Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

ACLN - Issue #76

Architects and Engineers


A Look at Duty of Care, Causation and Contributory
Negligence
Bailey v Redebi Pty Ltd & Or, NSWSC, Santow J
Stewart Muirhead
Carter Newell
Brisbane

T HE RECENT DECISION OF BAILEY ~ Did the architect undertake


v Redebi Pty Ltd & Ors (1999) engineering design services, or otherwise
NSWSC 918 considered a number of fail in its supervisory role so that both
issues commonly found in negligence cases architect and engineer should share
against building professionals who work responsibility?
together on a project. What is the extent of
the architect's duty of care? Where does that The engineer conceded that it was negli-
responsibility end and the structural engi- gent; therefore, the court's attention was
neer's duty begin? concerned as to whether the architect should
bear, or share, any liability. Generally, an
In May 1989, Mr Bailey retained an ar- architect does not undertake a duty of care
chitect to prepare plans for a development to a client to include an assumed responsi-
which, for financial reasons was to be built bility for specialized aspects of engineering
in two stages. The architect engaged a design, in the absence of an express under-
builder and structural engineer and provided taking. The onus of establishing an extended
them with plans for the fIrst stage of the duty of care to embrace additional responsi-
project. Building began in 1990 and 20 bility is placed on Mr Bailey.
weeks later, the fIrst stage was completed.
Unbeknown to Mr Bailey, a western wall The architect argued that engineering
had been constructed as an internal wall matters were outside the scope of their duty
(awaiting the second stage), whereas it to Mr Bailey. The court found that the archi-
should have been constructed as an external tects held themselves out to be design and
wall. building consultants, and they also failed to
ensure that the engineer understood their
By 1992 a dispute arose between Mr instructions regarding the western wall.
Bailey and the builder. Mr Bailey obtained a
building consultancy report (BCS report) Here, the architect's duty was capable of
which raised concerns about the wall and arising incrementally by embracing the ad-
recommended that a structural engineer ex- ditional responsibilities such as supervising
amine it. A structural engineer prepared the engineering design team. In this regard,
three reports between July 1992 and the court adopted the High Court's treat-
December 1992, stating that the stability of ment of the scope of duty of care in Perre v
the western wall was inadequate. Recom- Apand Pty Ltd (1999) HCA 36.
mendations were put forward to resolve the
problem. The dispute was later settled at THE ARCHITECT'S DEFENCE
mediation.
~ Did Mr Bailey fail to act reasonably to
On November 1994, following high protect his interests by omitting to rectify
winds the western wall collapsed. Mr the defects which were detected in the BCS
Bailey sued the architect and structural reports?
engineer.
~ If so, does such a failure give rise to a
THE ARCHITECT VERSUS defence based on novus actus interveniens,
ENGINEER - WHO IS interrupting causation or rendering the
RESPONSIBLE? damage not a foreseeable consequence of
any negligence?
~ Who is liable to Mr Bailey in
~ Is there contributory negligence,
negligence by failing to design a structurally
sound building - the architect, engineer, or aggravation of damage or a failure to
both? mitigate a loss?
ACLN - Issue # 76

CAUSATION - HOW DID THE CONTRIBUTORY NEGLIGENCE


COLLAPSE COME ABOUT?
Contributory negligence is a plaintiffs
The collapse came about by the archi- failure to meet the standard of care to which
tect's failure to supervise and properly com- it is required to conform for its own protec-
municate with the engineer the need to have tion and which is a legally contributing
the western wall properly stabilized. In de- cause, together with the defendant's default,
termining causation, the court adopted the in bringing about its injuries. The type of
formula in Bennett v Minister for duty that a defendant owes to the plaintiff
Community Welfare (1992) 172 CLR 408, will affect the degree to which the plaintiff
causation being a question of fact which is may be said to be contributory negligent.
resolved as a matter of common sense. This The nature of the defendant's duty may pre-
is a two stage process: clude liability altogether, or reduce it.

~ Firstly, the court will look at the The architect contended that Mr Bailey
factors and external factors relevant to the failed to take proper care for his own prop-
architect which lead to the events giving rise erty's protection when he failed to carry out
to the damage claimed. This involves the remedial works recommended by the
identifying all material factors contributing BCS report. The BCS report highlighted the
to the loss and then determining which, if inadequacy of the western wall, and the ar-
any, was sufficient in themselves to cause chitect contended that a layman would have
the loss of the but for kind. understood the need to take remedial action.
Mr Bailey responded by arguing that firstly,
~ Secondly, which factors should be the advice in the report was not explicit, the
treated as making a difference. Here, the BCS report never stating that the building
court will assess the architect's conduct in would have collapsed, only secondly, had
its factual context with reference to the the BCS recommendations been carried out,
following considerations: the building still would have collapsed.

• the scope of the duty of care; The court analysed the expert evidence
in determining whether Mr Bailey had acted
• the foreseeability of damage, i.e. the reasonably. The court found that Mr Bailey
likelihood of the wall falling down; was unable to proceed with the second stage
of the project because he did not have the
• in cases of negligence by omission, funds to do so and therefore to assume Mr
whether performance of the duty Bailey could have rectified the western wall
would have averted the risk; was unwarranted.

• the remoteness of damage. The architect failed to establish that had


Mr Bailey adopted the recommendations in
The architect said that Mr Bailey's failure the BCS report, the building would still be
to carry out the recommendations in the BCS standing today. Further, the court found that
report was so unreasonable as to displace any the architect could not substantiate that it
causative effect over his acts or omissions. would have been reasonable for Mr Bailey
to carry out the proposed works as a result
The court determined that it was not pos- of the cost. In determining the reasonable-
sible to establish a novus actus interveniens ness of Mr Bailey's action, the court fol-
in this case unless the breach is shown to lowed McCauley v London Transport Ex-
have had no causative effect. ecutive. The advice and the prospects of
success of a proposed operation or treatment
The reason is that the injury would have must be clearly put to the plaintiff so that as
occurred (or the risk of it) even had the duty a reasonable man he would have been able
been performed properly. The architect to appreciate the position.
couldn't prove that the BCS report recom-
mendations would have worked. SHOULD MR BAILEY HAVE
MITIGATED HIS LOSS?
We compare this with the rationale in
Chapell v Hart, where the minority would The plaintiff s conduct was similarly
have concluded that a surgeon's failure to assessed for unreasonableness by reference
warn did not materially contribute to the of whether the plaintiffs omission to act,
plaintiff s injury. judged by reference to the defendant's duty
ACLN - Issue #76

of care and its extent, made the plaintiff the


effective cause of his or her own injuries.
The issue of Mr Bailey's reasonableness
turned on whether he failed after the loss to
take some precaution or step which was
reasonable to take in the light of the archi-
tect's wrong doing. This could not be made
out as the failures relied upon by the archi-
tect preceded that loss. The loss only oc-
curred when the wall collapsed.

The court held that the damage that oc-


curred could not be excluded under any
principles of remoteness or reasonable fore-
seeability. Mr Bailey had not aggravated the
damage, nor did he fail to act reasonably in
their mitigation. Both architect and engineer
were held liable to pay Mr Bailey damages
without any reduction in respect of con-
tributory negligence. [t]

Stewart Muirhead's article first appeared in


Carter Newell's Construction Notes bulletin
(September 2000). It is reprinted here with
permission.

You might also like