Professional Documents
Culture Documents
Maintenance Procedure For Improved Sustainability of DSM Pump Load Shifting Projects
Maintenance Procedure For Improved Sustainability of DSM Pump Load Shifting Projects
Abstract - Mine dewatering systems are energy intensive and less electricity than multistage centrifugal pumps, include
present ample opportunity for the implementation of electricity
turbine pumps and three-chamber pipe feeder
cost saving measures. One such electricity cost saving measure is
systems (3-CPFS) [4].
the implementation of load shifting projects to shift pumping load
from the peak periods to the off-peak periods of the Eskom Fig. 1 shows the layout of a mine's dewatering system,
Megaflex tariff structure. However, past experience has shown that henceforth referred to as Mine A, where a combination of
the electricity cost savings generated by a pump load shifting conventional centrifugal pumps are used in conjunction with
project can deteriorate without proper maintenance. The major a 3-CPFS. The hot water from the mining operations
causes of the deterioration were therefore investigated with the aim
accumulate in the Level 66 hot dam. The pumping station on
of developing a maintenance procedure. The maintenance
procedure consists of four sections: data loss prevention,
Level 66 consists of six dewatering pumps that pump the
mechanical failure prevention, control & instrumentation water from the Level 66 hot dam to the Level 45 hot dam.
maintenance and control parameter optimisation. The developed The mine also has a 3-CPFS installed on Level 45 that
maintenance procedure was implemented on the dewatering pumps water from the Level 45 hot dam to the surface hot
systems of South African gold mines. Results indicate that the dam. There is also a conventional pumping station on Level
application of the maintenance procedure resulted in both increased
45. This pumping station serves as backup for the 3-CPFS.
electricity cost savings and sustained performance.
The Level 45 pumping station consists of three pumps that
Index Terms- DSM; mine dewatering; load shifting; can also pump water from the Level 45 hot dam to the
maintenance procedure; sustainability surface hot dam.
1 INTRODUCTION
F
j tdl ::�: bd
The price of electricity in South Africa has risen above
the inflation rate since 2008. From 2008 to 2015, electricity
___________ _________________________________ __ o_ ' __________________________ _____ _
tariffs increased by 300%, while inflation over this period
3-CPFS
2 MINE DEWATERING
Water used for various mmmg purposes, and natural Fig. 1. Simplified layout of the dewatering system of Mine A
ground water, accumulates at the bottom of a deep level
gold mine. This water needs to be pumped to surface to 3 LOAD SHIFTING
prevent mine flooding. The water is normally pumped to
A proven measure for reducing the electricity cost of
surface by a series of multi-stage centrifugal pumps installed
dewatering pumps is to implement a load shifting project.
on various mining levels. These pumps are generally
This is achieved by controlling the dewatering pumps to
powered by electrical motors ranging from 1500 to 4000
minimise pumping during the expensive peak periods of the
MW.
Eskom Megaflex tariff structure, while maximising pumping
Multi-stage dewatering pumps are therefore one of the
during off-peak periods when lower tariffs apply.
biggest consumers of electricity on a deep level gold mine
Load shifting is made possible by using the water storage
and account for approximately 15% of the total electricity
dams on the various mining levels as buffers [5]. Pumping is
costs [3]. Alternative dewatering equipment, that consume
maximised in off-peak periods to ensure that the water
storage dams reach their minimum levels at the start of the
peak period. This ensures that water can flow into the
storage dams during the peak period without the need to
H.J. Groenewald,CRCED-Pretoria,North-West University, Pretoria,
utilise more than the minimum number of dewatering
South Africa (e-mail: hgroenewald@researchtoolbox.com).
J.F. van Rensburg,CRCED-Pretoria,North-West University, Pretoria, pumps.
South Africa (e-mail: 10728023@nwu.ac.za) Load shifting can either be achieved through manual or
J.H. Marais,CRCED-Pretoria,North-West University, Pretoria,South
automated pump control. Manual control entails that pumps
Africa (e-mail: jhmarais@researchtoolbox.com).
are manually stopped or started by control room operators or performance of the pump load shifting project at Mine B
pump attendants. Automated pump control entails a control decreased over a period of 12 months. This resulted in
system that automatically controls pumps according to a missed electricity cost savings opportunities of
pre-defined control philosophy. approximately R1.5-million.
Although pump attendants or control room operators can
be instructed to manage dam levels and control pumps to 4 REASONS FOR UNDERPERFORMANCE
achieve load shifting, this manual load-shifting intervention
There are various reasons for the underperformance of
is subject to interruption. This is because the initiative will
load shifting projects on the dewatering system of a deep
only last as long as there is someone who monitors the load
level gold mine. These vary from software problems related
shifting performance on a regular basis; or if the pump
to the control system to mechanical problems such as
attendants or control room operators are incentivised for the
dewatering pumps with low efficiency.
performance of their manual load-shifting attempts. A fully
Consider for example the load shifting project on Mine
automated control system, that is maintained correctly, will
A where the performance of the project depends on the
therefore be more sustainable than manual load shifting.
proper operation of the 3-CFPS. If the 3-CPFS is not
Fig. 2 shows a typical power profile, over 24 hours,
operational, the three conventional pumps on Level 45 must
which was achieved through the implementation of a
be used to pump the water from the Level 45 hot dam to the
successful pump load shifting project on the dewatering
surface hot dam. However, only two of these pumps can be
system of a mine, henceforth referred to as Mine B.
simultaneously used on Level 45.
An average hourly morning-peak load shift of 3.3 MW
The problematic aspect is the lower flow rate of the
and an average hourly evening-peak load shift of 4.6 MW
Level 45 pumps in comparison with the flow rate delivered
were achieved on this mine in November 2014. If correctly
by the 3-CPFS. The 3-CPFS achieves a flow rate of about
maintained, this project will generate an annual electricity
400 eis, which is significantly higher than the combined
cost saving of more than R5-million (based on the
flow rate achieved by the two pumps on Level 45, which
2015/2016 Megaflex tariffs for users located within 300 km
average at 260 els.
of Johannesburg and a supply voltage ranging from 500V to
The result of the lower flow rate of the conventional
66kV).
pumps on Level 45 is a drastic reduction in the buffer
capacity of the Level 45 hot dam, which is required for load
shifting. This often necessitates that the Level 45 pumps
often have to pump throughout the peak periods if the 3-
CPFS is unavailable.
Fig. 4 shows how the statuses of the Level 45 pumps and
the 3-CPFS affect the flow rate from Level 45 to surface.
12
6 MAINTENANCE PROCEDURE
Fig. 6. Impact of operational 3-CPFS on project performance - Section 3: Control and instrumentation maintenance
Mine A
Maintenance on control and instrumentation can be
5 CONDITION-BASED MAINTENANCE divided into three categories, namely, software,
Studies conducted on the performance of maintenance communication and instrumentation. Detailed maintenance
systems in the South African mining industry indicated a procedures for each of these three categories were
predominantly reactive culture towards maintenance [6] & developed and incorporated into the overall maintenance
[7]. This maintenance type, known as "run to failure", is the procedure.
least desirable maintenance method. It can only be used for
Section 4: Control parameter optimisation
equipment that is not critical to safe operation and/or
production. Control parameter maintenance is divided into three
A better solution is to implement advanced maintenance categories, namely, constraints, preferences and feedback.
techniques such as reliability-centred maintenance [8] or System constraints include values such as the maximum
condition-based maintenance [9]. Condition-based number of pumps that can be simultaneously utilised on
maintenance involves monitoring the condition of critical each pumping station, dam sizes and pump capacities.
equipment in order to perform maintenance only when the Preferences are client specific and include, for example,
need arises. This maintenance techniques relies on the aspects like minimum and maximum dam levels and
availability of condition monitoring instrumentation. additional criterion for certain pumps to operate. Continuous
Unfortunately, the relatively high cost of condition feedback between all stakeholders is also important to
monitoring instrumentation prevents the application of ensure that system changes are incorporated in the control
condition-based maintenance on South African mines. philosophy.
The automation of dewatering pumps requires the
installation of equipment such as network infrastructure,
automated valves and instrumentation such as power and
water flow meters. This equipment can also be used to
implement a condition-based maintenance system. For
Yes - Maintenance not required 4 000 R 800 000
1 000
1/ \ R 200 000
- Peak impact -Winter 2012 - Peak inl-lact -Winter 2013 - Peak impact -Winter 2014
70
60t-------�
so t------------------------------------e,{�, � I� .
I
4 0 t----------------------------.�� � ,1H�1H�1H� 1� 1� �
No
� � � � � � � � �
� I i;
� tz � <:I �. �
0 '- " 0
:El <:if � 0 " � � < �. ] :El <if � 0 6
z 0 " �
Yes
DCumulatiyc im pact • Cumulatiyc target
8 CONCLUSION