Professional Documents
Culture Documents
Cost Management-Deliverable Two
Cost Management-Deliverable Two
Branch Kandy
2|Page
INTRODUCTION
This is a cost report for a new development of 22 semi-resident houses. The area of new
development is 8000m2.Previous project estimate have been used for the new development. In
the Preliminary plan the client needed to make use of building design of resident houses to save
time and cost for the design. The time and location factors were considered in this project. The
client needed to reduce height of resident houses and also the clients requested to reduce the cost
per house by increasing the no of house units by remaining the same overall GIA of the previous
project. In this report the estimation of this project has been calculated by rebasing the time and
location factor and assessed the cost implication due to decrease of story height and grouping of
houses.
Factor Calculation
The previous project location was Colombo and the period of the project was 3rd quarter of
2018.The location of new project is Kurunegala and the project period will be 3rd quarter of
2020.
Past Proposed
Location Colombo Kurunegala
Location Factor 95 96
Quarter 3rd Q 2018 3rd Q 2020
TPI 1784 1841
3|Page
Summary of New Development Estimation with height modification
4|Page
Justification for for story height modification
The effect of change in story height to the elemental quantities and elemental rates were justified under this
section with necessary assumptions.
Sl. Element By Quantity By Rate
No.
1 Sub Structure No impact to the quantity When the building height decrease the strength of the foundation should
decrease. So the sub-structure rate will have to decrease.
Foundation weightage in Sub-structure = 50%
Height different = (2.8-3.0)/3.0
-7%
(A) = -4%
5|Page
4 Roof No impact to the quantity Adjustment for method related charges due to decreased height
( Crane,Scafolding & etc.)
Assume that method related charges will be 8% of rate
Method related charges = 8%
Decrease = (2.8-3.0)/3.0
-7%
(A) -1%
6|Page
12 Ceiling Finish No impact to the quantity Adjustment for method related charges due to decreased height
(Crane,Scafolding & etc.)
Assume that method related charges will be 8% of rate
Method related charges = 8%
Decrease = (2.8-3.0)/3.0
-7%
(A) -1%
7|Page
Task 2 – COST ESTIMATE OF REVISED SCHEME
8|Page
Justification for GIA modifications
2.1 Frame
Same as Sub structure quantity Factor adjustment = 45%
2.3 Roofs
Same as Sub structure quantity Factor adjustment = 45%
Apply 3% rate increase for eave additional gutters and down pipe = 3%
Rate Factor adjustment = 1.03
9|Page
2.5 External wall
External wall length -previous house unit = 85.94
External wall length -new house unit = 56.04
Quantity reduced = -35%
Quantity Factor adjustment 0.65
Rate will increase similar to the External wall and foundation(47%).But the External = 23%
finish will be included in external wall.so 50% of wall finishes will be considered.
Rate Factor adjustment = 1.23
10 | P a g e
CONCLUSION
As for the client’s new requirements, construction of 22 no: of semi-residence houses needs
Rs.85,049,372.10 rather than previous 10 no of residence houses.
REFERENCE
BCIS. (2012). Elemental Standard Form of Cost Analysis (4th ed.). London.
Royal Institution of Chartered Surveyors (RICS). (n.d.). RICS new rules of measurement (1st ed.). UK.
11 | P a g e