Department of Public Works and Highways (DPWH) : Instructions For Completeting The Summary of Bid Prices
Department of Public Works and Highways (DPWH) : Instructions For Completeting The Summary of Bid Prices
Department of Public Works and Highways (DPWH) : Instructions For Completeting The Summary of Bid Prices
Contract ID : 21LB0216
Contract Name : Construction of Road in Barangay 8-A (Poblacion District), Davao City,
Davao del Sur
ABC: Php 14,850,000.00
Location of the Contract : Davao City
Fourteen Million Seven Hundred One Thousand One Hundred Twenty Seven Pesos and 67/100.
Duly authorized to signed the Bid for and on behalf of NEN Builders and Development Services Corp.
Department of Public Works and Highways (DPWH)
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location of the Contract : Davao City
BILL OF QUANTITIES
Part No. Part Description :
Section Scope of Work Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART B OTHER GENERAL REQUIREMENTS
In Words In Words
Eight Thousand Two Hundred Eighty Six Thousand Two Hundred Fourteen
B.4(1) Construction Survey and Staking Kilometer 0.75
Five Pesos and 76/100. Pesos and 32/100.
In Figures 8,285.76 In Figures 6,214.32
In Words In Words
Project Billbord/Signboard (2- Five Thousand One Hundred Two Fifteen Thousand Three Hundred Seven
B.5 4'x8' DPWH Billboard, 1-8'x8' Each 3.00
Pesos and 55/100. Pesos and 66/100.
COA Billboard)
In Figures 5,102.55 In Figures 15,307.66
In Words In Words
Four Hundred Twenty Five Thousand Four Hundred Twenty Five Thousand
Occupational Safety and Health
B.7 (2) Lump Sum 1.00 Eight Hundred Eighty One Pesos Eight Hundred Eighty One Pesos
Program
and 86/100. and 86/100.
In Figures 425,881.86 In Figures 425,881.86
In Words In Words
B.8(2) Traffic Management Lump Sum 1.00 Sixty Eight Thousand Forty Pesos. Sixty Eight Thousand Forty Pesos.
In Figures 68,040.00 In Figures 68,040.00
In Words In Words
One Million Three Hundred Thousand One Million Three Hundred Thousand
B.9 Mobilization/Demobilization Lump Sum 1.00
One Hundred Ten Pesos. One Hundred Ten Pesos.
In Figures 1,300,110.00 In Figures 1,300,110.00
In Words
Sub-Total for this Page: One Million Eight Hundred Fifteen
Thousand Five Hundred Fifty Three
Pesos and 85/100.
In Figures 1,815,553.85
Submitted by:
In Words
Sub-Total for this Page: Three Million Seven Hundred Fifty Three
Thousand Three Hundred Ninety Four
Pesos and 44/100.
In Figures 3,753,394.44
Submitted by:
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location of the Contract : Davao City
BILL OF QUANTITIES
Part No. Part Description :
Section Scope of Work Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART D SUBBASE AND BASE COURSE
In Words In Words
One Thousand Three Hundred Twelve One Million Sixty Thousand Nine Hundred
200(1) Aggregate Subbase Course Cubic Meter 808.40
Pesos and 45/100. Eighty Six Pesos and 24/100.
In Figures 1,312.45 In Figures 1,060,986.24
PART E SURFACE COURSES
In Words In Words
Portland Cement Concrete One Thousand One Hundred Forty One Four Million Four Hundred Fifty Six
Square
311(1)c2 Pavement (Unreinforced), 0.23m 3,903.80 Pesos and 68/100. Thousand Eight Hundred Ninety Eight
Meter
thk, 7 days Pesos and 46/100.
In Figures 1,141.68 In Figures 4,456,898.46
PART G DRAINAGE AND SLOPE PROTECTION
In Words In Words
Five Thousand Six Hundred Thirty Nine Three Million Two Hundred Forty Eight
Pipe Culverts, 910mm Ø, Class Linear
576.00 Pesos and 90/100. Thousand Five Hundred Eighty Three
500(1)b3 IV, RCPC Meter
Pesos and 66/100.
In Figures 5,639.90 In Figures 3,248,583.66
In Words In Words
Manholes (910mm dia., Eleven Thousand Seven Hundred Three Hundred Sixty Five Thousand
Each 31.00
502(1)a3 concrete) Ninety Seven Pesos and 13/100. Seven Hundred Eleven Pesos and 2/100.
In Figures 11,797.13 In Figures 365,711.02
In Words
Sub-Total for this Page: Nine Million One Hundred Thirty Two
Thousand One Hundred Seventy Nine
Pesos and 38/100.
In Figures 9,132,179.38
Submitted by:
Contract ID : 21LB0216
Contract Name : Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao
del Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
No. of Qty. Description Rate per Day No. of Days COST (ADD)
1 Construction Foreman 650.00 1 650.00
2 Instrumentman 475.00 1 950.00
4 Surveyman 475.00 1 1,900.00
3 Laborer 350.00 1 1,050.00
SUB-TOTAL 4,550.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 4,550.00
Contract ID : 21LB0216
Contract Name : Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao
del Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 1,475.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 1,475.00
Contract ID : 21LB0216
Contract Name : Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del
Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 12,080.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 12,080.00
Contract ID : 21LB0216
Contract Name : Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del
Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL -
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P -
Total Direct Cost P 60,000.00
O.C.M. P -
Profit P 4,800.00
TAX P 3,240.00
Total Indirect Cost P 8,040.00
Total Cost P 68,040.00
Unit Cost P 68,040.00
Department of Public Works and Highways (DPWH)
Contract ID : 21LB0216
Contract Name : Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del
Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL -
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P -
Total Direct Cost P 1,238,200.00
O.C.M. P -
Profit P -
TAX P 61,910.00
Total Indirect Cost P 61,910.00
Total Cost P 1,300,110.00
Unit Cost P 1,300,110.00
Department of Public Works and Highways (DPWH)
Contract ID : 21LB0216
Contract Name : Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del
Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 12,150.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 12,150.00
Contract ID : 21LB0216
Contract Name : Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del
Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
No. of Days
No. of Qty. Description Rate per Hour/Day COST (ADD)
1 Project Foreman 650.00 29.0 18,850.00
3 Laborer 350.00 29.0 30,450.00
SUB-TOTAL 49,300.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 49,300.00
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)
129.00 kg. Reinforcing Steel Bar 44.10 5,688.90
87.00 lit. Curing Compound 95.00 8,265.00
36.00 lit. Asphalt Sealant 44.00 1,584.00
138.00 m. Steel Forms (Rental) 61.00 8,418.00
38.00 cu.m. Sand 556.00 21,128.00
69.00 cu.m. Gravel 676.00 46,644.00
653.00 bag Cement 260.00 169,780.00
1.00 pc Concrete Saw 8,000.00 8,000.00
3.00 m. Pipe Sleeve, 2"Ø 97.00 291.00
3.00 lit. Grease/Tar 300.00 900.00
TOTAL Materials Cost P 270,698.90
SUB-TOTAL 303,750.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 303,750.00
9.5 P 3,597,173.90
O.C.M. P 359,717.39
Profit P 287,773.91
TAX P 212,233.26
Total Indirect Cost P 859,724.56
Total Cost P 4,456,898.46
Unit Cost P 1,141.68
Department of Public Works and Highways (DPWH)
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 141,750.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 141,750.00
Contract ID : 21LB0216
Contract Name :
Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 64,200.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 64,200.00
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 6.41 trips/day
Total DT travel time 70.21
say 6.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 6.41 trips/day
Total DT travel time 70.21
say 6.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: #REF! / 420.00 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: #REF! / 420.00 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
BACK-UP COMPUTATION
5b/8
Equipments Required :
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 cu.m/day
No. of days required: #REF! / 420 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
BACK-UP COMPUTATION
Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: #REF! / 420.00 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: - / 420.00 = - days say - days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: - / 210.00 = - days say - days
BACK - UP COMPUTATION
506 Riprap
Quantity:
Volume Multiplier
Cement = #REF! x 4.25 = #REF! bags say #REF! bags
Sand = #REF! x 0.62 = #REF! say #REF! cu.m.
Boulders = #REF! x 1.05 = #REF! say #REF! cu.m.
Quantity:
Volume Multiplier
Cement = #REF! x 4 = #REF! bags say #REF! bags
Sand = #REF! x 0.605 = #REF! say #REF! cu.m.
Boulders = #REF! x 1.05 = #REF! say #REF! cu.m.
Department of Public Works and Highways (DPWH)
Contract ID : 20LB0183
Contract Name : Construction of Drainage Along Davao – Cotabato Old Rd. K1520+745 –
K1520+750, Davao City
Location of the Contract : Davao City
MANPOWER
Project Engineer 1,000.00 / day
C & M Foreman / Eng'ng Assistant 650.00 / day
Laborer / T&C Helper 350.00 / day
Mason/ Steelman/ Carpenter/ Painter 475.00 / day
Welder/Eletrician 420.00 / day
H.E.O. (Bulldozer/Excavator/Loader/Grader/Crane/Prime Mover) 550.00 / day
Driver (Dumptruck/Water Truck) 475.00 / day
L.E.O. (Compactor, Vibrator, Mixer) 425.00 / day
Crane 80.00 lit. / day 21,250.00 / day
Bulldozer 80.00 lit. / day 15,780.00 / day
Back hoe 60.00 lit. / day 8,800.00 / day
Dump Truck 50.00 lit. / day 7,250.00 / day
Water Truck 35.00 lit. / day 5,725.00 / day
Road Grader 50.00 lit. / day 8,250.00 / day
Road Roller 40.00 lit. / day 6,700.00 / day
Pay Loader 50.00 lit. / day 11,550.00 / day
Transit Mixer 40.00 lit. / day 7,250.00 / day
PRIME MOVER/ LOW BED TRAILER 60.00 lit. / day 9,300.00 / day
Single Bagger Concrete Mixer 6.00 lit. / day 1,670.00 / day
Concrete Vibrator 6.00 lit. / day 1,030.00 / day
PLATE COMPACTOR 5.00 lit. / day 1,000.00 / day
Chainsaw Operated 2,400.00 / day
Concrete Cutter Operated 1,250.00 / day
BAR CUTTER /BAR SHEAR Operated 1,750.00 / day
BAR BENDER Operated 1,100.00 / day
Concrete Batch Plant 14,100.00 / day
Concrete Screeder 4,360.00 / day
Concrete Saw 260.00 / day
DIESEL 50.00 / liter
GASOLINE 60.00 / liter
Submitted by:
MATERIALS
Portland Cement 258.00 / bags
Reinforcing Deformed bars 44.00 / kg.
Asphalt cement 60/70 Hot poured 44.00 / liter
Plastic Canvass (12 ft. wide) 141.60 / mtrs
Hacksaw blade (Heavy duty) 82.00 / pcs
Deformed bars/RSB (Grade 40) 42.00 / kgs.
Assorted CW Nails 76.00 / kgs.
Tarpauline - as per design 25.00 / sq.ft.
Ordinary plywood, 10mm thk. x 4' x 8' 714.00 / pc/s
Marine plywood, 5mm thk. x 4' x 8' 714.00 / pc/s
Coco Lumber 18.00 / bdft.
Coco Net 120.00 sq.m.
Coco Log 390.00 ln.m.
Vegitation 81.00 sq.m.
Tie Wire, G.I # 16 80.00 / kgs.
4" CWN 70.00 / kgs.
Boulders Extraction 50.00 / cu.m.
CHB 4" 20.00 / pcs
REINFORCING STEEL 44.10 / kgs.
TIE WIRE # 16 76.00 / kgs.
HACKSAW BLADE 70.00 / pcs
WASHED GRAVEL 800.00 / cu.m.
WASHED GRAVEL Y-Y 700.00 / cu.m.
WASHED SAND 700.00 / cu.m.
AGGREGATE BASE COARSE 500.00 / cu.m.
AGGREGATE SUB-BASE COARSE 500.00 / cu.m.
BOULDERS 1,000.00 / cu.m.
GOODMIX 600.00 / cu.m.
Submitted by:
Contract ID : 20LB0183
Contract Name : Construction of Drainage Along Davao – Cotabato Old Rd. K1520+745 –
K1520+750, Davao City
Location of the Contract : Davao City
Submitted by:
Contract ID : 21LB0216
Contract Name : Construction of Road in Barangay 8-A (Poblacion District), Davao City, Davao del Sur
Location of the Contract : Davao City
ABC :
YEAR
PARTICULAR TOTAL
FIRST QUARTER SECOND QUARTER THIRD QUARTER FOURTH QUARTER
Percentage Accomplishment 100.00% 9.83% 21.36% 9.83% 58.98%
AMOUNT 1,445,112.45 3,140,646.78 1,445,112.45 8,670,255.99
Cumulative Percentage Accomplishment 100.00% 9.83% 31.19% 41.02% 100.00%
AMOUNT 1,445,112.45 4,585,759.23 6,030,871.67 14,701,127.67
Submitted by: