This document discusses adjudication as a means of dispute resolution in the UK construction industry under the Housing Grants, Construction and Regeneration Act 1996 (Construction Act). It provides the following key points:
1) The Construction Act introduced a statutory right to adjudication, aiming to provide fast, inexpensive, and interim binding decisions to resolve payment and other disputes quickly.
2) Adjudicators must provide decisions within 28 days, which are binding until the dispute is settled in arbitration or litigation.
3) Based on the author's experience, adjudication cost on average 15% of the cost of litigation/arbitration and mostly resolved payment disputes between contractors and subcontractors.
This document discusses adjudication as a means of dispute resolution in the UK construction industry under the Housing Grants, Construction and Regeneration Act 1996 (Construction Act). It provides the following key points:
1) The Construction Act introduced a statutory right to adjudication, aiming to provide fast, inexpensive, and interim binding decisions to resolve payment and other disputes quickly.
2) Adjudicators must provide decisions within 28 days, which are binding until the dispute is settled in arbitration or litigation.
3) Based on the author's experience, adjudication cost on average 15% of the cost of litigation/arbitration and mostly resolved payment disputes between contractors and subcontractors.
This document discusses adjudication as a means of dispute resolution in the UK construction industry under the Housing Grants, Construction and Regeneration Act 1996 (Construction Act). It provides the following key points:
1) The Construction Act introduced a statutory right to adjudication, aiming to provide fast, inexpensive, and interim binding decisions to resolve payment and other disputes quickly.
2) Adjudicators must provide decisions within 28 days, which are binding until the dispute is settled in arbitration or litigation.
3) Based on the author's experience, adjudication cost on average 15% of the cost of litigation/arbitration and mostly resolved payment disputes between contractors and subcontractors.
This document discusses adjudication as a means of dispute resolution in the UK construction industry under the Housing Grants, Construction and Regeneration Act 1996 (Construction Act). It provides the following key points:
1) The Construction Act introduced a statutory right to adjudication, aiming to provide fast, inexpensive, and interim binding decisions to resolve payment and other disputes quickly.
2) Adjudicators must provide decisions within 28 days, which are binding until the dispute is settled in arbitration or litigation.
3) Based on the author's experience, adjudication cost on average 15% of the cost of litigation/arbitration and mostly resolved payment disputes between contractors and subcontractors.
ADJUDICATION INTRODUCTION producing fast, inexpensive and
interim binding decisions by
-THE UK EXPERIENCE Adjudication as a means of dispute resolution is casting an ever- independent third party Andrew Kelly* increasing shadow overthe adjudicators. The goal of the Act Solicitor Australian construction industry. At was to precipitate the early Phillips Fox Lawyers present, security of payment resolution of disputes to avoid Brisbane legislation [including recourse to protracted arbitration or litigation fast track adjudication of payment and to provide a swift and cheap claims) has been introduced in New mechanism for pursuing payment. South Wales 1 and Victorian 2 draft The salient features of the security of payment bill in similar Construction Act are: terms is soon to be introduced • Parties to a construction contract before the parliament of Western are given a statutory right to refer Australia. 3 ln addition, there have to adjudication any disputes which been two recent significant may arise under that contract. The developments: application of the Act is not limited .In July 2002, the Queensland to payment disputes and the parties Building Services Authority [QBSA) are effectively entitled to refer any released a papertitled 'Preliminary dispute to adjudication including drafting instructions for a Building extension of time and delay and and Construction Industry disruption claims: Payments Bill 2003 . proposing new • The adjudicator's decision is legislation to regulate the building binding until the dispute is finally industry in Queensland including settled by arbitration or litigation as the introduction of an adjudication appropriate, or by agreement. The mechanism. 4 Construction Act did not abolish the .In March 2003, the central piece arbitration, or litigation of of financial reform recommended construction disputes. It introduced by the Cole Royal Commission is an intervening provisional stage in the introduction of Commonwealth the dispute resolution process. security of payment legislation .If a contract falls within the including a rapid adjudication province of the Construction Act,7 it process. 5 must provide for a number of The statutory right to adjudication is mandatory adjudication provisions. not however new. In the later part of If it fails to do so, a statutory the 1990s, the legal landscape of adjudication scheme will apply to the construction industry in the the dispute. The mandatory United Kingdom was forever adjudication provisions include the changed with the enactment of the following: adjudication provisions in the • the right of any party to the Housing Grants, Construction and contract to give notice at any Regeneration Act 7996 6 (simplified time of its intention to refer a by all in the construction industry to dispute to adjudication; the 'Construction Acf). Forthe better part of 3 years, I worked in • a timetable with the object of London for the largest construction securing the appointment of law practice in the United Kingdom the adjudicator and referral of and was involved first hand with the a dispute to an adjudicator adjudication process under the within 7 days of notice of the Construction Act. dispute;
THE CONSTRUCTION ACT • requirements on the
The Construction Act was intended adjudicator to act impartially, to reach a decision within 28 to introduce a speedy method of dispute resolution aimed at days of the referral of the dispute, or 42 days by
42 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #90 MAY/JUNE 2003
agreement with the referring although there were also a number Although it is difficult to party, or longer as agreed by of disputes concerning extension of gauge, I would estimate that the parties after the dispute time and delay and disruption the adjudication process has been referred. The claims. It was uncommon for an adjudicator has the powerto adjudication to consider issues would typically cost less take the initiative in relating to whetherworks were than 15% of the cost of ascertaining the facts and law; defective. litigation or arbitration. • No liability on the .The majority of disputes referred adjudicator in the discharge or to adjudication were between main purported discharge of his contractors and subcontractors functions as adjudicator unless ratherthan principals and main he acts in bad faith. contractors. At least 70% of the disputes I was involved in were .It is open to parties to a contract between main contractors and to specifically name an adjudicator subcontractors. or an adjudicator nominating body. The scheme implies that if the • My adjudication experience parties cannot agree on an ind icated that the cost of adjudicator or the one named in the adjudication was significantly less contract is not available, the than arbitration or litigation. referring party shall request an Although it is difficult to gauge, adjudicator nominating body [e.g. I would estimate that the the Construction Industry Council) adjudication process would typically to select a person to act as cost less tha n 15% of the cost of adjudicator litigation or arbitration.
OBSERVATIONS-HAS .A large numberof adjudications,
particularly in the early stages of ADJUDICATION WORKED? the Construction Act, involved Set out below are my personal preliminary challenges to the observations about the Construction adjudicator's jurisdiction. This Act and the tactics and strategies included such threshold issues as to used by parties. whetherthe contract was indeed a .In the first year of its operation, construction contract under the there appeared to be relatively few Construction Act orwhetherthe disputes referred to adjudication. 8 contract was entered into after 1 Parties were slowto accept and May 1998. For example, I was adopt the adjudication process but involved in a challenge to an in 1999 and following, there was a adjudicator's jurisdiction where substantial increase in the number letters of intent were issued priorto of disputes referred to 1 May 1998 and work commenced adjudication. 9 on site prior to 1 May 1998 but the contract was not formally executed • The adjudication process was until after 1 May 1998. more inquisitorial than adversarial. It usually did not allow the time or .A frequent occurrence was opportunity for a hearing or expert parties attempting to take analysis orthe taking of evidence. advantage of the compressed In my experience, adjudications timeframe and ambush their were based primarily on written opponents by, for example, serving submissions and it was not unusual exhaustive documentation for an adjudicatorto ask specific immediately before public holidays. questions following receipt of In my experience, it was not written submissions. uncommon for one of the parties to submit volumes of documentation • The majority of disputes I was out of all proportion to the amount involved in related to the failure to in dispute and the complexity of the comply with payment provisions issues to be dealt with. In myview,
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #90 MAY/JUNE 2003 43
Most participants would such tactics were largely advantageous to obtain an early, acknowledge that the unsuccessful and ineffective. albeit rough decision ratherthan a Differences between the parties later more expensive decision, or process was rough and were likely to have been raised in no decision at all. Approximately ready but considered it more the course of the project and it was 80% of the adjudications I was advantageous to obtain an unlikely that the reference to involved in resulted in the final early, albeit rough decision adjudication would come as a determination of the matter and rather than a later more complete surprise to a party. It was further disputes following an expensive decision, or no also my experience that adjudicator's decision did not adjudicators did not take kindly to usually materialise. The decision at all. such ambush tactics. Construction Act in myviewwas largely successful in achieving its • Often adjudications involved objective of resolving disputes particularly complex issues quickly and efficiently. requiring legal analysis to be assessed and determined. There THE ROAD FORWARD IN were occasions where a technical AUSTRALIA adjudicator appointed did not There are fundamental differences appear to have the requisite ability between the adjudication provisions to properly assess complex issues in the Construction Act and the of law so as to decide the rights and adjudication provisions in New liabilities of the parties in the time South Wales and Victoria and those allowed. A common concern of proposed for Western Australia and clients was doubts over the quality Queensland. However, the of adjudicators and their ability to experience of adjudications in the consider in detail legal issues. A United Kingdom will be fruitful in pattern did however emerge that predicting developments in adjudicators in such a position Australia. lO It is likely that the would seek out further independent following issues in any adjudication legal advice where difficult issues process will arise: of law arose. .Is there a contract, and if so, when • Other issues that arose included was the contract concluded? whether adjudicators had the power to award costs, whether .Is the contract a construction contract within the meaning of the adjudicators had the power to relevant legislation? correct manifest clerical or arithmetical errors in decisions and .Is it possible to restrict the right to how adjudicator's decisions were to adjudication by contract? be enforced following the decision. • Can an adjudicator consider his/ • There was a concern that this herownjurisdiction and howdo abbreviated form of justice would parties challenge an adjudicator's lead to binding decisions which j urisd iction? were ill considered and unfair. It • Will an adjudicator be required to was inherent in the rigid timeframe observe the rules of naturaljustice, of the adjudication process that and if so, when will an adjudicator from time to time mistakes and be deemed to have breached such injustices would take place. rules? However, it was my experience that the majority of participants of • What will be the effect of a adjudications under the previous adjudication decision on Construction Act considered it a fair, another adjudicator? fast, reliable and inexpensive form • Can an adjudicator make an of interim dispute resolution. Most award for costs? participants would acknowledge that the process was rough and • Can parties undertake ready but considered it more adjudication proceedings whilst
44 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #90 MAY/JUNE 2003
other proceedings such as Payments Bill 2003. Part 3 of the arbitration or litigation are Bill makes provision for rapid underway? adjudication • Can an adjudicator correct a 6. This came into force in the decision after it has been issued? United Kingdom on 1 May 1998. • On what grounds is it possible to 7. The Construction Act applies challenge an adjudicator's decision to all construction contracts (other in the courts? than with a residential occupier) which relate to the carrying out of • Howwill an adjudicator's decision be enforced? construction operations. It also applies to architectural, design or In light of the UK experience, the surveying works or contracts for advent of statutory adjudication in advice on building, engineering, Australia looks likely to be an interior or exterior decoration or exciting time for both industry landscaping works, insofar as they participants and construction law relate to construction operations. pra ct itioners. The main exclusions are in relation REFERENCES to supply only contracts, energy contracts and contracts expressly * BEcon, LLB (Hons) Phillips Fox Brisbane. excluded by statute. 8. This was due in part to the 1. Building and Construction Construction Act only applying to Industry Security of Payment Act 1999(NSW). Adjudication contracts entered into after 1 May 1998. provisions are principally found in Division II-Sections 17-26. 9. This is borne out by research 2. Building and Construction conducted by Glasgow Caledonian University, which indicated that Industry Security of Payment Act 2002 (Vic). Adjudication provisions during the second year after the are principally found in Division 11- Construction Act became binding, Sections 18-28. there was a 600% growth in the number of adjudications reported. 3. Preliminary drafting instructions for a Construction 10. For an index of over 100 cases concerned with the Construction Act Industry Payments Billwere issued by the Security of Payment Task see PeterSheridan and Dominic Helps, 'Construction Act Review' Force forthe Western Australian (2002) 18 Const LJ 457. Building and Construction Industry in February 2002.
4. Reference should also be
made to the discussion paper titled 'Security of Payment in the Building and Construction Industry' released by the QBSA in December 2001. 5. Royal Commission into the Building and Construction Industry, TRH Cole RFD QC tabled in Parliament on 26-27 March 2003. The security of payment section of the Royal Commission is found in Volume 8 Reform-National Issues Part 2, Section 14-Security of Payment. Attached to this section is Appendix 1: The Building and Construction Industry Security of
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #90 MAY/JUNE 2003 45