PROJECT DESCRIPTION
1.0 LOCATION
Gujrat city is located at a longitude 740 –05’ East and latitude 320-34’ North. The city is
situated on Lahore Rawalpindi Railway line and highway at the distance of 116 Km from
Lahore towards Rawalpindi. It is bounded on North/West by Bhimber Nullah and on
South River Chenab flows quite near the city at distance of about 9 Km.
1
Annexure - B
1.2 DESIGN
The design horizon of the Project has been taken up to year 2030. At present, 55 tube wells exist
in the city having capacity of 53.5 cusecs. To meet the additional water demand, 17 new tube
wells have been proposed. In the proposed system capacity of pumps is worked on maximum
daily demand with 16 hours of pumping to meet average daily demand. In order to make this
option financially feasible, the capacity of each overhead tank has been restricted to 100,000
gallons. So, 17 new overhead tanks with capacity of 100,000 gallons & 50,000 gallons have been
proposed.
2
Annexure - B
1.6 TIME
The project activities have been executed since April 09, 2009 and it was assessed that it will take
about 36 months after design to complete the remaining project activities subject to the
availability of funds. The time period is considered for balance works from the date of
demobilization of Consultants i.e. August, 2014.
1.7 COST
The total revised cost of this project has been estimated for Rs. 829.87 Million including 2%
contingencies.
1.8 SPECIFICATIONS
The work shall be executed as per Public Health Engineering Department specifications.
1.10 RATES
Two approaches of cost estimation has been exercised in estimate based on actually awarded
works to the contractors and work yet to be awarded. The awarded works have been reported as
Part – I in revised estimate and work yet to be awarded is presented as Part – II.
3
Annexure - B
The estimate for part – I has been based on market/ composite rates of Govt of Punjab for Gujrat
District for 1st Quarter 2009 ( the rate on which the work already awarded to the contractors).
While for Part – II, the market composite rates of Ist Bi-annual 2016 has been used.