Annexure - A

Page 12 of 17

WATER SUPPLY SYSTEM, GUJRAT

TABLE 1: DESIGN CALCULATION( ZONE-1)

PHASE-1 (UPTO 2015) PHASE-2 (UPTO 2030)

Population
Area Population Density Population Area Density Population
UC-45 641 41.4 26,537 UC-45 641 63.5 40,704
UC-46 749 33.81 25,324 UC-46 749 51.85 38,836
UC-47 282 77.82 21,945 UC-47 282 119.35 33,657
UC-50 (Part) 59 19.147 1,130 UC-50 (Part) 59 29.363 1,732

Total Population 74,936 Total Population 114,928


Per Capita Water Demand 50 Gallons/ Cap Per Capita Water Demand 50 Gallons/ Cap
Average Demand 3,746,800 Gallons Average Demand 5,746,413 Gallons
6.9 Cusecs 10.7 Cusecs

Max Demand 10.4 Cusecs Max Demand 16.1 Cusecs

16 Hr Max Demand 15.6 Cusecs 16 Hr Max Demand 24.2 Cusecs

Existing Tubewells: Existing Capacity 4 Cusecs


Current
Capacity
Working
(Cusecs)
Hour
TW-5 (Kiran Cinema) 1.04 18 Required Capacity 20.2 Cusecs
TW-6 (Khalid Abad) 0.98 17.5
TW-7 (Mohallah Ferozabad) 1.12 14 Additional Tubewell
TW-8 (Tibbi Gorian) 0.7 15
TW-32 (Tali Purra) 0.71 18 Two tubewells of 2 cusecs (PTW-3 & 4) will be required
TW-33 (Hayatpura) 1.19 18 in the area neareby Mohallah Lund Pur as the population
TW-42 (Jamna) 0.89 6 increases.
TW-44 (Aminabad) 1.08 18 Reinstalles
TW-51 (Kalra Kalan) 0.91 8 TW-5 2 Cusecs
TW-52 (Kalra Khasa) 0.23 12 TW-6 1 Cusecs
TW-53 (Wapda Colony) 1 18 TW-7 2 Cusecs
TW-54 (Qudrat Abad) 0.78 18 TW-8 2 Cusecs
TW-32 1 Cusecs
TW-33 1 Cusecs
Existing Capacity 10.63 Cusecs TW-42 2 Cusecs
TW-44 2 Cusecs
Required Capacity 4.97 Cusecs TW-53 1 Cusecs
TW-54 2 Cusecs
Additional Tubewell
Place Cusecs OHR Capacity Reqd 478,868 Gallons
PTW-1) Dera Kunjahi (UC-47) 2
PTW-2) Lund Pur Road (UC-46) 2
Total 4 Existing OHR Capacity 300,000 Gallons

OHR Required OHR Capacity 178,868 Gallons

OHR Capacity Required 312,233 Gallons

OHR Providing OHR Providing


Place Gallons Place Gallons
OHR-1) Near Tibbi Gorian Tubewell (UC-45) 100,000 OHR-4) Gali# 4 Hayat purra (UC-45) 50,000
OHR-2) Govt Girls Elementory School (UC-46) 100,000 OHR-5) Lund Pur Road (UC-46) 50,000
OHR-3) End of Staff Galla (UC-47) 100,000 OHR-6 & 7) 1.5 Lack OHR required in area nearby Mohallah
Lundpur as development increases.
Annexure - A
Page 13 of 17

WATER SUPPLY SYSTEM, GUJRAT

TABLE 1: DESIGN CALCULATION( ZONE-1)

PHASE-1 (UPTO 2015) PHASE-2 (UPTO 2030)


Annexure - A
Page 13 of 17

WATER SUPPLY SYSTEM, GUJRAT

TABLE 2 : DESIGN CALCULATION( ZONE-2)

PHASE-1 (UPTO 2015) PHASE-2 (UPTO 2030)

Population Population
Area Density Population Area Density Population
UC-48 364 73.87 26,889 UC-48 364 73.87 26,889
UC-49 412 73.08 30,109 UC-49 412 112.07 46,173
UC-50 (Part) 865 19.17 16,582 UC-50 865 29.393 25,425

Total Population 73,580 Total Population 98,486

Average Demand 3,678,985 Gallons Average Demand 4,924,323 Gallons


6.8 Cusecs 9.1 Cusecs

Max Demand 10.2 Cusecs Max Demand 13.7 Cusecs

16 Hr Max Demand 15.3 Cusecs 16 Hr Max Demand 20.6 Cusecs

Existing Tubewells Existing Capacity 6 Cusecs


Current
Capacity
Working
(Cusecs)
Hour
TW-2 (Nawaz Sharif Park) 0.97 18 Required Capacity 14.6 Cusecs
TW-3 (Noorpur Paday) 0.97 18
TW-4 (Dera Gulab Shah Grave yard) 1.09 14 New TW
TW-30 (Mohallah Sultan Pura) 0.79 17.5 Place Cusecs
TW-31 (Jatowakal Dera) 1.31 18 PTW-8) In Kalra Kalan when more developed 2
TW-34 (Railway Station) 1.08 18
TW-35 (Aluwala Gala) 0.98 6 Reinstalled
Tw 51 (Kalra Kalan) 0.91 8 TW-2 1 Cusecs
Tw 52 (Kalra Khasa) 0.23 12 TW-3 2 Cusecs
TW-4 2 Cusecs
TW-30 2 Cusecs
Existing Tubewells TW-31 2 Cusecs
(16 Hr Working) 8.33 Cusecs TW-34 1 Cusecs
TW-35 2 Cusecs
Required Capacity 6.97 Cusecs

Additional Tubewell OHR Capacity Reqd 410,360 Gallons


Place Cusecs
PTW-5) College at GT Road(UC-48) 2
PTW-6) Sir Syed College (UC-49) 2 Existing OHR Capacity 300,000 Gallons
PTW-7) Miran Sb Road (UC-49) 2
Total 6 Required OHR Capacity 110,360 Gallons

OHR Capacity 306,582 Gallons OHR Providing


Place Gallons
OHR-11) Nawaz Sharif Park (UC-49) 100,000
OHR Providing OHR-12) Jattowakal (UC-48) 50,000
Place Gallons
OHR-8) College at GT Road (UC-48) 100,000
OHR-9) Sir Syed College (UC-49) 100,000
OHR-10) Kalra TW (UC-50) 100,000
Annexure - A
Page 14 of 17

WATER SUPPLY SYSTEM, GUJRAT

TABLE 3: DESIGN CALCULATION( ZONE-3)

PHASE-1 (UPTO 2015) PHASE-2 (UPTO 2030)

Population Population
Area Density Population Area Density Population
UC-50 431.04 19.17 8,263 UC-50 431.04 29.36 12,655
UC-51 181.04 118.78 21,504 UC-51 181.04 118.78 21,504
UC-52 353.67 95.83 33,892 UC-52 353.67 146.94 51,968
UC-53 628.18 54.86 34,462 UC-53 628.18 84.132 52,850
UC-54 187.63 118.68 22,268 UC-54 187.63 118.68 22,268
UC-58 404.85 33.09 13,396 UC-58 404.85 50.75 20,546
UC-59 213.35 97.44 20,789 UC-59 213.35 97.44 20,789

Total Population 154,574 Total Population 202,580

Average Demand 7,728,718 Gallons Average Demand 10,129,023 Gallons


14.3 Cusecs 18.8 Cusecs

Max Demand 21.5 Cusecs Max Demand 28.2 Cusecs

16 Hr Max Demand 32.3 Cusecs 16 Hr Max Demand 42.3 Cusecs

Existing Tubewells Existing Capacity 12 Cusecs


Current
Capacity Working
Hour
(Cusecs) Required Capacity 30.3 Cusecs
TW-13 (Chah Trang) 0.61 18
TW-15 (Maqbool Abad) 0.59 18 New TW 2 Cusecs
TW-16 (Ghari Ahmedabad) 1.24 6 PTW-15) Near Benth (Proposed)
TW-19 (Jail Chowk) 0.56 18
TW-20 (Aurangzeb Jora) 0.52 18
TW-21 (Chowk Alipur) 0.73 18 Reinstalled
TW-22 (Qamar Sialvi Road) 0.77 18 TW-13 (Chah Trang) 2 Cusecs
TW-24 (Hassan Pura) 1.53 18 TW-15 (Maqbool Abad) 2 Cusecs
TW-25 (Mohallah Bagh Bawa) 1.34 18 TW-16 (Ghari Ahmedabad) 2 Cusecs
TW-26 (Mohallah Rehmatpura) 0.66 - TW-21 (Chowk Alipur) 2 Cusecs
TW-28 (Islam Nagar) 0.93 18 TW-22 (Qamar Sialvi Road) 2 Cusecs
TW-39 (Mohallah Shah Hussain) 0.88 18 TW-24 (Hassan Pura) 2 Cusecs
TW-40 (Kalu purra) 0.76 18 TW-25 (Mohallah Bagh Bawa) 2 Cusecs
TW-41 (Bairi Wala) 0.74 18 TW-26 (Mohallah Rehmatpura) 2 Cusecs
TW-45 (TMA Office) 0.98 18 TW-28 (Islam Nagar) 2 Cusecs
TW-47 (Bholey) 1 - TW-40 (Kalu purra) 2 Cusecs
TW-50 (General Bus Stand) 1 - TW-41 (Bairi Wala) 2 Cusecs
TW-45 (TMA Office) 2 Cusecs
Existing Tubewells TW-47 (Bholey) 2 Cusecs
(16 Hr Working) 13.64 Cusecs TW-50 (General Bus Stand) 1 Cusecs

Required Capacity 18.66 Cusecs OHR Capacity Reqd 844,085 Gallons


(2 hr Working)
Additional Tubewell
Place Cusecs Existing OHR Capacity 650,000 Gallons
PTW-9) Christian Grave Yard (UC-58) 2
PTW-10) End of Shadaula Road (UC-52) 2 Required OHR Capacity 194,085 Gallons
PTW-11) Back of Zahoor Palace (UC-52) 2
PTW-12) Mosque Haji M Din (UC-52) 2 OHR Providing
PTW-13) Gulberg Colony (UC-58) 2 Place Gallons
PTW-14) Shah Jhahan Tomb (UC-53) 2 OHR-21) Shah Jhangir Tomb (UC-53) 100,000
OHR-22) Require in the area near Banth
of 1 Lac Gallons
OHR Capacity 644,060 Gallons
Annexure - A
Page 15 of 17

WATER SUPPLY SYSTEM, GUJRAT

TABLE 3: DESIGN CALCULATION( ZONE-3)

PHASE-1 (UPTO 2015) PHASE-2 (UPTO 2030)


Annexure - A
Page 16 of 17

WATER SUPPLY SYSTEM, GUJRAT

TABLE 3: DESIGN CALCULATION( ZONE-3)

PHASE-1 (UPTO 2015) PHASE-2 (UPTO 2030)


OHR Providing
Place Gallons
OHR-13) TMA Office (UC-51) 50,000
OHR-14) Back of Zahoor Palace (UC-53) 50,000
OHR-15) Mohallah Shah Hussain (UC-59) 50,000
OHR-16) Cristian Grave Yard (UC-58) 100,000
OHR-17) Hassan Park (UC-54) 100,000
OHR-18) End of Shahdaula Road (UC-52) 100,000
OHR-19) Hud Purra (UC-52) 100,000
OHR-20) Children Park (UC-51) 100,000
Annexure - A
Page 16 of 17

WATER SUPPLY SYSTEM, GUJRAT

TABLE 4: DESIGN CALCULATION( ZONE-4)

Area Population Density Population


UC-55 49.61 390.48 19,372
UC-54 55.86 136.87 7,646

Total Population 27,017

Average Demand 1,350,864 Gallons


2.5 Cusecs

Max Demand 3.8 Cusecs

16 Hr Max Demand 5.7 Cusecs

Existing Tubewells
Current
Capacity
Working
(Cusecs)
Hour
TW-14 0.96 18
TW-18 0.77 18
TW-38 0.35 18

Existing Tubewells
(16 Hr Working) 2.08 Cusecs

Required Capacity 3.62 Cusecs

Additional Tubewell
Place Cusecs
PTW-16) Tehsil(UC-55) 2
2) Rehablitate the existing Tubewells

OHR Capacity Required 112,572 Gallons

OHR Providing
Place Gallons
OHR-23) Anayat Park (UC-55) 100,000
Annexure - A
Page 17 of 17

WATER SUPPLY SYSTEM, GUJRAT

TABLE 5: DESIGN CALCULATION( ZONE-5)

PHASE-1 (UPTO 2015) PHASE-2 (UPTO 2030)

Population Population
Area Density Population Area Density Population
UC-57 854.67 32.78 28,016 UC-57 854.67 50.28 42,973
UC-58 339.42 33.09 11,231 UC-58 339.42 50.75 17,226
UC-56 800.3 37.13 29,715 UC-56 800.3 56.94 45,569

Total Population 68,963 Total Population 105,767

Average Demand 3,448,131 Gallons Average Demand 5,288,373 Gallons


6.4 Cusecs 9.8 Cusecs

Max Demand 9.6 Cusecs Max Demand 14.7 Cusecs

16 Hr Max Demand 14.4 Cusecs 16 Hr Max Demand 22.1 Cusecs

Existing Tubewells
Current
Capacity
Working
(Cusecs)
Hour Existing Capacity 6 Cusecs
TW-1 (Mohammada More) 0.97 16-18
TW-9 (Kashmir pura) 1.01 15 Required Capacity 16.1 Cusecs
TW-10 (Mohammada Chowk) 0.69 18
TW-11 (Margazar Colony) 0.76 18 Additional Tubewell
TW-27 (Shadman) 1.21 18 Place Cusecs
TW-28 (Islam Nagar) 0.93 18 PTW-20) Amir Colony (UC-58) 2
TW-36 (Gulshan Colony) 1.42 18 PTW-21) Aziz Bhatti shaheed Hospital (UC-56) 2
TW-37 (Madina Colony) 1.04 18 Total 4
TW-43 (Zahoor Elahi Stadium) 0.59 18 Reinstalled
TW-46 (Baghdad Colony) 0.95 12 TW-1 1 Cusecs
TW-49 (Odawal) 1 - TW-9 2 Cusecs
TW-10 1 Cusecs
TW-11 2 Cusecs
Existing Tubewells TW-27 2 Cusecs
(16 Hr Working) 10.57 Cusecs TW-28 2 Cusecs
TW-36 1 Cusecs
Required Capacity 3.83 Cusecs TW-46 1 Cusecs
TW-49 1 Cusecs
Additional Tubewell
Place Cusecs OHR Capacity Reqd 440,698 Gallons
PTW-17) Zahoor Elahi Stadium (UC-56) 2 (2 hr Working)
PTW-18) Bismillah Chowk (UC-57) 2
PTW-19) Sultan Pura Grave Yard (UC-57) 2 Existing OHR Capacity 250,000 Gallons
Total 6
Required OHR Capacity 190,698 Gallons

OHR Capacity 287,344 Gallons OHR Providing


Place Gallons
OHR-27) Aziz Bhatti Hospital (UC-57) 100,000
OHR Providing OHR-28) Amir Colony (UC-58) 50,000
Place Gallons OHR-29) Zila Council Rest House 50,000
OHR-24) Zahoor Elahi Stadium (UC-56) 100,000
OHR-25) Bismillah Chowk (UC-57) 100,000
OHR-26) Margzar Colony (UC-57) 50,000