Professional Documents
Culture Documents
WTG66.Punch List 3
WTG66.Punch List 3
Gamesa
Customer: NREA Date:
inspector
NREA
Wind Farm: ZAFARANA 80 WTG Nº: 66 inspector
The following are NREA’s proposed general critical points for all the windfarm
If any FG has been tripping in the turbine, the circuit needs to be checked before NREA inspection
Hydraulic Unit intercooler should work under the specified temperatures and values
The following are NREA’s proposed general not critcal points for all the windfarm:
Any point related to blade bearing leakage will be under check and NREA will check it during the
next preventive maintenance
Any point related to main shaft bearing leakage will be under check and NREA will check it during
the next preventive maintenance
All the test (pitch movements, HU tests, etc.) should be in the range
Lighting system should be OK
The following points are the Defected faults that 8.2, as the independent expert responsible to inspect the turbine, has delivered on its End of
Warranty Inspection Report of the turbine, as a contractual requirement between Gamesa and NREA; in order to help both parts: NREA and
Gamesa, in the elaboration of a Punch List to be completed in the turbine
LOW
The insulation of the low voltage cables of the
VOLTAGE
69 TURBINE
CABLE
lamp and cooler fan are damaged. They have to
be exchanged.
INSULATION
VIBRATION VIBRATION The wire of the vibration sensor is not bent. The
62
SENSOR SENSOR pendulum weight could fall away.
YAW The cable of the yaw sensor (yellow box) is loose
44 YAW COUNTER and endangered to get damaged by the yaw
SENSOR teeth. It has to be fixed properly.
There is a slightly leakage at the transformer. It
5 has to be sealed and the affected area
has to be cleaned.
On the __th of _________, 2013, Eng. Hassan Ezzeldin Rifaat as representative of Gamesa and Eng. Osama,, Eng. Mahmoud Elbagory and
Eng. Ahmed Fouad, as representative of NREA, agreed on the Punch List above, as the Punch List to be executed in this particular turbine of
Zafarana 80 Wind Farm; in order to help both: Gamesa an NREA engineers in the site, to agree and follow exclusively the punch list points
mentioned and listed above.