Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

GOOD FAITH AND THE This paper attempts to give an of good faith and reasonableness in

DUTYTO WARN-THE overview of recent trends in contract performance [as distinct


construction law towards applying from contract formation) in
NEW PROACTIVE concepts of good faith and the duty Australian contract law. The case
APPROACH OF THE to warn. The paper deals with each also adds to the categories of
COURTS TO in turn. The cases mentioned are agreement to which the duty
CONSTRUCTION referenced and summarised in lists, applies.
CONTRACTING one at the end of the first section of
The duty of good faith creates
the paper on good faith, and the
obligations on contracting parties
Irene Wales second at the end of the second half
both at formation and in
Partner, Construction & of the paper, on the duty to warn.
performance of the contract. The
Transport Group
GOOD FAITH issue of practical relevance is that
PricewaterhouseCoopers The development of the duty of the duty of good faith may disturb
Legal, good faith is one of the most the settled principles of contract
Sydney significant developments in the law as they relate to contract
body of Australian contract law of performance by imposing a cap on
recent times. The courts have spent the parties' capacity to exercise
a considerable amount of time their contractual powers. This paper
addressing the operation of the duty reviews the development of the
and the circumstances in which it duty of good faith and
can be implied, and have identified reasonableness as a duty arising in
the issues which have the capacity both contract formation and
to disrupt the long established performance, and highlights the
principles serving the interests of present concerns and challenges
contractual certainty. The cases facing both the courts in refining the
cover a wide range of factual duty, and contracting parties who
commercial situations outside the must operate within its constraints.
construction industry, but given the BURGER KING
important general nature of the
principle, it will doubtless be The Facts
applied to construction contracts in In an attempt to strengthen its
equal measure to other kinds of Australian presence, Burger King
commercial agreements. Its entered into a series of
application to joint venture and to development agreements with
tendering and process contracts Hungry Jack's. Burger King then,
makes it especially relevant to however, used its contractual power
practitioners in the construction to impede Hungry Jack's capacity to
industry. perform its obligations by refusing
to approve development proposals
Before 2001, the circumstances in
and withdrawing its financial and
which an obligation to act in good
operational support. Burger King
faith was implied were generally
then purported to terminate the
described as falling into particular
contract. Hungry Jack's
categories or classes; for example,
commenced proceedings seeking
leases, motor dealership contracts,
orders that Burger King's conduct
tender process contracts etc.
lacked good faith and that its
However, a milestone in NSW termination of the contract was
occurred in 2001 when the NSW wrongful.
Court of Appeal, comprising
Sheller, Beazley and Stein JJA The Finding
delivered its joint judgment in The court found Burger King's
Burger King Corporation v Hungry termination was indeed wrongful
Jack's Pty Ltd. The judgment and resulted from its deliberate
upheld the decision of Rolfe J in the, attempts to impede Hungry Jack's
court belowwhich confirmed the capacityto perform its contractual
existence of a general implied duty obligations. Specifically, these acts

6 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003


were held to be in breach of the decisions of the courts which have The Scope and Operation of
duty of good faith and contributed to the formation of the the Duty of Good Faith
reasonableness which the court duty of good faith appear to indicate Having indicated that certainty in
implied into the contract. The court a willingness by the courts to depart contract may be at risk, we turn to
said that terms requiring good faith significantly from the well- examine what is of known about the
and reasonableness were implied established principles of contract scope and operation of the implied
into the development agreement in law when deciding the extent to duty of good faith and
this case, and that they were which one party can or may behave reasonableness.
implied as a matter of law. They pursuant to their contractual rights.
acknowledged that the In previous cases, where the duty of
If this is the case, it is not good faith was imposed, it was
development agreement did not
inconceivable that contracting restricted to particular classes of
fall into any of the traditional
parties might in proceedings assert contract or conduct so that the
classes of case where these terms
a breach of the implied duty of good presence or absence of good faith
had hitherto been implied, and the
faith in order to seek relief from could be determined by reference
decision therefore extends the
otherwise clear contractual to the standard of conduct which
principle into this 'new' class of
obligations. Indeed it is not can be reasonably required in those
agreement.
inconceivable that the implied duty particular circumstances. However,
Underlying Fairness of good faith might be used by one by extending the duty to
Inherent in Contractual party to suggest the 0 the r party has development agreements of the
misused, or is intending to misuse,
Justice type considered in Burger King, the
its contractual powers as a way of court has taken another step
The court's rationale in Burger King
increasing commercial pressure in towards the point where eventually
for its findings appears to be that
contract negotiations or during courts will apply the duty generally
the law of contract should be
performance of a contract. in contract law. This development
developed to embrace notions of
Notwithstanding these concerns, heightens the importance of
good conscience and good faith in
the courts do appear to be articulating the defined rules and
an attempt to strengthen and
committed to maintaining a stable standards as to what the duty of
encourage the use of contracts as a
basis for contractual activity. good faith requires of contracting
means of sound commercial
practice. This can be gleaned from The Integrity of the parties.
comments made by the judges in Contractual Objective Takes The court's willingness to impose
their decision. The history of these
Prominence Over the duty of good faith on contracting
attempts by the courts to govern the parties is clear: What is less than
practice of contracting have, over
Contractual Certainty
The need to provide a stable basis certain is what that duty actually
time seen the introduction of demands.
for contractual relationships is of
defined rules and standards as to
primary importance. The recent The duty of good faith has proven
the manner of both entry into and
good faith decisions appear to difficult to define and has resisted
performance of commercial
potentially downplay the attempts to describe the standard
contracts. A good example of this
importance of certaintywhere of conduct which will meet its
behaviourwas the introduction of
the Trade Practices Act. unfairness may otherwise result requirement and that which will
from its enforcement. The need for offend it. A starting point is Mason
The problem with such an approach a set of defined rules and standards J'Sl attempt to define the duty by
by the court is that it may have rather than an indeterminate reference to the characteristics
some unwanted consequences. For standard of conduct that nobody which will support it. That
instance, because the common law, entirely grasps was something that formulation required the parties'
as distinct from legislation, Gummow J addressed in Service loyalty to the contractual promise
develops graduallywith each new Station Association Ltd vBerg and their honesty and
decision, the absence of defined Bennett & Associates Pty Ltdin reasonableness in its performance.
rules and standards of what does or 1993. This has not, however, However, Mason J did not
does not constitute good faith deterred the courts from imposing particularly articulate the conduct
increases the risk that otherwise the duty where fairness requires it which would demonstrate
certain contract terms may become in the more recent cases. compliance with the duty.
uncertain of operation. This is
particularly so because the The difficultywith imposing a
standard by reference to qualities
such as honesty is that they are

AUSTRALIAN CONSTRUCTlpN LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003 7


The courfs willingness to notions of personal character faith resembles unconscionability at
impose the duty of good faith ratherthan standards of conduct equity, it is a natural extension of
which can be tested objectively. the law that the duty of good faith
on contracting parties is
Einstein J in Aiton v Transfield be moulded by the standards of
clear. What is less than considered the operation of the duty conduct identified as
certain is what that duty both internationally and within unconscionable. It is interesting to
actually demands. Australian law before attempting to note at this point that
define the scope of the duty. That unconscionabilitywithin the
attempt produced a useful guide as common law and under the Trade
to the standard of conduct which Practices Act is a concept confined
will see the duty breached, to particular classes of contract.
however, did not contribute much to The class limitation facilitates the
the definition of what the duty imposition of an objective standard
requires in orderto avoid its breach. of conduct bywhich to measure any
misconduct by the parties because
Burger King's contribution to the
a comparative examination of the
formulation of a standard is that the
behaviour complained of and the
implied duty of good faith and
behaviour required by the duty can
reasonableness is there to ensure
be undertaken.
thatwhile powers underthe
contract may be exercised to Withdrawing the class limitation
achieve a party's legitimate makes the task of defining the
contractual interests, they may not standard of conduct which will show
be exercised for a pu rpose the parties have acted in good faith
extraneous to the contract. In other more difficult. An objective standard
words, it may be a breach of the cannot be applied to a landlord and
duty of good faith where a party tenant relationship in the same way
exercises its powerto pursue an it would to joint venturers. Clearly
objective which the parties did not the commercial relationships
enter the contract to achieve. The involved create different obligations
result of this appears to be the requiring the importation of
emergence of a duty to act subjective standards. The
reasonably in pursuit of the established principles of
contractual objectives. Such a view unconscionability may however
of the duty does not limit the assist in identifying the obligations
parties' capacity to use reasonable which the duty of good faith and
pressure in commercial practice, reasonableness create. For
however, itwould appearto require example, section 51AD of the Trade
the parties to act reasonably in Practices Act requires compliance
pursuit of their contractual aims. with relevant Industry Codes. The
Where a party contracts for a benchmark forthe conductwhich
particular purpose and will not contravene these
subsequently changes its goal, unconscionability provisions is
good faith may bind it to the proper determined on an industry-specific
performance of the contract, by basis.
reference to the original goal or
When Will the Duty Apply
goals.
and What Conduct Amounts
Parallels Between Good to a Breach?
Faith and Unconscionability The following overview of some of
Acting fairly, reasonably and in the recent cases may give some
good faith are terms often used guidance on what behaviour might
interchangeably in Australian put a part at risk. This list is by no
contract law. The duty of good faith means exhaustive, and is intended
is a dutyto refrain from conduct as a sample only.
which is capricious or
unconscionable. Since lack of good

8 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003


OVERVIEW OF RECENT unenforceable mediation 5. Burger King vHungryJacks
CASES-GOOD FAITH agreement. [2001] NSWCA 187
Type of Agreement: Franchising
1. Renard Constructions (ME) Pty However, per Einstein J: 'To my
development agreement.
Ltd v Minister for Public Works mind, a notion of good faith is
(1992) 26 NSWLR234 implicit in any alternative dispute Finding: Held that the development
Type of Agreement: Construction resolution procedure, as without it agreement was subject to implied
Contracts. there is no chance of reaching a terms of cooperation, good faith
mutually satisfactory conclusion'. and reasonableness. Burger King
Finding: Showcause clauses-duty had breached those terms by:
to act reasona bly in: The judge then spelled out the core
content of the obligation: (1) imposing a freeze on awarding
(a) identifying breach which would of franchises to third parties;
activate clause; and (1) to undertake to subject oneself
to the process of negotiation or (2) withdrawing financial approval;
(b) considering whether or not mediation (which must be and
adequate cause shown-here the sufficiently precisely defined by the
dutywas breached. (3) withdrawing operational
agreement to be certain and hence
approval.
Comment: The duty has enforceable); and
subsequently been extended to 6. ALcateL Australia Pty Ltd v
(2) to undertake in subjecting
other clauses in construction Scarcella (1998) 44NSWLR 349
oneself to that process, to have an
contracts, e.g. clauses reserving Type of Agreement: Lease.
open mind in the sense of:
valuation powers to employers, Finding: Held that a duty of good
clauses empowering a contractorto (a) a willingness to consider
faith could by implication be
value progress claims by a such options for the resolution
imposed as part of a contract; in
subcontractor. of the dispute as may be
this case a lease. However, it was
propounded by the opposing
2. HughesAircraftSystems held not to be a breach of good
party orthe mediator, as
InternationaL vAirservices faith forthe lessorto pressure
appropriate; and
Australia (1997) 76FCR 151 council to issue fire orders with
Type of Agreement: Tender (b) a willingness to give respect to demised premises which
'process' contracts. consideration to putting forward were more stringent than those
options for the resolution of the which the tenant would otherwise
Finding: Duty on public bodies who dispute, L........ J. have had to complywith. 'The
are party to a tender process respondents had a legitimate
contract to: Comment: In this case, the judge
interest in ensuring the building
held that a fu rther ba r to the
(a) conduct tender evaluation was properly protected.'
plaintiff being successful was the
process fairly; and fact that it had not invoked the 7. Advance Fitness Corp Pty Ltd v
(b) deal fairly with tenderers. dispute resolution procedures Bondi Diggers MemoriaL &
Did not considerwhetherthese consistently itself. Sporting CLub Ltd[1999] NSW
terms breached here as case SC264
4. Garry Rogers Motors (Aust) Pty
decided on breach of express Type of Agreement: Lease.
Ltd vSubaru (Aust) Pty Ltd(1999)
process contract terms. ATPR41-703 Finding: Also involved a fire order-
Comment: The judge said Type of Agreement: Motor head lessee used the fire order as
nevertheless that there was dealership agreements. an excuse to close the premises
'evidence enough to warrant and terminate the sublease.
Finding: Held that there was an
Hughes' allegation of a breach of Nevertheless it was held that the
implied duty of good faith in such
the fair evaluation/fair dealing club's conduct was not
agreements, but the franchiser had
terms'. unreasonable.
not breached it. In fact the
3. Aiton v TransfieLd[1999] NSWSC franchisee was in breach of its own Comment: This was despite the fact
996 obligations, such that the franchiser that the club had an ulterior motive
Type of Agreement: Construction. was entitled to terminate. in wanting to accept an attractive
development proposal.
Finding: Express obligation to make
'diligent and good faith efforts to
resolve all disputes' was
unenforceable as tied to an

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003 9


8. Forklift Engineering Australia THE DUTY TO WARN Foundations of the Duty to
Pty Ltd vPowerlift (Nissan) Pty Ltd Warn
BC 200007795 Scope of Duty
The courts have viewed the duty as
Type of Agreement: Machinery The 'duty to warn' has emerged
arising in various ways, of which
dealership contract. gradually but inexorably over the
three main ones are apparent:
last 30 years into a well-recognised
Fi nd ing: Ad uty of good fa ith was
concept in construction law in 1. Some of the earlier cases
implied, and found to be breached
common law jurisdictions, and has discussed in this article seem to
on both sides. It was not open to
been applied in a variety of suggest that the duty is grounded in
one party to allege a breach of the a kind of 'fitness for purpose'
situations and to a variety of players
duty of good faith when it had
in the industry. obligation, where a party (generally
engaged in actions that constituted a contractor) enters into a contract
a breach of the duty on its own part. Though its genesis and foundations
with an ownerwho has in some way
are still the subject of some debate,
Comment: The judge drew a placed reliance on the contractorto
it is clear that it straddles both
pa,rallel with the equitable concept ensure that the resulting building
contract and tort. The obligations it
of clean hands'. (or other structure) fulfils the
imposes mean that not only must
intended purpose. Hence,
9. LMIAustraliaPtyLtdv parties look to protect those with
notwithstanding that the contractor
BauiLderstone Hornibrook PtyLtd whom they have a direct
himself may not be contractually
BC 200106393 contractual relationship, but they
responsible forthe particular
Type of Agreement: Heads of must also be concerned about
defective design orwork, he may be
agreement for stadium potential harm to others from
found liable for the consequences
management. whom traditionally they have been
of not warning the owner of the
one step removed.
Finding:Adopted BurgerKing risks of the substandard design or
principle that there are terms of Hence, subcontractors have been work in question.
good faith and reasonableness found liable to principals in respect
2. Other cases see the duty to warn
implied by law in virtually every of the faulty design of the principal's
as arising out of either an express
commercial contract. However own engineer, project managers to
here no contract emerged out ~f the
or an implied contractual obligation
principals in respect of design which
to act with the skill and care of a
heads of agreement and therefore theywere not themselves
reasonably competent contractor
no occasion for such terms to be employed to provide, and
(or project manager etc.). This
implied. contractors to principals where
approach is more common in
faulty information or design was
Comment: The judge also stressed recent cases.
provided by the principal's own
that the implied terms are not
consultant. 3. Thirdly, there are some cases
capable of rising above express
where the duty has been identified
terms. The result is to throw the spotlight
as arising in tort, as an extension of
on the interdependence of roles in
10. Cubic Transportation Systems a duty to exercise due skill and
an ever more sophisticated industry.
Inc &Anor vState ofNewSouth care. The tort approach has,
It seems likely that this continued
WaLes &2 Drs [2002] NSWSC 656 however, encountered difficulties in
trend will have effects on insurance
revised-27/02/2003 the jurisdictions where it has been
the drafting of contractual '
Type of Agreement: Government attempted. This is partly because of
indemnity clauses and more
tender process contract. the principle that that duty will only
practically, the extent to which
Finding: Judge held that there was extend to acts and omissions which
parties may feel encouraged or
an implied term of reasonableness are liable to cause injury to persons
obliged to take on the role of
and good faith but found that the or damage to property other than
'whistleblower' on site.
plaintiff tenderer had itself been the building being constructed, and
At the end of this paper is a partly because damage which
guilty of gross breaches of its own
summary of nine cases in this area, amounts only to pure economic
obligations of honesty, and thus its
several of which are referred to in loss is irrecoverable in tort. As the
claim failed.
the course of this paper. Those who law on both those principles has
Comment: This is another example wish to read further may find the developed somewhat differently in
of the courts insisting that a plaintiff remaining cases of assistance. Austra lia, however, it wi II be
alleging breach of good faith must interesting to see whetherthis area
himself come to court with 'clean develops in this country.
hands'.

10 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003


What Conduct will particularly in relation to the The ~duty to warn' has
Constitute Failure to Warn? inadequate ventilation; emerged gradually but
Although space will not permit of a (d) the contractor's obligation was inexorably over the last 30
detailed review of all nine cases, a to carry out work which would years into a well-recognised
brief review of five representative perform 'the intended duty or concept in construction law
samples of the cases will provide function' and that obligation
an idea of the range of conduct
in common law jurisdictions,
overrode the obligation to comply
which has been held to be a breach with the plans and specifications; and has been applied in a
of the duty. and variety of situations and to a
1. Brunswick Construction Ltd v (e) the contractorwas liable forthe
variety of players in the
NowLan (1974) 21 BLR27 failure of the work even though it industry.
The contractor in this case entered was carried out in accordance with
into a contract for the construction the plans and specifications.
of a house according to a design
It is clear that in this case reliance
specified by architects employed by
was an important factor. But forthat
the owner. Although the contract
factor, the implications of the
contemplated that an engineer
judgmentwould be ratherstartling;
would be appointed to supervise the
that a contractorwho is engaged to
works, no engineerwas appointed
perform work on the basis of design
and the contractor was to carry out
prepared by another forwhom the
the work on his own. The contract
owner is responsible, can be liable
specified that 'the contractor shall
forthe failure of that design. Later
give efficient supervision to the
cases, particularly Plant
work using his best skill and
Constructions, make it clearthat
attention' .
findings such as this are to be
The house developed serious leaks interpreted very much within the
and eventually required major confines of the facts of the
repairs. The problem appeared to particularcase.ln otherwords,
be that there was inadequate such findings are not to be taken as
ventilation in the roofwhich led to applying necessarily to other
rotting of the timbers. similar cases.
The owner took out proceedings 2. Victoria Unj1~·ersity ofManchester
against the contractor for breach of vHugh Wilson (1984) 2 Const LR 1
contract. He lost at first instance, The case concerned defects
but this was reversed on appeal. appearing in tiled cladding to
The contractor further appealed to buildings owned by the University.
the Supreme Court of Canada. The University commenced action
The Supreme Court upheld the against the architects, the
decision of the Appeal Court in contractors and nominated
favour of the owner, saying that: subcontractors. Proceedings were
settled against the architects but
(a) a company of the experience of one of the questions which arose
the contractor should have detected was whether the contractors had a
that the design of the house was duty to warn the architects of
bad; defects in design. The judge said
(b) since no engineer or architect that:
was appointed to supervise, it was In this case I think that a term was
clear that the owner relied on the to be implied in each contract
skill and attention of the contractor; requiring the contractors to warn
(c) since the contractor knew of the the architects as the University's
reliance which was placed on him, agents of defects in design, which
he was under a duty to warn the they believe to exist. Belief that
owner of the danger inherent in there were defects required more
executing the architects plans, than mere doubt as to the

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003 11


correctness of the design, but less the plaintiffs been hesitant or
than actual knowledge of errors'. reluctant to agree to the request, a
competent builder and project
In reaching this conclusion, the
manager would have sought to
judge relied on the case of Duncan
impress upon them the importance
v Blundell (1820) 3 Stark 6, and on
of obtaining such a report for
Brunswick Construction Limited v
ensuring the achievement of the
Nowlan, both of which
plaintiffs objectives and compliance
acknowledged reliance to be a
with the defendant's contractual
factor in finding that the duty
obligations.
existed.
The judge held that had a report
This case goes a little further,
been obtained, the likelihood was
however, than Brunswick, in that Mr
that itwould have recommended
Justice Judson in Brunswickfound
the correct solution to solve the
that:
problem.
A contractor of this experience
However, the judge did not
should have recognized the defects
specifically address the issue of
in the plans which were so obvious
whether or not the ownerwould
to the architect, Arnoud,
have acted on the warning given. It
subsequently employed by the
appears that the judge merely
respondents ...
assumed that that would have been
In other words, the defects were the case. The judge found that the
obvious. In this case, however, the project manager had been in
duty is said to extend to defects in breach of contract.
design which the contractors
4. Plant Constructions Plc vClive
'believe to exist'. This is a much
AdamsAssociates andJHM
lower th reshold.
Construction Services Ltd[2000]
Again, however, the more recent BlR137
decision of Plant cautions that In this case the Ford Motor
cases such as this should be Company employed Plant
restricted to thei r facts. Constructions to design and
3. Palermo Nominees Pty Ltd v construct two pits for engine mount
Broad Construction Services Pty rigs. Plant engaged JMH as a
Ltd[1999] 15 Bel 20 subcontractor It was part of the
The defendant project manager subcontract that JMH was to
was employed to design and complywith instructions given by
construct a nightclub. The internal Ford's senior engineer, Mr Furley.
acoustics were found to be Clive Adams Associates were
defective. The contract provided engaged as consulting structural
that the project managerwas to engineers by Plant.
'furnish the necessary professional During the project, Mr Furley for
skills, superintendence ... · to ensure Ford instructed JMH to support the
that the project was completed 'in a roof trusses by mea ns of fou r Acrow
thorough and workmanlike props at specified positions. The
manner' The project manager propping was inadequate and
failed to identify the need for an collapsed.
expert acoustics consultant for the
The judge held that the temporary
interior of the nightclub. The judge
roof su pport works were obviously
said:
dangerous and were known by JMH
/ am also persuaded that a to be dangerous. It was further held
competent builder and project that JMH had an implied obligation
manager in the circumstances then to perform with skill and care which
existing would have made such a carried with it an obligation to warn
request !i.e. to appoint an expert of the dangerwhich they perceived.
acoustics consultant]. Further, had Such warnings were not given.
12 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003
The Court of Appeal referred the obligation to exercise reasonable
matter to the trial judge on the care and skill in relation to the
issue of causation. The trial judge's duties which they agreed to
findings on that question are undertake. It was accepted that this
contained in a later section of this included the giving of appropriate
paper and will not be repeated safety advice to Pride Valley.
here. However, the Court of Appeal
There was a direct conflict on the
made the following important
evidence as to whether the project
comments on the extent of the duty:
manager had in fact given a
Any analysis of implied terms in a warning to the owner of the dangers
building contract must start with concerned with utilizing the
and take proper account of express particular insulation panels which
terms. Subject to the express terms, the ownerchose.ln the event, the
there will normally be an implied judge found that the project
term that the contractor will manager had not given the warning
perform his contract with the skill which it was claimed to have been
and care of an ordinarily competent given.
contractor in the circumstances of
The judge set out the detailed type
the actual contractor. In my
of information which he believed
judgment, the factual extent of the
the project manager should have
performance which this term
included in its warning. This
requires, will depend on all
information was based on
relevant circumstances which may
knowledge of the product which the
vary enormously. I shall not attempt
court found the project manager
to make a comprehensive list of
had at the time. The court also
possible circumstances.
found that the project manager's
Although in this case the knowledge of the danger of
subcontractor ought to have installing these particular panels:
warned of such an obvious danger,
went beyond that which was
the court went on to say:
generally accepted by fire officers
I would expressly reserve for future and others in the industry for whom
consideration circumstances the use ofsuch panels was
where: acceptable. If Hall had such
fa} the contractor did not know, but knowledge at the time they should
have communicated the nature and
arguably ought to have known, that
extent of the risk of the use of EPS
the design was dangerous; and
panels to Pride Valley.r... JIf Halls
fb} there was a design defect, of had given Pride Valley this advice
which the contractor knew or ought and it had been accepted I find that
to have known, which was not on the balance ofprobabilities the
dangerous. fire would not have occurred.
5. Pride VaLLey Foods Ltd vHaLL and As can be seen from extracts
Partners [2000] EWHC Technology contained in the following section
106 on the question of causation, the
Hall & Partners were engaged as a judge in fact found that the owner
project manager for the would not have followed the advice
construction of a bread factory. given. The court did find that the
Because of the use of certain project managers, as a competent
flammable insulating panels, fire and prudent firm of quantity
spread throughout the factory and surveyors and project managers,
destroyed it. The claim against the should have given the advice in
project managerwas that it caused writing. However, the court did not
the fire by failing to discharge its consider how much further the
contractual duty of care. By the warnings should have been taken.
contract, Halls were under an

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003 13


The Question of Causation additional fee, which Plant might or came to worst, JM H could simply
One of the more interesting aspects might not have been prepared to refuse to work further (whether or
of the duty to warn is that it carries pay. If the calculations had been not that might have been in breach
with it an essential subsidiary done they would have shown that of contract) and that to that extent
question: Would the party receiving the scheme was unsafe but might the duty to warn would have been
the warning have acted on it? In or might not have persuaded Mr discharged, whether or not the
other situations where a duty of Furley of his error. If so, and if Mr collapse eventually occurred.
care or a similar duty is being Adams had produced a safe design,
Although this seems rather
considered, whether arising in Mr Furley might or might not have
extreme, it is, I submit, the logical
contract or in tort, the particular accepted it, and in the latter event
conclusion which that line of
breach usually involves some might or might not have produced a
enquiry eventually reaches. The
visible consequences which can new and safe scheme of his own.
judge no doubt considered such
readily be examined to see whether Despite this considerable degree of evidence as was put before him as
they have caused the loss uncertainty, the judge went on as to the likely conduct of the parties
complained of. In most cases, the follows: being warned, and has bravely
question of causation can be tackled head on the uncertainty
disposed of by hearing expert It is unnecessary to make such
which that evidence produced.
evidence, from which a judge can findings because whatever the
often readily arrive at a conclusion. detail of the route there were, on It is submitted that whilst every
my findings above as to what JMH case will be different on its own
However, in the case of a duty to should have done, only two possible facts and there may well be cases
warn, quixotic aspects of human destinations. Either there would where evidence of what the warned
nature intervene. Just as one may have been a new design which JMH party would have done is
lead a horse to water but not make could consistently with its safety compelling, in many cases the duty
it drink, one may warn a party but responsibilities accept orJMH to warn will continue to suffer from
not oblige him to heed that warning. would have declined to execute the shadow of this subsidiary
Many of the cases gloss over this what it believed to be an unsafe question.
aspect, or assume that the party scheme. f. ..J It is in my view a
In Pride Valley Foods Limited, an
being warned would have acted in a legitimate, and indeed inevitable,
even more interesting situation
way which, with hindsight, would inference that on the balance of
arose. The judge in that case was
have appeared sensible and logical. probabilities there would have been
asked to directly address the
no collapse had there been a
However, some of the more recent question of whether the advice
design which JMH, on the above
cases, in particular, Plant would have been followed. He dealt
basis, accepted.
Constructions and Pride Valley with it in this way:
Foods Limited, examine this issue It is notable that the judge did not
Mr Rezaei says that if the advice
more directly. considerwhether or not there
had been given in clear terms he
would have been any collapse had
In Plant Constructions, His Honour would have accepted it even if it
JMH not been presented with any
Judge Hicks of the Technology and meant that the cost of the building
design with which it was happy.
Construction Court examined what was substantially increased.
Indeed, elsewhere in the judgment,
the consequences of adequate
thejudgeasked howfar JMH
warning might have been:
should have gone in carrying I find that Mr Rezaei was an honest
Again it would be difficult and is through its warning: witness who nowgenuinely
unnecessary to make detailed believes that if Halls had given the
The crucial question is whether
findings as to the course which advice in the terms in which they
JMH could and should, in the last
events would then have followed. It say they did he would have
resort, have refused to continue
would be difficult because the accepted such advice and the fire
work if the safety of workmen was
contingencies are so varied. Plant would never have occurred.
at risk, as it had done in the case of
might or might not have instructed
the ring main. I am clear that it
MrAdams to carry out the
could and should have done so.
necessary calculation to I do not find that he would have
demonstrate the inadequacy of Mr It is clear from this that the judge done so. I have come to the
Furley's scheme or to design an accepted that there was no conclusion that Mr Rezaei would
adequate and safe one. If they had certainty that the warning would be have rejected Hall's advice unless it
done so, Mr Adams would, on his accepted, but he seemed to be was supported by a requirement
evidence, have required an clear in his own mind that if worst from the Planning or Fire

14 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003


Authorities and/or was required by merely give a simple warning, and
his insurers. places an onus on a class of
construction industry participants
who are not even recognized as a
/ do not regard this attitude as separate profession, and must give
unreasonable .... them pause forthought as to their
Here the judge had ample time to potential liabilities and the
assess the witness and form his inevitable effect it will have on their
own conclusion. Interestingly, the insurance requirements.
judge did not consider this question Given that robust beginning, it
under the heading of causation, and seems likely that Plant
instead examined causation in a Constructions and Pride Valley
different way, namelywhetherthe Foodswill find some resonance in
use of the defective materials in the Australian courts when the matter
way in which they were used in this next arises for consideration.
case involved a foreseeable risk of
Hitherto, there is little to suggest
fire. In otherwords, the judge
that the concept of the duty to warn
examined the physical chain of
will take on a life of its own
causation but considered the
independent of a basis in contract
question of whether or not the duty
ortort, but given the direction being
to warn would have been acted on
taken in the area of good faith, it is
as a separate issue. He summed up
not out of the question that a similar
his thinking as follows:
philosophical approach might not
/ conclude on all the evidence that be applied. Inth e cas e 0 f the duty to
the loss, i.e. damage by fire was warn, its environment is further
entirely foreseeable and that the affected by increased regulation in
failures of Halls to warn Mr Rezaei the areas of environmental
of the nature and the extent of the protection and occupation health
risk of which they were aware and safety. At all events, the
would have been an effective cause message to industry participants is
of the loss if / had concluded that to watch the development of this
Pride Valley would have accepted concept with a wary eye, and most
and acted upon the advice. certainly to err on the side of
Contributory Negligence caution where defective design or
da ngerous construction methods
Another interesting feature of the
come to light. It seems safe to say
cases involving a duty to warn is the
that integration of responsibility for
extent to which contributory
safety and defects on construction
negligence has been a feature of
sites is the most likely direction for-
the decision. Space in this paper
this area of the law to take, rather
will not permit of an exhaustive
than a return to strict and narrow
analysis of how this issue has been
contractual interpretation of
dealt with in the cases, but the
res po nsib ility.
summary at the end of this paper
provides a check-list for readers OVERVIEW-DUTY TO
interested in considering this issue. WARN CASES
Possible future directions 1. Brunswick Construction Ltd v
Whilst the duty to warn has not Nowlan (1974) 21 BLR27
reached far into Australian case law Allegation: Breach of contract by
as yet, Palermo Nominees Pty contractorwhere the house is
Limited has already meant that the virtually uninhabitable, despite
concept has a robust foothold in this being constructed in accordance
country. The obligations imposed by with plans prepared by owner's
that case on project managers go architect.
further than a requirement to

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003 15


Contract/1o rt: Contract (empmasis
l
had a duty to warn the owner that it (c) even if surveyor had given
on reliance-owners did not employ was impossible to erect a building assurances, should have put up
architectto supervise construction). on the site as it existed without temporary propping.
resulting in damages.
Finding:,lhe contractor undertook Causation: Not directly considered.
to carry out the work to 'pe,rrform a Causation: Not directly consi'dered.
Contributory Negligence: Yes-
certain duty or furnction', irm
Contributor)' Negligence:: N'ot surveyor 75% responsible and
accordance with plans and
relevant., CGJHl1ltractor 25%.
specifiications.The works
constructed in accordance with the 4. UniveJfSityCourt ofGiasgowv Ii. Bow Valley Husky (Bermuda) Ltd
plans and specifications could not Whitfie,IdandJohn Laimg v'SaintJohn Shipbuilding Ltd
perform that duty or function. The (Construction) Ltd(19fJ8) 42 BlR 66
J
(Supreme CaurtofCanada,
contractor was in breach of a duty Allegation: Architectsclaimed judgment deliM!red December
towarn the owners of the danger against the contractor in third party 1997)
inherent in executing the architect's proceedings, alleging negligence in Allegation: Supplier alleged to
plans. construction or failure to warn the have breached duty to warn owner
university or architect of defects in about flammability of therm!al
Causation: Not directly considered.
the architect's design of art gallery. wrapping.
Contributory Negligence: Not
Contract/Tort: Both. ContractlTort: Tort.
relevant.
Finding: Re. University-Contract Finding: Supplier found liable to the
2. Victoria University ofManchester
had no liabilityforcontribution owner for breach of duty to warn,
v Hugh Wilson (1984) 2 Canst lR 1
based on any liability to the despite the fact that the supplier
Allegation: That contractor had a
university in contract, as statute- warned the contractor and despite
duty to warn the architect (as agent
ba rred by Civil Liability the fact that the owner knew as
of principal) of defects in the
(Contribution) Act 1978. Also, no much about the product as did the
architect's own design.
duty in tort, as that would be limited supplier and contractor (owner had
Contract/Tort: Contract-reliance to avoiding damage to property selected supplier-contractor had
appeared to be an issue. otherthan the building. not).
Re. Architect-Could only be in tort
Finding: A term was to be implied Causation: Addressed-held that
as there was no contractual
into contract requiring the the owner would have either
relationship. Here-no duty to avoid
contractor to warn the architect (as declined to use thermal wrapping
what could only be economic loss to or taken steps to deal with its
the university's agents) of defects in
the arch itect. inflammability had it been warned.
design, which they believed to exist.
'Belief required more than mere Causation: Not relevant. Contributory Negligence: Owner's
dou bt as to the correctness of the claim reduced by 60% to take
Contributory Negligence: Not
design, but less than actual account of the owner's negligence.
relevant as between contractor and
knowledge of errors.
architect. 7. Palermo Nominees Pty Ltd v
Causation: Not directly considered. Broad Construction Services Pty
5. Edward Lindenburg v Joe
Contributory Negligence: Not Canning(1992) 62 BlR 147 Ltd[1999] 15 BCl 20
relevant. Allegation: Contractor in breach of Allegation: Project manager
an implied term to work with skill alleged to be in breach of
3. Triple A Investments Ltd vAdam
and care and in good and contractual duty as competent
Brothers Ltd(1985) 23 DlR (4 th )
workmanlike mannerwhere he builder and project manager, to
Allegation: Breach of obligation to
demolished load-bearing walls, warn the owner of the dangers of
perform work in a proper and
which were marked 'non-load- not securing a report of an expert
workmanlike mannerwhere the
bearing' on plan by the owner's on internal acoustics of the
contractor knew that, because the
surveyor. nightclub.
site was not properly compacted,
the building would not be fit for its Contract/Tort: Contract. Contract/Tort: Contract.
purpose. Finding: Contractor in breach of Finding: Project manager in breach
duty. Contractor should have:
Contract/Tort: Contract-reliance of contract in failing to recommend
an Issue. (a) realised wall likely to be load- to the ownerthe appointment of an
bearing; expert consultant on internal
Finding: Contractor must be taken
acoustics. Had the owner been
to have known that fill had not been (b) raised doubts with surveyor (i.e.
reluctant, a competent builder and
properly compacted. Contractor duty to warn); and

16 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003


project ;managerwould have sought the owners.
to impress upon the owner the
Contract/Tort: Contract.
importance of doing so.
Finding: Projectmanagerwas
Causation: If a report had been
under duty to prepare a schedule of
obtained, the likelihood is that it
requirements which to their
would have recommended a
knowledge did not constitute an
correct solution (no analysis of
unacceptable fire risk. If the owner
whether ownerwould have acted
specified materials which were an
on itl.
unacceptable fire risk, the project
Contributory Negligence: Not manager had a duty to warn. This
addressed. dutywas breached. The project
manager had knowledge of the
8. Plant Constructions Plc vClive
danger of the materials which went
Adams Associates [2000] BLR 137
beyond the knowledge of the fire
Allegation: Subcontractor in breach
department and others in the
of an implied term to perform the
industry. He should have
contract with the skill and care of
communicated this to owner but did
an ordinarily competent contractor
not.
by not warning the owner of
dangerous temporary roof support Causation: Judge held that the
works. owner would have ignored the
advice, and therefore the owner
Contract/Tort: Contract.
was not entitled to recover (this
Finding: Held the subcontractor in amounted to a finding of break in
breach of an implied term. Factual the chain of causation, although not
extent of the performance which the characterised that way by the
implied term requires will depend judgel.
on all relevant circumstances in
Contributory Negligence: Had the
each case. The duty to warn was not
owner been entitled to recover,
a contractual duty, but arose out of
would have reduced it by 50% due
the implied duty of skill and care.
The trialjudge said the to contributory negligence.
subcontractor should have pressed
objections, which should have been REFERENCE
progressively more formal and 1. Contract, Good Faith and
insistent if not met, including Equitable Standards in Fair Dealing
reporting to regulatory authorities. (2000) 116 LOR 66.
If necessary, should have 'downed
tools'.
Irene Wales' paperwas presented
Causation: Addressed-either a at the seminar Recent Issues in
new safe design would have been Building & Construction Law,
adopted orthe subcontractorwould presented by Legalwise Seminars
have declined to carry out unsafe Pty Ltd, held on 28 October 2003 in
scheme; therefore on the balance Sydney. Reprinted with permission.
of probabilities, there would have Irene Wales acknowledges the
been no collapse. assistance of Helena Golovanoff,
Contributory Negligence: Not and Andrew Wallis & Melanie
addressed. Maslem with regard to the section
on Good Faith.
9. Pride Valley Foods Ltd vHall and
Partners [2000] EWHC Technology
106
Allegation: That fire was caused in
a bread factory by the project
manager failing to discharge a
contractual duty of skill and care to

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #93 NOVEMBER/DECEMBER 2003 17

You might also like