List of works executed from 28 Sep`21 to 13 Oct`21

Sr.# Description Status Discipline Approved IR In Progress IR

A Top-Roof
1 Water Proofing 100% Civil A -
2 OHWT water proofing 60% Civil A -
3 Roof concrete works 100% Civil A -

B Pent House
1 Grey work of upstand beam (EXTERNAL) 100% Civil A
2 Water Proofing (EXTERNAL) 100% Civil - Submitted
3 Duct work 100% MEP - In Progress
4 Copper Piping 100% MEP - Submitted
5 Flushing Tanks installation 3/6 completed MEP - In Progress
6 Core cutting 80% MEP A
7 N.G Piping 100% MEP - Submitted
8 Wiring power 100% MEP A

C 5th Floor
1 Cracks Repairing 100% Civil - In Progress
TOTAL 3 zones
* 2 zones completed - Submitted
2 Power wiring * 1 Remaining MEP
3 N.G Piping 1/3 zones completed MEP - In Progress
4 Duct work 25% MEP - In Progress
5 Blockwork Lift-wall 100% Civil A

D 4th Floor
1 Floor conduiting' 100% MEP A Zone 3 In Progress
2 CDP completed MEP A Zone 3 In Progress
3 Screeding 100% Civil Zone 1& 2 Approved Zone 3 In Progress
4 Cracks Repairing 100% Civil - In Progress
5 Blockwork Lift-wall 100% Civil A

E 3rd Floor
1 Floor conduiting' 1/3 zones completed MEP Zone 1/3 Submitted
2 CDP 1/3 zones completed MEP Zone 1/3 Submitted

F 2nd Floor
1 Screed 2/3 zones completed Civil Zone 2 IR Approved Zone 1 IR Submitted
2 Floor conduit 100% MEP Zone 2 & 1 IR Approved Zone 1 IR Submitted
3 CDP 100% MEP Zone 2 IR Approved Zone 1 IR Submitted

G 1st Floor
1 Screed last zone 100% Civil A -
2 CDP & conduiting 100% MEP A -

H Ground Floor
1 Reception screed 100% Civil A
2 Reception conduit works 100% MEP A -

I Basement
1 Grey work Walk-Way In-progress (20%) Civil - In Progress
2 Preparation for white wash (LIFTS) In-progress (20%) Civil - In Progress