extend the longest path by 5 days, the entire project's duration will increase by 5 days. (Grne)pr false? b, _If you reduce the longest path by 5 days, the entire project's duration will decrease by 5 days. True orfalsy c. If youreduce the longest path by 10 days, the entire project's duration will decrease by 8 days. True ors) y 7. E. Activity A has 6 days of total float and 2 days of free float: Which statement is correct: ° If activity A is delayed 4 days, the project will finish 2 days late. If activity A is delayed 4 days, nothing will be impacted. a b. © If activity A is delayed 4 days, the completion date of the project will not be impacted but the succeeding activity(s) will be impacted. d. Activity A can be delayed a total of 8 days (6+2) before it delays the completion of the project. Problem 2 A mason contracted with a general contractor to build an exterior wall from CMUs. The ‘mason must finish a 1250 CMU wall within (5) days and gets paid $5 per block. At the end of day 1, the mason has installed 600 CMU blocks. His actual cost (including overhead and profit) was $1125. Analyze the situation with regard to both budget and the schedule. What is estimated cost to complete (ETC) and the estimated cost at completion (EAC)? [Show calculations to prove your results] Tom Guomer (@sc) = (2D tof #6250 — Pommerseo Paso ceo /Divg = SD xl eg F280 — CHU/pay Renna Buoner /Dacy = €6,2 aa #1280 — ony Hemtere > 22 = 48% , Acwe= 4 — 7 ba P= (A enorerr) (Bre) » Fie Ai aso Bee = (fermen Pupuctens / Omg )(lmee /eru ) = H1 4 err= BuP _ ieee 2 2672 S 107,“ unpse -—Ruomet P ns sie bab, dom 0%, Doo —* Melo wesoeone 1,207.28 7 F128, = (Bo,2s0 - #3000)/2.67 Sete = FI? eS = - CPL es (ie, seen) SS cnce Ha 4 $127.23 ene = $2,342.23 Problem 3 Draw the following network diagram: Type Rel. Activity | Duration 5 7 IPA Lag EF = 10. 13 IZ Got. Gun. a le ye-s-10=3 fe IS-3-127O SS SS FF 10 4 4c | FF 13 2 D. iS 2 D FF 1S 3 | GEF 21 I+ | DENOTES RELATIONSHIP IS FINISH START AND LAG |S ! F: ZERO 2 tS, 0€F: HT [Show the node network diagram with all total floats and free floats, and lags per activity — Use Attached Template to transfer results from Node Network] | csanea. rch: A-C- =) | a | Daina Aen 3,10 ———— Seo! Dee = nays ers dr, o | 16 DAE zo, ten Mneed & Sop 2 Ute = min Vc, (uc-€*)| ste = alee (ces) ~ (e-EP) | N ale kerry Cees Ae ATE CSES 7 QO aye eh Tes Sap tune =O = FF A i. roblem 4 se Draw the node network for the project below. Do the CPM calculations based on the most likely durations, What paths are the critical paths if activity D were lagged by 3 days: (a) Calculate the Expected Duration and Standard Deviations for the chosen Critical Path’s Activities, using 80% confidence. () Determine the Level of Confidence if the longest path that yielded a higher certainty date were to be performed in 30 days (Ts). Te = Tp?'/Tm¢ To yew a e =e Activity | IPA Duration — Expected Duration | Standard Deviation | Variance Optimistic Most Likely Pessimistic = a ; o.0yy oe a 2 3 6 3.333 0.6677 yt ie al 3 4 8 4.500 0.4633 0.644 palsy e cia 3 5 8 LT 0.823 0.644 ar Dd _|ec| 2 5 8 S000 1,000 t.ove E c 2 6 9 $.833 VAG 1.361 — A F [oe 2 4 6 4,000 0.667 O. Uy —>| q 6 |r 4 7 1 7,000 1.000 00 [Show the node network diagram with all total floats and free floats per activity] [eerem bret AR c-0-F-G | Bil € 4 Na Ile Tel, BD 48 AS 16,20 20,27 Te Tare FB S22 FI 36 F Le ica ¢ Bull 4 6,20 30,27 [loretuanon Gan: s }—Je aeeziee 3/8 one |? Zt Zona - Cura) ly Te + 234 LUT SH0 + Bite + Heo + 7.0% & Te-27800 Hee OMNy ¢ a644 + Ho0e + OMYLY (000 > Vex 3-882 oe Ne = 182, Tee Te+ 9? (Zax) 0.0 on 02 03 04 Os 06 07 08 09 1.0 1a 12 13 14 15 1.6 17 18 19 2.0 24 22 23 24 25 26 27 28 29 0.5040 0.5080 05438 0.5478 0.5832 0.5871 0.6217 0.6255 0.6591 0.6628 0.6950 0.6985 0.7291 0.7324 0.7611 0.7642 0.7910 0.7939 o.aiss 0.8212 0.2438 0.8461 o.a66s 0.8686 o.a869 0,9049/1) [0 0.9207 0.9222 0.9345 0.9357 0.9463 0.9474 0.9564 0.9573 0.9649 0.9656 0.9719 0.9726 0.9778 0.9783 0.9826 0.9830 0.9864 0.9868 0.9896 0.9898 0.9920 0.9922 0.9940 0.9941 0.9955 0.9956 0.9966 0.9967 0.9975 0.9976 0.9982 0.9982 0.9987 Lotyge — 069066 0.9082 -0.F 06. 4 0.9987 0.5120 0.5517 0.5910 0.6293 0.6664 0.7018 0.7357 0.7673 0.7967(+) 0.8238 0.8435 0.8708 0.5160 0.5857 0.5948 0.6331 0.6700 0.7054 0.7389 0.7704 0.7995 0.8264 0.8508 0.8729 0.8925 0.9099 0.9251 0.9382 0.9495 0.9591 0.9671 0.9738 0.9793 0.9838 0.9875 0.9904 0.9927 0.9945 0.9959 0.9969 0.9977 0.9984 0.9988 0.5239 0.5636 0.6026 0.6406 0.6772 0.7123 0.7454 0.7764 0.8051 0.8315 0.8554 0.8770 0.8962 0.9131 0.9279 0.9406 0.9515 0.9608 0.9686 0.9750 0.9803 0.9846 0.9881 0.9909 0.9931 0.9948 0.9961 0.9971 0.9979 0.9985 0.9989 0.5273 0.5675 0.6064 0.6443 0.6808 0.7157 0.7486 0.7794 0.8078 0.8340 0.8577 0.8790 0.8980 0.9147 0.9292 0.9418 0.9525 0.9616 0.9693 0.9756 0.9808 0.9850 0.9884 9911 0.9932 0.9949 0.9962 0.9972 0.9973 0.9985 0.5359 0.5753 0.6141 0.6817 0.6879 0.7224 0.7549 0.7852 0.8133 0.8389 0.8621 0.8830 0.9015 0.9177 0.9319 0.9441 0.9545 0.9633 0.9706 0.9767 0.9817 0.9857 0.9890 0.9916 0.9936 0.9952 0.9964 0.9974 o.gs81 0.9986

You might also like