Professional Documents
Culture Documents
Mombasa Final Report
Mombasa Final Report
1
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
All rights are reserved. This document or any part thereof may not be copied or repro-
duced without permission in writing from Pöyry Switzerland Ltd.
2
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Contact
Christian Bergerhoff
Hardturmstrasse 161, P.O. Box
CH-8037 Zurich/Switzerland
Tel. +41 44 355 55 55
Fax +41 44 355 55 56
http://www.poyry.ch
Christian Bergerhoff
Project Manager
1
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
EXECUTIVE SUMMARY
2
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The investment costs have been estimated on the basis of a preliminary bill of quanti-
ties. The operations costs include the costs of staff (stations, depots and workshops), in-
frastructure (depreciation, maintenance and replacement) and train operations (person-
nel, fuels and lubricants, depreciation, maintenance and replacement of rolling stock).
A Road Map for the project implementation has been developed based on 12 sections
within the 6 corridors described above. These have been prioritised according to the cri-
teria investment costs, operation costs and expected traffic volume. A further criterion is
the development of a coherent network in each stage of system implementation; sections
will only be realised, if they have connectivity to the network (no stand-alone sections).
The economic viability assessment considers the macro-economic environment, costs
and externalities to assess the economic surplus generated by the project. The first result
obtained is a negative NPV (with an interest of 5.5%) and an EIRR of 4.3% for the to-
tal project. The sensitivity analysis assuming increased infrastructure costs results in a
more negative NPV and reduced EIRR of 3.3%, whereas an increase in benefits im-
proves the results and renders a positive NPV and an EIRR of 7.1%.
To improve the economic viability of the project a new calculation was made for a re-
duced project which excludes the least viable corridors 5 and 6. The reduced project is
based on the same Road Map but includes only 10 sections within 4 corridors, with a to-
tal length of 365 km. The corresponding calculation gives a positive NPV and an EIRR
of 6.3%. The sensitivity analysis assuming increased infrastructure costs results in a
negative NPV and reduced EIRR of 5.1%, whereas an increase in benefits improves the
results and renders an increased NPV and an EIRR of 9.1%.
The financial viability assessment considers the micro-economic context of the project
itself, focusing on identification of the financial gap or surplus from construction and
operations and the financing resources required to execute it. From the financial point of
view the project NPV (excluding subsidies) is negative, and consequently the FIRR
cannot be computed. It concludes that the project, as such, is not considered financially
viable and able to sustain its own financing. Operations will require an operations sub-
sidy to break even.
The study includes a Risk Analysis which identifies and describes the various types of
risks which are critical for the future realisation of the project, and proposes mitigation
measures for all the identified risks at the various project phases.
The consultant recommends to develop the Mombasa commuter railway project with
the reduced scope including the corridors 1 to 4. The corridor 6 Malindi – Lamu should
be examined by a new study with the focus freight transport in conjunction with the
Lamu port project. The corridor 5 Mazeras – Takaungu shall be included to this freight
traffic study representing a bypass to Mombasa for freight trains from Lamu to Nairobi.
1
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Contents
EXECUTIVE SUMMARY.............................................................................................................. 1
2
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
3
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
5
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Table of Tables
7
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Table 8.5: Yearly global investment costs for the reduced project .............................................. 142
Table 9.1: Parameters for the Economic Appraisal .................................................................... 147
Table 9.2: Values for travel times ............................................................................................. 150
Table 9.3: Time savings ............................................................................................................ 150
Table 9.4: Vehicle operating costs for road traffic ..................................................................... 151
Table 9.5: Saved VOC Costs ..................................................................................................... 151
Table 9.6: Infras-IWW unit costs – Euro for base year 2000 ...................................................... 152
Table 9.7: Transfer coefficients based on GDP/capita ................................................................ 152
Table 9.8: Yearly savings from externalities .............................................................................. 153
Table 9.9: Road Accidents in Kenya per year (rough figure)...................................................... 153
Table 9.10: Values for saved accidents ........................................................................................ 153
Table 9.11: Accident reduction savings ....................................................................................... 154
Table 9.12: Economic analysis – details ...................................................................................... 156
Table 9.13: Overview of economic analysis result ....................................................................... 157
Table 9.14: Share of effects in total present value ........................................................................ 157
Table 9.16: Economic analysis results with increased investment costs ....................................... 158
Table 9.17: Economic analysis results with increased benefit values ........................................... 158
Table 9.17: Economic analysis results with increased benefit values ........................................... 158
Table 9.18: Share of effects of the Reduced Projekt in total present value.................................... 159
Table 9.19: Economic analysis of the reduced projekt – details (all values in mn KES) ............... 160
Table 10.1: Monthly Staff Costs and crew mixes- Stations .......................................................... 169
Table 10.2: Monthly Staff Costs and crew mixes- Maintenance Facilities .................................... 170
Table 10.3: Monthly Staff Costs and crew mixes- Rolling Stock(Train operations) ..................... 170
Table 10.4: Financing instruments for Mombasa Commuter Rail - review of opportunities ......... 173
Table 10.5: Financing Gap and ODA Loan disbursement for construction financing ................... 177
Table 10.6: Base Case Financial Feasibility Results .................................................................... 179
Table 10.7: Reduced Investment Financial Feasibility Results ..................................................... 180
Table 10.8: Sensitivtiy Analysis Results ...................................................................................... 181
Table 10.9: Cash Flow prognoses – D&B Phase .......................................................................... 183
Table 10.10: Cash Flow prognoses – Operating Phase until 2045 .................................................. 183
Table 11.1: Large bridges of the Corridor 1: Mombasa – Likoni – Ramisi ................................... 184
Table 11.2: Large bridges of the Corridor 2: Mombasa – Kilifi – Malindi.................................... 184
Table 11.1: Large bridges of the Corridor 4: Likoni Ferry – Junda – Bamburi ............................. 184
Table 13.1: Content of Corridor Study and Population Mapbook ................................................. 194
Table 13.2: Content of Longitudinal Sections Mapbook .............................................................. 195
Table 13.3: Content of Environment and Socio-economic Mapbook............................................ 196
Table of Figures
8
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Figure 3.1: Work Steps of Market Study and Traffic Demand Forecast ......................................... 25
Figure 3.2: Increase of Traffic Demand in Chatchment Area (Demand Forecast) .......................... 27
Figure 3.3: Increased Area with Travel Time To Centre < 45 min. due to Railway (exemplary) .... 27
Figure 3.4: Map of Mombasa Island ............................................................................................. 28
Figure 3.5: Map of proposed lines in the Mombasa Region ........................................................... 29
Figure 3.6: Population Distribution in and around Mombasa......................................................... 30
Figure 3.7: Composition of travel mode for Nairobi...................................................................... 31
Figure 3.8: Travel modes in Nairobi ............................................................................................. 32
Figure 3.9: Modal Share Mombasa Region 2013 .......................................................................... 32
Figure 3.10: Average trip distance and travel speed per mode ......................................................... 33
Figure 3.11: Transportation Network around Mombasa and the Surrounding Towns ...................... 34
Figure 3.12: Typical pedestrian condition in rural area.................................................................... 35
Figure 3.13: Rural road with pedestrian and bycicle traffic on side strip ......................................... 35
Figure 3.14: Matatu ........................................................................................................................ 36
Figure 3.15: Tuk_Tuk ..................................................................................................................... 37
Figure 3.16: Motorcycle taxi........................................................................................................... 37
Figure 3.17: Bicycle Taxi ............................................................................................................... 38
Figure 3.18: Likoni Ferry................................................................................................................ 39
Figure 3.19: LAPSSET Transport Corridor Development Plan ....................................................... 43
Figure 3.20: Mombasa Southern Bypass and Kipevu Link Road Development Plan ....................... 44
Figure 3.21: Kenya Population Projection....................................................................................... 45
Figure 3.22: Population Forecast: Population within 3km areas around stations .............................. 46
Figure 3.23: Modal split changes 2009 - 2045................................................................................. 47
Figure 3.24: Daily trips per transport mode 2020 – 2050................................................................. 47
Figure 3.25: Trip shifts to railway system (2045) ............................................................................ 49
Figure 3.26: Ramp-up of trips acording to built railway infrastructure ............................................ 49
Figure 3.27: Total passengers per year and line. Traffic volumes in catchment area of the railway
system in 2013, 2020 and 2045 ................................................................................... 50
Figure 3.28: Passengers per day and route section in 2045 .............................................................. 51
Figure 4.1: Mombasa Port Projects ............................................................................................... 57
Figure 4.2: Lamu Port Project ....................................................................................................... 58
Figure 4.3: Mombasa Main Station ............................................................................................... 60
Figure 4.4: The Dongo Kundu Table Mountain............................................................................. 60
Figure 4.5: The Ramisi Sugar Plant Area ...................................................................................... 61
Figure 4.6: Topology of Corridor 1, Section Mombasa Main Station– MOI International Airport . 63
Figure 4.7: Topology of Corridor 1, Section Tsunza - Tiwi ........................................................... 63
Figure 4.8: Topology of Corridor 1, Section Ukunda – Ramisi...................................................... 64
Figure 4.9: Mombasa Central Business District ............................................................................ 65
Figure 4.10: Mombasa Harbour with relicts of the old pontoon bridge ............................................ 66
Figure 4.11: The Kilifi Creek .......................................................................................................... 66
Figure 4.12: Malindi Main Road ..................................................................................................... 67
Figure 4.13: Mida Creek near Watamu ........................................................................................... 69
Figure 4.14: Topology of Corridor 2, Section Mombasa – Shimo la Tewa ...................................... 70
Figure 4.15: Topology of Corridor 2, Section Mtwapa – Kilifi ........................................................ 70
Figure 4.16: Topology of Corridor 2, Section Mtondia – Malindi ................................................... 70
Figure 4.17: Miritini Railway Station ............................................................................................. 71
9
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
10
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
11
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
vii. Financial and economic viability assessment: determine the financial and eco-
nomic viability of proposed lines and appropriate investment in equipment.
Identify financially viable (bankable) routes or systems. Where economic viabil-
ity is the criteria determine funding gap required to attract Public Private Part-
nership (PPP) and lender funding. In making evaluation due consideration to be
given to time based development plan (project phasing) that would assure finan-
cial and/or economic viability.
viii. Develop a risk matrix for the project in view of various project implementation
and funding option
ix. Examine various project funding options including Government budget provi-
sions, county budget support during operation and PPP options.
x. Upon consultations with the Client, stakeholders and investor market sensing,
make recommendations on preferred option and priority routes.
xi. Prepare project implementation schedule and funding requirement covering de-
tailed design and development for the recommended project implementation op-
tion.
xii. Make any other relevant recommendation deemed necessary.
The entire study will be undertaken over a period of 6 (six) calendar months after com-
mencement of the study.
12
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
iii. Possible risks and challenges anticipated to arise during the period of services;
iv. An overview of existing projects documentation and information;
v. Results of existing field investigation;
vi. Presentation of the quality assurance mechanisms for implementation of the
work;
vii. Quality Plan that the Consultant shall adhere to during Study implementation.
Quality Plan shall include sets of success indicators that shall be used for moni-
toring and quality assessment;
viii. The name list of authorities, with whom contacts were made during preparation
of project and the meetings protocols;
The Interim Report shall cover issues outlined in section 5.4 (i) to (iv) of TOR and
should analyze and reflect the working in a way that gives Client an adequate picture of
the main outcomes and the reasons thereof.
The Draft Final Report shall cover all issues outlined the TOR. The Draft final shall in-
clude all the findings, analysis, conclusions and recommendations of the Consultant. It
shall be submitted to the Client and subsequently discussed. The Consultant, upon con-
sideration of the Clients views shall review and prepare the Final Report which shall
take into account all the Clients input and include final conclusions and recommenda-
tions.
13
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
freight traffic too but freight traffic evaluation, conception of installations and economic
assessment for freight traffic are not subject of this study.
The study will be based on a tariff system accordant to the system which is foressen for
the Nairobi Commuter Railway. The relevant information must be made available to the
consultant.
14
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
2 PROJECT BACKGROUND
1
East African Community
2
COMESA website
Figure 2.3: Kenya - Administration
Pöyry Switzerland Ltd.
190 591.10
15
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Climate
Kenya has a tropical climate. It is hot and humid at the coast, temperate inland and very
dry in the north and northeast parts of the country. There is however a lot of rain be-
tween March and May, and moderate rain in October and November. The temperature
remains high throughout these months. 3
Transport administration
The central governing authority is the Government of Kenya (GoK). There are several
relevant and important government Ministries. Examples are the Ministry of Transport,
the Kenya Ministry of Environment and Natural Resources, the Kenya Roads Board,
and the Kenya Railways Corporation (KRC), who is the Client for the Kenya railway
project.
The main mode types of transport in Kenya are: road, rail, air, maritime and pipeline.
The transport sector is seen by the government as “crucial in the promotion of socio-
economic activities and development. An effective, efficient and reliable transport sys-
tem is a mainspring for rapid and sustained development in terms of national, regional
and international integration, trade facilitation, poverty reduction and improvement of
welfare of the citizenry”5.
3
Wiki Kenya
4
Vision 2030, Second Annual Progress Report (2009-2010)
5
MoT website
16
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
17
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
largest city and the gateway to the country from the Indian Ocean. It has a population of
about 940,000 people. The populations of the adjoining counties of Kilifi and Kwale are
approximately 1,359,100 and 649,950 respectively.
Mombasa lies on the eastern shores of the Indian Ocean and has a major international
sea port and an international airport. The city also serves as the centre for coastal tour-
ism industry and provides pivotal linkage to the Tsavo National Park located to the east
of the city. The Central Business District for the city is located on Mombasa Island, but
the city extends to the mainland. Mombasa Island is connected to the mainland to the
north by Nyali bridge, to the south by Likoni ferry and to the west by Makupa cause-
way. Mombasa port is the largest port in East Africa and serves Kenya, Uganda, Rwan-
da, Burundi, the eastern part of the Democratic Republic of Congo (DRC), Northern
Tanzania and South Sudan.
Mombasa, being the a major tourist destination, an administrative and commercial cen-
tre and with a combined population of 3 million people in the city and adjoining coun-
ties, is in serious need of an efficient and reliable transport system. Indeed there is need
for a sustainable transport solution now and in the near future in order to address the so-
cio-economic needs of the cities and surrounding populations as envisaged in the mil-
lennium development goals.
Currently, the City is linked by two international road networks: International Trunk
Road A109 Mombasa to Kampala through Nairobi running to the north east, Interna-
tional Trunk Road A14 Mombasa-Lungalunga road running south-west to Likoni,
Kwale and to the Tanzania border with linkage to Dar-es-Salaam and National Road B8
running due north east to Malindi and Garissa. The city is also connected by an interna-
tional railway main line that runs north-east to the capital city of Nairobi and to Kampa-
la, Uganda.
18
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Moi International Airport (MIA) serves the city of Mombasa. It is located in the town-
ship of Port Reitz. The airport handles growing air traffic with a substantial number of
airlines flying directly from and to Europe, and offering connections to over twenty cit-
ies in the region.
Within the city, Mombasa road, which is part of the International Trunk road A109 and
Digo Roads and Nyerere Avenue transverses through the center of the city in east - west
direction and also serves the Moi International airport; Moi Avenue which connects the
Central Business District to the Kilindini Harbour, Lumumba Road which links road
A109 to Mombasa Central Railway Station and Ziwani- Nyali Road which connects to
the Mombasa-Malindi Road B8.
19
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
2.4.1 Mombasa
An Island lying on the Indian Ocean, Mombasa City is Kenya’s second-largest city, ac-
cording to the 2009 Census, has a population of 939,370. Mombasa is an international
seaport that serves Kenya’s neighbouring land locked countries. The county is situated
in the South Eastern part of Coast Province. It borders Kilifi County to the North,
Kwale County to the South West and the Indian Ocean to the East. The Tudor Creek
and Kilindini Habour separate Mombasa Island from the mainland. The Nyali Bridge
connects the island is connected to the mainland to the North whereas the Likoni Ferry
connects it to the South and the Makupa Causeway connects the island to the West. The
majestic and imposing baobab trees dot the coastal region.
The original Arabic name of the city is Manbasa. Mombasa’s Swahili name, Kisiwa
Cha Mvita (or Mvita for short), which means "Island of War" name is a depiction of the
numerous wars fought over the centuries for ownership of the island. Mombasa is an
ancient city whose rapid expansion in the last two decades has resulted in the prolifera-
tion of informal settlements and general poor urban planning.
Mombasa is a regional cultural and economic hub. The city is the tourism capital of the
coastal region and a major cog in Kenya’s tourism sector. The main industries in Mom-
basa County include the Bamburi Cement, Mombasa Cement factory, Kenya Breweries
Limited and The Tourism Industry and supporting services industry is very well devel-
oped in Mombasa County. The tourist attractions include the world famous white sandy
beaches, Fort Jesus Museum, Bamburi Nature Trail, Mombasa Marine Park, Water
Pöyry Switzerland Ltd.
190 591.10
20
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Sports, Haller Park, Mamba Village, Nguuni Nature Sanctuary, Mombasa Old Town,
Gedi Ruins amongst numerous others.
Mombasa has a well-developed transport connection to the neighbouring counties and
the country in general. The Moi International Airport in Port Rietz, the second busiest
after Jomo Kenyatta International Airport, links Mombasa to the international world.
The Kilindini Harbour connects Mombasa to the rest of the world by sea. The city is al-
so linked to the rest of the country by the Uganda Railway that ferries both goods and
passengers known for its unpredictability and unreliability. The town is also linked with
Voi town and the rest of the country by a rail to Uganda, connecting the landlocked
country with the port. The A109/A104/A1, major national highways, connect Mombasa
to Eldoret and Busia through the capital city, Nairobi. Mombasa is also linked to Lamu,
Kwale, Kilifi and Voi by road.
Mombasa County is home to the Mombasa Polytechnic University College. Additional-
ly, all the main national universities have their constituent colleges in Mombasa.
2.4.2 Kwale
Kwale with a population of 649,931 is located to the south of Kenya. It borders Tanza-
nia to the South West, Taita Taveta to the West and North West, Kilifi to the North and
North East; Mombasa to the East; and Indian Ocean to the East and South East. Kwale
town is the capital of the county. Kwale’s beauty is embedded in its four topographical
features; the Coastal Plain, the Foot Plateau, the Coastal Uplands and the Nyika Plateau.
Tourism plays an important role in the economy of Kwale. Kwale County is home to the
picturesque Diani Beach, the Colobus Trust and Kaya Kinondo Sacred Forest; key tour-
ist attractions. Tourist attractions include the Tsavo East and Tsavo West National
Parks, Shimba Hills National Reserve, Kisite Mpunguti National Park and Reserve,
Shedrick Falls, Maji Moto Springs and Mwaluganje Elephant Sanctuary amongst others.
Deposits of rare earth minerals have been found in Kwale leading to a recent develop-
ment of the mining sector in the county with Titanium mining having commenced. Ag-
riculture is important to the county with vast sugarcane, coconut vegetables and fruit
farms cover the landscape of the county
Kwale County is accessible by road network through the neighbouring counties from
Kenya’s capital city, Nairobi. The nearest airport is the Moi International Airport in
Mombasa County and the Diani Airstrip in Diani.
Kwale County does not have a University. However, the Mombasa Polytechnic Univer-
sity College maintains a campus in Ukunda.
2.4.3 Kilifi
Kilifi County with a population of 1,109,735 is 60 km from Mombasa City and one of
the six counties within Kenya’s Coastal Region. Bordering Kilifi County to the South is
Mombasa County; to the North, Tana River and Lamu; to the West Taita Taveta whilst
to the East is the Indian Ocean. Kilifi extends to Malindi, Takaungu and Mazeras. It has
four major topographical features; the Foot Plateau, the Coastal Range and the Nyika
21
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Plateau. Kilifi, set midway between Mombasa and Malindi, is an ancient coastal Swahili
town steeped in history and local African Culture.
The county is famous for the ancient Mnarani ruins dating back to 14th century; its pris-
tine white sandy beaches, the startlingly beautiful blue and emerald creek and a magnif-
icent coral reef are key drivers of its tourism industry. Malindi with a population of ap-
proximately 120,000 is the largest town in Kilifi County and a key tourist destination.
There are also several industrial developments in Kilifi County as well as agricultural
enterprises.
Kilifi County is accessible by road network through the neighbouring counties from
Kenya’s capital city, Nairobi. The Mombasa International Airport and the Malindi Air-
port serve Kilifi County.
Kilifi County is also home to Pwani University. There are also several constituent col-
leges of the various national universities.
22
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
planning has led to scarcity of parking space in the CBD in Mombasa. Because of the
inefficiency of urban transport due to poor infrastructure, transport costs are high for
both passengers and goods. The majority of low-income urban workers currently find
public transport costly and financially inaccessible and hence meet most of their
transport needs through walking and head loading. Some of them, however, risk their
lives by utilizing non-motorized and intermediate means of transport
(NMIMTs),especially bicycles, motorcycles and mikokoteni for which there is no ap-
propriate infrastructure. Given that about 50 per cent of the country’s total GDP is gen-
erated in the urban areas, the adverse consequences of the above scenario on worker’s
efficiency and productivity, fuel consumption, education, health and the environment
cannot be overemphasized.
Mombasa city is currently experiencing traffic congestion on all the major road arteries
linking it to adjoining towns and counties. With the growing population and freight ton-
nage handled at the port of Mombasa, both passenger and freight traffic is anticipated to
rise leading to more traffic congestion pressure on the roads. In order to address this im-
pending traffic snarl on the roads, there is need to develop a new safe and reliable
transport mode, which will increase passenger transport capacity and at the same time
facilitate intermodal interchange at important nodal points.
The Kenya Vision 2030 gives the perspective for development of efficient mobility of
people in the cities of Nairobi, Mombasa and Kisumu and their environs.
The challenges of climate change call for sustainable transport solutions and the rail
mode of transport is friendly to the environment, damaging less per person moved in
comparison with other modes of transport.
In consideration of the above, KR which organization is charged with rail development
as a Government Agent in the Vision 2030, has decided to facilitate stakeholders con-
sultations. In addition, KR plans to undertake studies necessary for development of a
modern metropolitan Commuter rail network within Mombasa city and with linkages
with principal urban centres in the surrounding counties in the coast region.
23
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
24
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
2.8 Authorities
The following authorities, among others, were contacted during the preparation of the
project:-
Table 2.1: Authorities
Organisation Web
Ministry of Transport www.transport.go.ke
Ministry of Environment and Mineral Resources www.environment.go.ke/
Kenya railways corporation www.krc.co.ke/home.asp
Kenya roads board www.krb.go.ke/
Kenya Ports Authority www.kpa.co.ke
Kenya Airports Authority www.kaa.co.ke
Mombasa Municipality Authority www.mombasamunicipal.org
Kenya Pipeline Corporation www.kpc.co.ke
Kenya Roads Board www.krb.go.ke
Kenya National Highways Authority www.kenha.go.ke
Kenya Urban Roads Authority www.kura.go.ke
Kenya Rural Roads Authority www.kerra.go.ke
Water Resources Management Authority www.wrma.or.ke
Kenya Wildlife Service www.kws.org
National Environmental Authority NEMA www.nema.go.ke/
Communications Commission of Kenya CCK www.cck.go.ke
25
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
3.1 Introduction
In this chapter, a market demand analysis will be conducted and the future demand over
a period of 30 years will be forecasted based on qualitative and quantitative macro-
economic data of the existing situation in the Mombasa area. Thereby, different factors
that influence passenger transport demand will be pointed out and quantified to facilitate
future demand analyses.
Figure 3.1: Work Steps of Market Study and Traffic Demand Forecast
26
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
27
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
3.2).Fig. 3.3 exemplarily compares the areas from which the city centre can be reached
in less than 45 minutes with and without railway.
Figure 3.3: Increased Area with Travel Time To Centre < 45 min. due to Railway
(exemplary)
The detailed tasks of Work Step 3 are displayed in the following. The results from the
demand forecast will also be the basis for the economic analysis of the project as well as
for the design of the future operating system.
Detailed Tasks of Work Step 3:
a. Evaluation of trips to be shifted from existing modes to the railway system
b. Distribution of estimated total trips among the assessed lines and route sections
c. Evaluation of the assessed lines/corridors regarding the passenger demand
d. Calculation of passenger-km (Paxkm/year)
28
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
3.3.1 Geography
The Mombasa region is characterized by the major city situated on the island with East
Africa most important port and sub-centres situated along the north and south coast of
Mombasa.
Major industrial and logistical developments of Mombasa are situated at the north west-
ern area of the island where also the connection to Nairobi is established.
The whole region is influenced by the bay situation and its limited possibilities connect-
ing the districts and sub centres.
29
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
30
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
31
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Due to a lower economic development and the structure of housing / working routes,
and the limited number of trips for spare time and shopping, a slightly lower figure has
been assumed for the catchment area of Mombasa; and a lesser value for the rural areas..
Urban areas: 3 trips per day
Rural areas: 2 trips per day
Source: UITP, “Report on statistical indicators of public transport performance in Africa”JICA Study
2006
Figure 3.7: Composition of travel mode for Nairobi
32
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Source: Githui John Ngatia,The Structure of Users’ Satisfaction on Urban Public Transport Service in
Developing Country: the Case of Nairobi
Figure 3.8: Travel modes in Nairobi
Adopting the above shown distribution of transport modes to the Mombasa Region a
slightly different modal share has been assumed, and cross checked with observations of
the consultant and selective surveys.
Mat at u
30%
Walking
49%
pr ivat e car
10%
Pik iPiki
2%
Mot orbik e Bicycle
BodaBoda 2%
1%
2%
Walking Bicy cle BodaBoda Mot orbike Pik iPik i priv at e car Mat at u Bus School bus Rail way
33
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
70
Railway
60
average travel speed (km/h)
Bus (Long
50
Distance)
40
Private Car
30 Motorbike
PikiPiki
Matatu
20
School Bus
10 Bicycle
BodaBoda
Walking
0
0 10 20 30 40 50 60
average travel distance (km)
Figure 3.10: Average trip distance and travel speed per mode
34
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
35
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Figure 3.13: Rural road with pedestrian and bycicle traffic on side strip
36
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
3.3.4.4.1 Matatu
Most used public transport mode with a capacity of 14 passengers per vehicle and vari-
able timetables and price structures. They are generally used for short and long distance
trips also for transport of small goods. Figure 3.14 is a picture the typical Matatu vehi-
cle.
3.3.4.4.2 Tuk-Tuk
This is the public transport mode with a carrying capacity of 3 passengers. It serves as a
taxi mainly within urban areas where there are paved roads. It is used for short inner
37
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
city distance trips mostly in the Mombasa city. The figure below is a picture of a Tuk-
Tuk.
3.3.4.4.3 Motorcycle
Motorcycles are used either as private modes or as a public transport mode (motor-taxi).
They are used for short and medium distance trips in the city and rural areas. The figure
below is a picture of a typical motor cycle taxi, often known as Boda-Boda.
38
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
3.3.4.4.5 Railway
Passenger railway has got a low share of the overall modal split of public transport in
the Mombasa region.
Actually two overnight passenger trains from Nairobi via Voi are running every week.
This service covers more or less the tourism and long distance market for passenger
transport. Limited influence in the commuter market can be expected by serving the
Mazeras station.
Ticket prices are higher than parallel running bus services which also reduces the actual
demand on this line.
39
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Summarizing it can be said that air traffic has got a low influence in the public transport
within the Mombasa region but the airports serve as origins/destinations for passengers
due to touristic trip reasons.
40
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
41
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Road section Motorcy- Passenger Large Matatu/ Small bus Large bus Pick-
cles car passenger Minibus up/Van/L.
car, 4WD G.V
Mtwapa
Mombasa - Kilifi 24 26 13 28 1 1 7
Panga - Malindi 55 10 9 10 5 2 9
Mombasa - Likoni 21 21 14 27 1 1 15
Mombasa - Lamu 51 15 15 8 2 0 8
Mombasa -
Changamwe 27 34 5 21 3 1 9
Mombasa - Kwale 44 19 8 16 4 1 9
Ramisi - Likoni 38 13 8 26 2 5 7
Airport - Chang-
amwe 37 22 3 30 2 1 4
Kaloleni - Mazeras 60 9 2 21 3 1 5
Source: GA-Consultant, March 2013 Field Work
From Table 3.2, the motorcycles are the majority along the roads, followed by passen-
ger cars and matatus. This modal split points to general congestion on the roads as vehi-
cle occupancies for these three traffic categories are lower compared to the large buses,
or the proposed commuter rail.
3.3.5.2 Average travel time and cost of passenger trips to main centres
The current average travel time and cost from Mombasa to surrounding areas is given in
Table 3.3 below.
Table 3.3: The average travel time & cost from Mombasa to the surrounding sub centres
Origin Destination Estimated Estimated Estimated
place place trip distance travel time trip cost (KES)
(km) (min)
Mombasa Town Tudor 4 10 30
Mombasa Town Mishomoroni 6 15 60
Mombasa Town Kisauni 6 12 60
Mombasa Town Changamwe 7 20 60
Mombasa Town Mtwapa 15 30 100
Mombasa Town Kilifi 56 50 400
Mombasa Town Nyali 5 14 50
Mombasa Town Likoni 8 30 20
Mombasa Town Mtongwe 14 35 80
Mombasa Town Kwale 60 80 600
Mombasa Town Malindi 116 120 500
Mombasa Town Voi 180 150 400
42
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
3.3.6 Outlook
The future development of the study area will be mainly influenced by the population
and the economic development as well as planned traffic infrastructure projects and
changes in the travel behaviour.
43
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6
Source: http://www.cbcglobal.org/images/uploads/library/KIS2012_LAPSSET_Corridor_Silvester_Kasuku.pdf
44
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
ject is to facilitate trade and economic development in Kenya and neighbouring coun-
tries in East Africa. The project is scheduled to end in 2015.
Figure 3.20: Mombasa Southern Bypass and Kipevu Link Road Development Plan
7
Source: http://www.jica.go.jp/kenya/english/office/topics/topics130320_06.html
45
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
120
Population (million)
100
80
Urban Population
60
40
Rural Population
20
—
2010 2015 2020 2025 2030 2035 2040 2045 2050
The growth rates estimated by the UN have been applied to the number of inhabitants
living within the catchment areas of the projected station locations (radius 3km). To
achieve an estimate as realistic as possible, urban and rural growth rates have been con-
sidered separately. Thereby, urban growth rates have been applied to catchment areas
with a density of more than 20’000 inhabitants per 3km radius, whereas areas with a
lower density have been considered rural.
The results of the calculation show that the number of inhabitants within the catchment
areas of the projected stations is going to increase significantly and could almost triple
within the next 40 years (see figure below). As population growth rates for urban areas
are higher than for rural areas, the passenger potential of lines passing mainly trough
urbanised areas (i.e. Likoni Ferry - Panga Line) is expected to increase significantly
faster than for lines in rural environments (i.e. Mazeras - Kaloleni - Takaunga Line).
46
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
3.000
2.500
2.000
Corridor 1: Mombasa - Mtwapa - Kilifi - Malindi
Figure 3.22: Population Forecast: Population within 3km areas around stations
47
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6,00%
5,00%
5,00%
4,00%
3,00%
2,00%
2,00%
1,00%
1,00%
0,00% 0,00% 0,00%
0,00%
Walking Bicycle BodaBoda Motorbike PikiPiki private car Matatu Bus School bus Railway
-1,00% -0,50% -0,50%
-2,00%
-3,00%
-3,00%
-4,00%
-4,00%
-5,00%
16'000'000
14'000'000
12'000'000
10'000'000
8'000'000
6'000'000
4'000'000
2'000'000
48
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Table 3.4 shows the development of yearly trips and travelled passenger kilometre for
the catchment area in the Mombasa Region.
Table 3.4: Traffic volumes in catchment area 2013, 2020 and 2045 without railway system
2013 2020 2045
N° of trips per year (Mn) 3.8 5.7 13.8
Mn Passenger km per year 39.2 58.3 141.9
49
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
8,00%
7,00%
7,00%
6,00%
5,00%
4,00%
3,00%
2,00%
1,00%
0,00%
0,00%
Walking Bicycle BodaBoda Motorbike PikiPiki private car Matatu Bus School bus Railw ay
-1,00% -0,50% -0,50% -0,50% -0,50%
-1,00% -1,00% -1,00%
-2,00%
-2,00%
-3,00%
The main source of shifted traffic will be the Matatu system due to higher safety, shorter
travel time and the assumption that this system will have significant problems to serve
the traffic demand of the future population of the Mombasa area.
But also the other modes for short and long distance trips will lose their proportion.
The ramp-up of the future railway system users is shown in the next figure. According
to the total railway km built, the number of passengers is increasing. But also after final-
ising the whole network it will take some years until the people will take advantage of
the network.
Estimated Trips per Day and km Built
(Railway only)
1.000.000 700 km
900.000
600 km
800.000
700.000 500 km
600.000 400 km
500.000
400.000 300 km
300.000 200 km
200.000
100 km
100.000
0 0 km
2020 2025 2030 2035 2040 2045
50
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The calculated future passenger numbers for the railway system reflect those people
starting their trip at a certain station and return on the same day to that station. Destina-
tions are not known in detail at this stage of the project and it was assumed that 90% of
all trips will be made to the city centre area and 10% within a radius of 2 stations to the
origin station. The average trip distance with the railway system was assumed by 20 km
once the system is fully in operation.
150
Mombasa - Mazeras - Voi Line
100
Mombasa -Mtwapa - Kilifi -
50 Malindi Line
Mombasa - Ramisi Line
0
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
2049
Figure 3.27: Total passengers per year and line. Traffic volumes in catchment area of the
railway system in 2013, 2020 and 2045
51
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Status as of June
2013. Later chang- Mazeras - Kaloleni - Takaunga Corridor
es to the number,
location, or name
of stations are pos-
sible. Though, they
are not expected Mombasa - Ramisi Corridor
have significant
impact on the de-
mand potential de-
termined.
52
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The following table displays the load per route section in daily passengers at cross sec-
tion between the stations for different years. (numbers at stations represent the number
of cross section between stations). D indicate stations that serve two lines.
Table 3.5: Passengers per day, detailed route section in 2020/30/45
2020 2030 2045
Corridors Stations Passengers per day at cross sections
53
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
54
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
sons like market visits. A 10% proportion of the daily ridership is a common number in
other regions and goes conform with the traffic counting which were made in the Mom-
basa region.
Maximum passenger numbers were found in the Mombasa – Mtwapa – Kilifi - Malindi
Corridor cross section with about 8 thousand passengers travelling in one hour towards
the city centre. Assuming a train configuration can cover 1.000 passengers, 7 services
(every 8.5 minutes) per peak hour are required to cover the demand. This is the maxi-
mum passenger demand for the year 2045 with the above described input data.
Table 3.6: Estimation of required train services
Daily Railway
required
Trips 2045 10% Peak Hour
Corridor Population 2045 services
max. Cross to Centre
per hour
Section
Mombasa - Ramisi Line 1’969’024 113’243 5’662 6
Mombasa -Mtwapa - Kilifi - Malin-
2’249’812 145’018 7’250 7
di Line
Mombasa - Mazeras - Voi Line 913’693 68’500 3’425 3
Likoni Ferry - Panga Line 1’120’588 72’291 3’614 4
Mazeras - Kaloleni - Takaunga
141’444 5’792 289 1
Line
Malindi - Lamu Line 214’327 1’143 57 1
Total 6’608’889 405’989 20’299 23
Due to different demand levels on the corridors it has to be observed very detailed at
which cross section a decrease of the passenger demand is given to plan an optimal train
operation concept with short running trains or overlapping lines makes sense. Detailed
descriptions of the passenger demand for each corridor are given in Figure 3.28.
To calibrate those figures it is highly recommended to build up in further planning
phases a proper traffic model which includes the detailed destination specification of the
passengers which can be made by passenger interviews. In the model on hand the desti-
nations are determined by using the above described method that 90% are travelling to
the city centre area and 10% within an area of 2 stations from the origin station.
55
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.1 Introduction
This chapter proposes alignment standards for the commuter railway system, considers
interdependencies to other projects in development and defines the corridors of the
study.
The initially identified corridors listed in Section 1.4 have now been adjusted to reflect
the findings of the field trip and the advancement of the study, resulting in the following
lines:-
Corridor 1: Mombasa – Airport – Likoni - Ramisi Corridor
Corridor 2: Mombasa – Mtwapa – Kilifi – Malindi Corridor
Corridor 3: Mombasa – Mazeras – Voi Corridor
Corridor 4: Likoni Ferry – Bamburi Corridor (Mombasa Ring Corridor)
Corridor 5: Mazeras – Kaloleni – Takaungu Corridor
Corridor 6: Malindi – Lamu Corridor
In plain regions the design speed can also be increased to allow fast train operations
where applicable. The alignment standards will be discussed and agreed during the
workshop in the inception phase.
56
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
57
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
58
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
59
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
60
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
After passing the airport loop the proposed corridor turns to south following the Mom-
basa Southern Bypass with a direct link to the new Dongo Kundu Industrial Area in a
common corridor. Some adaptations of the alignment are necessary because of limita-
tion of the maximum slope for the railway.
After crossing the Dongo Kundu Area the corridor will have a slope to Likoni to tap in-
to this densely populated area by rail. From Likoni to the South the corridor runs along
the coast road up to the terminal station at the Sugar Factory of Ramisi.
61
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.4.1.2 Stations
The total corridor length is about 86 km with following proposed stations:-
Table 4.2: Stations of the Mombasa – Airport – Likoni - Ramisi Corridor
Station Mileage Interval Rail Level
Mombasa Main Station km 0.0 21 m asl
Makupa km 1.9 1.9 km 25 m asl
Chaani km 6.1 4.2 km 40 m asl
MOI International Airport km 9.0 2.9 km 27 m asl
Tsunza km 17.6 8.6 km 23 m asl
Dongo Kundu km 23.1 5.5 km 12 m asl
Likoni km 29.8 6.7 km 28 m asl
Magaoni km 34.4 4.6 km 28 m asl
Waa km 41.2 6.8 km 29 m asl
Tiwi km 47.3 6.1 km 26 m asl
Ukunda km 53.3 6.0 km 34 m asl
Mwabungu km 62.2 8.9 km 19 m asl
Gazi km 71.3 9.1 km 30 m asl
Msambweni km 78.4 7.1 km 20 m asl
Ramisi km 87.9 9.5 km 14 m asl
asl = above sea level
62
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.4.1.4 Junctions
The corridor has following junctions to other corridors and railway lines:-
Table 4.4: Junctions of the Mombasa – Airport – Likoni - Ramisi Corridor
Station Mileage Connection
Mombasa Main Station km 0.0 Mombasa – Mtwapa – Kilifi – Malindi Corri-
dor
Makupa km 1.9 Likoni Ferry – Bamburi Corridor
Mombasa – Mazeras – Voi Corridor
4.4.1.5 Alternatives
There are two alternatives to be considered within this corridor:-
63
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Advantage: The Miritini –Waa – Alternative eliminates the 2 crossings of the Mwache
and the Bombo Creek along the base corridor. Since these crossings are foreseen to
build the Mombasa Southern Bypass and the proposed base corridor is following the
road alignment, the advantage of elimination of these crossings is limited.
Disadvantage: The Miritini – Waa Alternative is about 8 km longer than the base corri-
dor. The alternative runs mostly along low populated areas. Neither the Dongo Kundu
Industrial Area nor the high density populated Likoni Town is connected to the corridor.
Figure 4.6: Topology of Corridor 1, Section Mombasa Main Station– MOI International Airport
64
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
65
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The corridor traverses to Kisauni crossing the Mombasa Harbour by a bridge in the axis
of the former pontoon bridge. The bridge with a length of about 700 m is planned to be
constructed as a wide span steel bridge with a rail level of 31 m above sea level to allow
crossing of ships.
66
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Figure 4.10: Mombasa Harbour with relicts of the old pontoon bridge
In the further course the corridor is proposed to be routed at ground level with overpass-
es of crossing roads. An elevated gradient can be considered in the town of Kisauni but
preferably by an embankment instead of a viaduct to limit costs.
The course of the corridor up to Mtwapa is determined by the Haller Park along the
coast road and the Bamburi Airfield that must be bypassed. Up to Kilifi there are three
creeks to be traversed with bridges of a length of 300 m to 550 m. The bridges can be
67
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The terminal station is proposed to be situated between Malindi City and Malindi Air-
port. The Mombasa – Mtwapa – Kilifi – Malindi Corridor may be extended by the Ma-
lindi – Lamu corridor.
4.4.2.2 Stations
The total corridor length is about 114 km with following proposed stations:-
Table 4.5: Stations of the Mombasa – Mtwapa – Kilifi – Malindi Corridor
Station Mileage Interval Rail Level
Mombasa Main Station km 0.0 21 m asl
Makadara km 1.6 1.6 km 28 m asl
Kongowea km 4.1 2.5 km 25 m asl
Freretown km 6.7 2.6 km 18 m asl
Bamburi km 8.9 2.2 km 22 m asl
Utange km 11.9 3.0 km 19 m asl
Shimo la Tewa km 14.2 2.3 km 22 m asl
Mtwapa km 16.4 2.2 km 25 m asl
68
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.4.2.4 Junctions
The corridor has following junctions to other corridors and railway lines:-
Table 4.7: Junctions of the Mombasa – Mtwapa – Kilifi – Malindi Corridor
Station Mileage Connection
Mombasa Main Station km 0.0 Mombasa – Airport – Likoni – Ramisi Corri-
dor
Mombasa – Mazeras – Voi Corridor
Bamburi km 8.9 Likoni Ferry – Bamburi Corridor
Mombasa – Voi Corridor
Takaungu km 47.6 Mazeras – Kaloleni – Takaungu Corridor
Malindi Km 113.7 Malindi – Lamu Corridor
4.4.2.5 Alternatives
69
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
bridge will be allocated at the Ras Makawaiwa near Mombasa Polytechnic University
College. The city viaduct has to be elongated along the Tom Mboya Avenue – Tom
Mboya Road – Rassini Road over about 1’800 m.
Advantage: It is only one bridge built over Mombasa Harbour to connect Mombasa Is-
land to the northern territories. The town centre of Kisauni is directly connected to the
railway line. One more Station (Politechnic University) on Mombasa Island allows a
higher service level in Mombasa CBD.
Disadvantage: The corridor 2 is guided in a loop around Mombasa CBD which reduces
attractiveness of the diameter route. The elongation of the city viaduct of about 1’800 m
balances cost reduction resulting from omission of the 2nd harbour bridge (Junda creek
bridge) along corridor 4, Likoni Ferry – Bamburi.
70
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
71
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.4.3.1 Description
The corridor starts at Mombasa Main Station following the Mombasa – Airport Corridor
up to the western side of the Makupa Causeway. A new branch is built to connect the
proposed long distance railway at Changamwe Marshalling Yard. With the branch to
Mombasa Main Station there is a gap in the Mileage between the commuter railway cor-
ridor and the long distance railway Mombasa – Nairobi of about 7.5 km. The following
mileage is based on the commuter railway corridor starting at Mombasa Main Station.
The passing stations along the long-distance railway Mombasa – Nairobi are mostly
corresponding to the stations which are planned for commuter railway services. Criteria
for the location of the passenger stations are:
the proximity to residential areas,
the proximity to other interesting points.
Such an interesting point is e.g. the Bachuma gate of the Tsavo National Park. Situated
close to the railway line the Bachuma Station can be reached with the commuter railway
from Mombasa within 1:40h and become an attractive target for tourists in the Momba-
sa area.
72
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The terminal station for the commuter railway service in Voi is proposed to be located
close to the main street C105 to allow a good connection to the city.
Further adjustment of the station location has to be done with the design of the railway
line. The following table shows the corresponding stations of the commuter railway cor-
ridor and the long-distance corridor:-
73
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Table 4.8: Comparison of stations along the Mombasa – Mazeras – Voi Corridor
Commuter Railway Station Mileage Long Dist. Railway Station Mileage
Mombasa Main Station km 0.0
Makupa km 1.9
Changamwe km 5.4
Mikindani km 9.0 Mombasa Station km 1.0
Miritini km 12.5
Mazeras km 19.3 Mazeras km 12.0
Mariakani km 34.2 Mariakani km 25.4
Maji Ya Chumvi km 49.0 Manjewa km 39.6
Samburu km 60.3 Samburu km 51.0
Taru km 73.8 Mugalani km 65.2
Mackinnon Road km 84.6 Mackinnon Road km 78.3
Bachuma km 97.1 Miaseny km 92.2
Wangala km 106.2
Maungu km 122.9 Maungu km 118.7
Ngutini km 129.7
Voi km 152.7 Voi km 142.8
Mileage gap 7.5 km
4.4.3.2 Stations
The total corridor length is about 153 km with following proposed stations:-
Table 4.9: Commuter Service Stations of the Mombasa – Mazeras – Voi Corridor
Station Mileage Interval Rail Level
Mombasa Main Station km 0.0 21 m asl
Makupa km 1.9 1.9 km 25 m asl
Changamwe km 5.4 3.5 km 28 m asl
Mikindani km 9.0 3.6 km 58 m asl
Miritini km 12.6 3.6 km 40 m asl
Mazeras km 19.3 6.7 km 135 m asl
Mariakani km 34.2 14.9 km 207 m asl
Maji Ya Chumvi km 49.0 14.8 km 234 m asl
Samburu km 60.3 11.3 km 294 m asl
Taru km 73.8 13.5 km 353 m asl
Mackinnon Road km 84.6 10.8 km 360 m asl
Bachuma km 97.1 12.5 km 430 m asl
Maungu km 122.9 25.8 km 520 m asl
Voi km 152.7 29.8 km 570 m asl
asl = above sea level
74
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.4.3.4 Junctions
The corridor has following junctions to other corridors and railway lines:-
Table 4.10: Junctions of the Mombasa – Mazeras – Voi Corridor
Station Mileage Connection
Mombasa Main Station km 0.0 Mombasa – Mtwapa – Kilifi – Malindi Corri-
dor
Makupa km 1.9 Likoni Ferry – Bamburi Corridor
Mombasa – Airport – Likoni – Ramisi Corri-
dor
Mazeras km 19.3 Mazeras – Kaloleni – Takaungu Corridor
4.4.3.5 Alternative
Not applicable.
75
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
76
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.4.4.1 Description
The southern terminal station of the Likoni Ferry – Bamburi corridor is situated at the
landing stage of the Likoni Ferry on the Mombasa Island. The corridor follows the
abandoned meter-gauge railway line to Makupa.
At Makupa there is a junction to the Mombasa – Airport and to the Mombasa – Mazeras
– Voi Line. The corridor passes the southern Mombasa Island and crosses the Junda
creek to establish a 2nd connection to the northern mainland.
77
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The northern terminal station of this corridor at Bamburi is also the connection station
to the northern Mombasa – Mtwapa – Kilifi – Malindi Corridor.
4.4.4.2 Stations
The total corridor length is about 13 km with following proposed stations:-
Table 4.11: Stations of the Likoni Ferry – Bamburi Corridor
Station Mileage Interval Rail Level
Likoni Ferry km 0.0 12 m asl
Cruise Pier km 1.7 1.7 km 19 m asl
Makupa km 4.3 2.6 km 25 m asl
Junda km 8.4 4.1 km 25 m asl
Kengelani Road km 11.0 2.6 km 47 m asl
Mtopanga km 13.1 2.1 km 30 m asl
Bamburi km 14.8 1.7 km 22 m asl
asl = above sea level
78
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.4.4.4 Junctions
The corridor has following junctions to other corridors and railway lines:-
Table 4.13: Junctions of the Likoni Ferry – Bamburi Corridor
Station Mileage Connection
Makupa km 4.3 Mombasa – Airport – Likoni – Ramisi Corri-
dor
Mombasa – Mazeras – Voi Corridor
Bamburi km 14.8 Mombasa – Mtwapa – Kilifi – Malindi Corri-
dor
4.4.4.5 Alternative
In combination with alternative Ras Makawaiwa Bridge of corridor 2, Mombasa –
Mtwape – Kilifi – Malindi, the alternative joins the corridor 2 line at Polytechnic Uni-
versity.
Advantage: The junction to line 2 at Polytechnic University station omits a 2nd bridge to
the territories northern to Mombasa. The significant shortening of the corridor reduces
the necessary investments.
Disadvantage: The alternative needs a northern city viaduct along Tom Mboya Road –
Rassini Road with a length of about 1,500m. This viaduct compensates the cost ad-
vantage of omission of the Junda Creek bridge partially. The junction to corridor 2 at
Polytechnic University omits the railway corridor from Junda to Bamburi with signifi-
cant reduction of service quality in this area.
79
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
80
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
81
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Between Mazeras and Kaloleni the railway follows the road C111 building a common
traffic corridor of railway and road. From Kaloleni to Takaungu a new corridor has to
be established. The terminal station at Takaungu is also the connection station to the
northern Mombasa – Mtwapa – Kilifi – Malindi Corridor.
4.4.5.2 Stations
The total corridor length is about 52 km with following proposed stations:-
82
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.4.5.4 Junctions
The corridor has following junctions to other corridors and railway lines:-
Table 4.16: Junctions of the Mazeras – Kaloleni – Takaungu Corridor
Station Mileage Connection
Mazeras km 0.0 Mombasa – Mazeras – Voi Corridor
Takaungu km 51.7 Mombasa – Mtwapa – Kilifi – Malindi Corri-
dor
4.4.5.5 Alternative
Not applicable.
83
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
84
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The northern terminus is situated beneath the new Lamu Port Area must be adapted to
the detailed concept of the Lamu Port Project.
4.4.6.2 Stations
The total corridor length is about 205 km with following proposed stations:-
Table 4.17: Stations of the Malindi – Lamu Corridor
Station Mileage Interval Rail Level
Malindi km 0.0 12 m asl
Gongoni km 22.0 km 22.0 18 m asl
Garsen km 102.0 km 80.0 16 m asl
Witu km 142.0 km 40.0 18 m asl
85
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
4.4.6.4 Junctions
The corridor has following junctions to other corridors and railway lines:-
Table 4.19: Junctions of the Malindi – Lamu Corridor
Station Mileage Connection
Malinde km 0.0 Mombasa – Mtwapa – Kilifi – Malindi Corri-
dor
4.4.6.5 Alternative
Not applicable.
86
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
87
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Corridor 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
KRC/PLM/40/2011
88
190 591.10
89
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
5 OPERATIONAL CONCEPT
5.1 Introduction
This chapter presents an evaluation and a draft proposition for suitable operations for
the planned new commuter railway network in Mombasa, including train schedules. It
proposes train services along 6 corridors and discusses alternative options.
90
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
5.3 Corridors
This network will consist of the following corridors:
91
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
92
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
5.5 Alternatives
93
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Passengers to all other directions (with exception of the northern corridor to Kisauni-
Bamburi-Kilifi) will lose time as they will run twice (there and back) on the section
Makupa-Mombasa main station.
From the network map, it is clear that Makupa is the only station where all commuter
services and also the service to Nairobi are connected.
94
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
For travellers to or from the Nairobi line, a stop in Makupa is also a better connecting
possibility for travellers to or from the airport, this saving time in comparison to a con-
nection in Mombasa main station.
For these reasons, we propose that:
Long-distance trains to or from the Nairobi corridor will make an additional stop in
Makupa before terminating in Mombasa main station.
Long-distance trains to or from Lamu (if built) will not stop only at Mombasa main
station, but will be extended to Makupa and the airport (Stabling facilities will be
necessary, ideally in the Airport to Likoni area)
Makupa can be designed as the central node for commuters and long-distance trains.
The timetables for all trains can be designed to offer good connections in Makupa ra-
ther than in Mombasa main station.
5.7.1 General
The following travel time tables have been developed on the basis of the distance be-
tween stations and the train speeds indicated. Allowance has been made for acceleration
and deceleration according to the line speed. Each stop is assumed to last 2 minutes (in-
cluded in the row “Interval time incl. Stop” on the following tables).
95
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Interval
Ac-/De-
Station Mileage Interval Speed Ride time Time incl. Travel Time
celeration
Stop
Makupa km 2.5 00:01:49 00:03:49 00:06:17 01:44:25
3.9 Km 100 km/h 00:02:20 00:02:20 00:08:38 01:40:36
Chaani km 6.4 00:01:49 00:03:49 00:12:26 01:38:16
2.9 Km 90 km/h 00:01:56 00:01:56 00:14:22 01:34:27
MOI International
km 9.3 00:01:49 00:03:49 00:18:11 01:32:31
Airport
6.9 Km 100 km/h 00:04:08 00:04:08 00:22:19 01:28:43
Tsunza km 16.2 00:02:00 00:04:00 00:26:19 01:24:34
5.5 Km 100 km/h 00:03:18 00:03:18 00:29:37 01:20:34
Dongo Kundu km 21.7 00:02:26 00:04:26 00:34:04 01:17:16
6.8 Km 120 km/h 00:03:24 00:03:24 00:37:28 01:12:50
Likoni km 28.5 00:02:53 00:04:53 00:42:20 01:09:26
4.7 Km 120 km/h 00:02:21 00:02:21 00:44:41 01:04:33
Magaoni km 33.2 00:02:53 00:04:53 00:49:34 01:02:12
6.7 Km 120 km/h 00:03:21 00:03:21 00:52:55 00:57:19
Waa km 39.9 00:02:53 00:04:53 00:57:48 00:53:58
6.0 Km 120 km/h 00:03:00 00:03:00 01:00:48 00:49:05
Tiwi km 45.9 00:02:53 00:04:53 01:05:41 00:46:05
6.1 Km 120 km/h 00:03:03 00:03:03 01:08:44 00:41:13
Ukunda km 52.0 00:02:53 00:04:53 01:13:37 00:38:10
8.9 Km 120 km/h 00:04:27 00:04:27 01:18:04 00:33:17
Mwabungu km 60.9 00:02:53 00:04:53 01:22:56 00:28:50
9.1 Km 120 km/h 00:04:33 00:04:33 01:27:29 00:23:57
Gazi km 70.0 00:02:53 00:04:53 01:32:22 00:19:24
7.0 Km 120 km/h 00:03:30 00:03:30 01:35:52 00:14:31
Msambweni km 77.0 00:02:53 00:04:53 01:40:45 00:11:01
9.4 Km 120 km/h 00:04:42 00:04:42 01:45:27 00:06:08
Ramisi km 86.4 00:01:26 00:01:26 01:46:53 00:01:26
01.46 h
96
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Interval
Ac-/De-
Station Mileage Interval Speed Ride time Time incl. Travel Time
celeration
Stop
2.6 Km 120 km/h 00:01:18 00:01:18 00:13:50 01:48:49
Freretown km 6.7 00:02:53 00:04:53 00:18:43 01:47:31
2.2 Km 120 km/h 00:01:06 00:01:06 00:19:49 01:42:38
Bamburi km 8.9 00:02:53 00:04:53 00:24:41 01:41:32
5.3 Km 120 km/h 00:02:39 00:02:39 00:27:20 01:36:40
Utange km 12.1 00:02:53 00:04:53 00:24:41 01:45:55
2.1 Km 120 km/h 00:01:03 00:01:03 00:25:44 01:41:02
Shimo la Tewa km 14.2 00:02:53 00:04:53 00:32:13 01:39:59
2.2 Km 120 km/h 00:01:06 00:01:06 00:33:19 01:35:07
Mtwape km 16.4 00:02:53 00:04:53 00:38:12 01:34:01
7.2 Km 120 km/h 00:03:36 00:03:36 00:41:48 01:29:08
Mwamba km 23.6 00:02:53 00:04:53 00:46:41 01:25:32
10.0 Km 120 km/h 00:05:00 00:05:00 00:51:41 01:20:39
Kibaoni km 33.6 00:02:53 00:04:53 00:56:34 01:15:39
14.0 Km 120 km/h 00:07:00 00:07:00 01:03:34 01:10:46
Takaungu km 47.6 00:02:53 00:04:53 01:08:26 01:03:46
6.8 Km 120 km/h 00:03:24 00:03:24 01:11:50 00:58:53
Kilifi km 54.4 00:02:53 00:04:53 01:16:43 00:55:29
6.3 Km 120 km/h 00:03:09 00:03:09 01:19:52 00:50:37
Mtondia km 60.7 00:02:53 00:04:53 01:24:45 00:47:28
23.3 Km 120 km/h 00:11:39 00:11:39 01:36:24 00:42:35
Uyombo km 84.0 00:02:53 00:04:53 01:41:17 00:30:56
9.8 Km 120 km/h 00:04:54 00:04:54 01:46:11 00:26:03
Watamu km 93.8 00:02:53 00:04:53 01:51:04 00:21:09
6.2 Km 120 km/h 00:03:06 00:03:06 01:54:10 00:16:16
Gede km 100.0 00:02:53 00:04:53 01:59:02 00:13:10
13.7 Km 120 km/h 00:06:51 00:06:51 02:05:53 00:08:17
Malindi km 113.7 00:01:26 00:01:26 02:07:20 00:01:26
02.13 h
97
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Interval
Ac-/De-
Station Mileage Interval Speed Ride time Time incl. Travel Time
celeration
Stop
Changamwe km 5.4 00:01:49 00:03:49 00:11:50 02:07:37
3.6 Km 100 km/h 00:02:10 00:02:10 00:14:00 02:03:49
Mikindani km 9.0 00:02:26 00:04:26 00:18:26 02:01:39
3.5 Km 120 km/h 00:01:45 00:01:45 00:20:11 01:57:13
Miritini km 12.5 00:02:53 00:04:53 00:25:04 01:55:28
6.8 Km 120 km/h 00:03:24 00:03:24 00:28:28 01:50:35
Mazeras km 19.3 00:02:53 00:04:53 00:33:21 01:47:11
14.9 Km 120 km/h 00:07:27 00:07:27 00:40:48 01:42:18
Mariakani km 34.2 00:02:53 00:04:53 00:45:41 01:34:51
14.8 Km 120 km/h 00:07:24 00:07:24 00:53:05 01:29:58
Maji Ya Chumvi km 49.0 00:02:53 00:04:53 00:57:58 01:22:34
11.3 Km 120 km/h 00:05:39 00:05:39 01:03:37 01:17:41
Samburu km 60.3 00:02:53 00:04:53 01:08:29 01:12:02
13.5 Km 120 km/h 00:06:45 00:06:45 01:15:14 01:07:10
Taru km 73.8 00:02:53 00:04:53 01:20:07 01:00:25
10.8 Km 120 km/h 00:05:24 00:05:24 01:25:31 00:55:32
Mackinnon Road km 84.6 00:02:53 00:04:53 01:30:24 00:50:08
12.5 Km 120 km/h 00:06:15 00:06:15 01:36:39 00:45:15
Bachuma km 97.1 00:02:53 00:04:53 01:41:32 00:39:00
25.8 Km 120 km/h 00:12:54 00:12:54 01:54:26 00:34:07
Maungu km 122.9 00:02:53 00:04:53 01:59:19 00:21:13
29.8 Km 120 km/h 00:14:54 00:14:54 02:14:13 00:16:20
Voi km 152.7 00:01:26 00:01:26 02:15:39 00:01:26
02.15 h
98
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Interval
Ac-/De-
Station Mileage Interval Speed Ride time Time incl. Travel Time
celeration
Stop
2.1 Km 100 km/h 00:01:16 00:01:16 00:24:52 00:07:17
Mtopanga km 13.1 00:02:00 00:04:00 00:28:52 00:06:01
1.7 Km 100 km/h 00:01:01 00:01:01 00:29:53 00:02:01
Bamburi km 14.8 00:01:00 00:01:00 00:30:53 00:01:00
00.30 h
99
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Interval
Ac-/De-
Station Mileage Interval Speed Ride time Time incl. Travel Time
celeration
Stop
Hindi km 204.9 00:01:26 00:01:26 02:04:51 00:01:26
02.04 h
100
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6 RAILWAY TECHNOLOGY
6.1 Introduction
This chapter describes the proposed technical characteristics of the railway system. It
outlines the specifications for:
Track work, stations and maintenance facilities
Signalling, train control and communication
Electrification and power supply
Rolling stock
101
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6.2.2 Stations
The stations shall be located so as to provide easy pedestrian and vehicular access, and
will include sheltered platforms and general facilities suited to the passenger volumes
and the requirements of the line operation. Junction stations shall be designed to allow
for easy flow of passengers and goods between the trains. The platforms shall be built,
as far as possible, along straight stretches of rail and their lengths shall be commensu-
rate to the planned lengths of the trains. All stations shall be planned so as to allow for a
future second track. End of section stations and crossing stations shall be built with two
tracks.
The station areas shall be suitable lit and protected with adequate fencing.
Station types:
Type 1:
Type 2:
102
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6.2.3.1 General
The new commuter railway network around the city of Mombasa will need appropriate
maintenance facilities.
The new facilities shall be designed to handle the envisaged operation and maintenance
activities for rolling stock and rail infrastructure, and have a final capacity to meet the
expected maximum fleet size of commuter rail vehicles.
The activities to be carried out at the new facilities are essentially:
Daily control, interior cleaning and external cleaning
Stabling of vehicles (after or between services)
Workshop for planned maintenance and minor repairs
It will also serve as base for the future maintenance of the rail infrastructure
Initially it could serve as base for the construction of the rail infrastructure
The maintenance facilities for the rail infrastructure could later be complemented by
service centres at suitable locations along the lines, thus enabling simple railway track
maintenance work to be carried out from local bases.
The planning of the new facilities shall take into consideration the needs of the parties
involved, i.e. the operator, the maintenance organisation including subcontractors and
owner.
103
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
104
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6.3.2 Conditions
105
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
systems complying with international (or European) standards. This allows the purchase
of hard- and software for vehicles and trackside from different manufacturers if neces-
sary.
Trackside signals needed, no cab signaling. The driver gets his movement authority
from the trackside signals.
Trackside train detection (track circuits, axle counters) needed
Fixed blocks: The train is allowed to enter a block section only when there is no oth-
er train on it.
Intermittent transmission to train using balises and loops (The train gets information
only when it passes a balise / loop) (Radio infill using GSM-R possible)
106
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Cab signalling, no trackside signals needed (only trackside panels indicating the train
stop locations). The driver gets his movement authority directly from the ETCS dis-
play (see example picture below).
107
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Figure 6.5: Example of cab signal display, Gautrain Unit 301.016, Pretoria 9.12.2011
108
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Cab signaling, no trackside signals needed. The driver gets his movement authority
directly from the ETCS display
Trackside train detection needed only at special locations. The train position is de-
termined by the train borne odometry, resettled by balises for way correction, and
transmitted by the train to the interlocking.
Moving blocks: Trains can follow each other in braking distance depending of speed,
no fixed stopping locations
Continuous transmission to and from the train using radio transmission (over GSM-R
network)
Balises as position markers only. They may be located mainly or only in the station
areas.
Proof of train integrity needed, either using trains with fixed composition or by using
end of train reporting devices (like, for example, FRED. See also chapter 6.3.5.2)
ETCS Level 3 is actually used on the Västerdal line in Sweden (see also the next chap-
ter 6.3.3.4 “ERTMS Regional”)
109
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
http://publikationswebbutik.vv.se/upload/6424/100456_ERTMS_on_the_vasterdal_line
_utg2_201204.pdf
http://publikationswebbutik.vv.se/upload/5940/100236_ertms_regional_eng.pdf
The implementation of further lines is planned in a near future (particularly in Sweden)
Figure 6.7: Principle schema ETCS Level 3 / ERTMS Regional with GPS tracking
110
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
reach the next station or radio covered area, according the last speed and location
information sent by the train before losing the communication.
As long as the “normal” time to reach the next station is not over, the track section
is considerate as occupied (Normal mode).
If the time to reach the next station or covered area (+ safety factor) is over without
communication with the train, the track section changes to the “Undefined” mode.
Trains can enter this section only on sight, and the “lost” train will also have to stop
or carry on travelling on sight (this depending of the regulations, which will have to
be defined in a later phase of the project).
In addition, it would be useful to install axle counters in the stations giving access to
dark territories, this allowing recognising a train with non-working radio equipment
when it enters a station, and then releasing the corresponding track section. This
train will then have to stop at the station and contact CCT for instructions.
Example:
As these axle counters will be installed in stations only (guarded areas), theft and
vandalism against them can be prevented.
With this solution, the dark territories will not be a safety problem, and the installa-
tion of radio relay stations between the stations (in unsafe areas) will not be neces-
sary.
111
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
lead to errors, but it is also possible for the driver to give the acknowledgment with-
out having actually checked the integrity.
End of train devices: System using an emitting device located on the last vehicle of
the train (Example: system FRED / Wilma, widely used on US railroads), allowing
the train ATP to check the distance between head and end of train, and giving an
alert if this distance reaches an incorrect value (Ex: coupling broken, wagon(s) lost).
This system is technically suitable and safe-proof, but it needs to always have the end
of train device correctly fitted on the last vehicle. These devices could be an interest-
ing target for thieves or vandals, so this solution is not recommended for this project.
Axle counters (Same devices like in the precedent chapter 6.3.5.1): These can safely
and automatically check the integrity of a train by counting the number of axles en-
tering / exciting a track section. It would then be necessary to install them not only at
stations giving access to dark territories, but generally on all entry / exit tracks of all
stations (or at least, on the lines where locomotive hauled trains can be expected). If
a train then leaves a track section without having the correct axle amount (Wagons
lost), CCT can block the corresponding track section (Undefined mode) and give an
alert to the driver.
112
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
be allowed to access the network (= CTC will have to be able to distinguish if a train
requesting to enter the network is equipped or not, and if not will have to be redirect
it on pocket tracks or, in case of emergency, on derailers)
Equipment of metre-gauge “pilot” engines with the commuter railway’s ATP
system: These pilots will be coupled in front of the metre-gauge engines entering the
network, and can consist of light or older locomotives equipped with ATP. Their
purpose will be to communicate with CTC, giving position, informing the driver with
MA’s and releasing emergency braking if necessary. No metre-gauge train will be al-
lowed to enter the network without pilot. Like in the case above, CTC must be able
to discriminate trains with or without pilot, and then grant or reject access to the net-
work.
113
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
ETCS Level 3 with GPS tracking needs neither trackside signals nor trackside train
detection, excepted on particular locations. Also balises are no longer needed, but the
technology is not yet available.
PTC: So far no concrete information has been obtained from providers.
For these reasons, we recommend the use of the combination of:
ETCS Level 3
GPS tracking (if available when the construction work actually starts)
ERTMS Regional
Additional measures due to the specific exploitation characteristics (Axle counters,
and other to be defined)
PTC may be an alternative, but this can be only be analysed when detailed information
about this system is available.
6.4.1 Purpose
The data transmission network will ensure the data and voice transmission between:
CTC
Stations
Trains
Mobile users (Handheld “mobile phones” for station personal, track worker teams,
track inspectors, security guards, etc.)
It has to be a dedicated network, as the public GSM of wired networks doesn’t ensure
the needed availability and transmission reliability for security sensible purposes.
114
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
115
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
116
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6.4.4.1 GSM-R
GSM-R (Global System for Mobile Communications – Rail) is a communication system
carrying voice and data for mobile users (persons and trains). It is a direct derivate of
GSM (standard for commercial mobile phone communication) with specific adaptations
for railway traffic purposes.
GSM-R is widely used on the most railways systems in Europe for voice and data
communication, including ETCS L2 and L3 applications in several countries.
6.4.4.2 Tetra
Tetra (TErrestrial Trunked RAdio) is a system initially developed for public services
transmissions (Police, fire departments, emergency services, public transports, etc.), and
is widely used worldwide. It is also used to transmit data for ATP applications (also
ETCS L3) in several countries
117
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
areas. But DC systems requires additional rectifier units (complex technic and addition-
al servicing) and are not ideal for long distances which is the case in this project.
Therefore a 25kV traction power supply system is proposed to energize the catenary
system for the different planned railway lines with single lengths up to 55 km. The de-
velopment of the electrification infrastructure shall be made step by step in accordance
with the development plans, but system and equipment should be utilized constant
throughout the complete commuter rail network.
Either a 1 x 25kV AC System or a 2 x 25kV AC autotransformer system may be con-
sidered. Railway electrification using 25 kV, 50 Hz AC has become an international
standard. There are two main standards that define the voltages of the system:
EN 50163:2004 - "Railway applications. Supply voltages of traction systems"
IEC 60850 - "Railway Applications. Supply voltages of traction systems"
A 2 x 25kV autotransformer system is considered which is the “modern” system (State
of the art) used widely e.g. for the Gautrain/ZA, in Algeria, India, France, for Germany
High speed lines, etc.). Energy losses can be reduced with such a system and the dis-
tance between substations may be extended up to approximately 50km which is a major
advantage for this case.
In an autotransformer system, the current is mainly carried between the overhead line
and a feeder instead of the rail. The voltage between the overhead line and the feeder
line is 50 kV but the voltage between the overhead line and the running rails remains at
25 kV which is the voltage supplied to the train. Due to the behavior of the autotrans-
former the electromagnetic interference and the current in the running rails are reduced
which is a further advantage.
118
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6.5.3 Substations
For the railway development considered in this study an estimated 9 to 10 substations
are required. The substations shall be supplied from the 132 kV national grid (three-
phase distribution system) and shall be utilized as redundant systems (high voltage and
traction substation equipment).
At the grid substation, a transformer is connected across two of the three phases of the
high-voltage supply. The transformer (autotransformer) lowers the voltage to 25 kV
which is supplied to the switching stations located beside the tracks. In the switching
stations electrical energy can be distributed to different feeding sections or feeding sec-
tions can be energized or de-energized. In addition paralleling substations may be con-
nected in parallel to the feeding stations.
Figure 6.11: Overhead contact lines on individual supports using concret poles.
119
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
6.6.1 General
The new commuter rail system envisaged for the city and region of Mombasa should
ideally support both urban and regional travel, i. e. trips made within the city over short
distances and also trips between the city and regional towns and settlements. The system
will accordingly comprise corridors in the built-up environment of Mombasa, and po-
tentially other urban areas, as well as typical mainline railway alignments in the coun-
tryside.
120
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Figure 6.12: Typical configuration schema of rolling stock for commuter rail
6.6.3 Capacity
Capacities of up to 200 passengers per coach are achievable, under crush loading condi-
tions. Total capacity of a train with 15 coaches may be up to 3,000 passengers.
The capacity of the same train in the regional network would be only around half of the
above, as crush loading would only be acceptable over short distances (e. g. for inner-
city travel).
With train intervals not shorter than 10 minutes, maximum train length and crush load-
ing, the achievable line capacity could theoretically arrive at ~18,000 passengers per
hour per direction on one track.
The initial fleet size will be derived from the expected patronage figures which will be
estimated at a later stage.
121
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
It is proposed that the floor height will not exceed 600 mm.
122
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
7.1 Introduction
As part of the Feasibility Study both a preliminary Environmental Impact Assessment
and a Preliminary Social Impact Assessment were to be conducted. These were pre-
pared together as a preliminary Environmental and Social Impact Assessment (ESIA),
in the form of the present Screening Report that meets the requirements of the National
Environment Management Authority (NEMA). The full report is presented in Annex 4
to the Final Report.
The Preliminary ESIA was carried out in compliance with national policies and legisla-
tion and international standards (World Bank Operational Policies and international pol-
icies and treaties ratified by Kenya).
The Screening Report includes the following parts:
General basis of the study, sections 1 to 5 (Introduction, Project description, Study
area, Methodology, Legislative and regulatory framework)
Sectoral studies, sections 6 to 8 (physical, natural and socio-economic environ-
ments: current baseline in the project area, identification of impacts and recom-
mended mitigation measures)
Analysis of social context, sections 9 to 11 (Socio-economic Survey, Resettlement
Planning, Consultation and Public Participation).
Synopsis, section 12 (summary of project impacts, evaluation of project alternatives,
Environmental and Social Management Plan).
To identify sensitive environmental or socio-economic areas and advise railway engi-
neers on alternative corridor alignments, as well as maintain flexibility to update the en-
vironmental and socio-economic assessment based on changes in corridor alignment,
Geographic Information Systems (GIS) were used extensively. The results are repre-
sented in the following mapbooks:
Environmental Mapbook: includes important environmental features for the entire
study area (excl. Mombasa – Mazeras – Voi Corridor), as well as a land use / land
cover analysis for the study area between Waa and Gongoni Stations.
Socio-economic Mapbook: includes important socio-economic infrastructure for the
entire study area.
123
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Three levels of study were used to explore the environmental and socio-economic im-
pacts of the project, with according degrees of detail:
1. Construction area: the area of direct and irreversible impacts of the railway
corridor, between 15 and 60 m wide depending on the topography. This is the
area in which detailed data analyses were performed.
2. Influence area: the area of potentially high but at least in part reversible impacts
of the railway. To screen for project impacts, a 1 km wide influence area was
used, centered on the railway line.
3. Study area: the larger area encompassing all railway corridors for the Mombasa
commuter railway. The considered study area corresponds to the Kenyan coast-
line between Ramisi and Lamu, extending about 80 km inland. This is the area
in which the regional baseline and issues at stake are being investigated.
At this project stage, no information is available yet on the exact location and design of
stations, maintenance facilities and temporary structures. Therefore, these were included
as part of the study area. Their impacts were analysed with the information available,
i.e. standard impacts expected as part of the construction and operation of a railway giv-
en the local conditions.
124
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Mtwapa Creek, Takaungu Creek, Kilifi Creek, Mida Creek, Lamu River Delta). The
high sediment load of water bodies draining towards the Indian Ocean, caused largely
by poor land-use practices upstream, threatens the sustainability of coastal habitats. The
project’s main impacts on water resources will be pollution and increased sedimenta-
tion, as well as the physical alteration of water bodies which could lead to a modifica-
tion of drainage patterns.
In the study area, air quality in areas of urban/industrial land use and along roads with
heavy road traffic is expected to be poor and ambient noise levels are expected to be
high. This is particularly the case in Mombasa City. In areas of agricultural land use and
natural areas on the other hand, air quality is expected to be high and ambient noise lev-
els are expected to be low. During the construction phase, the project will lead to in-
creased noise levels and vibrations, as well as a degradation of air quality due to exhaust
and dust emissions. During the operation phase however, the overall impact on the
study area will be positive due to a reduction in road traffic, except in the direct vicinity
of the railway. Here, disturbances due to increased noise and vibrations and reduced air
quality are expected mainly in residential and wildlife areas.
125
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
126
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The freshwater ecosystems of the Kenyan coast are part of the “Tana, Athi & Coastal
Drainages” Freshwater Ecoregion. The coastal rivers of this ecoregion, with their asso-
ciated swamps, floodplains and lakes, host a relatively depauperate fish fauna which in-
cludes a number of endemic species, as well as a rich avifauna and herpetofauna. The
main impacts of the project on freshwater ecosystems are due to impacts on water bod-
ies, i.e. loss of habitat due to physical modifications, and mortality or degradation of
health condition of aquatic species and terrestrial species depending on aquatic ecosys-
tems due to negative impacts on water quality.
Marine ecosystems found in the study area include estuaries, mangrove forests, seagrass
beds, soft-bottom habitats, rocky shores and coral reefs, which are all closely inter-
linked. They harbour high levels of biodiversity, including many threatened species.
Coastal flagship species include marine turtles, which nest on Kenyan beaches, and du-
gongs, which live in shallow waters and sheltered bays and lagoons. The railway corri-
dors will cross numerous brackish and marine ecosystems, such as creeks, estuaries and
mangrove forests. The project is likely to impact both these ecosystems and sensitive
ecosystems towards which they drain. The main consequences will be loss of habitat
through physical modifications, destruction and degradation of marine ecosystems, and
mortality or degradation of health of marine species due to pollution. These impacts are
especially critical for marine ecosystems of high conservation value such as coral reefs
and mangroves, and for threatened species (e.g. marine turtles, dugongs, endangered
fish and corals).
Due to the high levels of biodiversity on the Kenyan coast, both terrestrial and marine,
the project is located in an area with an exceptionally high value for conservation. This
is reflected by the number of protected areas found in the study area. There are 11 na-
tional parks (NP) and national reserves (NR), of which five are located in the construc-
tion and/or influence area of the railway corridors: Watamu Marine NP, Malindi-
Watamu NR, Arabuko-Sokoke NR, Gede Ruins National Monument and Tsavo East
NP. There are also a large number of sensitive areas, i.e. areas that have been recog-
nised nationally or internationally as exceptional and/or unique because of the ecosys-
tems and/or species they harbour, but that are not officially protected (e.g. Ramsar sites,
Important Bird Areas).
Although protected and sensitive areas were avoided wherever possible during the de-
sign of the corridor alignment, in a few instances this was not possible due to geograph-
ical constraints. These critical areas, where the train passes close to or even through
protected and/or sensitive areas, are:
Watamu-Malindi Ecosystem
Tana River Delta Ecosystem
Tsavo East National Park
In these critical areas, the impacts of the project are expected to be very high both dur-
ing the construction and operation phases. There is also a considerable risk that this will
ensue in delays in the project approval and licensing process.
127
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
128
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Mazeras – Kaloleni – Takaungu: this corridor passes towns densely populated but the
environs comprise farmland.
Mombasa city, surrounding areas and commercial centres within the corridor are dense
with both commercial and residential structures; while outside the county the settle-
ments are sparse, especially areas surrounded by the Tsavo game reserve land and
Shimba Hills.
The corridors have varied settlements criss-crossed by farmland as the railway line
moves away from the growing towns. The densely settled areas (towns and city) point
towards need for carrying out a full-fledged Resettlement Action Plan (RAP) as people
will need to be resettled or compensated. The more densely settled the area, the more
likelihood for compensation and relocation.
The population and settlement location is indicative of where the commuter train will
have more impact, both negative and positive.
129
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
7.5 Synopsis
7.5.1.1 Analysis
Screening the different features of the physical, natural and socio-economic environ-
ment in the study area allowed determining variable sensitivities to project impacts ac-
cording to the corridor section considered. This is due to the high diversity of ecosys-
tems as well as the unequal distribution of population along the Kenyan coast.
To obtain an overview of these findings, a preliminary evaluation of the overall impact
of each future railway corridor section on key features of the physical, natural and so-
cio-economic environment was conducted and is recapitulated in the following table.
Table 7.2: Preliminary evaluation of overall project impacts per corridor section
Overall project im-
pact
Feasibility Study
Corridor section
Length (km)
economic envi-
Priority
Physical and
natural envi-
ronment
ronment
Socio-
From To
Low to
1.1 Makupa Moi International Airport 7.1 2 High
medium
Low to
1.2 Moi International Airport Likoni 20.8 5 High
medium
1.3 Likoni Ramisi 58.1 8 High High
2.1 Mombasa Main Station Mtwapa 16.4 3 High Very high
2.2 Mtwapa Kilifi 38.0 7 High Very high
2.3 Kilifi Malindi 59.3 10 Very high High
Low to
3.1 Mombasa Main Station Mazeras 19.3 1 High
medium
Low to Low to
3.2 Mazeras Samburu 41.0 6
medium medium
Low to
3.3 Samburu Voi 92.4 9 High
medium
4 Likoni Ferry Bamburi 14.8 4 High Very high
Low to
5 Mazeras Takaungu 51.7 11 High
medium
6 Malindi Hindi 204.9 12 Very high High
130
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
7.5.2 Conclusion
The challenges of urbanisation and climate change call for sustainable transport solu-
tions. Therefore, the development of the Mombasa commuter railway project is ex-
pected to have an overall positive impact on the natural and socio-economic environ-
ment, as railway transport is a sustainable alternative to increasing motorised vehicle
traffic.
However, based on the screening conducted in this Preliminary ESIA, the impacts of the
project on many different aspects of the physical, natural and socio-economic environ-
ment will be considerable, due to:
The extensive scale of the area traversed by the railway corridors.
The large variety of land uses it crosses, including:
Densely inhabited urban areas that will require the resettlement of a large num-
ber of people.
Areas of exceptional biodiversity (including protected areas), that will require
extensive stakeholder involvement to identify appropriate mitigation measures.
131
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The Consultant is therefore the opinion that a full ESIA and RAP will need to be con-
ducted in the next project stage.
Furthermore, in the corridor sections for which a very high overall project impact has
been identified, the following specific recommendations apply:
Kilifi-Malindi corridor: given the sensitivity of the Watamu-Malindi Ecosystem and
the number of protected and sensitive areas located in this ecosystem, KRC should
consider developing the corridor as a separate project with its own ESIA.
Malindi-Hindi corridor: given the extreme sensitivity and relatively pristine state of
the Tana River Delta Ecosystem, as well as the sparse population of the area, the de-
velopment of a commuter railway on this corridor is not recommended from an envi-
ronmental perspective. Should KRC nonetheless choose to include this corridor in
the Detailed Design stage, the corridor should be developed as a separate project with
its own ESIA to avoid delays in project approval and licensing for the other corridors
that have a lesser impact.
Likoni-Ramisi corridor: very densely populated on approaching Likoni and several
houses will be grazed, while in Ukunda the aerodrome and airport will be interfered
with, as they lie within the corridor. KRC should be prepared to have high expenses
in compensation after verification from RAP exercise, should the present proposed
route be maintained.
Mtwapa – Kilifi corridor: the extensive stretch of sisal plantations is a great contribu-
tor to the economy and employment of the region. While the Mnarani Club and other
resorts within the corridor, which are all private, are not only contributors to the tour-
ist industry (economy and employment), but Mnarani Club and Beach area extends
right up to the creek, where the private beach is surrounded by a coral reef. More dis-
turbances to the creek and coral ought to be minimised. Should the proposed corridor
be approved, then KRC should start early to negotiate land acquisition for the pro-
ject, bearing in mind that the cost will be colossal.
Likoni Ferry – Bamburi corridor: this has extremely dense settlements both commer-
cial and residential structures. As there is no land that is unoccupied here, alternative
land for resettlement will have to be sought; it is not known how many settlements
will willingly move to Junda where there appears to be land. It would be advisable to
do a separate and thorough RAP for this corridor.
132
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The ESMP was prepared for the planning, construction and operation phases. The plan-
ning phase ESMP will be crucial in the preparation of the Detailed Design, as the need
for and/or extent of many mitigation measures recommended for the construction and
operation phases can be reduced or made redundant by applying the recommended
planning phase measures. Therefore, it is essential that the preliminary ESIA and espe-
cially the ESMP be made available to the detailed design engineers and the consultant
preparing the ESIA and the RAP.
The mitigation measures recommended for the planning phase are presented in the table
below.
Table 7.3: Impacts and mitigation measures identified for the planning phase
Impacts Impacts
Soils: - ESIA: detailed geological and soil survey
erosion - Plan appropriate drainage structures
- Plan infrastructures to protect from rock fall
- Adapt size of bridges and culverts to large floods
- Avoid passing too close to shoreline
- Avoid passing through mangrove forests
Water resources: modifi- - ESIA: detailed evaluation of water resources with field evaluations of water body
cation of physical envi- and catchment area status to define the sensitivity of the water bodies concerned
ronment and degradation - Following survey, where possible, avoid sensitive water resources
of water quality - Plan environmental and water protection management system
- Plan construction sites and large-scale facilities away from water bodies
- Design bridges instead of embankments in mangrove forests, wetlands and flood-
plains
- Plan crossing of permanent waterways where banks are stable and waterway is the
narrowest
- Plan construction activities across seasonal rivers during dry season
Noise: pollution - ESIA: noise mapping in urban areas
- ESIA: noise pollution modelling
- Plan noise protection measures in sensitive areas based on findings from noise
mapping and modelling
Landscapes: permanent - Railway corridor should follow existing road corridors
modification - Avoid passing through unique and/or exceptional landscape features
- Avoid passing through continuous natural landscapes such as coastal forests,
mangroves and wetlands
- Plan temporary structures in areas that are already impacted by human presence
Vegetation: destruction, - ESIA: refine land cover analysis through ground-truthing to further distinguish dif-
fragmentation, degrada- ferent vegetation types and their sensitivity
tion - ESIA: evaluate land cover between Gongoni and Malindi as well as Waa and Ra-
misi
- Avoid passing through highly sensitive vegetation types (coastal forests, man-
groves, wetlands)
- Railway corridor should follow existing road corridors whenever possible, and espe-
cially through sensitive vegetation types
- Plan temporary structures in areas where the vegetation is already impacted by
human presence and in low sensitivity vegetation categories
133
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Impacts Impacts
- Integrate communities as stakeholders depending on forest resources
Mangroves and wet- - ESIA: refine land cover analysis through ground-truthing to evaluate exact man-
lands: grove and wetland location
destruction - ESIA: perform land cover analysis between Gongoni and Lamu as well as Waa and
Ramisi to determine exact location of mangroves and wetlands
- Avoid mangrove areas and wetlands
- Design bridges instead of embankments in mangrove and wetland areas
Wildlife: - ESIA: further identify species present in project area, especially threatened and
disturbance, fragmenta- endemic species
tion, - ESIA: identify wildlife migration corridors
mortality - Avoid cutting through wildlife migration corridors, if impossible design under- or
overpasses so they are appropriate for species concerned
- Maintain corridors of forest open to allow movement of species. Where fragmenta-
tion of key habitats cannot be avoided, design under- or overpasses in the form of
green corridors and appropriate for species concerned
- Design bridges instead of embankments
- Avoid or minimise any impacts on protected and sensitive areas
Freshwater ecosystems: - ESIA: detailed survey of freshwater ecosystems crossed by corridors
degradation - Following survey, where possible, avoid sensitive freshwater ecosystems
- All measures for water resources, vegetation and soils
Marine ecosystems: deg- - ESIA: detailed survey of marine ecosystems crossed by corridor (creeks, man-
radation groves, etc.)
- All measures for water resources, vegetation and soils
- Avoid passing close to turtle nesting beaches
Protected and/or sensi- - Avoid protected or sensitive areas
tive areas: - ESIA: if impossible to avoid, involve all stakeholders likely to be affected to agree
destruction, on appropriate compensation measures, and obtain written consent letters giving
degradation authority for implementation of project
- In particularly critical areas (Watamu-Malindi Ecosystem, Tana River Delta Ecosys-
tem), the development of the corridors concerned as separate projects with their
own ESIA should be considered
- ESIA: evaluate movement of animals between Arabuko-Sokoke Forest and Mida
Creek
- Watamu-Malindi corridor: follow existing road passing through plantation area of
Arabuko-Sokoke along the northern side of said road, design appropriate over- or
underpasses for species concerned
- Tana River Delta ecosystem: railway should not be built on an embankment in
mangrove and wetlands areas, but follow the recommended bridge design
- Tsavo East National Park: reevaluate measures of SGR ESIA with increased traffic
and construction of new stations once more information becomes available on traf-
fic and exact location of stations, if necessary propose additional measures
Land acquisition and - PAPs (those losing land, crops, houses and other assets) be relocated or stay if
involuntary more than 60 m from the railway tracks. Must be compensated first before the land
resettlement / displace- is taken into use.
ment of persons - Carry out full-fledged RAP to ensure capturing all directly affected PAPs and ascer-
tain owners of land that may be expropriated; engage local communities and their
134
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Impacts Impacts
leaders, Ministry of Lands and National Land Commission on all issues to do with
land.
- Continue public consultations and engage PAPs in all aspects of project, especially
when RAP starts.
- In accordance with OP 4.12 and Kenyan legislation on land acquisition, draw up
agreements with affected and compensate them before any land take occurs.
Loss of access to and - Carry out RAP and identify access to and livelihoods from land whether titled or not.
livelihood from land; Identify all categories of land use.
land use - Compensate as will be spelt out in RAP.
- Alternative livelihood strategy
Loss of property and - Carry out full-fledged RAP to mark structures within corridor that will be destroyed.
assets Also includes social infrastructure (schools, health centres, mosques, churches,
etc.)
- Where commercial and residential structures affected, owners to be compensated
as required by Kenyan legislation and WB’s OP 4.12. For social infrastructure, re-
place these at new sites for continued use by community.
Traffic diversions and - Provide safe alternative, temporary access for those portions of roads and other
risk to existing buildings infrastructure (bridges, etc.)
Interference with Sisal, - RAP: Where corridors cannot be re-aligned, ascertain owners of plantations that
tea, fruits (mangoes, co- might be interfered with and compensate owners for loss of crops and trees.
conuts, palms, bananas, - Engage PAPs and local leaders work out modalities for compensation and compen-
etc.) Plantations and sate before destruction of plantations.
Tree Research Plots
Disturbances to bore - RAP: Together with local communities and technical staff at county level, ascertain
holes, water piping and sites of water pipes, boreholes and storage and secure and protect these.
storage systems - Carry out a full-fledged RAP
Destruction of social in- - RAP: Ascertain social infrastructure to be affected in railway corridor e.g. Waa Dis-
frastructure pensary in Waa Kwale District and Taqwa Muslim School in Likoni.
- SRG: check Samburu-Voi corridor: Ensure McKinnon Road Mosque and Ndonivyo
Primary school not impacted.
- If impossible to avoid destruction, ensure assets replaced at new site for continued
use by community.
Cultural Heritage - RAP: Carry out an indepth comprehensive study and demarcation of entire corri-
dors required.
- Use communities’ knowledge for the heritage site identification and re-route railway
to avoid destruction of such sites.
- Where burial sites and sacred sites are affected, relocate these and perform neces-
sary rituals and project pays for relocation.
Population and social - Do not fragment family units, special attention to be given to vulnerable groups as
network identified during RAP.
- Relocation to areas similar to those relocated from.
135
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
8.1 General
The preliminary cost estimates present the total investment and operation costs for the
sections and the total length of the lines.
They correspond to the routes and alignments described in Section 4 and reflect the state
of definition of the project.
It is assumed that the project will be realised according to the Time Line presented in
Figure 4.33. Two scenarios are considered for the implementation of the project. The
first alternative assumes a total implementation of the project by the end of 2030, and
the second a reduced implementation by 2027, leaving out sections 5 Mazeras – Kalole-
ni – Takaunga and 6 Malindi – Hindi.
The prices are given in KES (Kenyan Shillings) and USD (US Dollar), reflecting the
share of local and imported supplies and services.
They correspond to 2013 prices and do not take into account inflation and the cost of in-
terests.
The investment cost items are grouped in the following categories:
A. Land acquisition
B. Civil works for the sections excl. stations (Earthworks, bridges, tunnels, cul-
verts)
C. Rail facilities (Trackwork, signalling, TC & communication, electrification)
D. Stations
E. Maintenance facilities (Workshop, equipment, vehicles) and yard
F. Ancillary works (Streets, crossings, utilities, landscaping, costs of Environmen-
tal and Social Management Plan (ESMP) and Resettlement Action Plan (RAP)).
G. Rolling stock (incl. spare parts)
H. Engineering services (Project management, design, construction supervision and
commissioning)
The main operation costs items are station and maintenance staff, infrastructure and
train operation.
136
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
gation measures) are given a flat price. Engineering services, comprising project man-
agement, project design, construction supervision and commissioning, are estimated on
a percentage basis of the total investment cost.
A breakdown of the investment costs for all sections is included in Annex 7.
The operation costs are based on station and light maintenance staff costs, infrastructure
operations costs and train operations costs.
The yearly station staff costs are based on 5 personnel categories and staff numbers
commensurate to the 5 station categories. The yearly light maintenance staff costs are
based on 5 personnel categories and assumed staff numbers for workshop & depot,
workshop extension and infrastructure service point. The infrastructure operation costs
cover the depreciation, maintenance and replacement costs for the infrastructure over 30
years run time, taking into account the life spans of the various items.
The train operation costs are made up of staff costs, fuel costs and depreciation, mainte-
nance and replacement costs for the rolling stock with a life span of 30 year, over 30
years run time.
No Corridor Length Sub Total Costs per Cost Group Total Cost local foreign
1.1 Mombasa - Airport - Likoni - Ramisi 6.5 km 358 691 440 153 43 404 1'564 465 4'118 634 2'082 23.96
Makupa - Airport 2.5 km 9.0 km
1.2 Mombasa - Airport - Likoni - Ramisi 20.8 km 737 19'665 1'119 188 26 981 1'420 3'335 27'470 1'321 24'112 39.51
Kenya Railways Corporation KRC
2.2 Mombasa -Mtwapa - Kilifi - Malindi 38.0 km 317 5'607 1'944 306 43 343 1'275 1'336 11'171 294 5'744 63.85
Mtwapa - Kilifi 16.4 km 54.4 km
2.3 Mombasa -Mtwapa - Kilifi - Malindi 59.3 km 456 4'443 3'062 369 309 409 1'564 1'428 12'041 203 6'268 67.91
Kilifi - Malindi 54.4 km 113.7 km
Cost estimation of capital costs
3.1 Mombasa - Mazeras - Voi 19.3 km 342 1'005 1'043 529 662 553 3'392 1'013 8'539 442 3'708 56.83
Mombasa - Mazeras 0.0 km 19.3 km
3.2 Mombasa - Mazeras - Voi 41.0 km 2 8 245 216 903 69 986 341 2'770 68 869 22.36
Mazeras - Samburu 19.3 km 60.3 km
3.3 Mombasa - Mazeras - Voi 92.4 km 3 14 386 369 9 23 1'479 320 2'602 28 696 22.43
Samburu - Voi 60.3 km 152.7 km
4 Likoni Ferry - Bamburi 14.8 km 917 7'763 794 342 17 955 1'913 1'655 14'355 970 7'659 78.77
Likoni Ferry - Bamburi 0.0 km 14.8 km
5 Mazeras - Kaloleni - Takaungu 51.7 km 633 6'550 2'705 279 51 442 986 1'564 13'210 256 10'172 35.74
Mazeras - Takaungu 0.0 km 51.7 km
6 Malindi - Lamu 204.9 km 1'171 11'316 10'214 279 456 880 2'465 3'626 30'407 148 21'043 110.16
Malindi - Lamu 0.0 km 204.9 km
Total Costs 623.2 km 6'348 70'522 25'976 3'994 2'826 6'556 21'361 18'548 156'131 251 100'221 657.76
Cost Groups A Land Acquisition E Maintenance facilities
B Civil Works F Ancillary works
C Rail Facilities G Rolling stock
D Stations H Engineering Services
137
190 591.10
Final Report
No Corridor Start / Duration [month] Costs Investment costs per year [mn KES]
KRC/PLM/40/2011
Planning Construction Opera. [mn KES] 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Total costs
Mombasa - Mazeras 10/13 18 04/15 30 10/17 7'526 2'256 3'014 2'256 7'526
1.1 Mombasa - Airport - Likoni - Ramisi 465 72 143 143 107 465
Makupa - Airport 07/14 15 10/15 24 10/17 3'653 455 1'829 1'369 3'653
Kenya Railways Corporation KRC
2.1 Mombasa -Mtwapa - Kilifi - Malindi 2'479 366 367 368 367 367 367 277 2'479
Mombasa - Mtwapa 01/14 27 04/16 54 10/20 18'507 3'085 4'109 4'109 4'109 3'096 18'507
4 Likoni Ferry - Bamburi 1'655 226 301 301 301 301 226 1'655
Likoni Ferry - Bamburi 04/16 18 10/17 48 10/21 12'700 791 3'173 3'173 3'181 2'382 12'700
Mombasa Commuter Railways Feasibility Study
1.2 Mombasa - Airport - Likoni - Ramisi 3'335 119 477 476 476 476 477 476 357 3'335
Airport - Likoni 10/15 24 10/17 60 10/22 24'136 1'203 4'824 4'824 4'838 4'824 3'622 24'136
2.2 Mombasa -Mtwapa - Kilifi - Malindi 1'336 179 356 356 356 90 1'336
Mtwapa - Kilifi 07/20 15 10/21 30 04/24 9'835 980 3'932 3'932 991 9'835
1.3 Mombasa - Airport - Likoni - Ramisi 987 132 263 263 264 66 987
Likoni - Ramisi 07/21 15 10/22 30 04/25 7'475 745 2'988 2'997 745 7'475
Samburu - Voi 10/21 12 10/22 24 10/24 2'282 284 1'139 858 2'282
2.3 Mombasa -Mtwapa - Kilifi - Malindi 1'428 191 381 380 380 95 1'428
Kilifi - Malindi 07/23 15 10/24 30 04/27 10'613 1'059 4'247 4'247 1'059 10'613
6 Malindi - Lamu 3'626 100 403 403 404 403 403 403 404 403 302 3'626
Malindi - Lamu 10/21 30 04/24 78 10/30 26'782 3'091 4'118 4'118 4'118 4'129 4'118 3'091 26'782
Total Costs 156'131 63 691 3'592 9'395 11'169 13'250 13'278 12'765 10'831 11'065 9'465 10'563 13'217 13'374 9'900 5'598 4'520 3'393 156'131
Engineering Service costs (management, design, supervision, comissioning)
Construction costs (incl. Land acquisition and rolling stock)
138
190 591.10
Final Report
all costs in [mn KES]
KRC/PLM/40/2011
Figure 8.1:
16'000
Kenya Railways Corporation KRC
200'000
14'000
Upgrading Infrastructure
150'000
System Implementation
10'000
Total Investments
8'000
100'000
6'000
2'000
0 0
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045
139
190 591.10
Final Report
all costs in [mn KES]
KRC/PLM/40/2011
Figure 8.2:
18'000
Kenya Railways Corporation KRC
250'000
16'000 Malindi - Hindi
Mazeras - Takaungu
Likoni Ferry - Bamburi
14'000 Kilifi - Malindi
200'000
Mombasa Commuter Railways Feasibility Study
Mtwapa - Kilifi
Mombasa Main Station - Mtwapa
12'000
Likoni - Ramisi
MOI International Airport - Likoni
Makupa - MOI International Airport
10'000 150'000
Samburu - Voi
Mazeras - Samburu
2'000
0 0
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045
140
190 591.10
190 591.10
141
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Table 8.4: Cost estimation of capital costs for the reduced project
Total Costs
Cost Groups (mn KES)
A Land Acquisition 4'545
B Civil Works 52'656
C Rail Facilities 13'056
D Stations 3'436
E Maintenance facilities 2'317
F Ancillary works 5'233
G Rolling stock 17'910
H Engineering Services 13‘359
Total 112'514
142
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Table 8.5: Yearly global investment costs for the reduced project
Engineering Construction
Service Costs Costs
Year (mn KES) (mn KES)
2013 63 0
2014 691 0
2015 882 2'711
2016 1'468 7'927
2017 1'441 9'728
2018 1'144 12'106
2019 1'172 12'106
2020 1'348 11'418
2021 1'330 9'401
2022 1'168 9'494
2023 917 8'059
2024 815 5'905
2025 446 4'993
2026 380 4'247
2027 95 1'059
Total 13'359 99'155
The total costs for implementation of the reduced project are 112'514 mn KES against
156’131 mn KES for the total project.
The cost chart in Figure 8.3 shows the yearly and accrued investment costs for the initial
system implementation and later upgrading of the reduced project.
The yearly and accrued operation costs for each section for the reduced project are pre-
sented in chart form in Figure 8.4: Yearly and accrued operation costs for each
section for the reduced projectFigure 8.4.
Figure 8.3:
180'000
12'000
Kenya Railways Corporation KRC
160'000
10'000
140'000
Upgrading Ro lling Stock
Mombasa Commuter Railways Feasibility Study
Upgrading Infrastructure
120'000
System Implementation
8'000
Total Investments
100'000
6'000
80'000
60'000
4'000
40'000
20'000
0 0
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045
143
190 591.10
Final Report
all costs in [mn KES]
KRC/PLM/40/2011
Figure 8.4:
14'000
Kenya Railways Corporation KRC
Mtwapa - Kilifi
Mazeras - Samburu
4'000
50'000
2'000
0 0
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045
Yearly and accrued operation costs for each section for the reduced project
144
190 591.10
190 591.10
145
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
9 ECONOMIC APPRAISAL
9.1 Introduction
The key question in economic evaluation is if a project or a policy intervention is
worthwhile from an overall social point of view. The main purpose of project economic
analysis is to help design and select projects that contribute to the welfare of a country.
It is most useful when used early in the project cycle, and has very limited use when
used solely as a single figure hoop through which projects must jump once prepared.
According to the Guideline of the World Bank, the following questions will be an-
swered as a result of this report.
a) What is the objective of the project?
b) What is the project’s social, environmental and economic impact?
c) Is the project worthwhile?
d) Is this a risky project?
Most of these questions must be answered during a wide discussion process of the in-
volved stakeholders. This analysis aims to provide a basis for such a discussion and sets
values and data which help to argument in one or another direction.
The general approach is the comparison between a Do-Nothing Scenario, which is de-
fined as the current transport distribution in which no railway system is existent and
most of the private and public transport will be done as described in chapter 2. The
overall transport volume will increase dramatically due to increasing population expec-
tations and will cause significant problems in the catchment area and its surroundings. It
can be expected that neither the existing public transport systems nor the existing and
planned traffic infrastructure will have sufficient capability to satisfy the upcoming pas-
senger transport demand. Changes between the modes are quite moderate and it can be
expected that especially the Matatu system will reach the limits of its capacity.
The case which is compared to the Do-Nothing Scenario is the railway project as de-
scribed in this study. Costs are clearly defined as described in chapter 8. The expected
economic benefits are listed in this chapter and are related to the costs caused by the
project. Most of the benefits are generated by shifted passenger trips from other
transport modes to the railway system as described in chapter 2. These benefits usually
base on standard unit values connected to the quantity of shifted trips.
Western European, Asian and Northern American countries have proven values for the
economic evaluation of transport projects. In Kenya, and in most of the comparable Af-
rican countries, these data do not exist and no scientific research has been made in re-
cent times. Accordingly, no specific local values for economic evaluations are on hand.
In this case values of other countries were adopted or assumptions were made to gener-
ate a reliable analysis.
146
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
9.2 Methodology
The methodology of this appraisal follows common structures of economic evaluations
like the World Bank or the European Union uses for transport projects. The following
figure shows the basic structure of the methodology. This appraisal follows this struc-
ture where applicable and differs where no data or values were available.
Source: A framework for the economic evaluation of transport projects, World Bank 2005
Figure 9.1: Transport Economic Appraisal Structure
In accordance with generally accepted economic principles, this study applies the meth-
odology of a Socio-Economic Cost Benefit Analysis (CBA) for the Economic Analysis.
The CBA looks at the broad effects of a project to society as a whole, hence encompass-
ing more than the financial picture.
The CBA compares
Do-nothing scenario (transport development without implementing a commuter rail
system) and
147
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
148
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
149
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
150
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
151
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
costs are the lowest (using therefore a conservative approach). These unit values, pre-
sented in the following table, are constant over the study period.
Table 9.4: Vehicle operating costs for road traffic
Car Matatu Bus
Cost for roughness
0.329 0.345 0.728
IRI: 6; USD)
RUC Component (con-
0.313 0.318 0.635
sumables) in USD
Total KES per km 54.76 56.55 116.27
Total USD per km 0.642 0.663 1.363
Source: International Roughness Index
For motorbikes and BodaBoda 30% of the VOC for cars were assumed. For walking
and bicycle traffic no VOC were calculated.
Multiplying the above listed cost units with the saved vehicle kilometres results in the
following values:
Table 9.5: Saved VOC Costs
2018 2021 2030 2045
Saved trips (all modes) 9’164 16’872 234’289 594’383
Saved vehicle km (relevant modes) 102’969 189’526 2’629’701 6’662’976
VOC benefits mn KES 5.77 10.62 146.85 370.24
VOC benefits mn USD 0.067 0.12 1.72 4.33
152
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
9.5.4 Externalities
Externalities include noise, air pollution, and climate change, which can be saved by
shifting passengers to the railway system.
For the With-Project Case, the total rail passenger km were calculated. For the same
traffic, the corresponding amount of road passenger km has been calculated.
The Consultant has then used the results of the Infras-IWW study dated 2004 in order to
assess the cost of externalities (air pollution, climate change and noise) per passenger
km and ton km on road and rail.
Table 9.6: Infras-IWW unit costs – Euro for base year 2000
Average costs in
2000 - EA 17 Average cost (EUR / 1000 pkm)
Road Rail
Car Bus
Noise 5.2 1.3 3.9
Air pollution 12.7 20.7 6.9
Climate change 17.6 8.3 6.2
Total EA 17 35.5 30.3 17
Source: Infras-IWW study dated 2004
The above table shows the unit costs defined by Infras-IWW for the EA 17 (EU 15 plus
Switzerland and Norway) for the base year 2000.
These unit costs have been transferred to Kenyan values on the basis of the GDP/capita
expressed in USD. This transfer has been made by calculating a transfer coefficient
which adopts European GDP to Kenyan GDP in 2000 and increases the coefficient to
the year 2012 in the same relation like the GDP growth..
Table 9.7: Transfer coefficients based on GDP/capita
Population transfer coeffi-
GDP (mn USD) USD/capita
(1’000) cient
EA 17 (EU 15 +
Switzerland + Nor-
way) 2000 8’645’360 389’634 22’188
Kenya 2000 12’000 31’254 384 0.018
Kenya 2012 37’229 43’178 862 0.038
Source: AMECO, Opendata
The total value of externalities for rail passenger km as well as for road passenger km
has been calculated and their difference is the savings of externalities linked with the
avoidance of road traffic.
153
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
154
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The following table shows the number of yearly saved accidents by groups for selected
years and the total savings in USD.
Table 9.11: Accident reduction savings
2018 2021 2030 2045
9.5.6 Revenues
Revenues are calculated by using the yearly passenger kilometre (paxkm) of the railway
users. Fares are set at 3 KES per paxkm.
A reduction has been made for passengers who are usually free of charge like children
and pensioners (5%) and for people who usually pay a reduced price (30% discount)
like students (5%).
Fares are considered without taxes.
155
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Additional benefits which are listed in chapter 9.2 will not be monetised and must be
evaluated in a separate stakeholder discussion.
Accidents savings 0 0 0 1'384 1'441 1'497 2'647 3'077 3'679 4'034 4'548 4'733 5'228 5'591 5'789 5'986
Externalities 0 0 0 30 31 32 55 75 164 226 460 478 592 701 725 749
Job Creation 0 0 0 480 480 480 612 932 944 996 1'052 1'052 1'108 1'128 1'128 1'128
Revenues 0 0 0 140 157 174 655 1'008 1'509 2'148 2'472 3'058 3'503 3'844 4'152 4'472
Residual value 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Mombasa Commuter Railways Feasibility Study
total costs -2'033 -5'946 -7'296 -10'044 -10'044 -9'934 -8'836 -9'966 -10'216 -10'498 -14'329 -15'595 -12'335 -13'357 -11'798 -12'725
total effects 0 0 0 2'040 2'114 2'188 3'981 5'107 6'330 7'451 8'627 9'419 10'554 11'411 11'945 12'490
Table 9.12: Economic analysis – details
Cash flow -2'033 -5'946 -7'296 -8'003 -7'929 -7'746 -4'855 -4'859 -3'886 -3'047 -5'702 -6'176 -1'782 -1'946 147 -234
Economic analysis 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045
Investments costs -3'226 -2'464 -2'295 -3'081 -1'961 -1'921 -1'658 -4'522 -725 -3'272 -4'337 -3'426 -3'028 -6'409 -3'622
Operation costs -10'152 -10'439 -10'737 -11'046 -11'367 -11'701 -12'047 -12'408 -12'782 -13'171 -13'575 -13'994 -14'431 -14'884 -15'355
Road traffic avoided 228 237 245 254 263 273 263 293 304 314 325 336 348 359 370
Time savings 15 15 16 16 17 17 18 18 19 20 20 21 22 22 23
Accidents savings 6'248 6'479 6'710 6'941 7'172 7'435 7'699 7'962 8'226 8'489 8'783 9'076 9'369 9'663 9'956
Externalities 1'160 1'202 1'244 1'286 1'328 1'376 1'424 1'471 1'519 1'566 1'619 1'672 1'724 1'777 1'829
Job Creation 1'304 1'304 1'304 1'304 1'304 1'304 1'304 1'304 1'304 1'304 1'304 1'304 1'304 1'304 1'304
Revenues 5'698 6'138 6'597 7'070 7'560 8'106 8'672 9'254 9'856 10'478 11'158 11'861 12'583 13'328 14'092
Residual value 0 0 0 0 0 0 0 0 0 0 0 0 0 0 104'609
total costs -13'378 -12'902 -13'032 -14'126 -13'328 -13'622 -13'706 -16'929 -13'507 -16'443 -17'912 -17'420 -17'459 -21'293 -18'977
total effects 14'653 15'374 16'115 16'871 17'644 18'511 19'379 20'302 21'228 22'171 23'209 24'270 25'350 26'453 132'183
Cash flow 1'274 2'472 3'084 2'744 4'316 4'889 5'673 3'373 7'721 5'728 5'297 6'849 7'891 5'159 113'205
156
190 591.10
190 591.10
157
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Following table shows the share of effects caused by the project. Biggest effects result
from saved accident costs and the residual value which gives the asset value at the end
of the project.
Table 9.14: Share of effects in total present value
Present values Share of Benefits
Savings of road VOC 5'254 1.0%
Time savings 333 0.1%
Accidents savings 169'837 33.5%
Externalities 26'515 5.2%
Job Creation 31'080 6.1%
Revenues 169'742 33.5%
Residual value 104'609 20.6%
total 507'369 100.0%
158
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
159
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The following table shows the share of effects caused by the project. Most significant
effects result from the revenue incomes and from the residual value which is the asset
value at the end of the project in 2045.
Table 9.18: Share of effects of the Reduced Projekt in total present value
Present values
Share of Benefits
(mn KES)
Savings of road VOC 5'200 1.1%
Time savings 330 0.1%
Accidents savings 165'982 35.0%
Externalities 26'241 5.5%
Job Creation 27'016 5.7%
Revenues 168'021 35.5%
Residual value 81'094 17.1%
total 473'884 100.0%
Accidents savings 0 0 0 1'384 1'441 1'497 2'647 3'077 3'679 4'034 4'548 4'733 5'228 5'423 5'618 5'813
Externalities 0 0 0 30 31 32 55 75 164 226 460 478 592 693 717 741
Job Creation 0 0 0 480 480 480 612 932 944 996 1'052 1'052 1'052 1'052 1'052 1'052
Revenues 0 0 0 140 156 173 655 1'008 1'508 2'146 2'471 3'058 3'504 3'798 4'104 4'421
Residual value 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Mombasa Commuter Railways Feasibility Study
total costs -2'033 -5'946 -7'296 -10'044 -10'044 -9'934 -8'836 -9'966 -10'216 -8'185 -9'065 -9'606 -6'346 -8'960 -8'143 -9'838
total effects 0 0 0 2'040 2'113 2'187 3'981 5'107 6'328 7'449 8'626 9'419 10'499 11'110 11'639 12'181
Cash flow -2'033 -5'946 -7'296 -8'003 -7'930 -7'747 -4'856 -4'859 -3'888 -736 -439 -186 4'153 2'149 3'496 2'343
Economic analysis 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045
Investments costs -3'226 -2'464 -2'295 -3'081 -1'961 -1'921 -1'658 -4'522 -725 -3'272 -4'337 -3'426 -3'028 -6'409 -3'256
Operation costs -7'842 -8'117 -8'403 -8'700 -9'009 -9'330 -9'665 -10'012 -10'374 -10'750 -11'142 -11'549 -11'972 -12'413 -12'871
Road traffic avoided 225 234 242 251 260 270 260 290 301 311 322 333 345 355 366
Time savings 15 15 16 16 17 17 18 18 19 20 20 21 22 22 23
Accidents savings 6'041 6'269 6'498 6'726 6'955 7'216 7'477 7'739 8'000 8'261 8'553 8'844 9'136 9'427 9'719
Externalities 1'145 1'187 1'228 1'270 1'312 1'360 1'407 1'454 1'502 1'549 1'602 1'655 1'707 1'760 1'812
Job Creation 1'052 1'052 1'052 1'052 1'052 1'052 1'052 1'052 1'052 1'052 1'052 1'052 1'052 1'052 1'052
Revenues 5'622 6'060 6'513 6'983 7'469 8'010 8'571 9'150 9'747 10'364 11'041 11'739 12'457 13'197 13'958
Residual value 0 0 0 0 0 0 0 0 0 0 0 0 0 0 81'094
total costs -11'068 -10'580 -10'698 -11'780 -10'970 -11'252 -11'323 -14'534 -11'100 -14'022 -15'479 -14'975 -15'001 -18'822 -16'127
total effects 14'100 14'817 15'549 16'298 17'064 17'925 18'785 19'702 20'621 21'556 22'589 23'643 24'718 25'813 108'024
Table 9.19: Economic analysis of the reduced projekt – details (all values in mn KES)
Cash flow 3'032 4'236 4'851 4'518 6'095 6'673 7'462 5'168 9'521 7'534 7'110 8'668 9'718 6'992 91'897
160
190 591.10
190 591.10
161
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
10 FINANCIAL ASESSMENT
10.1 Introduction
The illustration below shows the interaction and differences between these two apprais-
al tools, and the respective focus of Public and Private sectors (if any):
Socio-economic, environmen-
tal and other external effects Inv, Ops Perspective
Public
Private and Financial
perspective
costs and revenues
Therefore, when performing the financial appraisal, only direct monetary costs and rev-
enues (i.e. the operating, investment and financial cash flows) are taken into account to
test the efficiency of use of capital invested and identify an operating gap or surplus,
expressed in the form of a financial Internal Rate of Return (fIRR). Additionally, the fi-
nancial appraisal can be used to test whether the project can sustain its own external fi-
nancing and if not, the equivalent Funding Gap existing and that needs to be covered by
the beneficiaries of the project (being the recipient of the overall economic benefits).
162
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
163
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Taxes
Financing Costs
Revenue from sale of
Financing Gap tickets
One of the main objective in performing the financial appraisal of the Mombasa Com-
muter Rail project is therefore to 1- identify the financing gap and 2-establish the fund-
ing gap/surplus and 3- test the efficiency of the investment by calculating the IRR. Us-
ing the financial model specifically design for the project (see chapter 3), the cash flows
are forecasted on the overall project lifetime, assuming a minimum of 30 years mini-
mum for each section.
164
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
c. Financing Cash Flow: the financing cash flow of the project is the aggregation
of any financing sources (loans, equity, etc.) used to cover the investment costs,
as well as all associated financing costs such interests and fees; the financing
cash flow also include the repayment of these source, either in the form or a debt
amortisation of redemption of any capital to investors (dividends or bonds in the
case of private capital sources).
The aggregation of the operational and investment cash flow is the Free Cash Flow (also
referred to as Project Cash Flow). This Free Cash Flow provide important information
to establish the financial viability of the project, namely:
Identifies the financing gap generated from the investment period;
Indicates whether the project is operationally viable (i.e. if the revenue is sufficient to
cover the cost);
Serves as the base to calculate the Project IRR (or fIRR).
The third layer, the financing cash flow, illustrates the costs and amount of external fi-
nancing injected into and repaid by the project and whether the operational surplus is
sufficient to sustain this external financing.
2/ (-) investments CF
165
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
8
www.fast-standard.org. FAST is an industry recognised, license-free modelling convention designed to standardise the construction of spreadsheet models in a
transparent and comprehensive manner, using a set of structural and visual conventions enhancing robustness and reliability.
166
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Dashboard
167
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The Mombasa Commuter Rail system operating entity is subject to a 30% corporate
tax, and allowed to carry losses forward for a maximum of 5 years. Taxes are as-
sumed to be paid the same year they are due.9
The fixed assets are presented on the Balance Sheet at Book Value, assuming a Line-
ar depreciation starting with the respective operating periods, using depreciation
rates specific to each asset class on basis of the economic lifetimes indicated in
Chapter 10.3.4.1 hereafter.
Net Present Value(s) are based on an annual Discount Rate of 5%.
Figures are presented in Millions KES(otherwise specified). Currency exchange rate
from USD to KES is 1 USD = 85 KES.
The model timeline is an annual resolution, and values stated at End of Period (i.e.
each columns is a period of 12 calendar months).
Inflation rates are as follows, with reference date as of 1/1/2014 (except ticket price
which is escalated from 2018 onwards):
CPI (Consumer Price Index) 2.5%, annual
Salary costs inflation CPI + 0.5%, annual
Ticket Price escalation 3% every 24 months
Working Capital: Creditors payment term of 45 days and Debtor term of 0 days.
9
Ignoring the usual delay in time between calculation of Taxes on basis of previous year results and actual payment, often
occurring within the following financial year. This convention is chosen for an more accurate calculation of ratios and
cash flows.
168
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
169
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
period, the total consolidated investments for the 6 corridors (including additional in-
vestments during the operating phase to meet forecasted increases in service level and
replacement of materials) in Nominal terms is KES 214,446 Mln (KES 214,5 Bln).
With regards to Rolling Stock investments, the unit cost for a 4 cars train set is USD 9,2
Mln (KES 782 Mln). The investment is calculated per corridor rather than sections, as
each corridors has an incremental investment in rolling stock following the combination
of volume growth and implementation of extensions (second and third sections for cor-
ridors 1, 2 and 3) and corresponding to an increase of units in operation to maintain
scheduled services. The implementation of rolling stock/train sets, rolled out in the peri-
od 2017 to 2045 in line with expected traffic volume increase is presented in Annex 7.
Similar to the construction costs, rolling stock investment costs are calculated in real
terms and corrected an annual CPI indexation of 2.5% p.a. is applied on actual spending
(as from 1/Jan/2014). Total investment in rolling stock amounts to KES 132 Bln in
Nominal costs until 2045.
170
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Table 10.2: Monthly Staff Costs and crew mixes- Maintenance Facilities
Monthly
Workshop + Workshop exten- Infrastructure
Costs
Depot sion service point
(KES)
workshop manager 400,000 - 1 -
manager/ engineer 200,000 3 2 1
office staff 60,000 3 2 1
technician 60,000 10 10 5
security staff 24,000 6 2 4
Total (Monthly) Cost 1,524,000 1,568,000 656,000
Table 10.3: Monthly Staff Costs and crew mixes- Rolling Stock(Train operations)
Monthly Crew per train
Costs (KES) (FTE)
driver 100,000 2.5
conductor 70,000 2.5
attendant 70,000 2.5
security 50,000 2.5
Total (Monthly) Cost 725,000
171
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
172
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
173
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
undertaken with commercial debt (with full payment guaranteed by the Au-
thority);
Combined infra and train operations concessions, including full traffic risk, for
high density connections between International airports and city centres. Exam-
ple are Dedicated rail services in Oslo or Stockholm.
In the table below we discuss the possibilities and downsides of alternative financing
mechanisms:
Table 10.4: Financing instruments for Mombasa Commuter Rail - review of opportunities
Type Public Instruments Private Instruments
Governmental / sovereign loans contracted by
KRC with a State Guarantee or directly by the
GoK, then allocated to Mombasa rail system im-
plementation. These includes ODA loan or similar, Any type of commercial debt, equity or bond
Nature
guarantees and credit-enhancement products. placement
Also could take the form of debt co-financing by
an IFI (e.g. World bank), common in infrastructure
financing.
- Financing primarily the acquisition of Rolling
Stock. Private debt for rail infrastructure financ-
ing is highly unlikely (risk profile)
Should be used in priority to finance the construc-
Use - Could be considered for construction of stations,
tion of the rail systems and buildings
should the traffic is materialising in the future,
raising the potential commercial value of build-
ing along the system
- Cheap costs of financing; - Private financing brings more stringent financial
- Ability to raise more substantial amounts under management of projects and operations, im-
a single agreement (in case of ODA financing) proving the long term viability of the system
Benefits
- Would enable long grace period in line with long - Create additional incentives to stimulate com-
construction timeframe, and long maturities in plementary commercial value to pay for the sys-
line with such project’s common term. tem
- Private finance is substantially more expensive
than ODA-type of financing, due to the high risk
ODA financing is often tied, bringing limita- profile of the project.
Downsides/ tions/rigidity in the procurement and missing on - Maturity is comparatively short, requiring ex-
Challenges most efficient technical solutions and life-cycle pensive refinancing during the project.
synergies - At regional level, as well as for rail infrastructure
in general, private capital is seldom available to
undertake such large projects.
A Public financing source is the most likely to be
possible to finance the construction of the Mom- Private financing products could be considered to
basa Commuter Rail system. Rail infrastructure is procure Rolling Stock, such as leasing solutions
on rare instances financed with private capital on PPP-based procurement including a “F” com-
Conclusions
(only few examples in Europe), and mainly for ponent. In any case, State guarantees will be criti-
commercially viable operations like High speed cal to ensure bankability of any private financing
trains or International Airports to City centres con- instruments and remove demand risk.
nections
174
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
175
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
176
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
10.4.3.1 Assumptions
In consideration of the various instruments available, the economic nature of the Mom-
basa Commuter Rail system, shear size of the necessary investment and prospective
planning for implementation, the financial appraisal is structured around the following
financing scheme:
1. An initial Public subsidy of KES 10 Bln, estimated to be available from the KES
22 Bln already allocated by the State in the current budget and complementary
grants from the World Bank10, and to be used in priority of any external financ-
ing to initiate the implementation of the system. This subsidy is primarily allo-
cated to project development and the capital investment in infrastructure.
2. A recurring annual subsidy of totalling KES 10 Bln on the period 2015-2017
(respectively KES 5 Bn, KES 2,5 Bln and KES 2,5 Bln), based on share of fore-
casted funds generated by the newly introduced Rail Development Levy (RDL)
reserved for the Mombasa Commuter Rail. This is based on an annual 8%
growth of imports on which the RDL is computed (being 1.5% of value of im-
ports)
10
To finance the detailed design of the first section as confirmed by KRC.
177
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
10.4.3.3 Results: level of financing required for Mombasa Commuter Rail system imple-
mentation
On basis of a-the capital investments and implementation planning, b-the estimate of
subsidies that can be allocated to the project and c-a generic ODA-type of loan and
terms described above, the following Financing Gap is calculated:
Table 10.5: Financing Gap and ODA Loan disbursement for construction financing
in Billion KES 2017 2018 2019 2020 2021 2022 2023 2024
Total Disbursement 5.5 12.6 13.4 19.1 19.0 19.4 15.4 21.9
of which Annual Interest 0.2 0.5 0.9 1.5 2.1 2.7 3.1
Repayments - - - - - - - -
178
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
11
The grace period is the period (starting at first availability of funds) in which the lender does not require repayment of
the principal but is still entitled interests over the total sum disbursed under the loan.
179
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
12
A project IRR can not be computed on an aggregated set of negative cash flow. N/A refers to a case where an IRR is
not mathematically relevant and can not be computed.
180
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
13
Average over of operations period of the system from completion of the first corridor until the year 2045.
14
A project IRR can not be computed on an aggregated set of negative cash flow. N/A refers to a case where an IRR is
not mathematically relevant and can not be computed.
181
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
The reduced investment scenario as a significant impact on the funding gaps consider-
ing:
The required capital investment is reduced by 34% for infrastructure and track and
by 7.5% for rolling stock (on the period until 2045)
While the equivalent reduction in revenue is only -1%, due to the relatively lower
ridership volumes compared to corridors 1 to 4.
These 2 corridors also being realised at later stage, not implementing them results in
shortening the financing period, which adds to the cost saving potential for the KRC in
this scenario.
10.5.4 Results
Results of the sensitivity analysis are presented in the table below:
Table 10.8: Sensitivtiy Analysis Results
OpEx
CapEx CapEx RS OpEx - OpEx - OpEx Vol - Vol Cons +
in Billion KES RS +20 RS -
-20 +20 -20% 20 20 RS +20 20 +20 6m
20
Project IRR n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a
Project NPV (Excl.
(229.0) (272.3) (239.3) (262.0) (244.6) (256.7) (221.7) (279.7) (268.7) (232.7) (248.8)
Subsidies)
Project NPV (Incl.
(124.0) (167.6) (134.4) (157.2) (145.8) (145.8) (145.8) (145.8) (145.8) (145.8) (144.9)
Subsidies)
Funding Gap (until
838.2 1,037.6 889.1 986.7 919.3 956.5 848.6 1,027.2 997.0 878.8 935.6
2060)
Funding Gap (dis-
318.6 399.0 341.3 376.3 352.7 364.9 329.8 387.8 376.8 340.8 356.2
counted @ 5 %)
External Financing
214.0 298.6 241.5 271.1 256.3 256.3 256.3 256.3 256.3 256.3 256.1
Required
Operating Subsidy
Required (to break- 245.7 245.4 245.6 245.5 227.0 264.2 156.2 334.9 304.6 186.5 244.1
even)
Operating Subsidy
86.5 86.3 86.4 86.3 80.3 92.4 57.3 115.3 104.3 68.3 85.4
Required (NPV)
182
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
OpEx
CapEx CapEx RS OpEx - OpEx - OpEx Vol - Vol Cons +
in Billion KES RS +20 RS -
-20 +20 -20% 20 20 RS +20 20 +20 6m
20
Average Annual
8.5 8.5 8.5 8.5 7.8 9.1 5.4 11.5 10.5 6.4 8.4
Ops subsidy
183
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Total FA Capital Expenditures CF Mln KES (169,665) - - (660) (1,902) (6,602) (9,598) (12,470) (12,812) (13,636) (11,876) (13,491) (9,829) (11,743) (15,976) (16,670) (12,779) (7,342) (6,063) (6,215)
Total Rolling Stock Nominal Costs CF Mln KES (132,725) - - - - - (6,737) - - (4,534) (5,577) (3,811) (2,930) (7,007) - (5,259) (15,092) - - (11,609)
Asset Class-Land&Infra Reinvestment, Nominal CF Mln KES - - - - - - - - - - - - - - - - - - - -
Asset Class-Power Supply & Ancillaries Reinvestment, Nominal CF Mln KES - - - - - - - - - - - - - - - - - - - -
Asset Class-Superstructures&Buildings Reinvestment, Nominal CF Mln KES - - - - - - - - - - - - - - - - - - - -
Asset Class-Rolling Stock Reinvestment, Nominal CF Mln KES - - - - - - - - - - - - - - - - - - - -
Asset Class-Signalling&Communication Reinvestment, Nominal CF Mln KES (2,384) - - - - - - - - - - - - - - - - - - -
Asset Class-Development Cos ts Reinvestment, Nominal CF Mln KES - - - - - - - - - - - - - - - - - - - -
Investment During Operational Phase Nominal CF Mln KES (42,397) - - - - - - - - - - - - - - - - - - -
Investment Subsidy Rec eived CF Mln KES 20,000 - - 10,000 7,500 2,500 - - - - - - - - - - - - - -
Free Cash Flow Mln KES (327,171) - 9,340 5,598 (4,102) (16,335) (12,470) (12,812) (18,171) (17,453) (17,302) (12,759) (18,751) (15,976) (21,929) (27,871) (7,342) (6,063) (17,824)
ODA Senior Debt Interest Paid CF Mln KES (132,497) - - - - - - (165) (544) (945) (1,518) (2,087) (2,669) (3,132) (3,788) (4,381) (5,171) (6,162) (6,567) (6,946)
ODA Senior Debt Linear Repay ment CF Mln KES (256,296) - - - - - - - - - - - - - - - - - - -
Cash Flow Available for Subordinated Debt Mln KES (459,668) - 9,340 5,598 (4,102) (10,836) (0) 0 0 0 (0) - 0 0 0 0 (0) - (0)
Cash Balance BEG Mln KES - - 9,340 14,938 10,836 - (0) 0 0 0 (0) (0) (0) 0 0 0 (0) (0)
Plus:
Net Cas h Movement over the Period - Mln KES (459,668) - - 9,340 5,598 (4,102) (10,836) (0) 0 0 0 (0) - 0 0 0 0 (0) - (0)
Cash Balance Mln KES - 9,340 14,938 10,836 - (0) 0 0 0 (0) (0) (0) 0 0 0 (0) (0) (0)
ODA Senior Debt Interest Paid CF Mln KES (132,497) - (7,689) (7,433) (7,176) (6,920) (6,664) (6,407) (6,151) (5,895) (5,639) (5,382) (5,126) (4,870) (4,613) (4,357) (4,101)
ODA Senior Debt Linear Repayment CF Mln KES (256,296) - (8,543) (8,543) (8,543) (8,543) (8,543) (8,543) (8,543) (8,543) (8,543) (8,543) (8,543) (8,543) (8,543) (8,543) (8,543)
Cash Flow Ava ila ble for Subordinate d De bt Mln KES (459,668) (23,479) (21,615) (24,759) (19,262) (19,703) (22,019) (22,477) (19,541) (19,981) (23,134) (25,150) (18,694) (25,203) (27,335) (19,166)
Cash Balance BEG Mln KES (0) (23,479) (45,094) (69,853) (89,115) (108,818) (130,837) (153,314) (172,856) (192,837) (215,971) (241,121) (259,816) (285,019) (312,354)
Plus:
Net Cash Movement over the Period - Mln KES (459,668) - (23,479) (21,615) (24,759) (19,262) (19,703) (22,019) (22,477) (19,541) (19,981) (23,134) (25,150) (18,694) (25,203) (27,335) (19,166)
Cash Balance Mln KES (23,479) (45,094) (69,853) (89,115) (108,818) (130,837) (153,314) (172,856) (192,837) (215,971) (241,121) (259,816) (285,019) (312,354) (331,520)
184
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Table 11.3: Large bridges of the Corridor 4: Likoni Ferry – Junda – Bamburi
Name Structure Mileage from - to Length Costs (mn KES)
Junda Creek Bridge km 6.4 km 7.3 900 m 7’344
The consultant recommends to create an in-depth feasibility study for these bridge struc-
tures to verify the feasibility and the estimated costs as well as for limitation of the risks
before detailed planning is started.
185
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
11.2 Environmental and social impact
The development of the Mombasa commuter railway is expected to have an overall pos-
itive impact on the environment, as railway transport is a sustainable alternative to in-
creasing motorised vehicle traffic. However, the impacts of the project on many differ-
ent aspects of the physical, natural and socio-economic environment will be considera-
ble, due to:
The extensive scale of the area traversed by the railway corridors.
The large variety of land uses it crosses, including densely inhabited urban areas, a
very high number of small parcels of land, and areas of high biodiversity.
The Consultant therefore recommends:
Carrying out a full ESIA and RAP in the next project stage
Making the Preliminary ESIA and especially the planning phase ESMP available
to the detailed design engineers: the need for and/or extent of many mitigation
measures recommended for the construction and operation phases can be reduced
or made redundant by applying the recommended planning phase measures.
A strong focus on continued stakeholder involvement throughout the next project
phases.
186
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
It is therefore recommended to conduct further design studies and traffic demand inves-
tigations (e.g. including freight traffic demand) for the purpose of obtaining more pre-
cise cost and benefit assumptions.
187
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
risk on experienced international private operator(s), except the key Demand
risk which by nature can only be supported by KRC or the GoK in recognition
of the substantial (indirect) economic benefits gained from the project’s imple-
mentation (being a public service). Such involvement may include specific fi-
nancing instruments for parts of the project, particularly an integrated DBFM(O)
concession for rolling stock and train operations, with full demand risk support-
ed by KRC/GoK. It is strongly recommended to carry out further detailed Value
for Money assessment studies and analysis, with the realisation of a PPC and a
PSC, to confirm the level of benefits of private concession of operations and jus-
tify further PPP-based life-cycle procurement and financing package.
7. Considering the nature of the project, public financing sources in the form of
ODA-type of lending provided by Sovereign partners is the most likely route
(with or without complementary support from IFIs such as the World Bank and
the African Development Bank), which by nature provides for very long term
maturities, large facilities to undertake project of this size and low long term in-
terest rates. Meanwhile, it is important to highlight that ODA financing is often
tied to prescribed procurement rules from the lending State which in itself may
impact the overall cost and calendar of procuring the project.
188
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
12.1 Introduction
The Final Report brings an update of the risk analysis presented in the Inception Report
with the findings of the study. It concentrates on those items which are essential for the
future realisation of the project.
12.2 General
Although KRC requires risk assessments throughout the Project, we would like to un-
derline that it is not our intention to merely reduce this to a subject with a “negative per-
ception”. Clearly, we wish to address it as a “Chances and Risks” issue, because all of
us want to work out the Project as a “positive” one.
In our philosophy, chances must be taken and risk must be controlled; very often, how-
ever we meet the primary focus on risk mitigation, with the identification of chances be-
ing subordinate to it.
In the following, Sections 12.3 through 12.8 refer to external aspects that would affect
the implementation and operation of the Project.
The following tables indicate the understanding of each risk as well as measures to be
taken for its control and mitigation. The key issue is the on-time identification of the
risks and taking of preventive measures to avoid them. In any case for all the risks that
are identified corrective measures should also be foreseen.
189
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
190
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
191
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
12.6 Financial Risks
192
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
193
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
12.8 Operational Risks
194
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
13 ANNEXES
195
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Page Corridor
25/38 Corridor 3: Mombasa - Mazeras - Voi 9/9
26/38 Corridor 5: Mazeras - Kaloleni - Takaungu 2/3
27/38 Corridor 5: Mazeras - Kaloleni - Takaungu 3/3
28/38 Corridor 6: Malindi - Lamu 2/12
29/38 Corridor 6: Malindi - Lamu 3/12
30/38 Corridor 6: Malindi - Lamu 4/12
31/38 Corridor 6: Malindi - Lamu 5/12
32/38 Corridor 6: Malindi - Lamu 6/12
33/38 Corridor 6: Malindi - Lamu 7/12
34/38 Corridor 6: Malindi - Lamu 8/12
35/38 Corridor 6: Malindi - Lamu 9/12
36/38 Corridor 6: Malindi - Lamu 10/12
37/38 Corridor 6: Malindi - Lamu 11/12
38/38 Corridor 6: Malindi - Lamu 12/12
196
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
13.4 Annex 4: Preliminary Environmental and Social Impact Assessment
197
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Page Corridor
Corridor Port Reitz Alternative 2/3
Corridor Mombasa - Airport - Ramisi 3/7
28/32
Corridor Port Reitz Alternative 3/3
29/32 Corridor Mombasa - Airport - Ramisi 4/7
30/32 Corridor Mombasa - Airport - Ramisi 5/7
31/32 Corridor Mombasa - Airport - Ramisi 6/7
32/32 Corridor Mombasa - Airport - Ramisi 7/7
198
Kenya Railways Corporation KRC
Mombasa Commuter Railways Feasibility Study
KRC/PLM/40/2011
Final Report
Classification
Drawing/Reg./Serial No.
External distribution
Internal distribution
Contribution
Responsible BU
Revisions:
Original
Date of document 28.05.2014
Author/position/signature Christian Bergerhoff, Project Manager
Date of control
Checked by/position/signature Johan Dehli, Senior Engineer
A
Date of document
Author/position/signature
Date of control
Checked by/position/signature
B
Date of document
Author/position/signature
Date of control
Checked by/position/signature