Professional Documents
Culture Documents
Procurement Management
Procurement Management
Procurement Management
2. Which of the following is considered during the C. Procurement documents should be structured to
Procurement Planning Process? facilitate accurate and complete responses from
prospective sellers
A. Whether to procure
D. b and c
B. How to procure and how much to procure
E. all of the above
C. What and when to procure
6. Which of the following is a method for quantifying
D. b and c qualitative data in order to minimize the effect of
personal prejudice on source selection?
E. all of the above
A. Weighting system
B. Screening system
3. From a buyer's standpoint, which of the following is
true? C. Selecting system
C. Subcontractors are first considered during the A. Can often be found in procurement documents
Solicitation Process
B. Can be objective or subjective
D. none of the above
C. Used to rate or score proposals
4. Which of the following processes involves obtaining
information (bids and proposals) from prospective D. May be limited to purchase price if procurement
sellers? item is readily available from number of sources
B. Source Selection
8. Which of the following are inputs to the Source 12. In which of the following contract types is the
Selection Process? seller's profit limited?
D. a and b D. b and c
D. b or c D. $132,000
D. Firm-fixed-price contract C. $0
D. $5,000
16. Under what circumstances is it better for a 20. Which type of warranty is enacted if a service or
contractor to subcontract? product does not meet the level of quality specified in
the contract?
A. The subcontractor possesses special technical
and engineering skills that the contractor does not have A. Implied warranty of merchantability
E. all of them are appropriate 22. The purchasing cycle consists of all the following
elements except?
18. Which of the following are characteristics of a
purchase order? A. Defined need
E. General Requirements
C. Resource identification
A. Cost factors
36. __________ is a formal invitation to submit a price
B. Sales volume for goods and / or services as specified.
A. Assistance
B. Sealed bidding 37. Which contract type should be used by the owner
on a high risk project?
C. Competitive proposals
A. Cost plus percentage of cost
D. Acquisition
B. Cost plus incentive fee
E. Small purchases
C. Lump sum
A. Management
A. Contractor
43. A bilateral RFP is preferred to an invitation to bid
B. Owner when:
A. Sales forecast
B. Consumer price index 44. PMI suggests which of the following behaviors as
part of contract negotiations?
C. Production forecast
A. Probing, scratching, and small bites
D. Price forecast
B. Sniffing and smelling (olfactory)
C. Post-award phase
45. The bid package is developed in the:
D. Solicitation
A. Requirements phase
E. Award cycle
B. Requisition cycle
C. Solicitation cycle
42. Definitive contract terms are spelled out in the:
D. Award cycle
A. Pre-award phase
E. Award phase
B. Award phase
C. Post-award phase
46. The award phase includes the:
D. Purchasing phase
A. Requirements, requisition, and award cycles
C. Cost plus
B. Award and contractual cycles
D. Overseas
C. Requisition and solicitation cycles
D. Solicitation cycle
50. In the area of contracting, there are two basic types
E. Cycles required for the contract of contracts that reflect how the total price is
determined. The __________ contract has an objective
of a pre-determined end price while the __________
contract has an objective of a target end price.
47. To relieve pressure on the project schedule, Richard
decided to fast-track and hire a contractor to do part of A. Full value; Partial value
the work. Which form of contract(s) should he
consider? B. Definitive; undefined
E. Temporary D. Oligopoly
E. Monopoly
E. Contractual
A. Change notice
63. Warranties are given in two manners, either implied
B. New contract or expressed. The implied warranty differs from the
expressed warranty in that the implied warranty
C. Change order __________.
D. 100
64. A project manager may issue a "waiver" on items E. None of the above
received from a vendor because the items are less than
the purchase order specified. If the project manager
knowingly accepts faulty material, the vendor is usually
__________ any damages that the material may cause. 67. Payment bonds are often required by the contract
and require specific actions under the stated conditions.
A. Held responsible for Payment bonds are specifically designed to ensure
payment of __________ by the prime contractor.
B. Relieved of responsibility for
A. Insurance premiums
C. Made to pay a percentage of
B. Weekly payrolls
D. Willing to repair / correct
C. Incremental earned value charges
E. Not paid in the amount of
D. Subcontractors, laborers, and materials
70. The project manager is responsible for all the A. Top management
activities within a project and interfaces with external
functions, all of which consume his time. Therefore, B. Disputes resolution
when a contract administrator is assigned to the
project, the project manager __________ the contract. C. Problem processing
E. Planning function and cost disbursements for the 79. Contracting for project work follows a set sequence
project of activities that ensures a favorable contracting
strategy. The sequence of contracting activities includes
the following: develop a contracting plan; screen
contractors; select bidders; prepare invitations for bid;
77. During the proposal and bidding phase, the owner issue invitations for bid; __________; and award
(buyer) must assess the capability of the contractor contract.
(seller) to perform the work. For example, if the owner
believes the proposed team consists of some individuals A. Receive invitation for bid; review invitation for
who do not have the requisite qualifications and bid; submit bid
suggests that these individuals be replaced, the
contractor should __________. B. Prepare proposals; submit proposals; select
bidder
A. Disregard the owner's suggestions unless it
precludes the contractor from obtaining the contract C. Prepare proposals; receive proposals; review
proposals
B. Immediately make changes to follow the owner's
suggestions although the contractor believes the D. Prepare proposals; review proposals, submit
replacements are less qualified proposals
C. Discuss the suggestions with the owner and E. Receive proposals; evaluate proposals; select
clarify the qualifications of individuals priors to making a winner
change
A. Capacity, experience, capability, and interest D. A statement of work that describes how the
work will be accomplished
B. Capital, capacity, experience, and location
E. A price for the complete work to be performed
C. Experience, interest, financial stability, and skills
A. The owner (buyer) has a format that he routinely B. Quality versus cost
uses and wants to force the contractors to meet his
requirements C. Quality versus price
B. The Uniform Commercial Code specifies that all D. Risk versus opportunity
proposals will comply with the law and the standard
format E. None of the above
A. Union
B. Partnership
B. The tracking of claims is important for the best D. Substantial, complex, and extended
"win" position during the subsequential litigation commitments
E. Subcontractors, vendors, and suppliers 24 C -
25 C -
1 C - 26 A -
2 E - 27 B -
4 D - 30 C -
5 E - 31 E -
6 A - 32 B -
7 E - 33 D -
53 B -
54 C -
55 D -
56 A -
57 B -
58 B -
59 D -
60 D -
61 C -
62 D -
63 D -
64 B -
65 C -
66 D -
67 D -
68 A -
69 E -
70 C -
71 C -
72 anulada
73 B -
74 B -
75 D -
76 A -