Professional Documents
Culture Documents
0.summary of Cost (F)
0.summary of Cost (F)
SUMMARY OF COST
Total-1 1,992,615.75
Total-2 2,000,000.00
Total-1 1,949,682.66
Total-1 1,313,111.85
Total-3 197,577.00
RATE ANLYSIS FOR PROVIDING AND LAYING M.S FLANGED PIPE FOR NULLAH CROSSING
4" i/d 6" i/d 8" i/d 10" i/d 12" i/d
Sr.No. Descriptions Unit
Amount Amount
Qty Rate Amount (Rs.) Qty Rate Qty Rate Qty Rate Amount (Rs.) Qty Rate
(Rs.) (Rs.)
Excavation in open cutting for water supply pipe lines 10 feet length
1 %0Cft 120.00 1565.50 187.86 150.00 1565.50 234.83 150.00 1565.50 234.83 210.00 1565.50 328.76 210.00 1565.50
on both end of laid pipe.
2 Providing M.S pipe 4.88mm thick. Rft 15.00 342.24 5133.56 15.00 769.59 11543.85 15.00 1031.73 15475.93 15.00 1499.84 22497.54 15.00 1799.86
Providing C.I flange and welded with pipe in three pieces both ends
3 and welded with tail piece on one side including making arrangment Kg 14.99 49.90 748.00 68.96 49.90 3441.10 108.89 44.30 4823.83 156.00 44.30 6910.80 185.00 44.30
for nuts and bolts etc. complete 8 Nos. for each crossing.
4 Providing C.I bends 4 Nos. for each crossing. Kg 75.28 84.70 6376.22 94.36 84.70 7992.29 205.00 80.20 16441.00 264.96 80.20 21249.79 370.24 80.20
5 Providing C.I tail piece 2 Nos. for each crossing. Kg 34.56 49.90 1724.54 48.08 49.90 2399.19 77.13 44.30 3416.86 108.89 44.30 4823.83 150.00 44.30
Providing and laying nuts and bolts size No. of each side made of
6 Kg 2.12 49.90 105.79 8.00 49.90 399.20 8.00 44.30 354.40 8.00 44.30 354.40 10.00 44.30
nut 3/4" dia bend.
7 Providing and fixing of pvc tape core. Each 2.00 102.80 205.60 2.00 166.45 332.90 2.00 255.80 511.60 2.00 314.00 628.00 2.00 392.00
8 Rehandling of earth qty 80% of item No. 1 %0Cft 96.00 798.60 76.67 120.00 798.60 95.83 120.00 798.60 95.83 168.00 798.60 134.16 168.00 798.60
Labour, welding and making flanges and welded with M.S pipe etc.
9 complete including carriage charges from market to wake shop and Rft 15.00 110.00 1650.00 15.00 190.00 2850.00 15.00 210.00 3150.00 15.00 325.00 4875.00 15.00 450.00
back to site wake.
10 Add 20% contractor and overheads charges on item No. 2 and 9 6783.56 20% 1,356.71 14393.85 20% 2,878.77 18625.93 20% 3,725.19 27372.54 20% 5,474.51 33747.84 20%
(i) Rate of each nullah crossing Total 17,564.95 32,167.97 48,229.46 67,276.79
12" i/d
Amount (Rs.)
328.76
26997.84
8195.50
29693.25
6645.00
443.00
784.00
134.16
6750.00
79,971.50
6,749.57
86,721.07
5,781.40
WATER SUPPLY SYSTEM, GUJRAT
1) MATERIAL
Water meter
NS No. 1.00 6,000.00
Total
Say
R SUPPLY SYSTEM, GUJRAT
Amount
(Rs.)
6,000.00
300.00
6,300.00
1,260.00
7,560.00
7,560.00
CONSTRUCTION OF WATER SUPPLY SYSTEM, GUJRAT CITY
1 Water Meter No. 7,560 11555 87,355,800 9675 73,143,000 8770 66,301,200 226,800,000
4 6355 6355 9478
6 2430 2430 6898
3 1334 1334 2334
4 1918 1918
6 2664 2664
3 1000 1000
4 1205 1205
6 1804 1804
11290
18710