MFC FOR FIREWATER LINE PARTIAL REPLACEMENT PROJECT @ SHAYBAH NGL

WEEKLY EXECUTION PLAN (05/01/2021 – 05/07/2021)


DAILY
STATUS OF
DATE AREA LOCATION ACTIVITIES TO BE DONE RFI PIPE
THE ACTIVITY
REMARKS
METER
SEGMENT # 17 Asphalt cutting and breaking
UTILITY
SEGMENT # 16 Pipe Installation Yes YES
15
05/01/2021 RMU SEGMENT # 118 Pipe fabrication  
NGL SEGMENT # 37 Asphalt cutting and breaking
GAS TREAT SEGMENT # 106 Base Course Compaction Yes YES  
SEGMENT # 17 Asphalt cutting and breaking
UTILITY
SEGMENT # 16 Pipe Installation Yes YES  
05/02/2021 10
RMU SEGMENT # 49 Pipe Fabrication  
NGL SEGMENT # 37 Asphalt cutting and breaking  
SEGMENT # 16 Thrust block pouring Yes YES  
UTILITY
SEGMENT # 17 Asphalt cutting and breaking  
05/03/2021 10
RMU SEGMENT # 118 Pipe Installation YES
NGL SEGMENT # 37 Sand Backfilling and Compaction Yes YES  
SEGMENT # 16 Service test Yes YES
UTILITY
SEGMENT # 17 Hand Excavation
05/04/2021 10
RMU SEGMENT # 49 Pipe Installation YES
NGL SEGMENT # 37 Hand Excavation Yes
SEGMENT # 17 Hand Excavation
UTILITY
SEGMENT # 16 Stopaq wrapping Yes YES
11
05/05/2021 SEGMENT # 118 Thrust Block YES
RMU
SEGMENT # 49 Pipe installation YES
NGL SEGMENT # 37 Hand Excavation Yes  
SEGMENT # 17 Hand Excavation
UTILITY
SEGMENT # 16 Backfilling and shoring removal Yes
SEGMENT # 118 Service test need to start YES  
05/06/2021 RMU
SEGMENT # 49 Thrust block pouring YES  
NGL SEGMENT # 37 Hand Excavation
STATUS OF
DATE AREA LOCATION ACTIVITIES TO BE DONE RFI THE ACTIVITY
REMARKS

SEGMENT # 118 Service test Inspection Yes YES


RMU
SEGMEN # 49 Service test need to start Yes YES
05/07/2021 SEGMENT # 16 Backfilling and shoring removal Yes
UTILITY
SEGMENT # 17 Hand Excavation
NGL SEGMENT # 37 Hand Excavation and shoring Yes
Total Pipe
Total Activities 32 Activities Meter 56 meters
Planned
Completed Completed
activities pipe meter meters

Overall
Weekly
Weekly percentage
Percentag
Mousa Azaldian for activities Rama Reddy M
e for
Project Engineer Pipeline Project Co-ordinator