Professional Documents
Culture Documents
EDOC-Testing Connection Leads For Transmission Line Arresters
EDOC-Testing Connection Leads For Transmission Line Arresters
EDOC-Testing Connection Leads For Transmission Line Arresters
Line Arresters
Arresters
February 8, 2020 8 min read
▪
Transmission line surge arresters (TLSAs) are applied on
overhead lines to improve outage performance and, particularly
at EHV, to limit magnitude of switching overvoltages. There are
two basic types – externally gapped (EGLAs) and non-gapped line
arresters (NGLAs). NGLAs are comprised of a column of metal
oxide varistors (MOVs) packaged in a fiberglass-reinforced
polymeric housing and are installed between phase conductors
and towers using connection leads. One end is typically fitted with
a disconnector to break the electrical connection in the event of
arrester failure. Installation configurations fall into three broad
groups: Mounted onto tower structure or hung from a cross-arm;
hung from conductor; or installed in parallel to line insulator as
part of the insulator assembly
Service experience has shown that, from the electrical point of
view, application of NGLAs typically improves line performance
with relatively few failures. Nonetheless, utilities have reported
that installations are sometimes compromised by mechanical
issues such as failure of connection leads or disconnectors. While
arrester standards do not include mechanical tests or
requirements for the connections, IEC 60099-5 suggests an
arrester life expectancy of at least 25 years. Given these
considerations, EPRI began a research project to better
understand causes of lead breakages so that necessary functional
improvements could be included in future user specifications. This
edited contribution to INMR by Martin Hughes of EPRI reviews
findings and offers insight into requirements for mechanical
testing, with focus on NGLAs since these are the type most
commonly applied in the United States.
Background
NGLA installations should be designed to minimize mechanical stress on
connection lead and disconnector since these components (and the disconnector in
particular) are generally not able to tolerate high mechanical loads. Other
important mechanical design considerations are:
• Connections should allow free movement of phase conductors, which can take
the form of conductor swing, Aeolian vibrations, galloping and sub-span
oscillations;
• Connections and associated hardware should withstand all mechanical forces to
which they are subjected;
Lead wires are used to connect an arrester unit to the phase conductor or to a
grounded part of the line support structure and there are two types of lead
configurations:
• Lead wire pulling out of the lug, a common problem and possibly the result of
mechanical overload or poor crimping of the lead connection;
• Edge of the crimped lug ‘sawing’ into the lead conductor thereby severing strands
and mechanically weakening the lead, such as when a mechanically loaded lead is
not aligned with the lug;
Chain connections where the electrical lead connection woven through the chain
wears down due to continuous lead movement.
Fig. 2: Typical NGLA lead failures.
CLICK TO ENLARGE
Load Characterization Testing
Current standards do not provide guidance specific to applying line arresters nor do
they prescribe mechanical tests for leads. Therefore, with the goal of developing
suitable laboratory test methods for leads and disconnectors, EPRI constructed a
simulated field test to quantify typical in-service mechanical lead loads under
different environmental conditions. The simulated field test measures mechanical
loading of the arrester and leads under actual service conditions while also
monitoring and recording any mechanical degradation on the components. This
information then provides a good basis for subsequent laboratory testing.
Advertisement
Instrumenting an energized installation was not cost justified in this case since only
the mechanical forces on the lead are of interest. Three typical arrester
configurations were therefore installed on a de-energized test line commissioned at
EPRI’s High Voltage Test Facility in Lenox, MA in Jan. 2015 (see Fig. 3).
Mechanical loads in the leads are monitored continuously but only maximum load
over a 2-minute interval is logged. Special precautions were taken to ensure load
cells and their added weight did not influence the loads in the leads. A dedicated
weather station was used to continuously reconcile impact of the outdoor
environment during testing and backed up by another logging weather station
attached to a mast only a short distance away. The most important parameter, wind
speed, is monitored with a 2-D ultrasonic type anemometer, which has no moving
parts to wear out or to introduce errors from drag. Ultrasonic anemometers have
the further advantage of more accurately measuring lower wind speeds.
Fig. 3: EPRI’s
arrester test installation in Lenox.
CLICK TO ENLARGE
Load measurements taken over an 18-month period for each of the three arresters
were then compared and data from the position experiencing the highest loads was
reduced to a simplified test cycle. An acceleration factor was achieved by applying
loads at much shorter time intervals (16 hours of testing equivalent to one year of
service life). The original intent was to develop a test that enabled accelerated
ageing of just the arrester leads. However this was later extended to mechanical
testing of the arrester body as well.
Conclusions
Non-gapped line arresters are increasingly being applied to improve lightning
performance of transmission lines. While these arresters perform well electrically,
their installation is often compromised by failures of the connection leads or the
disconnector. Service experience shows that many of these failures are due to
installation related issues. For example, connections between arrester and
energized conductor or grounded structure are often subjected to static and
dynamic loads which could lead to fatigue or overloading, resulting in either
broken connections or damage to the arrester. The fact that present test standards
do not address requirements for arrester connecting leads prompted EPRI to
develop a mechanical measurement and testing approach to better understand these
issues. However, method of testing must be carefully selected so that failure modes
most closely replicate those actually experienced in service. Even minor changes to
test rig configuration can result in significant variations in types of failure
observed.
References
1. Cigré WG 33.11 Task Force 03: “Application of metal oxide arrester
to overhead lines”, Electra No. 186, October 1999, pp 83-112.
2. Williamson J., “Lightning Protection and Surge Arrester Application
on NB Power Transmission Lines”, IEEE PES Transmission and
Distribution Conference and Exposition, 2008.
3. Overhead Transmission Line Lightning and Grounding Reference
Book 2011. EPRI, Palo Alto, CA: 2011. 1023429.
4. Application of Transmission Line Surge Arresters. EPRI, Palo Alto,
CA: 2010. 1019954.
5. Guide for the Application of Transmission Line Surge
Arresters. EPRI, Palo Alto, CA: 2009. 1017709.