Professional Documents
Culture Documents
BCO - 2012 - On-Site Renewables - September 2012
BCO - 2012 - On-Site Renewables - September 2012
ACKNOWLEDGEMENTS
June Taylor, Patrick Dwyer and Simon Sturgis of
Sturgis Carbon Profiling, Sarah Cary of British Land,
Daniel Winder of Sheppard Robson, Jenny MacDonnell
of the British Council for Offices and Steven Clark and
David Selby from Hopkins Architects.
CONTENTS
© BCO 2012 3
ON-SITE RENEWABLES
TERMS OF REFERENCE
This research was commissioned by the British market, for example by acting as an incentive to
Council for Offices (BCO) to follow up its 2007 report retain and refurbish older stock
on the Greater London Assembly’s (GLA’s) policy I identify alternative policy structures that would offer
for achieving emissions reductions through on-site different compliance costs and generate additional
renewable energy provision. emissions reductions
I identify building types that are more capable of
Specifically, it set out to:
compliance, to aid investment decisions and offer
guidance to design teams
I quantify the impact of the GLA policy on the
environment (represented by the opportunity cost of I advise on which measures yield the greatest carbon
alternatives that could yield higher carbon savings) returns on financial investment
and on developers (represented by the additional I examine whether and to what extent the 2007
costs of building and operating renewable measures) report’s predictions have been fulfilled.
I examine whether this policy may have had
secondary effects on the City of London property
4 © BCO 2012
ON-SITE RENEWABLES
EXECUTIVE SUMMARY
INTRODUCTION
This research was commissioned by the BCO to follow
up its 2007 report on achieving emissions reductions
through on-site renewables. That report was written in
the context of the GLA’s proposal to increase its target
for the proportion of emissions reductions delivered by
on-site renewables from 10% to 20% of a building’s
regulated energy demand. It expressed concerns over
whether the policy offered an effective way of achieving
emissions reductions, and called for a more flexible
approach. This report seeks to identify whether these
concerns were justified.
FINDINGS
This report includes five case studies that suggest I many technologies can be integrated within building
valuable lessons for other developers: services design.
I there are many discrepancies between modelled Costs and benefits to developers
energy use and actual use
The report analyses 77 central London commercial
I more attention should be paid to renewable cooling office developments, and finds that:
solutions in commercial buildings
I occupiers should be given advice on optimising and I on-site renewables can generate modest financial
monitoring their energy use returns to investors and occupiers in the presence
© BCO 2012 5
ON-SITE RENEWABLES
of subsidies, but in most cases represent a financial I Cost is extremely sensitive to external factors – for
burden once indirect losses have been accounted for example, increasing by £208 if a building is subject
I the range of costs and benefits varies widely across to conservation area status (based on statistically
the sample (Figure 2) significant evidence at the 5% significance level
(P < 0.005)).
I the cost per tonne of emissions reduced also varies
widely, from a net present value (NPV)1 of £145 per I The cost per tonne is £360 higher where subsidies
tonne gain to a loss of £2800 per tonne, with an have been claimed (based on statistically significant
average cost of £380 per tonne even with the aid evidence at the 5% significance level (P < 0.005)).
of subsidies.
1,000,000
Benefit to developer: 10-year payback period, 8% discount rate
Benefit to developer: 7-year payback period, 13% discount rate
800,000
Benefit to developer: 3-year payback period, 33% discount rate
600,000 Total costs (PV)
400,000
200,000
–200,000
–400,000
–600,000
–800,000
–1,000,000
1 Figures for NPV profit and loss take account of all carbon saved by a measure, and the associated financial costs and benefits, over its
lifetime.
2 The P value is the probability of the null hypothesis that the effect detected is due to random variation of the sample and does not
represent the population. A low P value indicates that there is a very small chance that the null hypothesis is correct, and so the
regression coefficient is significant.
6 © BCO 2012
ON-SITE RENEWABLES
Cost to taxpayers
£59
million
454,000 £18 million
tonnes
£174 million
Figure 3 Aggregate costs and benefits
Social value
CO2 saved
of on-site renewables.
Cost to developers Courtesy of Sturgis Carbon Profiling LLP
RECOMMENDATIONS
This report recommends working towards higher I investigating more flexible policies, such as allowable
emissions reductions by: solutions or market-based alternatives, which can
provide a mechanism for delivering emission
I acknowledging that, economically, renewables have reductions in the most cost-effective way
more in common with conventional energy generation I making a more detailed enquiry into how these findings
processes than previously considered (returns to relate to other land markets and commercial building
scale and high fixed costs). types across the UK. (Currently, in the majority of
I carrying out a wider examination of the costs and circumstances, in the office sector renewables are
benefits of achieving emissions reductions across being installed simply to secure planning consents. This
the built environment – i.e. comparing the social has the negative impact of leading the renewables
and financial benefits from renewables on a level market through false market signals, and thus of
playing field with other alternatives such as embodied diverting resources from areas of technological
carbon reductions, decentralised power, community development that are more cost-effective.)
retrofit and better metering initiatives
I reviewing the efficiency of subsidies applicable As such, this report should be taken as a scoping
to on-site renewables – i.e. questioning whether study for a wider review of the economic and
it is possible to target subsidies more effectively environmental benefits of low-carbon legislation
to large-scale developments and thus encourage affecting commercial property in the UK, with the aim
developers to profit seek by using renewables of delivering the greatest carbon reductions at the
rather than through achieving minimum levels least cost to developers, building owners and occupiers.
of compliance
I examining the scope for district power solutions or
large-scale renewable installations, and the barriers
to their implementation
© BCO 2012 7
ON-SITE RENEWABLES
INTRODUCTION
AIMS
The construction and use of the built environment is
one of the largest sources of greenhouse gas emissions
in the UK, accounting for about half of total emissions
(CABE, 2007). Every year, construction of commercial
buildings in the UK produces over 80 million tonnes
of carbon dioxide (CO2) emissions (United Nations
Statistics Division, 2012), more than the combined
CO2 emissions of the Irish, Kenyan and New Zealand
economies.
Responses to this challenge have included the surrounding the use of on-site renewables. Crucially, we
formulation of policies that directly or indirectly require consider the full range of costs and benefits, including:
developers to include on-site renewable energy
generation capacity in all new developments. I tax benefits
I the indirect cost to taxpayers of subsidies
To date, various studies have been conducted to quantify I loss of lettable area (e.g. storage of fuel such as
the emissions reductions delivered by these policies wood chips can take a considerable amount of
(Day et al., 2007, 2009) and the predicted capital space (Figure 4))
cost of meeting the emissions reduction targets they
I sensitivity of future financial savings to occupiers’
specify (BCO, 2007). However, there has been limited
perceptions
progress in understanding either the actual capital
costs or the wider indirect costs. Likewise little work I hidden costs such as maintenance, repair and
has been done to quantify the benefits of on-site replacement fuels
microgeneration in terms of reduced running costs I forgone damage to the environment.
and forgone damage to the environment.
The study is based on a sample of 77 commercial
This study makes a unique contribution, by investigating buildings in London in which on-site renewables were
and developing an understanding of the fuller3 picture installed during the period 2006–2010.
3 The authors acknowledge that defining the range of relevant factors affecting costs is as much a subjective judgement as an empirical
question. To help clarify this stuation, only those items that have been shown to have a statistically significant impact on compliance have
been included.
8 © BCO 2012
ON-SITE RENEWABLES
REPORT STRUCTURE
First, a brief review is given of the policies driving Question 2: What are the dominant factors affecting
the adoption of on-site renewable energy generation the financial cost of using on-site renewables to
capacity in new London developments. This is followed reduce building emissions?
by a brief summary evaluation of the most widely
Question 3: How do these costs compare with those of
available renewable technologies. The installation
other policy alternatives?
of these technologies in five case study buildings
in London is then described, with an explanation Question 4: How do these costs compare with the
of the project teams’ rationale for choosing specific forgone environmental damage delivered by using
technologies and a review of their performance. on-site renewables?
To investigate the issues surrounding the use of on-site These questions were selected to provide insight into
renewables, four key questions have been identified, the efficiency of policies requiring the use of on-site
and these are addressed in sequence. Each question renewables in central London, a topic not yet addressed
is accompanied by a brief description of the data and in other reports in the public domain.
methods used in answering it, the results that arose,
and a discussion of the implications of these results. The report concludes with a discussion of the broader
implications of the study’s findings.
The four key questions identified by this report are:
POLICY BACKGROUND
The primary factor driving the adoption of on-site Plan, there is evidence to suggest that the intended
renewable energy generation capacity in new London reductions did not materialise (London South Bank
developments is the London Plan.4 It does so through University, 2009). A study by London South Bank
an explicit requirement for a reduction in building University (2009), reviewing emissions reductions through
emissions to be achieved using on-site renewables on-site renewables over progressive 12-month periods
wherever feasible. across 147 developments, found a significant reduction in
the average emissions reductions achieved, particularly
The origins of this requirement can be traced back to in early 2009 (Figure 6). This trend is partly explained
Merton Council’s introduction of a planning policy in 2003 by the fact that since the 2008 Plan, other alternatives
(Figure 5), requiring at least 10% of building energy to be have been allowed to be considered towards targets.
delivered by on-site renewables wherever feasible. This
requirement subsequently became known as ‘the Merton The most recent revision of the Plan, issued in 2011, is
Rule’, and was incorporated in the 2004 London Plan less prescriptive, stating only that: ‘major development
as part of a wider range of policies aimed at reducing proposals should provide a reduction in expected CO2
building emissions. The Plan was revised in 2008, emissions through the use of on-site renewable energy
when the required proportion of emissions reductions generation, where feasible’.5 Although it is no longer
from on-site renewables was increased to 20%. stated as an obligation, the policy's supporting text
includes a presumption that major developments will
Despite the more challenging target for emissions achieve a reduction of at least 20% through using
reductions from on-site renewables introduced in the 2008 on-site renewables.
4 The London Plan is a set of policies developed by the Mayor of London, which together make up London’s spatial development strategy
(Mayor of London, 2004, 2008, 2011b).
5 No definition of what constitutes ‘feasible’ is provided in the London Plan. Where a developer believes that compliance with the full
percentage requirement is not feasible, the onus is on him to justify his position and to provide evidence of having investigated possible
solutions.
© BCO 2012 9
ON-SITE RENEWABLES
Reviews Policies
2001 Enhanced capital allowance scheme introduced
2002
2003 Merton Council introduces 10% renewables requirement
2004
BCO first report 2005 The London Plan adopts the Merton Rule
2006
LSBU first review 2007 Feed-in tariffs scheme introduced
2008
2009 London Plan renewables requirement increased to 20%
LSBU second review
2010
2011 New target emission rate in the Building Regulations
2012
GLA monitoring review 2013 No requirement in the London Plan, but a presumption of 20%
2014
2015 Target date for 20% reduction on 2010 TER
2016
2017 Target date for 40% reduction on 2010 TER
2018
2019 Target date for zero-carbon commercial buildings
10 © BCO 2012
ON-SITE RENEWABLES
Figure 8 Potential likely future changes to the Part L target emissions rate.
Courtesy of Sturgis Carbon Profiling LLP
6 The scope of Part L covers only regulated emissions (fixed services), while the London Plan covers all emissions within a building.
© BCO 2012 11
ON-SITE RENEWABLES
12 © BCO 2012
ON-SITE RENEWABLES
CASE STUDIES
THE USE OF RENEWABLES ON FIVE BUILDINGS
ROPEMAKER PLACE
© BCO 2012 13
ON-SITE RENEWABLES
THE PEAK
14 © BCO 2012
ON-SITE RENEWABLES
Lessons learnt: The incorporation of PV cells onto buildings is becoming more common due to the FITS.
Relatively easy installation, coupled with minimal maintenance, makes PV cells a perfectly viable technology.
Although solar thermal is less common on office buildings, The Peak does have catering facilities, and so good
carbon savings are expected.
The Colt Colaris system is designed to use the near-constant year-round temperatures of chalk aquifer water
to improve heat-pump efficiency in both cooling and heating modes. When considering the constrained site
footprint in Victoria, the system made sense in terms of integrating services design with renewables requirements.
© BCO 2012 15
ON-SITE RENEWABLES
HERON TOWER
16 © BCO 2012
ON-SITE RENEWABLES
PORTCULLIS HOUSE (not part of the study sample, as it was opened in 2001)
Architects: Michael Hopkins and Partners Location: Bridge Street, London SW1
Developer: Parliamentary Works Directorate Floorspace: 20,000 m2
M&E: Crown House and Kaverner Rashleigh Weatherfoil Use: Parliamentary Offices
Rationale for installation: The borehole cooling system was a part of a pre-BREEAM ground-breaking sustainable
design approach backed by EU-funded research. It entailed passive elements of thermal mass, solar shading
and daylight enhancement.
Performance of the system: Some initial teething issues were evident before the building management and
occupants were able to ‘get the best out of the building’, which is not surprising as the system had not
been experienced before. After this initial period
of familiarisation with the building’s sustainable
features, dynamic seasonal variations etc., the use
of more sophisticated controls than those originally
utilised when the building was occupied enables
the building management team to make significant
reductions in the use of energy and water.
© BCO 2012 17
ON-SITE RENEWABLES
Rationale for installation: Solar thermal heating and PV cells were installed during the refurbishment of the
building to improve its environmental performance.
Performance of the system: The system has remained fully functional since its installation, delivering heating
and hot water, and significantly reducing the carbon footprint of the building’s occupants.
Lessons learnt: Solar thermal and PV cells were found to be cost-effective methods of improving the
environmental performance of a mixed-use building undergoing refurbishment, given the constraints of existing
structural loads and restricted floor-to-ceiling heights.
18 © BCO 2012
ON-SITE RENEWABLES
QUESTION 1:
WHAT ARE THE FINANCIAL COSTS AND BENEFITS TO DEVELOPERS AND
OCCUPIERS OF REDUCING EMISSIONS USING ON-SITE RENEWABLES?
Motivation involving the application of renewable technologies
Understanding the separate costs and benefits of were included in the sample, reducing the sample size
on-site microgeneration helps to examine whether to 82 in total. A further five buildings were removed
efficient decision-making is possible in the context from the sample as they used highly visible renewable
of energy efficiency. This is especially relevant given technologies, and thus valuing their aesthetic benefit
the incentive misalignment problems that frequently with any certainty was considered to be too complex.
result in non-optimal outcomes in this sector. These In total, 77 buildings were examined. Given this
problems include: relatively small sample size, generalisations made
later in this report to other office markets should be
I Landlord/tenant issues – capacity installed by the treated with some caution.
landlord delivers benefits to the tenants, and the
developer may not capitalise these benefits in rents.
Defining costs
I Allocation of risk – energy savings generated can
The specification given in Figure 9 was used to define
be subject to heavy discounting due to policy and
the present value of financial costs. It incorporates the
energy market uncertainty, which may not align with
main ongoing cost elements involved in using renewable
the risk profile of the building’s owner.
technologies, over the lifetime of the renewable measure:
I Developer/resale issues – capacity installed by the loss of rent derived from loss of lettable area; materials
project’s developer may not result in capitalisation in and labour used in maintenance; and replacement
the building’s value at sale, if it involves additional fuel. Appendix 1 provides a more detailed description
complexity in facilities management (as is often the of the methodology, discount rate and variables used
case with biomass). and the sources of data.
© BCO 2012 19
ON-SITE RENEWABLES
Construction Value of
cost renewable
obligation
– certificates
Tax benefit on
construction +
cost
Benefit = Value of
Deflated to other
2005 values subsidies
Discount
+ + ÷ rate and
Displaced period
gas use
Net area loss
× ×
Price of gas
Lost rent
(basement)
+
+ Displaced
Net area loss electricity use
Cost = × ×
Lost rent Price of
(above ground) OVER LIFETIME
Discount electricity
OF BUILDING
+ ÷ rate and
Maintenance period
materials
Figure 10 specification for defining benefits.
Courtesy of Sturgis Carbon Profiling LLP
+
Maintenance
labour Important Finding: The average costs and benefits of
+ the sample are £570 and £190, respectively. Figure 12
illustrates how these are broken down into their
Replacement
fuels OVER LIFETIME components from the specification described earlier.
OF BUILDING
Figure 13 illustrates a basic marginal abatement cost
Figure 9 Specification for defining costs. curve (dividing the net cost of a renewable technology
used on a building by the total number of tonnes of
Courtesy of Sturgis Carbon Profiling LLP carbon emissions displaced by the use of renewables in
a given year) constructed in order to compare renewable
technologies on a cost per tonne basis across the
been calculated for three distinct discount rates (8%, 13% sample. Further details are given in Appendix 1.
and 33% – see Appendix 1 for discussion on discount
rates). The variation in benefits at different discount For each building in the sample, the emissions displaced
rates illustrates how different occupiers might view over the lifetime of the technology were assessed, with
the risks associated with the returns from renewable each year of emissions given equal weighting. The total
technologies. For a technology with a 20-year lifespan, emissions displaced were then ranked according to
these discount rates correspond to an implied range of ascending costs along the horizontal axis in Figure 14,
payback periods of between 3 and 10 years, which is with the width of the bars representing the amount of
consistent with other occupier behavioural studies displaced emissions for each building. Thus the area
undertaken for small-scale microgeneration (Element of each bar becomes the total net cost or benefit of a
Energy, 2009). renewable technology.
20 © BCO 2012
ON-SITE RENEWABLES
1,000,000
Benefit to developer: 10-year payback period, 8% discount rate
Benefit to developer: 7-year payback period, 13% discount rate
800,000
Benefit to developer: 3-year payback period, 33% discount rate
600,000 Total costs (PV)
400,000
200,000
–200,000
–400,000
–600,000
–800,000
–1,000,000
Figure 11 The costs and benefits for the 77 developments assessed in this study.
Courtesy of Sturgis Carbon Profiling LLP
–
Cost of each Total benefit
tonne of CO2 = over lifetime
saved of building
Value of initial
÷
Capital cost subsidies
Total emissions
Indirect cost of Value of displaced fuel displaced
lettable area lost and heat
(over lifetime
Maintenance and Value of post-installation of building)
materials subsidies
Figure 12 Average costs and benefits to developers. Figure 13 Marginal abatement cost curve.
Courtesy of Sturgis Carbon Profiling LLP Courtesy of Sturgis Carbon Profiling LLP
© BCO 2012 21
ON-SITE RENEWABLES
1000
500
Savings
1.7 tCO2e saved at a cost of £1620.94/tCO2e to developer
Costs
Subsidised abatement cost (£/tCO2e)
1500
1000
22 © BCO 2012
ON-SITE RENEWABLES
Figure 14 incorporates the value of any subsidies that most instances the direct financial costs significantly
were applicable to specific buildings in the sample. Figure outweigh the direct financial benefits (associated
15 shows the same data with these values removed, environmental benefits will be considered later in
to illustrate the impact on costs of withdrawing subsidies. the report).
I The level of benefits varies significantly, even
between buildings that incurred similar costs.
Discussion
Two observations can be made on comparing the costs As illustrated in Figures 14 and 15, the net costs per
and benefits of installing renewable technologies in tonne of displaced carbon emissions across the
different building types: sample range from:
I Regardless of the discount rate chosen (based on a I £0.47/tonne CO2 to £3089/tonne CO2 when subsidies
comparison of three rates: 8%, 13% and 33%), in are not in place, to
20
Cars full hybrid
0
5 10 15 20 25 30 35 38
–20
Geothermal Abatement potential (GtCO2e per year)
–40 Rice management
Small hydro Solar CSP
–60 Waste recycling Reduced intensive
Efficiency improvements other industry agriculture conversion
–80
Landfill gas electricity generation High penetration wind
–100 Clinker substitution by fly ash Solar PV
Low penetration wind
–120 Building efficiency new build Degraded forest reforestation
Insulation retrofit (residential) Pastureland afforestation
–140 Tillage and residue management Degraded land restoration
Cropland nutrient management Nuclear
–160 Cars plug-in hybrid
Retrofit residential HVAC
–180
Second-generation biofuels
–200 Appliances residential
NOTE: The curve presents an estimate of the maximum potential of all technical GHG abatement measures below
€80 per tCO2e if each lever was pusued aggressively. It is not a forecast of what role different abatement measures
and technologies will play.
This graph attempts to show ‘all in one’ the various measures for greenhouse gas reduction, with both reduction (in carbon
dioxide equivalents (CO2e)) and cost (in Euros (€)) quantified.
Read from left to right, it gives the whole range of strategic options, ranging from ‘low hanging fruit’ (in green), such as
building insulation (coming with economic savings), to the increasingly ‘higher hanging ruit’ (in red), such as afforestation
and wind energy.
Figure 16 Global cost curve for greenhouse gas abatement measures beyond ‘business as usual’ (greenhouse
gases measured in GtCO2e1).
Courtesy of McKinsey & Company
© BCO 2012 23
ON-SITE RENEWABLES
QUESTION 2:
WHAT ARE THE DOMINANT FACTORS AFFECTING THE FINANCIAL COST
OF USING ON-SITE RENEWABLES TO REDUCE BUILDING EMISSIONS?
Motivation
Given the range of costs and the variation in size of
benefits of different buildings in the sample, the next
stage of the investigation sought to discover which
characteristics were driving these costs. Understanding
these costs may then help developers or owner-occupiers
to identify opportunities to reduce the cost of compliance
at an early stage and to understand the economic
fundamentals driving the costs of using renewable
technologies in commercial buildings (Figure 18).
7 ‘Efficiency’ here refers to the ability of governments to introduce legislation on the most cost-effective measures first. It is, however,
recognised that this can often cause other political complications due to matters such as distribution of wealth effects that make the most
efficient outcomes impossible.
24 © BCO 2012
ON-SITE RENEWABLES
installations given the limits of energy demand the use of on-site renewables and the other variables
(e.g. for heating) in a building deemed likely to affect emissions. The variables used
I whether other planning policies impact on the costs are: the maturity of the technology used; the quantity
of meeting requirements for on-site renewable of CO2 saved; the existence of supply incentives; the
technologies, for example by restricting the choice existence of tax incentives; whether the building is
of measures that could be used listed or located in a conservation area; the size of the
building; and whether the building is new or refurbished.
I whether it is easier and more cost-effective to install
The development of the regression model and the data
renewables in tall buildings or in low-rise structures.
used are described in more detail in Appendix 2.
Data
The sample used is the same as the one identified in Findings
Question 1 (a total of 77 buildings in central London Figure 19 gives an intuitive feel for the data and the
in which renewable technologies were installed). To trends within it, illustrating the relationship between net
identify the impact of various building characteristics average cost on a specific building (the dependent
on costs, a range of other explanatory variables are variable) and a single variable (the total quantity of
identified for each building. CO2 saved on the building) (explanatory variable X3).
Examining this relationship suggests a number of
basic trends, even without carrying out a complex
Methodology regression analysis:
The ordinary least squares (OLS) method of regression
analysis was used to identify the association between I Costs appear to be high at low values of total
the net average cost of emissions reductions due to emissions reduction, which could imply either that
500
Profitable installations
50 100 150 200 250 300 350
0
Carbon savings achieved (tCO2e)
–1000
–1500
–2500
–3000
Figure 19 The relationship between abatement costs and total carbon savings from renewables on each building.
Courtesy of Sturgis Carbon Profiling LLP
© BCO 2012 25
ON-SITE RENEWABLES
small installations are inefficient, or that there is I To capture this relationship of rapidly decreasing
selection bias, in that only high-cost measures are costs followed by slowly increasing costs suggests
capable of delivering low levels of carbon reductions a cubic function relating to quantity, hence the
(e.g. PV). explanatory variables X4 and X3 in the final
I The initial high costs per tonne of carbon abated regression specification.
may be explained by high fixed costs such as those
incurred by maintenance, where it can cost similar Table 2 shows the results from the final OLS model
amounts for a yearly service for a small or large described above.
renewable installation, or marginal costs increasing
at a lower rate than the marginal benefits. The minimum cost of compliance can be proven
(within this sample) to occur around the level of
I Costs decrease as the amount of emissions 90 tonnes of CO2 saved on each individual project.
reductions required increases, up to a point around
40–100 tonnes.
I Around this point, some buildings can realise a Discussion
profit from operating on-site renewables (green Of the explanatory variables investigated using the
points in Figure 19). regression model, the following are worthy of note:
I After this point, costs increase, but less rapidly than
they had decreased before, suggesting that there I The total quantity of emissions reduced on a building
may be competing influences on costs that are not was found to have a highly significant impact on
captured in this scatter plot. For example, technology cost in all the model terms (Quantity – linear,
becomes more economically efficient at higher levels Quantity – squared, Quantity –cubic, specifications).
of energy generation, but limits in demand for heat In statistical terms we are thus 99.9% confident that
may serve to restrict these potential gains. a 1 tonne increase in total emissions saved on a
COEFFICIENT t-VALUE P
Quantity 20.460 5.22 0.000
Quantity 2 –0.147 –5.35 0.000
Quantity 3 0.0003 5.04 0.000
New technology –232.111 –1.89 0.063
Supply incentive –368.714 –3.02 0.004
Tax incentive –113.969 –1.37 0.174
Conservation area –208.321 –2.02 0.048
New building 12.253 0.12 0.904
Number of floors –1.526 –0.77 0.443
Size –0.003 –0.76 0.452
Constant –432.456 –2.42 0.018
Observations 77
R2 0.524
Robust standard errors used: * significance at the 10% level; ** significance at the 5% level; *** significance at
the 1% level.
Source: Sturgis Carbon Profiling LLP
26 © BCO 2012
ON-SITE RENEWABLES
project will halve the cubic relationship to cost supply incentives for renewable measures on a
described in the specification. given building. This result is counter-intuitive, as
I To illustrate this effect through a point estimate, the supply incentives would be expected to reduce
effect of saving an additional tonne of carbon at a rather than increase costs. However, the reader
level where 50 tonnes are currently saved will is reminded that association does not constitute
reduce net average costs by £5.80 per tonne. causality; the most likely explanation in this case is
I The regression analysis indicates (at a 95% confidence that the regression model has identified a correlation
level) that, if a given building is subject to conservation between subsidies being in place for expensive
area legislation, the average cost of saving 1 tonne technologies, rather than a tendency for subsidies
of carbon will increase by £208 on that building. to make technologies more expensive.
I This conservation area effect could operate in one I Finally, there is weak statistical significance (at the
of two ways: 10% significance level) for the following variables:
– the cost of applying the same technologies could – whether the development is a new or refurbished
increase as a result of higher indirect associated building – new development is associated with
costs (e.g. installing the technology without reducing net average costs by £12 per tonne,
affecting the appearance of the building could compared with refurbishments
increase the area of lettable space lost) – the maturity of the technology – using a new
or technology is associated with increasing net
– the choice of measures that could be employed average costs by £232 per tonne.
on a building in a conservation area could be I The remaining three variables, size of building,
limited to those that are more expensive. number of floors and the existence of tax incentives,
I It can also be shown that a statistically significant were found to have no significant impact on costs in
and negative effect is associated with the use of the sample examined.
QUESTION 3:
HOW DO THESE COSTS COMPARE WITH OTHER POLICY ALTERNATIVES?
Motivation by choosing the optimum size of installation in the
At present, policies on the use of renewable energy presence of a uniform carbon-reduction subsidy.
target reductions in emissions at the level of individual In practice, however, while reducing the burden on
developments. In the discussion of Question 1 (see developers, such a policy might not deliver the quantity of
page 19) evidence was presented of the substantial emissions reductions deemed necessary by legislators.
variation in costs incurred, with net average costs per This approach would also depend on some quite strong
tonne ranging from –£2806 to +£145 (enabling building rational economic behavioural assumptions, which
owners to make a modest profit from the installation may not be realistic in practice, given the range of
of renewable technologies). discount rates observed and the problems of incentive
misalignment previously discussed.
Equally important to these findings are the sensitivity of
these costs to scale, with strong statistical evidence to An alternative approach would be for local authorities to
suggest that up to 37% of the variance in these costs be responsible for commissioning new renewable energy
can be explained by a single variable, the quantity of installations, identifying the most cost-effective and
emissions, alone.8 carbon-efficient generating solutions for each district, and
funding these projects through planning charges. Such
These findings could support arguments for an alternative an approach would provide greater certainty for legislators
policy instrument that encourages developers to target on the delivery of carbon reductions. While it might
more cost-effective levels of emissions reductions be less efficient than the ‘first best’ solution identified
and seek profits from the installation of renewable above, it could deliver carbon emissions reductions
technologies, subject to their respective constraints, at a significant cost saving over the status quo.
8 In the simplified OLS regression model, NACb = α + β2X2,b + β3X3,b + β4X4,b + εb, using robust standard errors R2 =37.65%.
© BCO 2012 27
ON-SITE RENEWABLES
To examine these issues, a simple comparison is scheme in Aberdeen (Energy Saving Trust, 2004)
made between the compliance costs associated with and adjusted to account for various factors specific to
the current policy and those associated with a district London (e.g. the higher cost of land and labour). The
CHP scheme.9 It is worth stressing here that it is not costs per tonne associated with the existing policy on
the intention of this report to advocate greater use of on-site renewable energy were taken from the average
CHP, but merely to question whether other policy of the sample used in the preceding sections.
alternatives exist that are more efficient.
It is recommended that more research should be carried On-site renewables District CHP
out in this area, and that the comparison outlined below
should simply be regarded as framing the problem to
be investigated. £130
Data £175
Data for the comparison exercise were taken from an
Energy Saving Trust study of a large-scale community
£380
9 For those wishing to find out more, London First’s report Cutting the Capital’s Carbon Footprint (2008) provides a detailed critique of the
challenges and opportunities associated with decentralised energy.
28 © BCO 2012
ON-SITE RENEWABLES
Discussion
This illustrative comparison suggests that, while
commissioning a large-scale district energy installation
could be both costly and practically complex, it could
also offer significant savings both to taxpayers (who Figure 22 Wildlife Mitigation Bank, California.
would incur less cost in subsidies) and developers. The Courtesy of Burns & McDonnell
comparison made here suggests that savings could be
in the region of £205 per tonne of CO2 abated to the
private sector and around £130 per tonne to taxpayers.
If indicative of relative costs across the UK as a whole,
I A private-sector approach: Developers could provide
the savings to both the private sector and taxpayers
carbon savings on-site and, where they are able to
could be in the region of £153 million every year.10
save in excess of their reduction requirements, then
sell excess reductions to other developers who are
Further research on the potential of large-scale
unable to achieve reductions as cost-effectively.
renewable energy installations is recommended to
explore these issues more fully, with reference to other Issues: Robust measurement and verification
UK locations and large-scale renewable technology procedures are required, which, due to transaction
alternatives. The type of approach adopted would costs, may wipe out the gains that a market-based
also need further consideration, and three options approach may provide.
are briefly outlined below: I A flexible approach: This is similar to the wetland
banking system used in the USA (Figure 22), in which
I A direct approach: Local authorities provide a default all developers are required to reduce emissions by an
means to achieve carbon emissions reductions, amount decided centrally by government, and where
through large-scale retrofitting projects or district-level compliance can be achieved through either buying
schemes, which could capitalise on economies of allowances from other parties (e.g. local authorities,
scale. These projects could be supported financially energy service companies or other developers who
through planning contributions, with an effective exceed their targets) or through providing low-cost
price per tonne of £125–175.11 At these price levels, renewables on site. Such a scheme may help change
efficient renewables will be encouraged that are attitudes towards carbon reduction, by fostering a
capable of being delivered for less than this, while partnership-based approach, allowing the sharing
the more expensive and inefficient renewable of risk more effectively and through the bargaining
applications will not be pursued. power benefits that local authorities may bring to
Issues: Weak evidence of successful local authority the table.
roll-out to date; lack of capacity and skills of local Issues: Again robust measurement and verification
authorities; no market incentive for good performance. procedures are required.
10 Based on an average annual number of tonnes reduced per square metre of 0.0027 tonne and a 10-year average new-build construction
for commercial properties of 8,301,000 m2. Although a crude estimate, it is believed that this should provide a conservative lower bound
for the potential savings, given that commercial property uplift figures do not take into account replacement (as occurs through demolition
and rebuilding) and do not include refurbishment projects. In addition, if retrofitting of existing stock and embodied carbon were also
considered, significant additional savings could be realised.
11 Such a price level should be based on the capacity of renewables to become cheaper over time due to the market maturing and
improvements in technology. Comparisons with similar technology sectors would suggest that 50–70% price reductions may be feasible,
supporting an initial price of carbon of £50/tonne.
© BCO 2012 29
ON-SITE RENEWABLES
QUESTION 4:
HOW DO THESE COSTS COMPARE WITH THE FORGONE
ENVIRONMENTAL DAMAGE?
Motivation forgone environmental damage is time dependent,
Earlier sections of this report have focused only on the the introduction of this particular policy might be
financial costs and benefits to developers and the costs more easily justified at a point in time when its cost
to taxpayers in the form of subsidies. These, however, better reflects the environmental benefit.
represent only half of the equation, as the purpose of
on-site microgeneration policies is to avoid harm to the Data
environment caused by the build-up of greenhouse This section uses the average measure of the costs and
gases such as CO2, which result in global warming. benefits of the sample, as a tonne of carbon saved on
one project is of equivalent value to society as any other
Although a discussion of the science associated with tonne of carbon saved on any other project. The value
these wider issues is outside the scope of this report, of forgone environmental damage is calculated using
we believe that examining the value placed by the shadow price of carbon. Although this is by no
government on avoiding this damage is an important means a perfect measure, it is widely used, its limits are
stage in appraising the on-site renewable energy well known12 and it provides considerable improvements
policy. Our reasons for doing so are three-fold: on the accuracy of measures employed previously.13
30 © BCO 2012
ON-SITE RENEWABLES
The figures suggest, in accordance with the cost curve Some evidence exists to support this course of action,
developed by McKinsey & Company (see Figure 16), in that the value of avoiding carbon emissions will
that many sectors of the UK economy are capable of increase to over £200 per tonne by 2050. However, it
delivering these savings in a far more cost-effective way. is clear that, without significant reductions in the costs
of the technology, most on-site renewable energy
Figure 25 shows an approximate ranking in terms of installations would continue to represent a financial
cost of the means by which carbon savings are being burden on developers, taxpayers and the environment.
Cost to taxpayers
On-site renewables
£130
1 tonne £40
£380
Social value
CO2 saved
Cost to developers
vs
District CHP
© BCO 2012 31
ON-SITE RENEWABLES
32 © BCO 2012
ON-SITE RENEWABLES
CONCLUSIONS
KEY FINDINGS
The findings from this research indicate that on-site the range of technologies available and the scale at
renewable energy installations can generate modest which they can be deployed, and reduces the level of
financial returns to investors and occupiers in the emissions reductions that can be achieved through
presence of subsidies, although they rarely do. this means.
Taking account of all the costs and benefits, the In response to this concern, a simple policy alternative
average net position is a cost of £382 per tonne, even has been examined, which suggests that similar
with the help of subsidies. environmental benefits could be delivered at lower
costs. This report, however, does not advocate a
The research has also shown that costs are sensitive specific technological solution: a wide range of
to external factors, such as conservation area status measures could reduce emissions far more cost-
(which increases costs by restricting the range of effectively than on-site renewables.
technologies that can be used).
The implications of these findings suggest that, as
Our calculation of the forgone value of environmental further carbon savings will be required from
damage in the UK, based on the government’s appraisal commercial buildings in the UK in the near future,
method, suggests grounds for serious concern. The other strategies to supplement on-site renewable
negative NPV to developers (£173 million) exceeds energy must urgently be explored. Only by doing so
the environmental benefits (£18 million) by a factor can the burden on occupiers and developers be
of ten each year. minimised and emissions reductions delivered in the
most cost-effective way.
These high costs are a consequence of the physical
constraints of dense urban environments, which limit
KEY RECOMMENDATIONS
I A wider review of the costs and benefits of achieving on-site renewable technologies where it is possible
emissions reductions across the built environment is to do so profitably, while local authorities should use
required, using MAC curves for a range of building their collective bargaining power to remove barriers
types and carbon reduction processes. in the delivery of large-scale solutions.
I The efficiency of subsidising on-site renewables, as I More flexible policy mechanisms should be
a means of reducing emissions, should be reviewed. investigated, allowing combinations of on-site
I Local authorities should explore the role of district solutions and purchase of carbon allowances at a
and large-scale renewable installations as realistic price in order to drive behavioural change
alternatives to on-site microgeneration, especially in (e.g. £125–175 per tonne), encouraging local
the context of hard-to-treat stock such as that in authorities to take an active role in creating and
historic city centres. delivering large-scale low-carbon power projects
and to make best use of their bargaining positions
I All parties should play to their strengths: developers
to reduce transaction costs.
should be encouraged to seek profits by installing
© BCO 2012 33
ON-SITE RENEWABLES
I A more detailed enquiry should be undertaken into for a larger investigation of the economic and
how these findings relate to other land markets and environmental benefits of low carbon legislation on
commercial building types across the UK. As such, commercial property in the UK.
this report should be perceived as a scoping study
34 © BCO 2012
ON-SITE RENEWABLES
REFERENCES
British Council for Offices (2007) Renewables and the London Plan. London: British Council for Offices. Available at:
http://www.bco.org.uk/uploaded/Renewables_report.pdf (accessed 3 June 2012).
Building Cost Information Service (2001) Life Expectancy of Building Components. London: Royal Institution of Chartered
Surveyors.
CABE (Commission for Architecture and the Built Environment) (2007) Sustainable Design, Climate Change and the Built
Environment. London: CABE. Available at: http://www.designcouncil.org.uk/Documents/Documents/Publications/CABE/
sustainable-design-and-climate-change.pdf (accessed 3 June 2012).
Carbon Trust (2010) Introducing Combined Heat and Power. Available at: http://www.carbontrust.com/media/19529/
ctv044_introducing_combined_heat_and_power.pdf (accessed 11 July 2012).
C B Richard Ellis (2010) Prime Rent and Yields Monitor Q2 2010. London: CB Richard Ellis. Available at:
http://www.cbre.co.uk/uk_en/news_events/news_detail?p_id=5167 (accessed 11 July 2012).
Clarkson R and Deyes K (2002) Estimating the Social Cost of Carbon Emissions. Government Economic Service Working
Paper 140. London: HM Treasury. Available at: http://www.hm-treasury.gov.uk/d/SCC.pdf (accessed 3 June 2012).
Day T, Ogumka P and Jones P (2007) Review of the impact of the energy policies in the London Plan on applications referred
to the Mayor (Phase 2). London: London South Bank University. Available at:
http://london.gov.uk/archive/mayor/planning/docs/lsbu-research.pdf (accessed 3 June 2012).
Day, T, Ogumka, P & Jones, P (2009). Monitoring the London Plan: Energy Policies – Phase 3. Part 1 Report. Final. London:
London South Bank University. Available at: http://static.london.gov.uk/mayor/priorities/docs/lon-plan-energy-policies-
monitoring-1.pdf (accessed 3 June 2012).
Department of Energy and Climate Change (2009) The UK Low Carbon Transition Plan. London: Department of Energy
and Climate Change. Available at: http://www.decc.gov.uk/assets/decc/White%20Papers/UK%20Low%20Carbon%
20Transition%20Plan%20WP09/1_20090724153238_e_@@_lowcarbontransitionplan.pdf (accessed 3 June 2012).
Department for Business Innovation and Skills (BIS) (2008) The Growth Potential for Microgeneration in England Wales and
Scotland. London: BIS. Available at: http://webarchive.nationalarchives.gov.uk/+/http://www.berr.gov.uk/files/file46003.pdf
(accessed 11 July 2012).
Dietz S (2007) Review of DEFRA paper: ‘The Social Cost of Carbon and the Shadow Price of Carbon: What They
Are, and how to Use Them in Economic Appraisal in the UK’. London: London School of Economics. Available at:
http://eprints.lse.ac.uk/21613 (accessed 3 June 2012).
Element Energy (2009) Uptake of Energy Efficiency in Buildings. Available at: http://downloads.theccc.org.uk/docs/
Element%20Energy_final_efficiency_buildings.pdf (accessed 3 June 2012)
Energy Saving Trust (2004) Aberdeen City Council: A Case Study of Community Heating. London: Energy Saving Trust.
Available at: http://www.energysavingtrust.org.uk/england/Publications2/Housing-professionals/Heating-systems/
Community-heating-Aberdeen-City-Council-case-study-2004-edition (accessed 3 June 2012).
HM Treasury (2011) The Green Book. Appraisal and Evaluation in Central Government. Treasury Guidance (updated
version of 2003 edition). London: TSO. Available at: http://www.hm-treasury.gov.uk/d/green_book_complete.pdf
(accessed 3 June 2012).
Mayor of London (2004) The London Plan: Spatial Development Strategy for Greater London. London: Greater London
Authority. Available at: http://legacy.london.gov.uk/mayor/strategies/sds/london_plan/lon_plan_all.pdf (accessed 3 June 2012).
Mayor of London (2008). The London Plan: Spatial Development Strategy for Greater London. Consolidated with Alterations
since 2004. London: Greater London Authority. Available at: http://www.london.gov.uk/thelondonplan/docs/londonplan08.pdf
(accessed 6 June 2012).
Mayor of London (2011a) The London Plan: Spatial Development Strategy for Greater London. London: Greater London Authority.
Available at: http://www.london.gov.uk/sites/default/files/The%20London%20Plan%202011.pdf (accessed 3 June 2012).
© BCO 2012 35
ON-SITE RENEWABLES
Mayor of London (2011b). Delivering London’s Energy Future. The Mayor of London’s Climate Change Mitigation and Energy
Strategy. London: Greater London Authority. Available at: http://www.london.gov.uk/sites/default/files/Energy-future-oct11.pdf
(accessed 3 June 2012).
McKinsey & Company (2010) Impact of the Financial Crisis on Carbon Economics: Version 2.1 of the Global Greenhouse Gas
Abatement Cost Curve. Available at: http://www.mckinsey.com/client_service/sustainability/latest_thinking/greenhouse_
gas_abatement_cost_curves (accessed 17 August 2012).
Price R, Thornton S and Nelson S (2007) The Social Cost of Carbon and the Shadow Price of Carbon: What They Are, and
how to use them in Economic Appraisal in the UK. London: Department of Environment, Food and Rural Affairs. Available
at: http://archive.defra.gov.uk/evidence/series/documents/shadowpriceofcarbondec-0712.pdf (accessed 3 June 2012).
Royal Institute of Chartered Surveyors (RICS) (2007) Code of Measuring Practice: A Guide for Property Professionals, 6th
edn. London :RICS.
United Nations Statistics Division (2012) Millennium Development Goals Indicators: Carbon Dioxide Emissions (CO2),
thousand metric tonnes of CO2 (CDIAD). Available at: http://mdgs.un.org/unsd/mdg/SeriesDetail.aspx?srid=749&crid=
(accessed 11 July 2012).
36 © BCO 2012
ON-SITE RENEWABLES
APPENDIX 1:
DEFINING COSTS
DEFINING COSTS
The following specification was used to define the R2 rent in area 2 (above ground)
present value of financial costs: Mb maintenance materials on building b
Lb maintenance labour on building b
Costb = {[CCb – (Taxe – CCb) × Defy]} +
Fb replacement fuel(s) on building b
t = lifespan
© BCO 2012 37
ON-SITE RENEWABLES
the item of technology identified, a developer would do R1 and R2, the value of forgone lettable areas
so (developers act rationally and are well informed); all (in the basement and above ground, respectively),
developers pay tax at a uniform rate of 28%; and, finally, were sourced from IRIS Engineering and Technology,
when a developer chose a technological measure a building consultancy firm specialising in asset
benefiting from ECA, they were expecting to make an management and environmental appraisals of
accounting profit from which the ECA could be deducted buildings in central London.
(projects would not be given the go ahead on a no-profit
basis). With these conditions holding true, the value of Data for Mb and Lb, the cost of materials and labour
the ECA variable would be 28% of the capital cost if required each year to maintain specific renewable
the measures used appeared on that year’s ECA list. technologies, and Fb, the cost of fuel, were provided
by the Energy Saving Trust.
A deflating factor, Defy, corrects for time-related cost
differences between observations by adjusting to 2005 A value of 6.13% was chosen for r, the discount rate
prices. The deflator was chosen on the basis of used by developers to capitalise future payments and
information from the Department for Business Innovation income into a present value, based on the 15-year
and Skills. Although the use of one deflator for different mean yield rate for offices sourced from CB Richard
costs is far from ideal, given the short time period of Ellis. It is acknowledged that yields are typically lower in
this study and the fact that all major cost variables central London, but evidence suggests that developers
positively correlate with construction costs, it was may discount future cash flows relating to renewable
decided that using a single value would not overly measures more heavily (Department for Business
compromise the specification. Innovation and Skills, 2008). Given this uncertainty
over a correct rate, various alternatives were
NIAb1 and NIAb2, the net internal areas (in the basement examined in the calculations of benefits.
and above ground, respectively) forgone by using a
particular technological solution, were measured (in Data for t, the lifespan of the renewable technologies
accordance with the Royal Institution of Chartered employed, were sourced from the Building Cost
Surveyors’ (RICS) Code of Measuring Practice (2007)) Information Service (2001).
from the plans submitted with planning applications
held by the Planning Archive.
DEFINING BENEFITS
The following specification was used to define the Eg energy generated that displaces gas use
present value of financial benefits: Ee energy generated that displaces electricity use
Pe price of electricity
Benefitb =
Pg price of gas
t = lifespan
r1,2,3 range of different discount rates used
∑
t=1
ROCb + SUBb + (Eg × Pg) + (Ee × Pe)
(1 + r1,2,3)t
t time period of discount rates.
ROCb value of renewable obligation certificates Eg and Ee, the quantity of energy generated that
generated by the renewables on building b displaces the use of gas and electricity, respectively, were
SUBb value of other subsides now introduced on obtained from the Energy Statement for each building
building b held in the Corporation of London Planning Archive.
38 © BCO 2012
ON-SITE RENEWABLES
Pe and Pg, the prices of gas and electricity, are the prices All prices and costs are baselined to 2005 to enable
offered on a commercial tariff in 2005 by Powergen, a comparisons to be made between projects within the
large utilities provider in the UK. sample carried out in different periods. Checks of
robustness were done by taking different alternative
Values for t are as defined for costs above. baseline time periods, none of which resulted in a
substantial change the findings of this report.
Three values (8%, 13% and 33%) are used for r, the
discount rate applied by occupiers.
∑ Emissionsb
t=1
© BCO 2012 39
ON-SITE RENEWABLES
APPENDIX 2:
REGRESSION MODEL
MODEL
Ordinary least squares (OLS) regression analysis14 expectations described above and after viewing the
was used to test the explanatory power of the different scatterplot, which supports the cubic functional form.
control variables on the variance of the net average I Model IV – the most parsimonious regression model,
costs per tonne. The basic estimation model is: introduces the new technology control and is given by:
Regulatory compliance cost (RCC)i = α + β1Quantity Net average costb= α + β1X1,b + β2X2,b + … β9X9,b + εb
+ γ1′ X + αi
The dependent variable is the net average cost on
where the dependent variable is the regulatory cost building b, given by the explanatory variables:
of CO2 abatement of building i. The main coefficient of
interest is β1, which measures the effect of one unit X1 the maturity of the renewable technology used
of emission reduction required. The other control
X2 the quantity of CO2 saved by the technology
variables are part of X, and εi is the error term.
Robust standard errors were used in all regressions. X3 (quantity of CO2)2
X4 (quantity of CO2)3
Four models of estimating the RCC were examined: X5 existence of supply incentives
X6 existence of a tax incentive
I Model I – a linear specification of all variables.
X7 building located in a conservation area or listed
I Model II – introduces a quadratic expression of
the Quantity variable (Quantity 2). X8 size of the building
I Model III – introduces a cubic specification into the X9 new or refurbished
Quantity variable (Quantity 3), in response to εb error term.
DATA
The variables used are explained in more detail below. of scale may help reduce regulatory compliance costs,
as the ‘output’ of emission reductions increase (by
Maturity of the renewable technology used. A control reducing the impact of fixed costs, such as yearly
dummy is introduced into the specification, as it is maintenance costs, or reducing heat losses through
anticipated that new methods of emission reduction higher efficiency components via the installation of
may be more expensive. A dummy variable of 1 is larger plants). The second effect, which contrasts with
given if the technology is new, and the expected this, may be that output constraints start to bind and
coefficient is negative. limit a developer’s ability to choose the most efficient
factors of emission reduction. For example, use of
Quantity of CO2 saved. It is anticipated that various the surrounding ground as a thermal store may be
effects may occur through this variable. First, economies constrained by fears of raising bedrock and water table
14 OLS regression analysis is a means of identifying the association between a single continuous variable (in this case, the net average cost
of emissions reductions using on-site renewables) and one or more other variables deemed likely to affect it. The method of estimation
involves identifying values for the parameters β1 to β9 in this model that are capable of predicting a value for the net average cost that is
as close as possible to the actual value. Tests of statistical inference are then carried out on these parameter values to decide if their
least squares estimates have significance and are robust.
40 © BCO 2012
ON-SITE RENEWABLES
temperatures. It is thus expected that, after a given level Size of building. It is expected that, as a building
of emission reduction, costs may again begin to rise, becomes larger, it will become easier to accommodate
although benefits from economies of scale may persist. a renewable measure (because of the additional
For these reasons, it is anticipated that the regulatory flexibility). The expected coefficient is positive.
compliance cost function, rather than being a quadratic
average cost curve function, may follow a cubic Number of floors. It is expected that the ratio of roof
relationship restricted within certain bounds. Thus area to energy demand will decrease as the building
three terms for the quantity of CO2 saved are included. height increases. The expected coefficient is negative,
as low-cost measures requiring large amounts of roof
Dummy variables are applied to control for projects on space (e.g. solar water heating) will become
which supply incentives have been awarded through increasingly difficult to apply.
ROCs or on which ECA tax incentives apply. The
expected coefficients are positive. New or unrefurbished space. This is typically less
efficient and less capable of accommodating new
Conservation area and listed building status. Buildings mechanical and electrical plant because of constraints
in these categories are subject to stricter planning of the existing structure. A dummy variable of 1 is
controls than others. This is expected to increase given if the space is new, and zero if it is refurbished;
developers’ costs and indirectly restrict their choices. the expected coefficient is negative.
A dummy variable of 1 is given if a building is inside
a conservation area or the property is a listed building.
The expected coefficient is negative.
RESULTS
The size of installation that minimises compliance –(–0.2932) ± (0.2932)2 – 4 × 20.46040 × 0.00075
Q=
costs was identified by taking the derivative of the 2 × 0.00075
fitted model with respect to quantity, setting the first
derivative equal to zero and solving with respect to Q = 90.9 (1 dp), 299.9 (1 dp)
quantity, as shown below:
to derive which point is a maximum and which is a
Net average cost (NAC) = α + β1X1 + β2X2 + … β9X9
minimum. Taking the second derivative
where β1 = 20.46040 (to 5 decimal places (dp)), Δ2NAC/ΔQ2 = –0.29320Q + 0.00150Q
β2 = –0.14660 (5 dp), β3 = 0.00025 (5 dp), and X1 = Q
(quantity saved on building b), X2 = Q1 and X3 = Q1. where
Taking the first derivative Q = 90.9 Δ2NAC/ΔQ2 < 0, therefore a maximum
© BCO 2012 41
ON-SITE RENEWABLES
APPENDIX 3:
MODELLING THE COSTS PER TONNE OF
A POLICY ALTERNATIVE
In this illustration, the methodology was revised slightly The prices per kilowatt-hour of gas and electricity (pg
to reflect the variables for which data were available and pe, respectively) are those offered by Powergen
(values are given in Table A3.1). on a commercial tariff in 2005 (as in Appendix 1), and
the annual net benefit (B) is calculated as the cost of
Data for the capital cost (CC) and whole-life cost (WLC) the displaced gas and electricity, minus the annual fuel
of the CHP plant (the latter including annual fuel (f) and maintenance cost and opportunity cost:
and maintenance (m) costs over 25 years (t)), and for
the total CO2 emissions (e) produced were sourced B = [(g × pg) + (e × pe) – [(f + m) + OC
from the original case study report (Energy Saving
Trust, 2004), where: The net average cost per tonne (NAC) is defined as the
difference between the capital cost and the net present
t = 25
E OPPORTUNITY COST
g=
[( ) ]
cg
× R 1 × (1 – R 2 )
Building (site)
Notional rent rate
2,500 ft2
£22.50
and extra over
Rent (OC) (£) 56250
e=
()E
ce
× R 1× R 2
Continued
42 © BCO 2012
ON-SITE RENEWABLES
© BCO 2012 43
ON-SITE RENEWABLES
APPENDIX 4:
CALCULATING THE VALUE OF FORGONE DAMAGE
Value of forgone damage = notional cost per tonne of CO2 emissions that can
be incorporated in policy and investment appraisals.
t = lifespan
∑ Emissionsb,t × Valuet The SPC set at that time was £25.50 per tonne: the
Department of Energy and Climate Change (2009) has
t=1
(1 + rsdr)t since proposed a short-term schedule of prices in the
non-tradable sector, increasing from £50 per tonne in
2008 to £60 per tonne in 2020.
where:
The social discount rate (rsdr), which is set out in
Emissionsb,t emissions saved in a particular time the government’s official guidance on appraisal and
period t in building b evaluation of projects (The Green Book, HM Treasury,
2011), adjusts for the timing of the occurrence of costs
Valuet value of forgone atmospheric damage
and benefits by discounting them to present values.
in a given time period
The recommended rate of 3.5% in real terms was
rsdr social discount rate of 3.5%, as introduced in the 2011 version of The Green Book,
recommended by HM Treasury replacing the previous recommended rate of 6%.
t the lifespan (in years) of a given
renewable technology.
Note
To ensure consistency in the comparison of the average
Data costs per tonne of CO2 emissions saved in the buildings
Emissionsb is the total number of tonnes displaced by in the sample, the value of forgone damage was divided
the use of renewables in a given time period in building by the total quantity of emissions saved over the lifespan
b, as defined in Appendix 1. of the technology. It is recognised that this makes an
‘absolute’ interpretation of the findings complex: if the
The amount of forgone atmospheric damage in a given reader seeks such an interpretation, reference should
time period (Valuet) is based on the shadow price be made to the original total NPV costs identified in
of carbon (SPC) as defined by Price et al. (2007), a Question 1.
44 © BCO 2012