Final Bill
Final Bill
B MASONRY WORKS
B01 Size Stone Masonary CM 1:6 Cft 720.00 180.00 129,600.00
B02 BBM 9" thk
Stilt floor Sft 1,873.53 200.00 374,706.00
Ground floor Sft 1,467.47 200.00 293,494.00
First floor Sft 1,490.93 200.00 298,186.00
Terrace floor Sft 817.88 200.00 163,576.00
B03 BBM 4.5" thk
Stilt floor Sft 486.13 120.00 58,335.60
Ground floor Sft 222.99 120.00 26,758.80
First floor Sft 197.88 120.00 23,745.60
1,368,402.00
C CONCRETE WORKS
C01 PCC 1:4:8
Below footing Cft 782.60 120.00 93,912.00
Below flooring Cft 962.17 120.00 115,460.40
C02 RCC Footing Concrete Cft 1,854.00 210.00 389,340.00
C03 RCC Plinth Beam Cft 288.70 300.00 86,610.00
C04 PCC 1:3:6 Sills
Stilt floor Cft 40.31 130.00 5,240.30
Ground floor Cft 8.54 130.00 1,110.20
First floor Cft 8.25 130.00 1,072.50
Terrace floor Cft 40.27 130.00 5,235.10
C05 RCC Column Concrete
Below Stilt floor Cft 69.75 330.00 23,017.50
Above Stilt floor Cft 165.38 330.00 54,575.40
Ground floor Cft 165.38 330.00 54,575.40
First floor Cft 165.38 330.00 54,575.40
Terrace Floor Cft 82.69 330.00 27,287.70
D STEEL
D01 Steel Reinforcement including
fabrication (Basic cost=Rs.50000
Stilt/-)floor Kgs 8,000.00 68.00 544,000.00
Ground floor Kgs 5,750.00 68.00 391,000.00
First floor Kgs 5,050.00 68.00 343,400.00
Terrace floor Kgs 675.00 68.00 45,900.00
1,324,300.00
F INTERIOR WORKS
G PLASTERING
G01 Outside Plastering
Stilt floor Sft 4,135.06 55.00 227,428.30
Ground floor Sft 2,345.50 55.00 129,002.50
First floor Sft 2,035.00 55.00 111,925.00
Terrace floor Sft 1,991.56 55.00 109,535.80
G02 Inside Wall Plastering
Stilt floor Sft 3,105.25 52.00 161,473.00
Ground floor Sft 3,242.40 52.00 168,604.80
First floor Sft 3,422.50 52.00 177,970.00
Terrace floor Sft 510.00 52.00 26,520.00
G03 Inside Ceiling Plastering
Stilt floor Sft 1,933.56 55.00 106,345.80
Ground floor Sft 1,572.21 55.00 86,471.55
First floor Sft 1,155.99 55.00 63,579.45
Terrace floor Sft 165.00 55.00 9,075.00
G04 Water proof plastering for toilets and
open area in terrace floor Ground floor Sft 145.75 60.00 8,745.00
First floor Sft 195.50 60.00 11,730.00
1,398,406.20
I PAINTING WORKS
I01 Plastic Emulsion
Stilt floor Sft 5,038.81 26.00 131,009.06
Ground floor Sft 4,814.61 26.00 125,179.86
First floor Sft 4,578.49 26.00 119,040.74
Terrace floor Sft 675.00 26.00 17,550.00
I02 Exterior Emulsion (Apex)
Stilt floor Sft 4,135.06 24.00 99,241.44
Ground floor Sft 2,345.50 24.00 56,292.00
First floor Sft 2,035.00 24.00 48,840.00
Terrace floor Sft 1,991.56 24.00 47,797.44
I03 Enamel Paint
Stilt floor Sft 360.63 22.00 7,933.86
Ground floor Sft 178.13 22.00 3,918.75
First floor Sft 226.88 22.00 4,991.25
I04 Melamine Polish
Stilt floor Sft 266.83 90.00 24,014.25
Ground floor Sft 510.63 90.00 45,956.25
First floor Sft 463.13 90.00 41,681.25
773,446.15
J MISCELLANEOUS
J01 Sump Tank Ltrs 10,000.00 10.00 100,000.00
J02 Anti-termite treatment for Pesticides Sft 2,400.00 10.00 24,000.00
J03 Bath Floor Filling
Ground floor Cft 70.00 80.00 5,600.00
First floor Cft 138.00 80.00 11,040.00
J04 Stone Slab over Drains Sft 200.00 250.00 50,000.00
J05 Chicken Mesh Sft 200.00 180.00 36,000.00
J06 Grooves 1/2" Sft 600.00 20.00 12,000.00
J07 Cornice works - 1 step Sft 400.00 30.00 12,000.00
2 steps Sft 200.00 50.00 10,000.00
J08 Washing Stone Sft 10.00 350.00 3,500.00
J09 20 mm granite for Name board No 1.00 5,000.00 5,000.00
J10 Granite Cutting for Sink Each 3.00 600.00 1,800.00
J11 Granite Cutting for Hob Each 1.00 300.00 300.00
J12 Chimney Hole Each 2.00 1,000.00 2,000.00
J13 Gas Piping L.S 15,000.00
J14 Rain Water Harvesting Each 2.00 15,000.00 30,000.00
J15 Rough Stone Cladding @ Outside Wall Sft 550.00 400.00 220,000.00
(Inclusive of Material) 538,240.00
K M.S. / S.S. WORKS (without Basic material cost but including Painting)
K01 M.S. Gate Sft 130.00 60.00 7,800.00
K02 M.S. Staircase Railing Sft 71.06 50.00 3,553.00
K03 M.S. Covering Grill Sft 871.50 40.00 34,860.00
K04 M.S. Balcony Railing Sft 45.00 35.00 1,575.00
K05 M.S. T-angle Set 1.00 350.00 350.00
K06 M.S. Sky light covering Sft 355.00 100.00 35,500.00
K07 M.S. Ladder L.S 1.00 1,500.00 1,500.00
K08 M.S.Door Sft 42.00 60.00 2,520.00
K09 M.S.Grill Door Sft 21.00 80.00 1,680.00
K10 M.S.Frame for Structural Glazing Sft 325.00 50.00 16,250.00
105,588.00
M.S. WORKS
1 M.S. Gate Sft 130.00 400.00 52,000.00
2 S.S Staircase Railing Sft 71.06 1,000.00 71,060.00
3 M.S. Covering Grill Sft 871.50 200.00 174,300.00
4 M.S. Balcony Railing Sft 45.00 180.00 8,100.00
5 M.S. T-angle Set 1.00 5,000.00 5,000.00
6 M.S. Sky light covering Sft 355.00 300.00 106,500.00
7 M.S. Ladder L.S 1.00 8,500.00 8,500.00
8 M.S.Door Sft 42.00 380.00 15,960.00
9 M.S.Grill Door Sft 21.00 300.00 6,300.00
10 M.S.Frame for Structural Glazing Sft 325.00 200.00 65,000.00
2,879,440.00
COST SUMMARY
A EARTHWORK 182,131.75
D STEEL 1,324,300.00
G PLASTERING 1,398,406.20
H FLOORING 1,288,610.15
S EXTRA WORKS
a) Sanction Plan Charges
b) BWSSB Prorata, Point & inspection
Charges
BESCOM( deposits
Approximately )
and office 150,000.00
c) expencess for Temparory
connection( Approximately)
BESCOM deposits and office 60,000.00
d) expencess for permanent
connection( Approximately) 100,000.00
e) Bore Well Pump 100,000.00
f) Solar Water Heater (200 ltr) 60,000.00
470,000.00
T FIXTURES & APPLIANCES (Including Labour)
a) 25 lts Geyser Nos 6.00 10,500.00 63,000.00
b) Ceiling Fans Nos 10.00 2,500.00 25,000.00
c) Tube Lights (LED) Nos 10.00 650.00 6,500.00
d) 40 W Light Nos 10.00 18.00 180.00
e) Calling Bell Nos 2.00 180.00 360.00
f) Bulkhead Fitting Nos 5.00 350.00 1,750.00
g) Electrical Chimney Nos 1.00 25,000.00 25,000.00
h) Hobb Nos 1.00 10,000.00 10,000.00
i) Towel Rod Nos 7.00 1,800.00 12,600.00
j) Towel Ring Nos 7.00 750.00 5,250.00
k) Soup Tray Nos 7.00 750.00 5,250.00
l) Mirror in Bathroom Nos 7.00 850.00 5,950.00
m) Corner Tray Nos 6.00 1,400.00 8,400.00
n) 1.0 H.P Water Pump & fittings Nos 1.00 12,000.00 12,000.00
o) Pelmet Rods Ls 1.00 60,000.00 60,000.00
241,240.00
AREA STATEMENT
512,720.00
295,970.00
232,500.00
171,250.00
200,000.00
100,000.00
2,000,000.00
300,000.00
300,000.00
2,900,000.00
3 . PREAMBLE TO SCHEDULE OF QUANTITIES
While quoting we assume the following basic rates (landed cost at site including
all taxes and levies) The Rates quoted will be for all leads and lifts
r Euro or Equivalent
r Euro or Equivalent
r Euro or Equivalent
r Euro or Equivalent
r Euro or Equivalent
r Euro or Equivalent
r Euro or Equivalent
Dr.PINAKINI.K.SHANKAR RESIDENCE
MEASUREMENT SHEET OF R.A. BILL - 1
A Earthwork
A01 Earthwork Excavation
A) For Footings
Earthwork Excavation @ Column Footing
F1 2.00 9.00 7.50 5.00 675.00
F2 7.00 7.50 7.00 5.00 1,837.50
F3 1.00 6.50 5.50 5.00 178.75
F4 1.00 8.50 7.00 5.00 297.50
F5 1.00 4.50 4.50 5.00 101.25
CF1 1.00 12.00 11.50 8.00 1,104.00
4,194.00 Cft
B) For S.S.M
North Side(40-10.5) 1.00 29.50 2.50 2.00 147.50
East Side(55-(7.5*2+6.5) 1.00 25.00 2.50 2.38 148.44
West Side(55-(7.5*4)) 1.00 30.00 2.50 2.50 187.50
South Side(40-(7+8.5)) 1.00 24.50 2.50 3.00 183.75
667.19 Cft
C)Below Plinth Beam
Horizontal
Grid 1A-1C 1.00 13.75 1.50 0.50 10.31
Grid 1C-1E 1.00 18.00 1.50 0.50 13.50
Grid 7A-7B 1.00 8.00 1.50 0.50 6.00
Grid 7B-7D 1.00 13.38 1.50 0.50 10.03
Grid 7D-7E 1.00 9.63 1.50 0.50 7.22
Grid 8A-8B' 1.00 10.38 1.50 0.50 7.78
Grid 8B'-8D 1.00 9.00 1.50 0.50 6.75
Vertical
Grid A1-A1' 1.00 9.08 1.50 0.50 6.81
Grid A1'-A4 1.00 9.17 1.50 0.50 6.88
Grid A4-A7 1.00 12.00 1.50 0.50 9.00
Grid A7-A8 1.00 14.25 1.50 0.50 10.69
Grid C1-C2 1.00 10.73 1.50 0.50 8.05
Grid C2-C6 1.00 15.50 1.50 0.50 11.63
Grid D7-D8' 1.00 17.25 1.50 0.50 12.94
Grid E1-E3 1.00 15.48 1.50 0.50 11.61
Grid E3-E5 1.00 8.25 1.50 0.50 6.19
Grid E5-E7 1.00 6.50 1.50 0.50 4.88
S.S.M Piller 2.00 2.00 2.00 0.50 4.00
154.26 Cft
5,015.44 Cft
B Masonry works
B01 Size Stone Masonry in CM 1:6
Compound wall
North Side
1st Course NW side 1.00 21.93 1.75 0.75 28.78
Next to sump 1.00 10.50 1.00 0.75 7.88
NE side 1.00 7.57 1.75 0.75 9.93
2nd Course NW side 1.00 21.93 1.75 0.75 28.78
Next to sump 1.00 10.50 1.00 0.75 7.88
NE side 1.00 7.57 1.75 0.75 9.93
3rd Course NW side 1.00 21.93 1.50 0.75 24.67
Next to sump 1.00 10.50 1.00 0.75 7.88
NE side 1.00 7.57 1.50 0.75 8.51
4th Course NW side 1.00 21.93 1.50 0.75 24.67
South Side
1st Course 1.00 40.00 1.75 0.75 52.50
2nd Course 1.00 40.00 1.75 0.75 52.50
3rd Course 1.00 40.00 1.50 0.75 45.00
4th Course 1.00 40.00 1.50 0.75 45.00
5th Course 1.00 40.00 1.50 0.75 45.00
East Side
1st course 1.00 7.50 2.00 0.75 11.25
2nd course 1.00 7.50 1.75 0.75 9.84
3rd Course(49+7.5) 1.00 56.50 1.75 0.75 74.16
4th Course(49+7.5) 1.00 56.50 1.50 0.75 63.56
West Side
1st Course 1.00 56.50 1.75 0.75 74.16
2nd Course 1.00 56.50 1.75 0.75 74.16
3rd Course 1.00 56.50 1.50 0.75 63.56
4th Course 1.00 56.50 1.50 0.75 63.56
SSM Piller Below Plinth Beam
1st Course 2.00 1.50 1.50 0.75 3.38
2nd Course 2.00 1.50 1.50 0.75 3.38
839.91 Cft
C Concrete works
C01 PCC 1:4:8
A) For Below Footings
At column footing
F1 2.00 9.00 7.50 0.50 67.50
F2 7.00 7.50 7.00 0.50 183.75
F3 1.00 6.50 5.50 0.50 17.88
F4 1.00 8.50 7.00 0.50 29.75
F5 1.00 4.50 4.50 0.50 10.13
CF1 1.00 12.00 11.50 0.50 69.00
378.00 Cft
Below S.S.M
North Side 1.00 29.50 2.50 0.50 36.88
Sump 1.00 10.50 1.00 0.50 5.25
South Side 1.00 40.00 2.50 0.50 50.00
East Side 1.00 55.00 2.50 0.50 68.75
West Side 1.00 55.00 2.50 0.50 68.75
229.63 Cft
Below Plinth Beam
Horizontal
Grid 1A-1C 1.00 13.75 1.50 0.25 5.16
Grid 1C-1E 1.00 18.00 1.50 0.25 6.75
Grid 7A-7B 1.00 8.00 1.50 0.25 3.00
Grid 7B-7D 1.00 13.38 1.50 0.25 5.02
Grid 7D-7E 1.00 9.63 1.50 0.25 3.61
Grid 8A-8D 1.00 20.88 1.50 0.25 7.83
Vertical
Grid A1-A4 1.00 19.75 1.50 0.25 7.41
Grid A4-A7 1.00 12.00 1.50 0.25 4.50
Grid A7-A8 1.00 14.25 1.50 0.25 5.34
Grid C1-C2 1.00 10.73 1.50 0.25 4.02
Grid C2-C6 1.00 15.50 1.50 0.25 5.81
Grid D7-D8' 1.00 17.25 1.50 0.25 6.47
Grid E1-E3 1.00 15.48 1.50 0.25 5.81
Grid E3-E5 1.00 8.25 1.50 0.25 3.09
Grid E5-E7 1.00 6.50 1.50 0.25 2.44
76.25 Cft
Total P.C.C Below Footings 683.88 Cft
B) Below Flooring
A1 1.00 13.75 28.50 0.50 195.94
A2 1.00 6.25 8.00 0.50 25.00
A3 1.00 22.13 15.00 0.50 165.94
A4 1.00 18.00 34.75 0.50 312.75
699.63 Cft
Vertical
Grid A1-A1' 1.00 9.08 0.75 1.25 8.52
Grid A1'-A4 1.00 9.17 0.75 1.25 8.59
Grid A4-A7 1.00 12.00 0.75 1.25 11.25
Grid A7-A8 1.00 14.25 0.75 1.25 13.36
Grid C1-C2 1.00 10.73 0.75 1.25 10.06
Grid C2-C6 1.00 15.50 0.75 1.25 14.53
Grid D7-D8' 1.00 17.25 0.75 1.25 16.17
Grid E1-E3 1.00 15.48 0.75 1.25 14.52
Grid E3-E5 1.00 8.25 0.75 1.25 7.73
Grid E5-E7 1.00 6.50 0.75 1.25 6.09
187.82 Cft
Plinth Beam Above S.S.M
North Side 1.00 40.00 0.75 0.50 15.00
East Side(60-2.5) 1.00 57.50 0.75 0.50 21.56
West Side(60-2.5) 1.00 57.50 0.75 0.50 21.56
58.13 Cft
245.95 Cft
D01 Steel
Bill dt.04.12.19 3,695.00
Bill dt.27.12.19 998.00
Steel brought from Renuka murthy site 120.00
4,813.00 Kgs
A Earthwork
A01 Earthwork Excavation
B) S.S.M For Stair case landing
Landing 1.00 3.50 2.00 2.50 17.50
Landing 1 1.00 3.50 4.50 3.25 51.19
68.69 Cft
B Masonry works
B01 Size Stone Masonry in CM 1:6
Landing (3 course) 1.00 3.50 2.00 2.25 15.75
Landing 1 (4 course) 1.00 3.50 4.50 3.00 47.25
63.00 Cft
B02 BBM 9" thk WALL
Stilt floor
Horizontal Walls
Grid 1(13.75+18) 1.00 31.75 0.75 9.00 214.31
Grid 6(3.5+4) 1.00 7.50 0.75 9.00 50.63
Grid 7(8+13.375+9.625) 1.00 31.00 0.75 9.00 209.25
Vertical Walls
Grid A(19.75+12) 1.00 31.75 0.75 9.00 214.31
Grid B 1.00 4.75 0.75 9.00 32.06
Grid C(15.5+5.5) 1.00 21.00 0.75 9.00 141.75
Grid D 1.00 14.25 0.75 9.00 96.19
Grid E(15.5+8.25+6.75) 1.00 30.50 0.75 9.00 205.88
Deduction
ED 3.00 3.50 0.75 7.00 55.13
LD 1.00 3.00 0.75 7.00 15.75
D2 1.00 3.00 0.75 7.00 15.75
W3 4.00 5.00 0.75 4.50 67.50
W5 2.00 3.00 0.75 4.50 20.25
W6 1.00 2.00 0.75 4.50 6.75
KW 1.00 3.00 0.75 4.50 10.13
V1 2.00 3.00 0.75 2.00 9.00
Opening 1.00 3.25 0.75 7.00 17.06
1,164.38 217.31
947.06 Cft
Deduction
PD 1.00 4.00 7.00 28.00
D2 2.00 3.00 7.00 42.00
D4 2.00 2.50 7.00 35.00
861.75 105.00
756.75 Sft
C Concrete works
C01 PCC 1:4:8
Landing 1.00 3.50 2.00 0.42 2.92
Landing 1 1.00 3.50 4.50 0.42 6.56
9.48 Cft
C04 PCC 1:3:6 Sills
Stilt floor
W6 in Reception 1.00 4.00 0.75 0.25 0.75
W3 in Room -2 1.00 6.50 0.75 0.25 1.22
W5 in Clinic 1.00 5.50 0.75 0.25 1.03
W5 in Clinic 1.00 4.67 0.75 0.25 0.88
W3 in Living 1.00 6.50 0.75 0.25 1.22
W3 in Room -1 1.00 6.25 0.75 0.25 1.17
W3 in Dining 1.00 6.00 0.75 0.25 1.13
KW 1.00 4.00 0.75 0.25 0.75
8.14 Cft
C05 RCC Column Concrete
Grid A1 1.00 0.75 1.50 10.50 11.81
Grid C1 1.00 0.75 1.50 10.50 11.81
Grid E1 1.00 0.75 1.50 10.50 11.81
Grid C2 1.00 0.75 1.50 10.50 11.81
Grid E3 1.00 0.75 1.50 10.50 11.81
Grid A4 1.00 0.75 1.50 10.50 11.81
Grid E5 1.00 0.75 1.50 10.50 11.81
Grid B6 1.00 1.50 0.75 10.50 11.81
Grid C6 1.00 1.50 0.75 10.50 11.81
Grid A7 1.00 0.75 1.50 10.50 11.81
Grid B7 1.00 0.75 1.50 10.50 11.81
Grid D7 1.00 0.75 1.50 10.50 11.81
Grid E7 1.00 0.75 1.25 10.50 9.84
Grid A8 1.00 0.75 1.50 10.50 11.81
Grid D8 1.00 2.00 0.75 10.50 15.75
Grid D8' 1.00 0.75 0.75 10.50 5.91
185.06 Cft
C06 RCC Lintel Concrete
Stilt floor
W6 & ED in Reception 1.00 9.50 0.75 0.50 3.56
ED IN Lift 1.00 7.33 0.75 0.50 2.75
LD 1.00 5.50 0.75 0.50 2.06
W3 in Room -2 1.00 6.25 0.75 0.50 2.34
Passage Beyond Room 2 1.00 5.75 0.75 0.50 2.16
W5 in Clinic 2.00 5.00 0.75 0.50 3.75
W3 & ED in Living 1.00 12.83 0.75 0.50 4.81
W3 in Room -1 1.00 7.00 0.75 0.50 2.63
W3 & D2 in Dining 1.00 11.25 0.75 0.50 4.22
Kitchen South wall 1.00 10.38 0.38 0.50 1.95
kitchen East wall 1.00 3.13 0.38 0.50 0.59
Toilet South Wall 1.00 13.75 0.38 0.50 2.58
Toilet East Wall 1.00 4.63 0.38 0.50 0.87
Room 1 West wall 1.00 12.00 0.38 0.50 2.25
Room 1 South Wall 1.00 12.38 0.38 0.50 2.32
Living South Wall 1.00 18.00 0.38 0.50 3.38
Room 2 West Wall 1.00 11.00 0.38 0.50 2.06
Toilet 2 North Wall 1.00 4.38 0.38 0.50 0.82
Toilet 2 West Wall 1.00 6.13 0.38 0.50 1.15
46.24 Cft
C07 RCC Chajja Concrete
Stilt floor
W3 in Room-1 1.00 6.00 2.00 12.00
W3 & ED In Living 1.00 11.83 3.00 35.50
W5 in Clinic 2.00 4.00 2.00 16.00
V1 2.00 4.00 2.00 16.00
79.50 Sft
C08 RCC ROOF Beam Concrete
Stilt floor
Horizontal
Grid B0-E0 1.00 25.33 0.50 1.50 19.00
Grid A1-C1 1.00 13.75 0.75 1.50 15.47
Grid C1-E1 1.00 18.00 0.75 1.50 20.25
Grid C3-E3 1.00 18.00 0.75 1.50 20.25
Grid C5-E5 1.00 18.00 0.75 1.50 20.25
Grid A6-B6 1.00 8.00 0.50 1.50 6.00
Grid B6-E6 1.00 3.50 0.75 1.50 3.94
Grid B7-D7 1.00 13.38 0.75 1.50 15.05
Grid D7-E7 1.00 9.63 0.75 1.50 10.83
Grid A7'-B7' 1.00 8.00 0.50 1.50 6.00
Grid A8-D8 1.00 20.88 0.75 2.00 31.31
Vertical
Grid 1A-4A 1.00 19.75 0.75 2.00 29.63
Grid 4A-7A 1.00 12.00 0.75 1.50 13.50
Grid 7A-8A 1.00 14.25 0.75 1.50 16.03
Grid 6B-7B 1.00 4.75 0.75 1.50 5.34
Grid 7B-8B 1.00 15.00 0.75 1.50 16.88
Grid 0C-1C 1.00 4.50 0.75 1.50 5.06
Grid 1C-2C 1.00 10.75 0.75 1.50 12.09
Grid 2C-6C 1.00 15.50 0.75 1.50 17.44
Grid 6C-7C 1.00 5.50 0.75 1.50 6.19
Grid 7D-8D 1.00 14.25 0.75 1.50 16.03
Grid 0E-1E 1.00 4.50 0.75 1.50 5.06
Grid 1E-3E 1.00 15.50 0.75 1.50 17.44
Grid 3E-5E 1.00 8.25 0.75 1.50 9.28
Grid 5E-7E 1.00 6.75 0.75 1.50 7.59
Grid 7E-7E' 1.00 4.00 0.75 1.50 4.50
Grid 3D-5D 1.00 9.00 0.75 1.50 10.13
360.53 Cft
C09 RCC ROOF Slab Concrete
Stilt floor
S1 1.00 5.83 4.50 0.42 10.94
S2 1.00 18.00 4.50 0.42 33.70
S3 1.00 13.75 28.50 0.50 195.94
S4 1.00 18.00 17.00 0.50 153.00
S5 1.00 18.00 9.00 0.42 67.51
S6 1.00 18.00 7.25 0.42 54.38
S7 1.00 3.00 12.75 0.50 19.13
S8 1.00 8.00 14.25 0.50 57.00
S9 1.00 13.38 15.00 0.50 100.31
S10 1.00 5.63 4.00 0.50 11.25
S11 1.00 8.00 6.75 0.42 22.50
Extra Portion Left Side To S1 1.00 4.50 4.17 0.42 7.81
733.46 Cft
C09 RCC Staircase Waist slab Type
Stilt floor
B Masonry works
C Concrete works
C04 PCC 1:3:6 Sills
Ground floor
W5 in Room 2.00 4.50 0.75 0.25 1.69
V in Toilet 1.00 6.50 0.75 0.25 1.22
V2 in Pwd Room 1.00 3.50 0.75 0.25 0.66
W2 in Dining 1.00 7.50 0.75 0.25 1.41
KW in Kitchen 1.00 4.50 0.75 0.25 0.84
W1 in Living 1.00 9.50 0.75 0.25 1.78
7.59
4.5" wall
Pwd room north wall 1.00 8.75 0.38 0.50 1.64
Pwd room south wall 1.00 8.75 0.38 0.50 1.64
Toilet east wall 1.00 9.38 0.38 0.50 1.76
Toilet south wall 1.00 7.00 0.38 0.50 1.31
28.76
60.25
26.25
34.13
15.75
36.00
27.00
20.25
10.13
7.50
6.75
183.75
Cft
38.50
38.50
Sft
Cft
Cft
Cft
Sft
Cft
Cft
Dr.PINAKINI.K.SHANKAR RESIDENCE
MEASUREMENT SHEET OF R.A. BILL - 4
B Masonry works
Vertical Walls
Grid A(1.25+19.75) 1.00 21.00 0.75 8.50 133.88
Grid A(12+14.25) 1.00 26.25 0.75 9.00 177.19
GRID A' 1.00 5.63 0.75 1.13 4.75
Grid B 1.00 4.75 0.75 9.00 32.06
Grid C(1.25+10.75+8.25+5.5) 1.00 25.75 0.75 9.00 173.81
Grid D 1.00 14.25 0.75 9.00 96.19
Grid E(1.25+15.5+8.25+7.25) 1.00 32.25 0.75 9.00 217.69
Deduction
D1 3.00 3.25 0.75 7.00
W1 2.00 8.00 0.75 6.00
W4 1.00 3.00 0.75 6.00
W5 5.00 3.00 0.75 4.50
V 2.00 5.00 0.75 2.00
Buch work 2.00 0.67 0.75 6.00
1,532.43
1,324.11
Vertical Walls
Grid A' 1.00 9.00 10.00 90.00
Grid A'' 1.00 6.00 10.00 60.00
Deduction
D3 2.00 2.75 7.00
295.75
257.25
C Concrete works
C04 PCC 1:3:6 Sills
First Floor
W5 in bedroom SW side 2.00 5.00 0.75 0.25 1.88
W5 in sun room north wall 1.00 5.00 0.75 0.25 0.94
V in A.toilet NW side 1.00 7.00 0.75 0.25 1.31
W1 in living north wall 1.00 10.00 0.75 0.25 1.88
W5 in bedroom NW side 2.00 5.00 0.75 0.25 1.88
V in A.toilet SW side 1.00 7.00 0.75 0.25 1.31
W1 in living east wall 1.00 10.00 0.75 0.25 1.88
W4 in open below east side 1.00 5.00 0.75 0.25 0.94
12.00
4 ½" wall
A.toilet NW side east wall 1.00 9.38 0.38 0.50 1.76
A.toilet NW side south wall 1.00 6.38 0.38 0.50 1.20
A.toilet SW side north wall 1.00 1.38 0.38 0.50 0.26
A.toilet SW side east wall 1.00 6.00 0.38 0.50 1.13
A.toilet SW side south wall 1.00 6.63 0.38 0.50 1.24
28.22
51.19
72.00
13.50
50.63
15.00
6.00
208.32
Cft
38.50
38.50
Sft
Cft
Cft
Cft
Sft
40.84
40.84
Cft
Dr.PINAKINI.K.SHANKAR RESIDENCE
MEASUREMENT SHEET OF R.A. BILL - 5
A Earthwork
A01 Earthwork Excavation
S.S.M For Garden North wall Below 1.00 12.63 2.00 1.50 37.88
Below Columns -
Grid A9 1.00 2.00 2.00 2.00 8.00
Grid D9 1.00 2.00 2.00 2.00 8.00
Grid E'9 1.00 2.00 2.00 2.00 8.00
For East Compound Wall 1.00 35.00 1.50 1.00 52.50
114.38 Cft
B Masonry works
B01 Size Stone Masonry in CM 1:6
For Garden North wall Below 1.00 12.63 2.00 0.75 18.94 Cft
Ground Floor
Pooja Bottom Course(9'9"+2'6"+2'6"+4'1.5") 1.00 18.88 0.75 0.33 4.71
Utility Brick Pillars 3.00 0.38 0.75 4.25 3.59
8.30 Cft
First Floor
Sun room 1 course(15'0"+10'4.5") 1.00 25.38 0.75 0.33 6.28 Cft
Terrace Floor
Horizontal Walls
Grid 4 1.00 14.50 0.75 7.50 81.56
Grid 6(8'+3'6") 1.00 11.50 0.75 7.50 64.69
Grid 7(8'+5'9") 1.00 13.75 0.75 7.50 77.34
Vertical Walls
Grid A 1.00 12.00 0.75 7.50 67.50
Grid C(5'6"+6'6") 1.00 12.00 0.75 7.50 67.50
For Placing Channel 1.00 4.75 0.75 4.42 15.73
Step To Channel Wall 1.00 5.50 0.75 1.75 7.22
For Placing Controller 1.00 3.00 1.42 1.17 4.98
Parapet wall
Horizontal Walls
Grid 0 1.00 32.50 0.75 3.00 73.13
Grid 7 1.00 10.38 0.75 3.00 23.34
Grid 8 1.00 14.50 0.75 4.50 48.94
Grid 8(2 Course) 1.00 8.38 0.75 0.63 3.93
Vertical Walls
Grid A(2+19.75+12.75) 1.00 34.50 0.75 3.00 77.63
Grid A 1.00 1.50 0.75 4.50 5.06
Grid E(2+15.5+8.25+7.25) 1.00 33.00 0.75 3.00 74.25
Grid D(2 Course) 1.00 14.25 0.75 0.63 6.68
Deduction
D1 2.00 3.25 0.75 7.00 34.13
Buch Work 2.00 0.67 0.75 6.00 6.00
699.48 40.13
659.35 Cft
B03 BBM 4 ½" thk WALL
Stilt Floor
Horizontal wall
Garden North Wall (2'6"+2'5"+2'5") 1.00 7.33 2.50 18.33
Compound Wall(55'6"+36'3"+13'6") 1.00 105.25 3.92 412.23
Vertical wall
NW Toilets
Clinic Toilet East Wall 1.00 4.63 7.00 32.38
Gen Toilet East Wall 1.00 4.63 10.00 46.25
Kitchen Paltform
North Side 1.00 8.25 0.42 3.44
West Side 1.00 5.50 0.42 2.29
Wardrobe Paltform
NE Bedroom 1.00 12.00 0.42 5.00
SE Bedroom(4'4.5"+1'6") 1.00 5.88 0.42 2.45
Deduction
D4 1.00 2.50 7.00 17.50
522.37 17.50
504.87 Sft
Ground Floor
Pooja
Horizontal Walls
North Wall 1.00 9.38 2.00 18.75
South Wall 1.00 3.75 2.00 7.50
West Wall 2.00 2.50 2.00 10.00
Infront Of Pooja(4'6"+4'0"+4'6") 1.00 13.00 0.33 4.29
Platform For Powder Room Flush Tank 1.00 2.25 4.25 9.56
Platform For SW Toilet Flush Tank 1.00 6.25 4.00 25.00
Kitchen Paltform
North Side 1.00 3.50 0.42 1.46
West Side(6'7.5"+1'9") 1.00 8.38 0.42 3.49
80.05 Sft
First Floor
Platform For SW Toilet Flush Tank 1.00 6.25 4.00 25.00
NW Wardrobe Platform
North Side 1.00 5.63 0.42 2.34
East Side(7'3"+1'9") 1.00 9.00 0.42 3.75
31.09 Sft
Terrace Floor
For Elliptical Cutout 1.00 34.08 0.67 22.73
OHT Parapet wall
Horizontal Walls
Grid 4 1.00 12.00 2.50 30.00
Grid 7 1.00 14.50 2.50 36.25
wall near Cut out 2.00 6.75 0.63 8.44
Vertical Walls
Grid A 1.00 12.00 2.50 30.00
Grid C 1.00 13.88 2.50 34.69
wall near Cut out 2.00 1.00 0.63 1.25
163.36 Sft
C Concrete works
C01 PCC 1:4:8
Below Footing
Below S.S.M 1.00 13.38 2.00 0.50 13.38 Cft
Terrace Floor
Grid A4 1.00 1.50 0.75 9.00 10.13
Grid A7 1.00 1.50 0.75 9.00 10.13
Grid B6 1.00 1.50 0.75 9.00 10.13
Grid B7 1.00 1.50 0.75 9.00 10.13
Grid C6 1.00 1.50 0.75 9.00 10.13
Short height
Grid A1 1.00 1.50 0.75 3.25 3.66
Grid C1 1.00 1.50 0.75 3.25 3.66
Grid E1 1.00 1.50 0.75 3.25 3.66
Grid C2 1.00 1.50 0.75 3.25 3.66
Grid E3 1.00 1.50 0.75 3.25 3.66
Grid E5 1.00 1.50 0.75 3.25 3.66
Grid D7 1.00 1.50 0.75 3.25 3.66
Grid A8 1.00 1.50 0.75 4.92 5.53
Grid D8 1.00 2.00 0.75 0.63 0.94
OHT Room
Grid A4 1.00 1.50 0.75 2.75 3.09
Grid A7 1.00 1.50 0.75 2.75 3.09
88.88 Cft
Terrace Floor
Grid A7-C7 (B1)(8'+5'9") 1.00 13.75 0.75 1.50 15.47
Grid A6-B6 (B2) 1.00 8.00 0.75 1.50 9.00
Grid B6-C6 (B3) 1.00 3.50 0.75 1.50 3.94
Grid B6-B7 (B3) 1.00 4.75 0.75 1.50 5.34
Grid A4-C4 (B4) 1.00 14.50 0.75 1.50 16.31
Grid A4-A7 (B5) 1.00 12.00 0.75 1.50 13.50
Grid C4-C7 (B6)(6'6"+5'6") 1.00 12.00 0.75 1.50 13.50
77.06 Cft
Terrace Floor
S1 1.00 13.75 6.50 0.42 37.24
S2 1.00 8.00 5.50 0.42 18.33
S3 1.00 5.00 5.50 0.50 13.75
69.33 Cft
WINDOWS
E06 Teak wood frame with Teak wood shutter for
Windows
Stilt floor
W3 4.00 5.00 4.50 90.00
W5 2.00 3.00 4.50 27.00
W6 1.00 2.00 4.50 9.00
KW 1.00 3.00 4.50 13.50
V1 1.00 3.00 2.00 6.00
145.50 Sft
Ground floor
W1 1.00 8.00 6.00 48.00
W2 1.00 6.00 6.00 36.00
W5 2.00 3.00 4.50 27.00
KW 1.00 3.00 4.50 13.50
V 1.00 5.00 2.00 10.00
V2 1.00 2.00 4.50 9.00
143.50 Sft
First Floor
W1 2.00 8.00 6.00 96.00
W4 1.00 3.00 6.00 18.00
W5 4.00 3.00 4.50 54.00
V 2.00 5.00 2.00 20.00
188.00 Sft
G PLASTERING
G01 Outside Plastering
Stilt floor
N,S,E & West Side 1.00 142.00 10.50 1,491.00
Parking East Wall 1.00 32.00 10.00 320.00
Column Grid A8(1'6"+9")*2 1.00 4.50 9.00 40.50
Compound Wall
N,E & West Side 1.00 294.08 4.17 1,225.45
Top 1.00 64.59 64.59
South Side
(3'9"+9")*2 1.00 9.00 7.50 67.50
(10'7.5"+9")*2 1.00 22.75 7.50 170.63
S Side Beam(1'6"+9")*2 1.00 40.00 4.50 180.00
Garden
E Side Wall(14'9"*2) 1.00 29.50 8.50 250.75
Lintel 1.00 14.75 1.75 25.81
North Wall 1.00 27.50 8.50 233.75
Lintel & Above 1.00 12.63 3.50 44.19
Chajjas
W3 in NE side 1.00 12.50 2.25 28.13
W3 & ED In Living 1.00 24.17 3.25 78.54
W5 in Clinic 2.00 8.50 2.25 38.25
V1 1.00 8.50 2.25 19.13
O 1.00 10.00 2.25 22.50
Deductions
Parking North Wall 1.00 32.50 0.50 16.25
South Compound Wall(3'9"+10'7.5"+9") 1.00 15.13 0.75 11.34
9" Junction 1.00 0.75 9.00 6.75
5.5" Junction 1.00 0.46 4.17 1.92
4.5" Junction 2.00 0.38 2.50 1.88
4" Junction 1.00 0.33 4.17 1.39
4,300.70 39.52
4,261.18 Sft
Ground floor
N,S,E & West side 1.00 172.00 10.50 1,806.00
Utility Wall 1.00 75.25 4.50 338.63
Top 1.00 14.39 14.39
Chajjas
W2 in Dining 1.00 14.50 2.25 32.63
W1 in Living 1.00 18.50 2.25 41.63
W5 In Bedroom Top & Bottom 4.00 15.00 1.00 60.00
W5 In Bedroom Sides 4.00 4.50 1.00 18.00
V in Toilet 1.00 12.50 2.25 28.13
V2 in Pwd room 1.00 6.50 2.25 14.63
Deductions
Entrance West Wall 1.00 34.13 0.50 17.06
4.5" Junction 2.00 0.38 4.50 3.38
2,354.02 20.44
2,333.58 Sft
First floor
All around 1.00 176.00 10.50 1,848.00
Railings Below(15'0"+8'4.5") 1.00 23.38 1.92 44.80
Sun room 1 course(15'0"+10'4.5") 1.00 25.38 1.92 48.63
Sunroom Top Portion
East Side
Top & Bottom(2'7"+2'3") 1.00 4.83 15.75 76.12
Sides(2'1"+2'3") 1.00 4.33 15.75 68.25
South Side
Top & Bottom(11.25"+11") 1.00 1.88 10.38 19.51
Sides(2'1"+2'3") 1.00 4.33 10.38 44.96
Pillars 7.00 1.00 8.00 56.00
Chajjas
W4 in open below east side 1.00 8.50 2.25 19.13
W1 in living east & North wall 2.00 18.50 2.25 83.25
W5 in bedroom NW side 2.00 8.50 2.25 38.25
V 2.00 12.50 2.25 56.25
W5 In Bedroom Top & Bottom 4.00 15.00 1.00 60.00
W5 In Bedroom Sides 4.00 4.50 1.00 18.00
2,481.15 Sft
Terrace floor
Level-1
All around 1.00 60.50 9.00 544.50
Parapet Wall
3'6" ht(106'7.5"+12'9") 1.00 119.38 7.75 925.16
4'6" ht(3'+15'3") 1.00 18.25 9.67 176.40
Sill Top & side (15'3"+5"+3'+5") 1.00 19.08 1.42 27.10
Sill Bottom 1.00 19.08 0.42 7.95
Elliptical Cutout 1.00 34.08 2.12 72.43
Level-2
All around 1.00 113.00 3.00 339.00
Cutout
Horizontal walls
Inside 2.00 6.00 1.08 13.00
Outside 2.00 6.75 0.58 7.87
Vertical walls
Inside 2.00 1.00 1.08 2.17
Outside 2.00 1.75 0.58 2.04
Chajjas
D1 2.00 10.00 3.25 65.00
2,182.62 Sft
Deduction
ED 3.00 3.50 7.00 73.50
LD 1.00 3.00 7.00 21.00
D2 3.00 3.00 7.00 63.00
D4 3.00 2.50 7.00 52.50
W3 4.00 5.00 4.50 90.00
W5 2.00 3.00 4.50 27.00
W6 1.00 2.00 4.50 9.00
KW 1.00 3.00 4.50 13.50
V1 1.00 3.00 2.00 6.00
O 1.00 4.63 1.00 4.63
PD 1.00 4.00 7.00 28.00
4,273.14 388.13
3,885.01 Sft
Ground floor
Living,Dining & Kitchen 1.00 69.00 10.00 690.00
Column Grid C2 1.00 4.50 10.00 45.00
Pooja east Wall 1.00 13.75 10.50 144.38
Pooja South Wall 1.00 6.00 10.50 63.00
Pooja NW Wall 1.00 24.50 2.50 61.25
Sill 1.00 26.75 0.33 8.83
Pooja SW Wall 1.00 12.50 2.50 31.25
Sill 1.00 14.00 0.33 4.62
Staircase West Wall 1.00 6.50 10.50 68.25
Foyer & Staircase South wall 1.00 40.00 10.00 400.00
Lift(5'0"+5'6")*2 1.00 21.00 10.50 220.50
Pwd Room(8'0"+5'0")*2 1.00 26.00 10.00 260.00
SW Toilet(6'3"+9'0")*2 1.00 30.50 10.00 305.00
SW Room 1.00 76.75 10.00 767.50
Kitchen Platform(6'10.5"+1'9") 1.00 8.63 2.08 17.94
Platform For Powder Room Flush
Tank(2'3"+4.5"+4.5") 1.00 3.00 4.83 14.50
Platform For SW Toilet Flush Tank 1.00 6.25 4.58 28.65
Deduction
ED/W 1.00 5.00 7.00 35.00
D1 2.00 3.25 7.00 45.50
D3 2.00 2.75 7.00 38.50
LD 1.00 3.00 7.00 21.00
W1 1.00 8.00 6.00 48.00
W2 1.00 6.00 6.00 36.00
W5 2.00 3.00 4.50 27.00
KW 1.00 3.00 4.50 13.50
V 1.00 5.00 2.00 10.00
V2 1.00 2.00 4.50 9.00
3,130.66 283.50
2,847.16 Sft
First floor
Living,Staircase & Study 1.00 138.50 10.00 1,385.00
NW Bedroom 1.00 74.00 10.00 740.00
NW Room Toilet(9'0"+6'0")*2 1.00 30.00 10.00 300.00
Lift(5'0"+5'6")*2 1.00 21.00 10.50 220.50
SW Bedroom 1.00 74.25 10.00 742.50
SW Room Toilet 1.00 40.50 10.00 405.00
Chinmay Wardrobe Platforms(7'4.5"+7'3") 1.00 14.63 2.08 30.42
Platform For SW Toilet Flush Tank 1.00 6.25 4.58 28.65
Deduction
D1 2.00 3.25 7.00 45.50
D3 2.00 2.75 7.00 38.50
LD 1.00 3.00 7.00 21.00
W1 2.00 8.00 6.00 96.00
W4 1.00 3.00 6.00 18.00
W5 4.00 3.00 4.50 54.00
V 2.00 5.00 2.00 20.00
Buch work 2.00 0.67 6.00 8.00
Opening From Room 1.00 6.00 7.00 42.00
Opening From Study 1.00 7.63 7.00 53.38
3,852.07 396.38
3,455.69 Sft
Terrace Floor
Staircase Room(13'9"+6'6")*2 1.00 40.50 8.50 344.25
Wall For placing channel
West Side 1.00 4.75 11.25 53.44
East Side 2.00 3.67 1.17 8.59
Step To Inspect Channel 1.00 5.58 2.58 14.42
Platform For Controller 1.00 3.00 2.84 8.52
Machine Room 1.00 40.00 8.50 340.00
Deduction
D1 2.00 3.25 7.00 45.50
Buch work 2.00 0.67 6.00 8.00
769.22 53.50
715.71 Sft
Folded staircase
Threads 11.00 4.00 0.83 36.65
Risers 12.00 4.00 0.54 26.00
Ceiling
S1 1.00 8.00 7.75 62.00
S2 1.00 8.00 6.75 54.00
S3 1.00 13.38 15.00 200.63
S4 1.00 9.63 4.00 38.50
S5 1.00 3.00 13.25 39.75
S6 1.00 31.70 31.70
S7 1.00 18.00 4.50 81.00
Sides(3'0"+12'9"+9'4.5") 1.00 25.13 0.50 12.56
Beams
Horizontal
Grid B0-E0 1.00 25.33 3.00 75.99
Grid C3-E3 1.00 18.00 2.75 49.50
Grid C5-E5(13'7.5"+4') 1.00 17.63 2.75 48.47
Grid A6-B6 1.00 8.00 1.00 8.00
Grid A7'-B7' 1.00 8.00 1.50 12.00
Grid A8-D8 1.00 20.88 4.25 88.72
Vertical
Grid C0-C1 1.00 4.50 2.75 12.38
Grid E0-E1 1.00 4.50 3.25 14.63
Grid C1-C2 1.00 10.75 2.75 29.56
Grid A7-A8 1.00 14.25 3.25 46.31
Grid B7-B8 1.00 15.00 2.75 41.25
Grid D3-D5 1.00 9.00 2.75 24.75
Grid D7-D7' 1.00 3.25 2.75 8.94
Grid E7-E7' 1.00 4.50 2.75 12.38
Deduction
Junctions 4.00 0.75 1.00 3.00
2,149.95 3.00
2,146.95 Sft
Ground floor
Foyer, Kitchen & Living 1.00 674.93 674.93
Sides(13'9"+18'6"+7'9") 1.00 40.00 0.50 20.00
Pwd Room 1.00 8.00 5.00 40.00
Toilet 1.00 6.25 9.00 56.25
Room 1.00 279.77 279.77
Ceiling
S1 1.00 9.63 15.00 144.38
S2 1.00 5.25 7.25 38.06
S3 1.00 13.75 1.25 17.19
S4 1.00 18.00 1.25 22.50
Beams
Horizontal
Grid A0-E0 1.00 33.25 3.25 108.06
Grid A4-C4 1.00 13.75 3.25 44.69
Grid D7'-E7 1.00 5.25 3.75 19.69
Grid D8-E8 1.00 10.38 4.25 44.09
Vertical
Grid A0-A1 1.00 2.00 4.25 8.50
Grid C0-C1 & E0-E1 2.00 1.25 3.75 9.38
Grid C1-C2 1.00 10.75 2.75 29.56
Grid C2-C4 1.00 8.25 2.75 22.69
Grid C4-C6 1.00 7.25 3.25 23.56
Grid E5-E7 1.00 7.25 3.25 23.56
Grid E7-E8 1.00 15.00 4.25 63.75
Deduction
Junctions 3.00 0.75 1.00 2.25
1,690.60 2.25
1,688.35 Sft
First floor
Living 1.00 18.00 36.75 661.50
NW Bedroom 1.00 259.92 259.92
NW Room Toilet 1.00 6.00 9.00 54.00
SW Bedroom 1.00 289.64 289.64
SW Toilet 1.00 86.84 86.84
Ceiling
S1 1.00 1.50 16.50 24.75
Beams
Horizontal
Grid A7-A7' 1.00 8.00 2.75 22.00
Deduction
Cutout 1.00 75.40 75.40
1,398.66 75.40
1,323.26 Sft
Terrace floor
Staircase Room 1.00 13.75 6.50 89.38
Machine Room 1.00 13.75 5.50 75.63
Beams
Horizontal
Grid B6-B7 1.00 4.75 2.75 13.06
Deduction
Cutout 1.00 1.50 6.00 9.00
178.06 9.00
169.06 Sft
First floor
NW Room 1.00 8.00 11.00 88.00
SW Room 1.00 10.00 14.25 142.50
230.50 Sft
First floor
Family & Study 1.00 661.51 661.51
Pinakini Dress Area 1.00 6.71 8.63 57.86
Chinmay Dress Area 1.00 7.38 9.46 69.75
Deduction
Cut Out 1.00 221.66 221.66
Chinmay Wardrobe(9'0"+7'4.5") 1.00 16.38 1.75 28.66
789.12 250.32
538.80 Sft
First floor
Family & Study 1.00 95.00 95.00
Chinmay Dress Area(5.7.5"+7.3"+1'9") 1.00 14.63 14.63
109.63 Rft
Ground floor
Kitchen Cabinets
West side(8'4.5"+1'9") 1.00 10.13 1.75 17.72
East side 1.00 11.50 2.00 23.00
40.72 Sft
Ground floor
Powder Room 1.00 8.00 5.00 40.00
H10 Ceramic Tiles Dadooing
Stilt floor
Attached Toilet 1.00 20.25 7.00 141.75
General Toilet 1.00 20.50 7.00 143.50
Clinic Toilet 1.00 17.25 7.00 120.75
Deduction
Door 3.00 2.50 7.00 52.50
406.00 52.50
353.50 Sft
Ground floor
Powder Room (8'0"+5'0")*2 1.00 26.00 10.00 260.00
SW Room Toilet (6'3"+9'0")*2 1.00 30.50 10.00 305.00
Deduction
Door 2.00 2.75 7.00 38.50
V 1.00 5.00 2.00 10.00
V2 1.00 2.00 4.50 9.00
565.00 57.50
507.50 Sft
Level -2
O.H.T Room 1.00 13.75 12.75 175.31
Deduction
Skylight 1.00 6.75 1.75 11.81
175.31 11.81
163.50 Sft
1,453.76
J MISCELLANEOUS
J03 Bathroom Filling
Stilt floor
Kitchen Platfrorm
North Side 1.00 10.00 1.75 0.25 4.38
West Side 1.00 5.25 1.75 0.25 2.30
Wardrobe Platfrorm
NE Bedroom 1.00 12.00 1.75 0.25 5.25
SE Bedroom 1.00 4.38 1.75 0.25 1.91
13.84 Cft
Ground floor
PWD Toilet 1.00 8.00 5.00 0.75 30.00
SW Toilet 1.00 6.25 9.00 0.75 42.19
Infront of Pooja 1.00 42.00 0.33 13.86
Kitchen Platfrorm 1.00 9.63 1.75 0.25 4.21
90.26 Cft
First floor
SW Toilet 1.00 86.84 0.75 65.13
Chinmay Wardrobe Floor 1.00 7.38 9.00 0.50 33.19
Wardrobe Platfrorm 1.00 14.34 1.75 0.25 6.27
104.59 Cft
First floor
Sun Room Portion
East Side
Bottom 1.00 2.25 15.75 35.44
Sides(2'1"+2'3") 1.00 4.33 15.75 68.25
pillars 7.00 1.00 8.00 56.00
159.69 Sft
322.68
P DEMOLITION WORKS
P01 S.S.M
Stilt Floor
Below Columns 3 Course Removing
Grid A9 1.00 2.00 2.00 2.25 9.00
Grid D9 1.00 2.00 2.00 2.25 9.00
Grid E'9 1.00 2.00 2.00 2.25 9.00
27.00 Cft
Ground Floor
Pooja Room North wall 1.00 9.75 0.75 2.50 18.28
Pooja Room West wall 2.00 2.50 0.75 2.50 9.38
Pooja Room South wall 1.00 4.13 0.75 7.00 21.66
Kitchen South wall 2.00 2.00 0.75 5.00 15.00
Kitchen East wall 1.00 10.75 0.75 9.00 72.56
SW Toilet shelf 1.00 1.00 0.75 2.00 1.50
138.38 Cft
First Floor
Sunroom West wall 1.00 6.00 0.75 8.00 36.00
Sunroom north wall 1.00 4.38 0.75 7.00 22.97
NW Toilet shelf 1.00 2.00 0.75 1.00 1.50
SW Toilet shelf 1.00 2.00 0.75 1.00 1.50
Deduction
W5 1.00 3.00 0.75 4.50 10.13
61.97 10.13
51.84 Cft
Terrace Floor
For Placing Channel 1.00 3.67 0.75 1.17 3.21 Cft
Ground floor
Kitchen Platforms(8'4.5"+1'9") 1.00 10.13 1.75 0.25
First floor
Chinmay Wardrobe Platform(9'0"+5'7.5") 1.00 14.63 1.75 0.25
J MISCELLANEOUS
J05 Chicken Mesh
Stilt floor
Compound Wall 1.00 30.00 3.83
Ground floor
Windows 4" Thk Band
Bottom 2.00 15.00 1.00
Sides 4.00 4.50 1.00
First floor
Sun Room Portion
East Side
Bottom 1.00 2.25 15.75
Sides(2'1"+2'3") 1.00 4.33 15.75
pillars 7.00 1.00 8.00
6.67
5.25
1.91
13.84
4.43
6.40
114.99 Sft
30.00
18.00
48.00 Sft
35.44
68.25
56.00
159.69 Sft
322.68
Dr. PINAKINI.K.SHANKAR RESIDENTIAL BUILDING
ABSTRACT OF R.A.BILL 1
S EXTRA WORKS
c) BESCOM deposits and office expencess for
Temparory connection( Approximately) 62,000.00
e) Bore Well Pump 75,000.00
137,000.00
lll ESCALATION
Cement
Bill dt.04.12.19 (360.00-375.00= -15.00) Bags (15.00) 40.00 -600.00
Bill dt.13.12.19 (360.00-375.00 = -15.00) Bags (15.00) 50.00 -750.00
Bill dt.22.12.19 (360.00-375.00= -15.00) Bags (15.00) 75.00 -1,125.00
Bill dt.04.01.20 (335.00-375.00= -40.00) Bags (40.00) 100.00 -4,000.00
Steel
Bill dt.04.12.19 (43.01-50.00= -6.99) Kgs (6.99) 3,695.00 -25,828.05
Bill dt.27.12.19 (46.00-50.00 = -4.00) Kgs (4.00) 998.00 -3,992.00
-36,295.05
COST SUMMARY
S EXTRA WORKS -
c) BESCOM deposits and office expencess for
Temparory connection( Approximately) 60,000.00 62,000.00 - - -
e) Bore Well Pump 100,000.00 75,000.00 - - -
f) Solar Water Heater (200 ltr) 60,000.00 - - -
470,000.00 137,000.00 -
lll ESCALATION
Cement
Bill dt.04.12.19 (360.00-375.00= -15.00) Bags -15.00 40.00 -600.00 40.00 40.00 -600.00
Bill dt.13.12.19 (360.00-375.00 = -15.00) Bags -15.00 50.00 -750.00 50.00 50.00 -750.00
Bill dt.22.12.19 (360.00-375.00= -15.00) Bags -15.00 75.00 -1,125.00 75.00 75.00 -1,125.00
Bill dt.04.01.20 (335.00-375.00= -40.00) Bags -40.00 100.00 -4,000.00 100.00 100.00 -4,000.00
Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00 100.00 -1,500.00 100.00 -1,500.00
Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00 50.00 -750.00 50.00 -750.00
Steel
Bill dt.04.12.19 (43.01-50.00= -6.99) Kgs -6.99 3,695.00 -25,828.05 3,695.00 3,695.00 -25,828.05
Bill dt.27.12.19 (46.00-50.00 = -4.00) Kgs -4.00 998.00 -3,992.00 998.00 998.00 -3,992.00
Bill dt.21.01.20 (49.98-50.00 = -0.02) Kgs -0.02 470.00 -9.40 470.00 -9.40
Bill dt.13.02.20 (47.50-50.00 = -2.50) Kgs -2.50 5,355.00 -13,387.50 5,355.00 -13,387.50
10,518.00
COST SUMMARY
B MASONRY WORKS
B01 Size Stone Masonary CM 1:6 Cft 720.00 180.00
B02 BBM 9" thk
Stilt floor Sft 1,873.53 200.00
Ground floor Sft 1,467.47 200.00
B03 BBM 4.5" thk
Stilt floor Sft 486.13 120.00
Ground floor Sft 222.99 120.00
C CONCRETE WORKS
C01 PCC 1:4:8
Below footing Cft 782.60 120.00
Below flooring Cft 962.17 120.00
Below Staircase Landing Cft 120.00
C02 RCC Footing Concrete Cft 1,854.00 210.00
C03 RCC Plinth Beam Cft 288.70 300.00
C04 PCC 1:3:6 Sills
Stilt floor Cft 40.31 130.00
Ground floor Cft 8.54 130.00
C05 RCC Column Concrete
Below Stilt floor Cft 69.75 330.00
Above Stilt floor Cft 165.38 330.00
Ground floor Cft 165.38 330.00
D STEEL
Steel Reinforcement including fabrication
D01 (Basic cost=Rs.50000 /-)
Stilt floor Kgs 8,000.00 68.00
Ground floor Kgs 5,750.00 68.00
S EXTRA WORKS
a) Sanction Plan Charges
b) BWSSB Prorata, Point & inspection Charges
( Approximately )
c) BESCOM deposits and office expencess for
Temparory connection( Approximately)
d) BESCOM deposits and office expencess for
permanent connection( Approximately)
e) Bore Well Pump
f) Solar Water Heater (200 ltr)
lll ESCALATION
Cement
Bill dt.04.12.19 (360.00-375.00= -15.00) Bags -15.00
Bill dt.13.12.19 (360.00-375.00 = -15.00) Bags -15.00
Bill dt.22.12.19 (360.00-375.00= -15.00) Bags -15.00
Bill dt.04.01.20 (335.00-375.00= -40.00) Bags -40.00
Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00
Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00
Bill dt.17.03.20 (335.00-375.00= -40.00) Bags -40.00
Steel
Bill dt.04.12.19 (43.01-50.00= -6.99) Kgs -6.99
Bill dt.27.12.19 (46.00-50.00 = -4.00) Kgs -4.00
Bill dt.21.01.20 (49.98-50.00 = -0.02) Kgs -0.02
Bill dt.13.02.20 (47.50-50.00 = -2.50) Kgs -2.50
Bill dt.24.02.20 (48.00-50.00 = -2.00) Kgs -2.00
Bill dt.16.05.20 (49.206-50.00 = -0.79) Kgs -0.79
COST SUMMARY
l Tendered Works
lll Escalation
IV Extra works
Value of R.A.Bill-3
Mobilization Advance Rs.10,00,000/-
Deduct 10% of Mobilization Advance
Advance paid till date
Balance payable
NI.K.SHANKAR RESIDENTIAL BUILDING
ABSTRACT OF R.A.BILL 3
37.34 37.34
135.00 135.00
544,000.00 8,813.00 8,813.00
391,000.00 5,411.00 367,948.00 1,825.00 7,236.00
1,032,672.50
- -
150,000.00
60,000.00
100,000.00
100,000.00
60,000.00
470,000.00 -
40.00 40.00
50.00 50.00
75.00 75.00
100.00 100.00
100.00 100.00
50.00 50.00
50.00 -2,000.00 - 50.00
- -
- -
3,695.00 3,695.00
998.00 998.00
470.00 470.00
5,355.00 5,355.00
181.00 -362.00 - 181.00
5,230.00 -4,131.70 - 5,230.00
15,929.00
-6,493.70
1,032,672.50
-6,493.70
1,026,178.80
100,000.00
926,178.80
Total Amount
76,261.95
28,523.30
162,523.80
189,412.00
234,928.00
90,810.00
49,010.40
82,065.60
83,955.60
1,137.60
320,604.90
73,785.00
1,058.20
986.70
21,261.90
61,069.80
55,872.30
13,872.00
8,628.00
19,477.50
14,761.25
109,961.65
108,027.95
223,705.30
192,509.90
7,760.00
29,872.00
54,000.00
599,284.00
492,048.00
3,604,523.80
-
-600.00
-750.00
-1,125.00
-4,000.00
-1,500.00
-750.00
-2,000.00
-
-
-25,828.05
-3,992.00
-9.40
-13,387.50
-362.00
-4,131.70
-58,435.65
3,604,523.80
-58,435.65
137,000.00
3,683,088.15
300,000.00
2,730,200.00
652,888.15
Dr. PINAKINI.K.SHANKAR RESIDENTIAL BUILDING
ABSTRACT OF R.A.BILL 4
lll ESCALATION
Cement
1 Bill dt.04.12.19 (360.00-375.00= -15.00) Bags -15.00 40.00 40.00 -600.00
2 Bill dt.13.12.19 (360.00-375.00 = -15.00) Bags -15.00 50.00 50.00 -750.00
3 Bill dt.22.12.19 (360.00-375.00= -15.00) Bags -15.00 75.00 75.00 -1,125.00
4 Bill dt.04.01.20 (335.00-375.00= -40.00) Bags -40.00 100.00 100.00 -4,000.00
5 Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00 100.00 100.00 -1,500.00
6 Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00 50.00 50.00 -750.00
7 Bill dt.17.03.20 (335.00-375.00= -40.00) Bags -40.00 50.00 50.00 -2,000.00
8 Bill dt.13.06.20 (400.00-375.00= 25.00) Bags 25.00 100.00 2,500.00 - 100.00 2,500.00
- -
- - -
Steel - - -
1 Bill dt.04.12.19 (43.01-50.00= -6.99) Kgs -6.99 3,695.00 3,695.00 -25,828.05
2 Bill dt.27.12.19 (46.00-50.00 = -4.00) Kgs -4.00 998.00 998.00 -3,992.00
3 Bill dt.21.01.20 (49.98-50.00 = -0.02) Kgs -0.02 470.00 470.00 -9.40
4 Bill dt.13.02.20 (47.50-50.00 = -2.50) Kgs -2.50 5,355.00 5,355.00 -13,387.50
5 Bill dt.24.02.20 (48.00-50.00 = -2.00) Kgs -2.00 181.00 181.00 -362.00
6 Bill dt.16.05.20 (49.20-50.00 = -0.79) Kgs -0.79 5,230.00 5,230.00 -4,131.70
7 Bill dt.01.07.20 (45.00-50.00 = -5.00) Kgs -5.00 288.00 -1,440.00 - 288.00 -1,440.00
8 Bill dt.18.07.20 (43.50-50.00) = -6.50) Kgs -6.50 5,580.00 -36,270.00 - 5,580.00 -36,270.00
Bill dt.25.07.20 (43.99-50.00) = -6.01) Kgs -6.01 100.00 -601.00 - 100.00 -601.00
-35,811.00 -94,246.65
COST SUMMARY
IV Extra works -
105,588.00 - -
-
-
-
L PLUMBING & SANITARY WORKS -
L01 3/4" CPVC pipe (Cold & Hot Water ) Rft 650.00 110.00 71,500.00 -
L02 1" CPVC pipe Rft 500.00 110.00 55,000.00 -
L03 2" CPVC pipe Rft 40.00 225.00 9,000.00 -
L04 3/4" gate valve Nos 3.00 730.00 2,190.00 -
L05 1" gate value Nos 8.00 1,442.00 11,536.00 -
L06 2" gate valve Nos 1.00 1,854.00 1,854.00 -
L07 Ball valve for sump tank Each 1.00 835.00 835.00 -
L08 PVC over head tank Ltr 2,000.00 9.00 18,000.00 -
L09 3/4" Non-Return Valve for Solar Each 1.00 850.00 850.00 -
L10 PVC Pipes -
a) 1 1/2" dia Rft 80.00 88.00 7,040.00 -
b) 2 1/2" dia Rft 270.00 160.00 43,200.00 -
c) 3" dia Rft 242.00 -
e) 4" dia (4kg/cm2) Rft 270.00 283.00 76,410.00 -
f) 5" dia (6kg/cm2) Rft 130.00 335.00 43,550.00 -
L11 PVC multi trap Each 14.00 900.00 12,600.00 -
L12 PVC P- trap Each 4.00 1,262.00 5,048.00 -
L13 Chambers 12"x12" Each 4.00 3,965.00 15,860.00 -
L14 Chambers 21"x21" Each 4.00 4,532.00 18,128.00 -
L15 Chambers 24"x24" Each 1.00 5,253.00 5,253.00 -
Fixtures (labour only) -
L16 E.W.C with flushtank fixing Each 1,365.00 - -
L17 Wall mounted Commode fixing Each 6.00 2,009.00 12,054.00 -
L18 Concealed Flush tank fixing Each 6.00 1,365.00 8,190.00 -
L19 Wash basin fixing Each 7.00 412.00 2,884.00 -
L20 Shower and shower arm fixing Each 6.00 283.00 1,698.00 -
L21 Angle cock & stop cock fixing Each 25.00 52.00 1,300.00 -
L22 Grating with frame fixing Each 16.00 62.00 992.00 -
L23 Wall mixer fixing Each 6.00 361.00 2,166.00 -
L24 2 IN 1 bib cock & Heaalth faucet fixing Each 6.00 124.00 744.00 -
L25 Sink Cock fixing Each 2.00 345.00 690.00 -
L26 Short body bib cock fixing Each 3.00 52.00 156.00 -
L27 Bootle Trap Fixing Each 6.00 82.00 492.00 -
L28 Single liver diverter Each 258.00 - -
L29 Spout Each 36.00 - -
L30 Waste pipe fixing Each 6.00 52.00 312.00 -
L31 Concealed stop cock Each 6.00 52.00 312.00 -
L32 Washing mechine tap Each 1.00 42.00 42.00 -
L33 Rain water filter fixing Each 1.00 7,983.00 7,983.00 -
L34 Sink fixing Each 3.00 258.00 774.00 -
Advance 450,000.00 1.00 450,000.00
438,643.00 450,000.00 450,000.00
-
-
M ELECTRICALWORKS (Anchor roma ) -
M01 Light point Each 90.00 649.00 58,410.00 -
M02 Spot Light point Each 10.00 805.00 8,050.00 -
M03 Fan point with Regulator Each 8.00 1,133.00 9,064.00 -
M04 Bell point Each 2.00 1,076.00 2,152.00 -
M05 Individual plug point Each 28.00 773.00 21,644.00 -
M06 Plug point Each 30.00 392.00 11,760.00 -
M07 Two way point Each 10.00 1,015.00 10,150.00 -
M08 30 amps DP socket heating point and 5
amps switch with socket Each 10.00 1,000.00 10,000.00 -
M09 15 amps socket point for geezer & AC Each 15.00 541.00 8,115.00 -
M10 30 amps DP point for geezer control Each 15.00 654.00 9,810.00 -
M11 Lighting circuit Rft 600.00 50.00 30,000.00 -
M12 Heating circuit & Main Circuit Rft 700.00 72.00 50,400.00 -
M13 Telephone point Each 3.00 500.00 1,500.00 -
M14 Telephone circuit Rft 200.00 36.00 7,200.00 -
M15 Main circuit and lift 3 phase Rft 200.00 134.00 26,800.00 -
M16 Antana point Each 4.00 500.00 2,000.00 -
M17 Antana circuit Rft 170.00 36.00 6,120.00 -
M18 Pump point No. 1.00 1,076.00 1,076.00 -
M19 Pump Circuit Rft 100.00 72.00 7,200.00 -
M20 Main distribution board (24 way) control for
mains Each 11,500.00 - -
M21 Main distribution board (12 way) control for
mains Each 3.00 6,180.00 18,540.00 -
Main distribution board (8 way) control for
mains Each 4,635.00 - -
M22 Main Panel board L.S. 1.00 100,000.00 -
M23 Main grounding (8' 0" depth) Each 1.00 2,936.00 2,936.00 -
M24 Internal grounding ( 6' 0" depth ) Each 3.00 2,446.00 7,338.00 -
M25 Providing & fixing and laying 35 Sq mm UG
cable with earth work with pvc pipe.(App)
Rft 90.00 150.00 13,500.00 -
M26 CC T.V. Dummy Conduits (1") Rft 150.00 25.00 3,750.00 -
M27 Spot lights for interior works L.S 5,000.00 -
M29 Chandalear point -
M32 Lift Pannel 1.00 15,000.00 15,000.00 -
M33 Lift light Wireing and 5amps plug point L.S 1.00 6,000.00 6,000.00 -
M34 G.I.Earth srtip 120.00 130.00 15,600.00 -
-
Advance 100,000.00 -
Advance 150,000.00 1.00 150,000.00
469,115.00 150,000.00 250,000.00
-
N MATERIALS TO BE SUPPLIED BY THE OWNER -
-
FLOORING & CLADDING MATERIALS -
1 Italian marble Sft 2,000.00 400.00 800,000.00 -
2 Vitrified tiles Sft 1,225.00 80.00 98,000.00 -
3 20 mm Granite slabs for Flooring Sft 525.00 200.00 105,000.00 -
4 20 mm Granite slabs for external stair case Sft 200.00 200.00 40,000.00 -
5 20 mm Granite slabs for cladding Sft 310.00 200.00 62,000.00 -
6 20 mm granite slab for kitchen / Counters Sft 150.00 200.00 30,000.00 -
7 40 mm Granite slabs for Utility Sft 25.00 200.00 5,000.00 -
8 Parking tiles Sft 1,200.00 150.00 180,000.00 -
9 Ceramic tiles- Floor Sft 450.00 80.00 36,000.00 -
10 Ceramic tiles- Dadoo Sft 1,600.00 100.00 160,000.00 -
11 Wooden Flooring Sft 700.00 150.00 105,000.00 -
12 Wooden Skirting Rft 225.00 100.00 22,500.00 -
13 Wooden profile Rft 50.00 110.00 5,500.00 -
14 Clay Tiles Sft 1,200.00 15.00 18,000.00 -
-
M.S. WORKS -
1 M.S. Gate Sft 130.00 400.00 52,000.00 -
2 S.S Staircase Railing Sft 71.06 1,000.00 71,060.00 -
3 M.S. Covering Grill Sft 871.50 200.00 174,300.00 -
4 M.S. Balcony Railing Sft 45.00 180.00 8,100.00 -
5 M.S. T-angle Set 1.00 5,000.00 5,000.00 -
6 M.S. Sky light covering Sft 355.00 300.00 106,500.00 -
7 M.S. Ladder L.S 1.00 8,500.00 8,500.00 -
8 M.S.Door Sft 42.00 380.00 15,960.00 -
9 M.S.Grill Door Sft 21.00 300.00 6,300.00 -
10 M.S.Frame for Structural Glazing Sft 325.00 200.00 65,000.00 -
Advance 300,000.00 1.00 300,000.00
-
-
PLUMBING AND SANITORY WORKS -
1 Wall mounted Commode Each 6.00 9,800.00 58,800.00 -
2 Concealed Flush tank Each 6.00 9,000.00 54,000.00 -
3 Wash basin Each 7.00 3,300.00 23,100.00 -
4 Shower and shower arm Each 6.00 2,750.00 16,500.00 -
5 Angle cock & stop cock (With Flange) Each 25.00 810.00 20,250.00 -
6 Grating with frame Each 16.00 140.00 2,240.00 -
7 Wall mixer Each 6.00 4,125.00 24,750.00 -
8 Connection pipes Each 24.00 145.00 3,480.00 -
9 Wastepipe & coupling Each 10.00 605.00 6,050.00 -
10 Pillar cock Each 7.00 2,000.00 14,000.00 -
11 Health faucet Each 6.00 1,210.00 7,260.00 -
12 2 IN 1 bib cock Each 6.00 2,065.00 12,390.00 -
13 Short body bib cock Each 10.00 935.00 9,350.00 -
14 Sink Cock Each 3.00 2,000.00 6,000.00 -
15 Single liver diverter Each 10,000.00 - -
16 3/4" Extension Nipple Each 10.00 80.00 800.00 -
17 1" Extension Nipple Each 10.00 100.00 1,000.00 -
18 X- Nipple With Flange Each 100.00 - -
19 Stainless steel Sink for kitchen -
Stilt floor Each 1.00 6,000.00 6,000.00 -
Ground floor Each 2.00 15,000.00 30,000.00 -
GLASS WORKS -
1 Shower partition Each 3.00 45,000.00 135,000.00 -
2 Design Glass for railings Sft 200.00 - -
3 Laminated Glass for Sky light Sft 355.00 800.00 284,000.00 -
4 Structural Glazing Sft 325.00 300.00 97,500.00 -
-
KITCHEN ACCESSORIES ( Haffele Blum) -
a) Tandom Box 30 Kg Nos 8.00 5,975.00 47,800.00 -
b) Tandom Box 65Kg with Gallery Nos 6.00 8,125.00 48,750.00 -
c) Spice Rack Nos 1.00 11,975.00 11,975.00 -
d) Dust bin holder Nos 1.00 2,875.00 2,875.00 -
e) Detergent holder Nos 1.00 950.00 950.00 -
f) Aventos Nos 4.00 14,725.00 58,900.00 -
-
1 H.M.G Bill -1 1.00 1,800,000.00
2 H.M.G Bill -2 1.00 115,000.00
3 H.M.G Bill -3 1.00 307,400.00
4 Chabria & Sons Bill-1 1.00 200,000.00
5 Chabria & Sons Bill-2 1.00 370,000.00
6 S.S. Ceramics Bill-1 1.00 84,000.00
7 S.S. Ceramics Bill-2 1.00 4,500.00
8 Nitko Bill -1 1.00 55,000.00
9 Nitko Bill -2 1.00 144,000.00
10 Muniraj Stones 1.00 192,066.00
11 Wood & Moulding 1.00 100,000.00
P DEMOLITION WORKS -
P01 SSM
Stilt floor Cft 70.00 27.00 1,890.00
P02 BBM 9" thk -
Stilt floor Cft 70.00 13.13 919.10
Ground floor Cft 70.00 138.38 9,686.60
First floor Cft 70.00 51.84 3,628.80
Terrace floor Cft -
P03 BBM 4.5" thk -
Stilt floor Sft 50.00 28.75 1,437.50
Ground floor Sft 50.00 -
First floor Sft 50.00 -
Terrace floor Sft 50.00 -
-
P04 R.C.C Work Demolition -
P04A PCC 1:3:6 Sills
Stilt floor Cft 120.00 7.39 886.80
Ground floor Cft 120.00 1.69 202.80
First floor Cft 120.00 -
Terrace floor Cft 120.00 -
-
P04B RCC Lintel Concrete
Stilt floor Cft 150.00 0.87 130.50
Ground floor Cft 150.00 -
First floor Cft 150.00 -
Terrace floor Cft 150.00 -
P04C RCC Chajja Concrete
Ground floor Cft 150.00 0.28 42.00
First floor Cft 150.00 0.28 42.00
- 18,866.10 18,866.10
Q ESCALATION
Cement
1 Bill dt.04.12.19 (360.00-375.00= -15.00) Bags -15.00 -
2 Bill dt.13.12.19 (360.00-375.00 = -15.00) Bags -15.00 -
3 Bill dt.22.12.19 (360.00-375.00= -15.00) Bags -15.00 -
4 Bill dt.04.01.20 (335.00-375.00= -40.00) Bags -40.00 -
5 Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00 -
6 Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00 -
7 Bill dt.17.03.20 (335.00-375.00= -40.00) Bags -40.00 -
8 Bill dt.13.06.20 (400.00-375.00= 25.00) Bags 25.00 -
9 Bill dt.18.08.20 (400.00-375.00= 25.00) Bags 25.00 50.00 1,250.00
10 Bill dt.24.08.20 (400.00-375.00= 25.00) Bags 25.00 25.00 625.00
11 Bill dt.14.09.20 (390.00-375.00= 15.00) Bags 15.00 50.00 750.00
12 Bill dt.02.10.20 (400.00-375.00= 25.00) Bags 25.00 50.00 1,250.00
13 Bill dt.02.10.20 (400.00-375.00= 25.00) Bags 25.00 50.00 1,250.00
14 Bill dt.15.10.20 (400.00-375.00= 25.00) Bags 25.00 50.00 1,250.00
15 Bill dt.24.10.20 (400.00-375.00= 25.00) Bags 25.00 50.00 1,250.00
16 Bill dt.08.11.20 (400.02-375.00= 25.00) Bags 25.00 50.00 1,250.00
17 Bill dt.16.11.20 (400.00-375.00= 25.00) Bags 25.00 100.00 2,500.00
18 Bill dt.29.12.20 (390.00-375.00= 15.00) Bags 15.00 50.00 750.00
19 Bill dt.03.01.21 (400.00-375.00= 25.00) Bags 25.00 50.00 1,250.00
20 Bill dt.10.02.21 (390.00-375.00= 15.00) Bags 15.00 50.00 750.00
21 Bill dt.03.03.21 (400.00-375.00= 25.00) Bags 25.00 50.00 1,250.00
Steel
1 Bill dt.04.12.19 (43.01-50.00= -6.99) Kgs -6.99 -
2 Bill dt.27.12.19 (46.00-50.00 = -4.00) Kgs -4.00 -
3 Bill dt.21.01.20 (49.98-50.00 = -0.02) Kgs -0.02 -
4 Bill dt.13.02.20 (47.50-50.00 = -2.50) Kgs -2.50 -
5 Bill dt.24.02.20 (48.00-50.00 = -2.00) Kgs -2.00 -
6 Bill dt.16.05.20 (49.20-50.00 = -0.79) Kgs -0.79 -
7 Bill dt.01.07.20 (45.00-50.00 = -5.00) Kgs -5.00 -
8 Bill dt.18.07.20 (43.50-50.00) = -6.50) Kgs -6.50 -
9 Bill dt.25.07.20 (43.99-50.00) = -6.01) Kgs -6.01 -
15,375.00 -78,871.65
S EXTRA WORKS
a) Sanction Plan Charges
b) BWSSB Prorata, Point & inspection Charges
( Approximately ) 150,000.00
c) BESCOM deposits and office expencess for
Temparory connection( Approximately) 60,000.00
d) BESCOM deposits and office expencess for
permanent connection( Approximately) 100,000.00
e) Bore Well Pump 100,000.00
f) Solar Water Heater (200 ltr) 60,000.00
NT1 Security Systems
Advance 50,000.00 1.00 50,000.00
NT2 A.C System
Advance 350,000.00 1.00 350,000.00
Advance 100,000.00 1.00 100,000.00
Q ESCALATION 15,375.00
S EXTRA WORKS 470,000.00 500,000.00
Balance payable
RE FINAL
Previous Qty Total Qty Total Amount
AMOUNT
- - -
8,813.00 8,813.00 599,284.00
7,236.00 7,236.00 492,048.00
5,580.00 5,580.00 379,440.00
288.00 288.00 19,584.00
100.00 100.00 6,800.00
- -298.80 -20,318.40
- - -
1,476,837.60
- - -
- - -
- - -
- - -
- - -
- 35.00 84,700.00
- - -
- 28.00 77,000.00
- 28.00 77,000.00
- - -
- 73.50 154,350.00
- 42.00 75,600.00
- 45.50 81,900.00
- 45.50 81,900.00
- - -
- - -
- 56.00 98,000.00
- - -
- - -
- 22.75 39,812.50
- - -
- - -
- - -
- 38.50 87,972.50
- 38.50 87,972.50
- 42.00 105,000.00
- - -
- - -
- 17.50 13,125.00
- - -
- - -
- 145.50 305,550.00
- 143.50 301,350.00
- 188.00 394,800.00
- - -
- - -
- - -
1.00 - -
- - -
- - -
2,066,032.50
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 1.00 500,000.00
- 1.00 200,000.00
- 1.00 500,000.00
1,200,000.00
- - -
- - -
- - -
- 4,261.18 234,364.90
- 2,333.58 128,346.90
- 2,481.15 136,463.25
- 2,182.62 120,044.10
- 11,258.53 -
- 3,885.01 202,020.52
- 2,847.16 148,052.32
- 3,455.69 179,695.88
- 715.71 37,216.92
- - -
- 2,146.95 118,082.25
- 1,688.35 92,859.25
- 1,323.26 72,779.30
- 169.06 9,298.30
- - -
- 160.75 9,645.00
- 230.50 13,830.00
1,502,698.89
- - -
- - -
- - -
- 991.85 198,370.00
- 538.80 107,760.00
- - -
- 96.17 12,502.10
- 109.63 14,251.90
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 234.22 18,737.60
- 412.88 33,030.40
- - -
- 888.44 71,075.20
- 40.72 3,257.60
- - -
- 290.00 21,750.00
- - -
- 69.02 5,521.60
- 40.00 3,200.00
- - -
- - -
- 353.50 31,815.00
- 507.50 45,675.00
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 121.19 18,178.50
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 1,453.76 123,569.60
708,694.50
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 11,258.53 -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 1.00 200,000.00
- - -
200,000.00
- - -
17,187.50 17,187.50 171,875.00
2,400.00 2,400.00 24,000.00
- - -
- 13.84 1,107.20
- 90.26 7,220.80
- 104.59 8,367.20
- - -
- 322.68 58,082.40
- 19.33 386.60
- 229.25 6,877.50
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - 277,916.70
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 1.00 450,000.00
- - 450,000.00
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
1.00 1.00 100,000.00
- 1.00 150,000.00
- - 250,000.00
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 1.00 300,000.00
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 1.00 1,800,000.00
- 1.00 115,000.00
- 1.00 307,400.00
- 1.00 200,000.00
- 1.00 370,000.00
- 1.00 84,000.00
- 1.00 4,500.00
- 1.00 55,000.00
- 1.00 144,000.00
- 1.00 192,066.00
- 1.00 100,000.00
- - -
3,671,966.00
- 1.00 300,000.00
- 1.00 290,000.00
590,000.00
- - -
- - -
- 27.00 1,890.00
- - -
- 13.13 919.10
- 138.38 9,686.60
- 51.84 3,628.80
- - -
- - -
- 28.75 1,437.50
- - -
- - -
- - -
- - -
- - -
- - -
- 7.39 886.80
- 1.69 202.80
- - -
- - -
- - -
- - -
- 0.87 130.50
- - -
- - -
- - -
- - -
- 0.28 42.00
- 0.28 42.00
18,866.10
-78,871.65
62,000.00
75,000.00
- 1.00 50,000.00
- 1.00 350,000.00
- 1.00 100,000.00
637,000.00
107,975.15
1,294,221.80
2,034,018.15
1,476,837.60
2,066,032.50
1,200,000.00
1,502,698.89
708,694.50
200,000.00
277,916.70
450,000.00
250,000.00
3,671,966.00
s
590,000.00
18,866.10
-78,871.65
637,000.00
16,407,355.74
15,547,855.00
859,500.74
Dr.PINAKINI.K.SHANKAR RESIDENCE
MEASUREMENT SHEET OF PRE FINAL BILL
B MASONRY WORKS
B02 BBM 9" thk
Stilt floor
Lift Well Platform 1 1.00 0.75 0.75 1.25 0.70 Cft
Terrace floor
For Placing AC controller 1.00 5.00 4.00 0.42 8.33
For Placing Lift controller 1.00 1.83 1.42 1.17 3.04
11.37 Cft
C CONCRETE WORKS
C01 PCC 1:4:8
Below flooring
Flagging Concrete Alround 1.00 429.60 0.33 143.06 Cft
Terrace floor
For Placing AC controller 1.00 5.00 4.00 0.25 5.00
For Placing Lift controller 1.00 1.83 1.42 0.25 0.65
5.65 Cft
F INTERIOR WORKS
F01 Wardrobes `
19 mm Century Commercial Ply, Inside 0.8mm
Laminate Finish & Outside Decorative Veneer of
Rs 150/- per sft With Mellamine Finish , Fittings all
are Hetich, Handles are below 150 Rs and Locks
are Europa.
Stilt floor
Below loft
NE Bedroom 1.00 12.00 7.00 84.00
SE Bedroom 1.00 4.38 7.00 30.63
114.63
Above Loft
NE Bedroom 1.00 12.00 3.00 36.00
SE Bedroom 1.00 4.38 3.00 13.13
49.13
Ground Floor
SW Bedroom(4'10.5"+6'4") 1.00 11.21 10.00 112.08
First floor
NW Bedroom(7'4.5"+7'0") 1.00 7.38 9.50 70.06
SW Bedroom(6'4"+6'4") 1.00 12.66 10.00 126.60
196.66
Ground floor
Below platform
North Side(8'6"+1'4.5") 1.00 9.88 2.50 24.69
East Side 1.00 11.75 2.50 29.38
54.06 Sft
Above platform
North Side 1.00 3.38 2.00 6.75 Sft
Above Loft
West Side 1.00 13.00 3.00 39.00 Sft
F03 T.V.Cabinet
Ground floor
Ground floor
Lift Wall(1'3"+2'0") 1.00 2.50 7.00 17.50
Jambs(9"+9") 1.00 1.50 7.00 10.50
Lintel 1.00 6.25 1.00 6.25
34.25
First floor
Lift Wall(1'3"+2'0") 1.00 2.50 7.00 17.50
Jambs(9"+9") 1.00 1.50 7.00 10.50
Lintel 1.00 6.25 1.00 6.25
34.25
102.00 Sft
G PLASTERING
G01 Outside Plastering
Stilt Floor
Garden North Wall 1.00 4.00 7.00 28.00 Sft
Ground Floor
Elevation Wall (15'3"+3'0") 1.00 18.25 10.50 191.63 Sft
First Floor
Elevation Wall (15'3"+3'0") 1.00 18.25 10.50 191.63 Sft
Terrace Floor
Elevation Wall (15'3"+3'0") 1.00 18.25 4.83 88.20 Sft
Terrace floor
For Placing AC controller 1.00 5.00 4.00 20.00
Sides 1.00 9.00 0.67 6.00
For Placing controller(1'10"+1'5") 1.00 3.25 1.42 4.60
30.61 Sft
Ground Floor
Living(18'0"+17'0")*2 1.00 70.00 70.00 Rft
First floor
NW Room 1.00 13.75 13.88 190.78
SW Room 1.00 15.50 15.00 232.50
423.28 Sft
First floor
NW Room 1.00 55.25 55.25
SW Room 1.00 43.13 43.13
151.75 Rft
First floor
NW Room 1.00 3.25 3.25
SW Room 1.00 17.88 17.88
31.25 Rft
Ground Floor
Utility Wall 1.00 63.75 4.67 63.75
Deductions
D1 1.00 3.25 3.25
63.75 3.25
60.50 Sft
First Floor
NW Toilet 1.00 6.00 9.00 54.00
SW Toilet 1.00 86.85 86.85
140.85 Sft
Ground floor
Foyer, Staircase & Dining 1.00 51.50 51.50
Living(18'0"+17'0") 1.00 35.00 35.00
86.50 Rft
First floor
Family 1.00 57.75 57.75
Lift,Passage & study(2'0"+1'3"+4'4.5"+2'+7'3') 1.00 16.88 16.88
74.63 Rft
Ground floor
Toilet doors 2.00 2.75 5.50 Rft
First floor
Toilet doors 2.00 2.75 5.50 Rft
16.00
First floor
SW room Toilet Flush Tank Top 1.00 6.25 6.25
Shelf (2'0"+1'0")*2 2.00 6.00 12.00
Toilet Door Patti (2'9"+7'0")*2 2.00 19.50 39.00
Windows Patti (5'0"+2'0")*2 2.00 14.00 28.00
85.25 Rft
First floor
SW room Toilet Flush Tank Top 1.00 6.25 6.25
Shelf (2'0"+1'0")*2 2.00 6.00 12.00
Toilet Door Patti (2'9"+7'0")*2 2.00 19.50 39.00
Windows Patti (5'0"+2'0")*2 2.00 14.00 28.00
85.25 Rft
First floor
NW Dress Room 1.00 7.38 7.38
Cut Out 1.00 50.00 50.00
57.38 Rft
First floor
NW Dress Room 3.00 7.38 22.13
Cut Out 3.00 50.00 150.00
172.13 Rft
H39NT ONYEX
Ground floor
Pooja 1.00 8.00 4.00 32.00 Sft
I PAINTING WORKS
I01 Plastic Emulsion
Stilt floor
Walls(3885.01+18.38) 1.00 3,903.39 3,903.39
Ceiling 1.00 2,146.95 2,146.95
6,050.34 Sft
Ground floor
Walls 1.00 2,847.16 2,847.16
Ceiling 1.00 1,688.35 1,688.35
4,535.51 Sft
First floor
Walls 1.00 3,455.69 3,455.69
Ceiling 1.00 1,323.26 1,323.26
4,778.95 Sft
Terrace floor
Walls(715.71+4.60) 1.00 720.31 720.31
Ceiling 1.00 169.06 169.06
889.37 Sft
Ground floor
For Doors
ED/W 1.00 5.00 7.00 35.00
PD 1.00 4.00 7.00 28.00
D1 2.00 3.25 7.00 45.50
D3 2.00 2.75 7.00 38.50
147.00
Factor 2.50 367.50
For Windows
W1 1.00 8.00 6.00 48.00
W2 1.00 6.00 6.00 36.00
W5 2.00 3.00 4.50 27.00
KW 1.00 3.00 4.50 13.50
V 1.00 5.00 2.00 10.00
V2 1.00 2.00 4.50 9.00
143.50
Factor 1.50 215.25
Total 582.75
First floor
For Doors
D1 2.00 3.25 7.00 45.50
D3 2.00 2.75 7.00 38.50
84.00
Factor 2.50 210.00
For Windows
W1 2.00 8.00 6.00 96.00
W4 1.00 3.00 6.00 18.00
W5 4.00 3.00 4.50 54.00
V 2.00 5.00 2.00 20.00
188.00
Factor 1.50 282.00
Total 492.00
Terrace floor
For Doors
D1 1.00 3.25 7.00 22.75
Factor 2.50 56.88
J MISCELLANEOUS
J04 Stone Slab over Drains 1.00 40.00 5.00 200.00
K M.S. / S.S. WORKS (without Basic material cost but including Painting)
K01 M.S. Gate
Stilt floor
Parking Gate 1.00 20.88 7.50 156.56
Small Gate 1.00 4.00 7.50 30.00
186.56 Sft
K02 S.S. Staircase Railing 1.00
Stilt floor
External Staircase(5'4"+12'0"+9'4.5"+12'9"+3') 1.00 42.46 3.00 127.37 Sft
KNT5 M.S. Frame For Glass Floor 1.00 7.75 4.00 31.00 Sft
KNT6 Louvers For Clinic Toilet 1.00 5.00 1.00 5.00 Sft
GLASS WORKS
1 Shower partition 4.00 4.00 Nos
2 Design Glass for railings
3 Laminated Glass for Sky light
Elliptical Skylight 1.00 105.60 105.60
Sun room Skylight 1.00 163.94 163.94
Staircase Skylight 1.00 7.25 2.25 16.31
4 Structural Glazing
5 Laminated Glass
Glass Floor 1.00 7.75 4.00 31.00
Infront Of pooja 1.00 4.00 4.00 16.00
Entrance Door pargola Top 1.00 12.75 3.50 44.63
Utility Top 1.00 25.58 3.50 89.51
Parking Pargola 1.00 23.63 3.50 82.69
16,254.17
11,258.53
3.00
1.00
Dr. PINAKINI.K.SHANKAR
ABSTRACT OF P
GROUP ESTIMATED
CODE DESCRIPTION OF WORK UNITS ESTIMATED RATE AMOUNT
QTY (in Rs) (in Rs)
CIVIL WORKS
A EARTH WORK
A01 Earthwork Excavation. Cft 6,754.45 15.00 101,316.75
A02 Earth Filling using available earth. Cft 5,291.00 5.00 26,455.00
A03 Excess Earth carting away from the site.
Cft 2,024.00 15.00 30,360.00
A04 Earth Filling brought from outside Cft 10.00 -
A05 Earth Shifting over area Cft 2,400.00 10.00 24,000.00
182,131.75
B MASONRY WORKS
B01 Size Stone Masonary CM 1:6 Cft 720.00 180.00 129,600.00
B02 BBM 9" thk
Stilt floor Sft 1,873.53 200.00 374,706.00
Ground floor Sft 1,467.47 200.00 293,494.00
First floor Sft 1,490.93 200.00 298,186.00
Terrace floor Sft 817.88 200.00 163,576.00
B03 BBM 4.5" thk
Stilt floor Sft 486.13 120.00 58,335.60
Ground floor Sft 222.99 120.00 26,758.80
First floor Sft 197.88 120.00 23,745.60
Terrace floor Sft 120.00
1,368,402.00
C CONCRETE WORKS
C01 PCC 1:4:8
Below footing Cft 782.60 120.00 93,912.00
Below flooring Cft 962.17 120.00 115,460.40
Below Staircase Landing Cft 120.00
C02 RCC Footing Concrete Cft 1,854.00 210.00 389,340.00
C03 RCC Plinth Beam Cft 288.70 300.00 86,610.00
C04 PCC 1:3:6 Sills
Stilt floor Cft 40.31 130.00 5,240.30
Ground floor Cft 8.54 130.00 1,110.20
First floor Cft 8.25 130.00 1,072.50
Terrace floor Cft 40.27 130.00 5,235.10
C05 RCC Column Concrete
Below Stilt floor Cft 69.75 330.00 23,017.50
Above Stilt floor Cft 165.38 330.00 54,575.40
Ground floor Cft 165.38 330.00 54,575.40
First floor Cft 165.38 330.00 54,575.40
Terrace Floor Cft 82.69 330.00 27,287.70
2,008,980.70
D STEEL
Steel Reinforcement including fabrication
D01 (Basic cost=Rs.50000 /-)
Stilt floor Kgs 8,000.00 68.00 544,000.00
Ground floor Kgs 5,750.00 68.00 391,000.00
First floor Kgs 5,050.00 68.00 343,400.00
68.00
68.00
68.00
Terrace floor Kgs 675.00 68.00 45,900.00
1,324,300.00
1,572,147.50
F INTERIOR WORKS
F01 Wardrobes
19 mm Century Commercial Ply, Inside
0.8mm Laminate Finish & Outside
Decorative Veneer of Rs 150/- per sft With
Mellamine Finish , Fittings all are Hetich,
Handles are below 150 Rs and Locks are
Europa.
Stilt floor
Below loft Sft 1,500.00 -
Above Loft Sft 900.00 -
Ground floor
Below loft Sft 80.50 1,840.00 148,120.00
1,400.00
Above Loft Sft 34.50 950.00 32,775.00
Glass Door 1,000.00
First floor
Below loft Sft 196.35 1,840.00 361,284.00
1,400.00
Above Loft Sft 84.15 950.00 79,942.50
Glass Door 1,000.00
Ground floor
Below platform Sft 63.13 2,200.00 138,886.00
2,600.00
Above platform Sft 50.50 1,600.00 80,800.00
1,670.00
Above Loft Sft 102.75 1,200.00 123,300.00
Tall unit Sft 21.00 1,600.00 33,600.00
1,750.00
F02NT1 Column panelling Sft 900.00
F02NT2 False ceiling Sft 1,000.00
F02NT3 Ribs Rft 900.00
F03 T.V.Cabinet
Stilt floor Sft 7,000.00
Ground floor Sft 70.00 1,500.00 105,000.00
F04 Crockery unit Sft 70.00 2,000.00 140,000.00
F05 Cot with back rest Each 3.00 75,000.00 225,000.00
F06 Study table Each 1.00 50,000.00 50,000.00
F07 Internal Staircase Railing in Teak Wood
With Glass Sft 303.00 1,200.00 363,600.00
FNT2 Staircase Steps 700,000.00
FNT3 Pooja Work 300,000.00
FNT4 Pooja Platform And Frame Works 1,800.00
FNT5 Pooja Wall Work (Brick Pattern)
FNT6 Glass Floor 1,250.00
FNT7 Lift Panelling 900.00
FNT8 T.V. Wall Panelling 900.00
Interior Work Advance 500,000.00
Pooja Work Advance 200,000.00
Stair Case & Railing Work Advance 500,000.00
1,956,652.50
G PLASTERING
G01 Outside Plastering
Stilt floor Sft 4,135.06 55.00 227,428.30
Ground floor Sft 2,345.50 55.00 129,002.50
First floor Sft 2,035.00 55.00 111,925.00
Terrace floor Sft 1,991.56 55.00 109,535.80
G02 Inside Wall Plastering
Stilt floor Sft 3,105.25 52.00 161,473.00
Ground floor Sft 3,242.40 52.00 168,604.80
First floor Sft 3,422.50 52.00 177,970.00
Terrace floor Sft 510.00 52.00 26,520.00
G03 Inside Ceiling Plastering
Stilt floor Sft 1,933.56 55.00 106,345.80
Ground floor Sft 1,572.21 55.00 86,471.55
First floor Sft 1,155.99 55.00 63,579.45
Terrace floor Sft 165.00 55.00 9,075.00
G04 Water proof plastering for toilets
Ground floor Sft 145.75 60.00 8,745.00
First floor Sft 195.50 60.00 11,730.00
1,398,406.20
I PAINTING WORKS
I01 Plastic Emulsion
Stilt floor Sft 5,038.81 26.00 131,009.06
Ground floor Sft 4,814.61 26.00 125,179.86
First floor Sft 4,578.49 26.00 119,040.74
Terrace floor Sft 675.00 26.00 17,550.00
I02 Exterior Emulsion (Apex)
Stilt floor Sft 4,135.06 24.00 99,241.44
Ground floor Sft 2,345.50 24.00 56,292.00
First floor Sft 2,035.00 24.00 48,840.00
Terrace floor Sft 1,991.56 24.00 47,797.44
I03 Enamel Paint
Stilt floor Sft 360.63 22.00 7,933.86
Ground floor Sft 178.13 22.00 3,918.75
First floor Sft 226.88 22.00 4,991.25
I04 Melamine Polish
Stilt floor Sft 266.83 90.00 24,014.25
Ground floor Sft 510.63 90.00 45,956.25
First floor Sft 463.13 90.00 41,681.25
Terrace floor Sft 90.00
Advance 200,000.00
773,446.15
J MISCELLANEOUS
J01 Sump Tank Ltrs 10,000.00 10.00 100,000.00
J02 Anti-termite treatment for Pesticides Sft 2,400.00 10.00 24,000.00
J03 Bath Floor Filling
Stilt floor Cft 80.00 -
Ground floor Cft 70.00 80.00 5,600.00
First floor Cft 138.00 80.00 11,040.00
J04 Stone Slab over Drains Sft 200.00 250.00 50,000.00
J05 Chicken Mesh Sft 200.00 180.00 36,000.00
J06 Grooves 3/4" Sft 600.00 20.00 12,000.00
J07 Cornice works - 1 step Sft 400.00 30.00 12,000.00
2 steps Sft 200.00 50.00 10,000.00
J08 Washing Stone Sft 10.00 350.00 3,500.00
J09 20 mm granite for Name board No 1.00 5,000.00 5,000.00
J10 Granite Cutting for Sink Each 3.00 600.00 1,800.00
J11 Granite Cutting for Hob Each 1.00 300.00 300.00
J12 Chimney Hole Each 2.00 1,000.00 2,000.00
J13 Gas Piping L.S 15,000.00 15,000.00
J14 Rain Water Harvesting Each 2.00 15,000.00 30,000.00
J15 Rough Stone Cladding @ Outside Wall
(Inclusive of Material) Sft 550.00 400.00 220,000.00
538,240.00
K M.S. / S.S. WORKS (without Basic material cost but including Painting)
K01 M.S. Gate Sft 130.00 60.00 7,800.00
K02 S.S. Staircase Railing Sft 71.06 50.00 3,553.00
K03 M.S. Covering Grill Sft 871.50 40.00 34,860.00
K04 M.S. Balcony Railing Sft 45.00 35.00 1,575.00
K05 M.S. T-angle Set 1.00 350.00 350.00
K06 M.S. Sky light covering Sft 355.00 100.00 35,500.00
K07 M.S. Ladder L.S 1.00 1,500.00 1,500.00
K08 M.S.Door Sft 42.00 60.00 2,520.00
K09 M.S.Grill Door Sft 21.00 80.00 1,680.00
K10 M.S.Frame for Structural Glazing Sft 325.00 50.00 16,250.00
KNT1 Pargola To Cover The Balcony Near
Entrance Door Sft 60.00
KNT2 Utility Covering Sft 60.00
KNT3 M.S. Staircase For Internal Staircase No 5,000.00
KNT4 M.S. Staircase In Terrace Floor No 5,000.00
KNT5 M.S. Frame For Glass Floor Sft 60.00
KNT6 Louvers For Clinic Toilet Sft 60.00
KNT7 Windows Patti Sft 30.00
KNT8 Sunroom Mesh Sft 30.00
KNT9 Compound Mesh Sft 30.00
KNT10 Sunroom Covering grill Sft
105,588.00
Advance 100,000.00
Advance 150,000.00
Advance 450,000.00
469,115.00
M.S. WORKS
1 M.S. Gate Sft 130.00 400.00 52,000.00
2 S.S Staircase Railing Sft 71.06 1,000.00 71,060.00
3 M.S. Covering Grill Sft 871.50 200.00 174,300.00
4 M.S. Balcony Railing Sft 45.00 180.00 8,100.00
5 M.S. T-angle Set 1.00 5,000.00 5,000.00
6 M.S. Sky light covering Sft 355.00 300.00 106,500.00
7 M.S. Ladder L.S 1.00 8,500.00 8,500.00
8 M.S.Door Sft 42.00 380.00 15,960.00
9 M.S.Grill Door Sft 21.00 300.00 6,300.00
10 M.S.Frame for Structural Glazing Sft 325.00 200.00 65,000.00
KNT1 Pargola To Cover The Balcony Near
Entrance Door Sft
KNT2 Utility Covering Sft
KNT3 M.S. Internal Staircase No
KNT4 M.S. Staircase In Terrace Floor No
KNT5 M.S. Frame For Glass Floor Sft
KNT6 Louvers For Clinic Toilet Sft
KNT7 Windows Patti Sft
KNT8 Sunroom Mesh Sft
KNT9 Compound Mesh Sft
KNT10 Sunroom Covering grill Sft
Advance 300,000.00
Advance 400,000.00
512,720.00
GLASS WORKS
1 Shower partition Each 3.00 45,000.00 135,000.00
2 Design Glass for railings Sft 200.00 -
3 Laminated Glass for Sky light Sft 355.00 800.00 284,000.00
Elliptical Skylight Sft 1,000.00
Sun room Skylight Sft 800.00
Staircase Skylight Sft 800.00
4 Structural Glazing Sft 325.00 300.00 97,500.00
3 Laminated Glass
Glass Floor Sft
Infront of Pooja Sft 600.00
Entrance Door pargola Sft 600.00
Utility Top Sft 600.00
Parking Pargola Sft 600.00
UPVC WINDOWS Sft 500.00
516,500.00
171,250.00
3,163,440.00
P DEMOLITION WORKS
P01 SSM
Stilt floor Cft 70.00
P02 BBM 9" thk
Stilt floor Cft 70.00
Ground floor Cft 70.00
First floor Cft 70.00
Terrace floor Cft
P03 BBM 4.5" thk
Stilt floor Sft 50.00
Ground floor Sft 50.00
First floor Sft 50.00
Terrace floor Sft 50.00
Q ESCALATION
Cement
1 Bill dt.04.12.19 (360.00-375.00= -15.00) Bags -15.00
2 Bill dt.13.12.19 (360.00-375.00 = -15.00) Bags -15.00
3 Bill dt.22.12.19 (360.00-375.00= -15.00) Bags -15.00
4 Bill dt.04.01.20 (335.00-375.00= -40.00) Bags -40.00
5 Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00
6 Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00
7 Bill dt.17.03.20 (335.00-375.00= -40.00) Bags -40.00
8 Bill dt.13.06.20 (400.00-375.00= 25.00) Bags 25.00
9 Bill dt.18.08.20 (400.00-375.00= 25.00) Bags 25.00
10 Bill dt.24.08.20 (400.00-375.00= 25.00) Bags 25.00
11 Bill dt.14.09.20 (390.00-375.00= 15.00) Bags 15.00
12 Bill dt.02.10.20 (400.00-375.00= 25.00) Bags 25.00
13 Bill dt.02.10.20 (400.00-375.00= 25.00) Bags 25.00
14 Bill dt.15.10.20 (400.00-375.00= 25.00) Bags 25.00
15 Bill dt.24.10.20 (400.00-375.00= 25.00) Bags 25.00
16 Bill dt.08.11.20 (400.02-375.00= 25.00) Bags 25.00
17 Bill dt.16.11.20 (400.00-375.00= 25.00) Bags 25.00
18 Bill dt.29.12.20 (390.00-375.00= 15.00) Bags 15.00
19 Bill dt.03.01.21 (400.00-375.00= 25.00) Bags 25.00
20 Bill dt.10.02.21 (390.00-375.00= 15.00) Bags 15.00
21 Bill dt.03.03.21 (400.00-375.00= 25.00) Bags 25.00
22 Bill dt.14.03.21 (400.00-375.00= 25.00) Bags 25.00
23 Bill dt.26.03.21 (400.00-375.00= 25.00) Bags 25.00
Steel
1 Bill dt.04.12.19 (43.01-50.00= -6.99) Kgs -6.99
2 Bill dt.27.12.19 (46.00-50.00 = -4.00) Kgs -4.00
3 Bill dt.21.01.20 (49.98-50.00 = -0.02) Kgs -0.02
4 Bill dt.13.02.20 (47.50-50.00 = -2.50) Kgs -2.50
5 Bill dt.24.02.20 (48.00-50.00 = -2.00) Kgs -2.00
6 Bill dt.16.05.20 (49.20-50.00 = -0.79) Kgs -0.79
7 Bill dt.01.07.20 (45.00-50.00 = -5.00) Kgs -5.00
8 Bill dt.18.07.20 (43.50-50.00) = -6.50) Kgs -6.50
9 Bill dt.25.07.20 (43.99-50.00) = -6.01) Kgs -6.01
S EXTRA WORKS
a) Sanction Plan Charges
b) BWSSB Prorata, Point & inspection
Charges ( Approximately ) 1.00 150,000.00 150,000.00
c)
BESCOM deposits and office expencess
for Temparory connection( Approximately) 1.00 60,000.00 60,000.00
62,000.00
d) BESCOM deposits and office expencess
for permanent connection( Approximately) 1.00 100,000.00 100,000.00
200,000.00
e) Bore Well Pump 100,000.00
75,000.00
f) Solar Water Heater (200 ltr) 60,000.00
NT1 Security Systems
Advance 50,000.00
Final payment 5,000.00
Wiring & Supervision 5,000.00
470,000.00
241,240.00
COST SU
Group
code Description of works Estimated Amount
A EARTHWORK 182,131.75
D STEEL 1,324,300.00
G PLASTERING 1,398,406.20
H FLOORING 1,288,610.15
P DEMOLITION WORKS
Q ESCALATION
Balance payable
ANKAR RESIDENTIAL BUILDING
ACT OF PRE FINAL BILL
PRE FINAL
Previous Qty Total Qty
QTY AMOUNT
- 5,198.51 5,198.51
- 5,704.66 5,704.66
- 98.28 98.28
- - -
- - -
- 107,975.15
- - -
- - -
- 921.85 921.85
- - -
0.70 140.00 1,147.69 1,148.39
- 1,182.94 1,182.94
- 1,330.39 1,330.39
11.37 2,274.00 659.35 670.72
- - -
- 1,261.62 1,261.62
- 488.47 488.47
- 288.34 288.34
- 163.36 163.36
2,414.00 1,296,635.80
- - -
- - -
- - -
- 697.26 697.26
143.06 17,167.20 699.63 842.69
- 9.48 9.48
- 1,544.69 1,544.69
- 258.49 258.49
- - -
29.73 3,864.90 57.33 87.06
- 58.13 58.13
- 75.84 75.84
5.65 734.50 70.13 75.78
- - -
- 64.43 64.43
- 213.75 213.75
- 169.31 169.31
- 169.31 169.31
- 88.88 88.88
- - -
- - -
- 58.83 58.83
- 30.64 30.64
- 31.22 31.22
- - -
- - -
- 81.50 81.50
- 60.25 60.25
- 95.25 95.25
- 28.50 28.50
- - -
- 400.75 400.75
- 354.19 354.19
- 340.69 340.69
- 77.06 77.06
- - -
- 745.31 745.31
- 631.18 631.18
- 671.90 671.90
- 69.33 69.33
- - -
- 19.40 19.40
- - -
- 37.34 37.34
- - -
- - -
- 135.00 135.00
- - -
21,766.60 2,055,784.75
- - -
- - -
- - -
- 8,813.00 8,813.00
- 7,236.00 7,236.00
- 5,580.00 5,580.00
- 288.00 288.00
- 100.00 100.00
- -298.80 -298.80
- - -
- 1,476,837.60
- - -
- - -
- - -
- - -
- - -
- 35.00 35.00
- - -
- 28.00 28.00
- 28.00 28.00
- - -
- 73.50 73.50
- 42.00 42.00
- 45.50 45.50
- 45.50 45.50
- - -
- - -
- 56.00 56.00
- - -
- - -
- 22.75 22.75
- - -
- - -
- - -
- 38.50 38.50
- 38.50 38.50
- 42.00 42.00
- - -
- - -
- 17.50 17.50
- - -
- - -
- 145.50 145.50
- 143.50 143.50
- 188.00 188.00
- - -
- - -
- - -
- - -
42.00 126,000.00 - 42.00
- - -
- - -
- - -
- - -
126,000.00 2,192,032.50
- - -
- - -
- - -
- - -
- - -
- - -
114.63 171,945.00 - 114.63
49.13 44,217.00 - 49.13
- - -
- - -
112.08 156,912.00 - 112.08
- - -
49.00 49,000.00 - 49.00
- -
- - -
- - -
196.66 275,324.00 - 196.66
- - -
112.00 112,000.00 - 112.00
- - -
- - -
- - -
- - -
37.50 78,750.00 - 37.50
- - -
14.00 18,200.00 - 14.00
- - -
- - -
- - -
- - -
54.06 140,556.00 - 54.06
- - -
6.75 11,272.50 - 6.75
39.00 46,800.00 - 39.00
- 121.19 121.19
- - -
- - -
13.25 1,325.00 - 13.25
86.50 8,650.00 - 86.50
74.63 7,463.00 - 74.63
- - -
- - -
- - -
- - -
- - -
265.50 26,550.00 - 265.50
5.25 262.50 - 5.25
6.00 900.00 - 6.00
- - -
- 1,453.76 1,453.76
- - -
110.25 5,512.50 - 110.25
85.25 4,262.50 - 85.25
- - -
220.50 11,025.00 - 220.50
85.25 4,262.50 - 85.25
- - -
78.50 7,850.00 - 78.50
57.38 5,738.00 - 57.38
- - -
322.50 32,250.00 - 322.50
172.13 17,213.00 - 172.13
32.00 16,000.00 - 32.00
571,573.45 1,280,267.95
- - -
- - -
- - -
6,050.34 157,308.84 - 6,050.34
4,535.51 117,923.26 - 4,535.51
4,778.95 124,252.70 - 4,778.95
889.37 23,123.62 - 889.37
- - -
4,261.18 102,268.32 - 4,261.18
2,333.58 56,005.92 - 2,333.58
2,481.15 59,547.60 - 2,481.15
2,182.62 52,382.88 - 2,182.62
- - -
145.50 3,201.00 - 145.50
143.50 3,157.00 - 143.50
188.00 4,136.00 - 188.00
- - -
717.00 64,530.00 - 717.00
582.75 52,447.50 - 582.75
492.00 44,280.00 - 492.00
56.88 5,119.20 - 56.88
-1.00 -200,000.00 1.00 -
- - -
669,683.84 869,683.84
- - -
- 17,187.50 17,187.50
- 2,400.00 2,400.00
- - -
- 13.84 13.84
- 90.26 90.26
- 104.59 104.59
200.00 50,000.00 - 200.00
- 322.68 322.68
474.34 9,486.80 19.33 493.67
- 229.25 229.25
- - -
10.00 3,500.00 - 10.00
1.00 5,000.00 - 1.00
3.00 1,800.00 - 3.00
1.00 300.00 - 1.00
2.00 2,000.00 - 2.00
1.00 15,000.00 - 1.00
1.00 15,000.00 - 1.00
- - -
102,086.80 380,003.50 - -
- - -
- - -
- - -
186.56 11,193.60 - 186.56
127.37 6,368.50 - 127.37
900.00 36,000.00 - 900.00
70.13 2,454.55 - 70.13
1.00 350.00 - 1.00
226.20 22,620.00 - 226.20
- - -
22.75 1,365.00 - 22.75
21.00 1,680.00 - 21.00
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 1.00 1.00
- 1.00 1.00
1.00 450,000.00 - 1.00
450,000.00 700,000.00
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 1.00 1.00
- 1.00 1.00
- 1.00 1.00
1.00 112,935.59 - 1.00
- 1.00 1.00
- 1.00 1.00
- 1.00 1.00
- 1.00 1.00
- 1.00 1.00
1.00 7,300.00 - 1.00
1.00 48,965.00 - 1.00
- 1.00 1.00
1.00 300,000.00 - 1.00
469,200.59 3,271,166.59
- - -
186.56 74,624.00 - 186.56
127.37 127,370.00 - 127.37
900.00 180,000.00 - 900.00
70.13 12,623.40 - 70.13
1.00 5,000.00 - 1.00
226.20 67,860.00 - 226.20
- - -
22.75 8,645.00 - 22.75
21.00 6,300.00 - 21.00
- - -
38.25 - - 38.25
191.56 - - 191.56
1.00 - - 1.00
1.00 - - 1.00
31.00 - - 31.00
5.00 - - 5.00
48.00 - - 48.00
159.69 - - 159.69
114.99 - - 114.99
233.94 - - 233.94
- 1.00 1.00
1.00 400,000.00 - 1.00
882,422.40 1,182,422.40
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 1.00 1.00
- 1.00 1.00
1.00 13,452.00 - 1.00
1.00 87,140.00 - 1.00
1.00 6,732.00 - 1.00
1.00 6,426.00 - 1.00
113,750.00 683,750.00
- - -
4.00 180,000.00 - 4.00
- - -
- - -
105.60 105,600.00 - 105.60
165.00 132,000.00 - 165.00
16.31 13,048.00 - 16.31
- - -
- - -
- - -
16.00 9,600.00 - 16.00
44.63 26,775.00 - 44.63
89.51 53,707.50 - 89.51
82.69 49,612.50 - 82.69
212.50 106,250.00 - 212.50
676,593.00 676,593.00
- - -
- - -
8.00 47,800.00 - 8.00
6.00 48,750.00 - 6.00
1.00 11,975.00 - 1.00
1.00 2,875.00 - 1.00
1.00 950.00 - 1.00
4.00 58,900.00 - 4.00
- - -
171,250.00 171,250.00
- - -
2,313,215.99 5,985,181.99
- 1.00 1.00
- 1.00 1.00
1.00 285,000.00 - 1.00
1.00 100,000.00 - 1.00
385,000.00 975,000.00
- - -
- - -
- 27.00 27.00
- - -
- 13.13 13.13
- 138.38 138.38
- 51.84 51.84
- - -
- - -
- 28.75 28.75
- - -
- - -
- - -
- - -
- - -
- - -
- 7.39 7.39
- 1.69 1.69
- - -
- - -
- - -
- - -
- 0.87 0.87
- - -
- - -
- - -
- - -
- 0.28 0.28
- 0.28 0.28
- 18,866.10
- 40.00 40.00
- 50.00 50.00
- 75.00 75.00
- 100.00 100.00
- 100.00 100.00
- 50.00 50.00
- 50.00 50.00
- 100.00 100.00
- 50.00 50.00
- 25.00 25.00
- 50.00 50.00
- 50.00 50.00
- 50.00 50.00
- 50.00 50.00
- 50.00 50.00
- 50.00 50.00
- 100.00 100.00
- 50.00 50.00
- 50.00 50.00
- 50.00 50.00
- 50.00 50.00
50.00 1,250.00 - 50.00
50.00 1,250.00 - 50.00
- - -
- - -
- 3,695.00 3,695.00
- 998.00 998.00
- 470.00 470.00
- 5,355.00 5,355.00
- 181.00 181.00
- 5,230.00 5,230.00
- 288.00 288.00
- 5,580.00 5,580.00
- 100.00 100.00
- - -
2,500.00 -76,371.65
- - -
1.00 1.00
- - -
1.00 200,000.00 - 1.00
- - -
1.00 1.00
- - -
- - -
- 1.00 1.00
1.00 5,000.00 - 1.00
1.00 5,000.00 - 1.00
- -
- - -
- 1.00 1.00
- 1.00 1.00
1.00 169,546.00 - 1.00
1.00 50,000.00 - 1.00
- -
- -
-
10.00 25,000.00 - 10.00
12.00 7,800.00 - 12.00
10.00 180.00 - 10.00
2.00 360.00 - 2.00
5.00 1,750.00 - 5.00
- - -
1.00 15,000.00 - 1.00
- - -
6.00 10,800.00 - 6.00
6.00 4,500.00 - 6.00
6.00 4,500.00 - 6.00
3.00 2,550.00 - 3.00
3.00 4,200.00 - 3.00
2.00 24,000.00 - 2.00
- - -
1.00 78,980.00 - 1.00
1.00 369,000.00 - 1.00
548,620.00 548,620.00
COST SUMMARY
-
- 107,975.15
-
2,414.00 1,296,635.80
-
21,766.60 2,055,784.75
-
- 1,476,837.60
-
126,000.00 2,192,032.50
-
1,947,986.50 3,147,986.50
-
35,741.08 1,538,439.97
-
571,573.45 1,280,267.95
-
669,683.84 869,683.84
-
102,086.80 380,003.50
-
117,660.65 117,660.65
-
150,000.00 600,000.00
-
450,000.00 700,000.00
-
2,313,215.99 5,985,181.99
-
385,000.00 975,000.00
-
- 18,866.10
-
2,500.00 -76,371.65
-
879,546.00 1,516,546.00
-
548,620.00 548,620.00
8,323,794.91
Total Amount
77,977.65
28,523.30
1,474.20
-
-
107,975.15
-
-
165,933.00
-
229,678.00
236,588.00
266,078.00
134,144.00
-
151,394.40
58,616.40
34,600.80
19,603.20
1,296,635.80
-
-
-
83,671.20
101,122.80
1,137.60
324,384.90
77,547.00
-
11,317.80
7,556.90
9,859.20
9,851.40
-
21,261.90
70,537.50
55,872.30
55,872.30
29,330.40
-
-
17,649.00
9,192.00
9,366.00
-
-
19,967.50
14,761.25
23,336.25
6,982.50
-
122,228.75
108,027.95
103,910.45
23,503.30
-
227,319.55
192,509.90
204,929.50
21,145.65
-
7,760.00
-
29,872.00
-
-
54,000.00
-
2,055,784.75
-
-
-
599,284.00
492,048.00
379,440.00
19,584.00
6,800.00
-20,318.40
-
1,476,837.60
-
-
-
-
-
84,700.00
-
77,000.00
77,000.00
-
154,350.00
75,600.00
81,900.00
81,900.00
-
-
98,000.00
-
-
39,812.50
-
-
-
87,972.50
87,972.50
105,000.00
-
-
13,125.00
-
-
305,550.00
301,350.00
394,800.00
-
-
-
-
126,000.00
-
-
-
-
2,192,032.50
-
-
-
-
-
-
171,945.00
44,217.00
-
-
156,912.00
-
49,000.00
-
-
-
275,324.00
-
112,000.00
-
-
-
78,750.00
-
18,200.00
-
-
-
-
140,556.00
-
11,272.50
46,800.00
61,250.00
60,750.00
72,560.00
10,800.00
-
7,000.00
-
92,000.00
150,000.00
-
360,000.00
700,000.00
300,000.00
79,200.00
-
38,750.00
91,800.00
18,900.00
-
-
-
-
3,147,986.50
-
-
-
235,904.90
138,886.55
147,002.90
124,918.75
-
202,976.28
148,052.32
179,695.88
38,808.64
-
118,082.25
92,859.25
78,478.95
9,298.30
-
9,645.00
13,830.00
1,538,439.97
-
-
-
4,400.00
198,370.00
107,760.00
-
2,275.00
21,602.10
14,251.90
-
-
21,687.50
-
-
4,684.40
8,465.60
-
533.80
1,577.50
-
101.30
312.50
-
18,737.60
33,030.40
-
71,075.20
3,257.60
-
21,750.00
-
5,521.60
12,661.60
99,700.80
-
35,235.00
51,120.00
-
-
-
-
-
-
-
-
39,048.80
-
6,261.20
-
6,187.50
15,493.50
-
92,850.00
-
-
-
-
-
71,056.80
-
24,390.00
-
12,450.40
-
3,806.25
-
-
-
-
-
-
18,178.50
-
-
1,325.00
8,650.00
7,463.00
-
-
-
-
-
26,550.00
262.50
900.00
-
123,569.60
-
5,512.50
4,262.50
-
11,025.00
4,262.50
-
7,850.00
5,738.00
-
32,250.00
17,213.00
16,000.00
1,280,267.95
-
-
-
157,308.84
117,923.26
124,252.70
23,123.62
-
102,268.32 16,254.17 16,254.17 26.00
56,005.92
59,547.60 11,258.53 11,258.53 24.00
52,382.88
-
3,201.00
3,157.00
4,136.00
-
64,530.00
52,447.50
44,280.00
5,119.20
-
-
869,683.84
-
171,875.00
24,000.00
-
1,107.20
7,220.80
8,367.20
50,000.00
58,082.40
9,873.40
6,877.50
-
3,500.00
5,000.00
1,800.00
300.00
2,000.00
15,000.00
15,000.00
-
380,003.50
-
-
-
11,193.60
6,368.50
36,000.00
2,454.55
350.00
22,620.00
-
1,365.00
1,680.00
-
2,295.00
11,493.60
5,000.00
5,000.00
1,860.00
300.00
1,440.00
4,790.70
3,449.70
-
117,660.65
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
450,000.00
150,000.00
600,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
100,000.00
150,000.00
450,000.00
700,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1,800,000.00
115,000.00
307,400.00
112,935.59
84,000.00
4,500.00
55,000.00
144,000.00
192,066.00
7,300.00
48,965.00
100,000.00
300,000.00
3,271,166.59
-
74,624.00
127,370.00
180,000.00
12,623.40
5,000.00
67,860.00
-
8,645.00
6,300.00
-
-
-
-
-
-
-
-
-
-
-
300,000.00
400,000.00
882,422.40
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
200,000.00
370,000.00
13,452.00
87,140.00
6,732.00
6,426.00
683,750.00
-
180,000.00
-
-
105,600.00
132,000.00
13,048.00
-
-
-
9,600.00
26,775.00
53,707.50
49,612.50
106,250.00
676,593.00
-
-
47,800.00
48,750.00
11,975.00
2,875.00
950.00
58,900.00
-
171,250.00
-
5,685,181.99
300,000.00
290,000.00
285,000.00
100,000.00
975,000.00
-
-
1,890.00
-
919.10
9,686.60
3,628.80
-
-
1,437.50
-
-
-
-
-
-
886.80
202.80
-
-
-
-
130.50
-
-
-
-
42.00
42.00
18,866.10
-600.00
-750.00
-1,125.00
-4,000.00
-1,500.00
-750.00
-2,000.00
2,500.00
1,250.00
625.00
750.00
1,250.00
1,250.00
1,250.00
1,250.00
1,250.00
2,500.00
750.00
1,250.00
750.00
1,250.00
1,250.00
1,250.00
-
-
-25,828.05
-3,992.00
-9.40
-13,387.50
-362.00
-4,131.70
-1,440.00
-36,270.00
-601.00
-
-76,371.65
150,000.00
-
62,000.00
-
200,000.00
-
75,000.00
-
-
50,000.00
5,000.00
5,000.00
-
-
350,000.00
100,000.00
169,546.00
50,000.00
-
-
300,000.00
-
-
1,516,546.00
25,000.00
7,800.00
180.00
360.00
1,750.00
-
15,000.00
-
10,800.00
4,500.00
4,500.00
2,550.00
4,200.00
24,000.00
-
78,980.00
369,000.00
548,620.00
107,975.15 74,156.60
-
1,296,635.80 71,766.20
-
2,055,784.75 -46,804.05
-
1,476,837.60 -152,537.60
-
2,192,032.50 -619,885.00
-
3,147,986.50 -1,191,334.00
-
1,538,439.97 -140,033.77
-
1,280,267.95 8,342.20
-
869,683.84 -96,237.69
-
380,003.50 158,236.50
-
117,660.65 -12,072.65
-
600,000.00 -161,357.00
-
700,000.00 -230,885.00
-
5,685,181.99 -2,521,741.99
-
975,000.00 125,000.00
-
18,866.10 -18,866.10
-
-76,371.65 76,371.65
-
1,516,546.00 -1,046,546.00
-
548,620.00 -307,380.00
24,431,150.65 -6,031,807.70
22,112,856.83
2,318,293.82
422,608.42
270,204.72
Dr.PINAKINI.K.SHANKAR RESIDENCE
MEASUREMENT SHEET OF Final Bill
B MASONRY WORKS
B02 BBM 9" thk
Stilt floor
Lift Well Platform 1 1.00 0.75 0.75 1.25 0.70
Parking West Wall 1.00 2.67 0.75 9.00 18.00
18.71 Cft
Terrace floor
For Placing AC controller 1.00 5.00 4.00 0.42 8.33
For Placing Lift controller 1.00 1.83 1.42 1.17 3.04
11.37 Cft
C CONCRETE WORKS
C01 PCC 1:4:8
Below flooring
Flagging Concrete Alround 1.00 429.60 0.33 143.06 Cft
Terrace floor
For Placing AC controller 1.00 5.00 4.00 0.25 5.00
For Placing Lift controller 1.00 1.83 1.42 0.25 0.65
Support for Breakfast marble 1.00 0.83 0.83 2.50 1.73
Platform for roof pipe over the floor 1.00 0.75 0.75 0.83 0.47
Pressure pump platform 1.00 1.00 1.00 0.33 0.33
Support for Shade To Pressure Pump 1.00 0.75 0.75 0.25 0.14
Support For Pipes @ Oht 6.00 0.75 0.75 0.33 1.12
9.45 Cft
Utility
North Side 1.00 33.75 4.50 151.88 Sft
351.88
F INTERIOR WORKS
F01 Wardrobes `
19 mm Century Commercial Ply, Inside 0.8mm
Laminate Finish & Outside Decorative Veneer of Rs
150/- per sft With Mellamine Finish , Fittings all are
Hetich, Handles are below 150 Rs and Locks are
Europa.
Stilt floor
Below loft
NE Bedroom 1.00 12.00 7.00 84.00
SE Bedroom 1.00 4.25 7.00 29.75
113.75
Above Loft
NE Bedroom 1.00 12.00 2.25 27.00
SE Bedroom 1.00 4.25 1.75 7.44
34.44
Beam Cover
SE Bedroom 1.00 4.25 3.00 12.75
Ground Floor
SW Bedroom
South Side 1.00 6.25 8.50 53.13
West Side 1.00 5.00 8.50 42.50
Dress Table 1.00 4.50 9.50 42.75
Sliding Door 1.00 6.75 9.50 64.13
202.50
First floor
SW Bedroom
North & South Side 2.00 6.25 8.25 103.13
Dress Table 1.00 4.75 8.25 39.19
Sliding Door 1.00 8.50 9.75 82.88
NW Bedroom
North Side 1.00 7.25 8.00 58.00
East Side 1.00 7.25 8.00 58.00
Dress Table 1.00 3.00 7.00 21.00
Sliding Door 1.00 7.25 9.25 67.06
429.25
Stilt floor
Below platform(7'9'+6'9") 1.00 14.50 2.75 39.88 Sft
Above platform 1.00 6.75 2.00 13.50 Sft
Ground floor
Below platform
North West Side 1.00 9.50 2.75 26.13
East Side 1.00 11.75 2.75 32.31
58.44 Sft
Above platform
West Side 1.00 4.25 3.25 13.81 Sft
Above Loft
West Side 1.00 13.00 2.75 35.75 Sft
F03 T.V.Cabinet
Ground floor 1.00 - Sft
North Column
South & East 1.00 1.92 8.00 15.33
West Side 1.00 0.75 3.75 2.81
Breakfast Down side 1.00 10.50 4.75 49.88
104.58 Sft
FNT2 Staircase Steps Sft
FNT5 Pooja Wall Work (Brick Pattern) 1.00 18.50 2.33 43.16 Sft
Ground floor
Lift Wall
Left 1.00 1.50 6.42 9.63
Right 1.00 2.42 6.42 15.51
Jambs 2.00 1.00 6.42 12.83
Lintel 1.00 2.58 1.00 2.58
Top 1.00 6.42 1.50 9.63
50.17
First floor
Left 1.00 1.50 6.42 9.63
Right 1.00 2.42 6.42 15.51
Jambs 2.00 1.00 6.42 12.83
Lintel 1.00 2.58 1.00 2.58
Top 1.00 6.42 1.50 9.63
50.17
141.62
FNT11 Ribs
Ribs 4.00 4.00 16.00 Rft
G PLASTERING
G01 Outside Plastering
Stilt Floor
Parking West Wall (2.667+0.75)*2 1.00 6.83 9.00 61.51 Sft
Ground Floor
Elevation Wall (15'3"+3'0") 1.00 18.25 10.50 191.63 Sft
First Floor
Elevation Wall (15'3"+3'0") 1.00 18.25 10.50 191.63 Sft
Terrace Floor
Elevation Wall (15'3"+3'0") 1.00 18.25 4.83 88.20 Sft
Terrace floor
For Placing AC controller 1.00 5.00 4.00 20.00
Sides 1.00 9.00 0.67 6.00
For Placing Lift controller(1'10"+1'5") 1.00 3.25 1.42 4.60
(Rework) Short Column-1(10"+10")*2 1.00 3.33 2.50 8.33
Top 1.00 0.83 0.83 0.69
Platform for roof pipe over the floor(9"+9"+9") 1.00 2.25 0.83 1.87
Top 1.00 0.75 0.75 0.56
Pressure pump platform(1'0"+1'0")*2 1.00 4.00 0.33 1.32
Top 1.00 1.00 1.00 1.00
Support for Shade To Pressure Pump(0.75+0.75)*2 1.00 3.00 0.25 0.75
Top 1.00 0.75 0.75 0.56
Support For Pipes @ Oht(9"+6")*2 6.00 6.25 0.33 12.38
Top 6.00 0.75 0.50 2.25
60.31 Sft
Ground floor
Lift Sill 1.00 3.00 0.75 2.25 Sft
First floor
B/w Study & Sunroom 1.00 7.63 0.75 5.72
Lift Sill 1.00 3.00 0.75 2.25
Demolished(Sun room Sliding door Sill) 1.00 6.00 0.75 4.50
12.47 Sft
Ground Floor
Living(18'0"+17'0")*2 1.00 70.00 70.00
Kitchen
North side(2'0"+2'0"+2'0") 1.00 6.00 6.00
South side(5'+1'3"+5') & (3'+1'3"+5') 1.00 20.50 20.50
East side 1.00 11.75 11.75
108.25 Rft
First Floor
Chinmay Dress area west side(6"+4'1.5") 1.00 4.63 4.63 Rft
First floor
NW Room 1.00 13.75 13.88 190.78
SW Room 1.00 15.50 15.00 232.50
423.28 Sft
First floor
NW Room 1.00 55.25 55.25
SW Room 1.00 43.13 43.13
151.75 Rft
First floor
NW Room 1.00 3.25 3.25
SW Room 1.00 17.88 17.88
31.25 Rft
Ground Floor
Utility Wall 1.00 63.75 4.67 63.75
Utility Wall Top 1.00 14.39 14.39
Deductions
D1 1.00 3.25 4.67 15.18
78.14 15.18
62.96 Sft
First Floor
NW Toilet 1.00 6.00 9.00 54.00
SW Toilet 1.00 86.85 86.85
140.85 Sft
First Floor
NW Toilet (6'0"+9'0")*2 1.00 30.00 9.00 270.00
SW Toilet 1.00 40.50 9.00 364.50
Deductions
D3 2.00 2.75 7.00 5.50
V 2.00 5.00 2.00 10.00
KW 1.00 3.00 4.50 3.00
634.50 18.50
616.00 Sft
Ground floor
Kitchen Platform
North & West(6'6"+3'4.5") 1.00 9.88 2.25 22.22
East 1.00 11.75 2.00 23.50
Brekfast table top 1.00 10.75 1.25 13.44
Brekfast table sides 1.00 11.75 1.25 14.69
South 2.00 5.00 1.25 12.50
86.34 Sft
First floor
Sun room Door Sill 1.00 6.00 0.75 4.50 Sft
Ground floor
Foyer, Staircase & Dining(51'6"+9"+9"+3'4.5"-(3'3"+3'0")) 1.00 50.13 50.13
Living(18'0"+17'0") 1.00 35.00 35.00
85.13 Rft
First floor
Family 1.00 57.75 57.75
Lift,Passage &
study(2'0"+9"+1'3"+9"+4'4.5"+2'+7'3"+9") 1.00 19.13 19.13
Chinmay Dress area west side(6"+4'1.5") 1.00 4.63 4.63
81.50 Rft
First floor
NW Toilet 4.00 30.00 120.00
SW Toilet 4.00 40.50 162.00
Deductions
Door 6.00 2.75 16.50
282.00 16.50
265.50 Rft
Ground floor
Balcony Wall Cladding
Horizontal(4'0"+4'4.5"+2'7"+3"+5'11") 2.00 17.13 34.25
Vertical 1.00 9.00 9.00
Main Door 1.00 19.00 19.00
Powder Room Flush Tank Top 1.00 2.25 2.25
SW Room Toilet Flush Tank Top 1.00 6.25 6.25
Shelf (2'0"+1'0")*2 1.00 6.00 6.00
Toilet Door Patti (2'9"+7'0"+7'0") 2.00 16.75 33.50
Utility Door(3'3"+7'0"+7'0") 1.00 17.25 17.25
127.50 Rft
First floor
SW room Toilet Flush Tank Top 1.00 6.25 6.25
Shelf (2'0"+1'0")*2 2.00 6.00 12.00
Toilet Door Patti (2'9"+7'0")*2 2.00 19.50 39.00
Windows Patti (5'0"+2'0")*2 2.00 14.00 28.00
Sunroom Platforms
South side 1.00 14.75 14.75
East side 1.00 10.00 10.00
110.00 Rft
Ground floor
Balcony Wall Cladding
Horizontal(4'0"+4'4.5"+2'7"+3"+5'11") 4.00 17.13 68.50
Vertical 2.00 9.00 18.00
Main Door(5'0"+7'0"+5'0") 2.00 19.00 38.00
Powder Room Flush Tank Top 2.00 2.25 4.50
SW Room Toilet Flush Tank Top 2.00 6.25 12.50
Shelf (2'0"+1'0")*2 2.00 6.00 12.00
Toilet Door Patti (2'9"+7'0"+7'0") 4.00 16.75 67.00
Utility Door(3'3"+7'0"+7'0") 4.00 17.25 69.00
220.50 Rft
First floor
SW room Toilet Flush Tank Top 1.00 6.25 6.25
Shelf (2'0"+1'0")*2 2.00 6.00 12.00
Toilet Door Patti (2'9"+7'0")*2 2.00 19.50 39.00
Windows Patti (5'0"+2'0")*2 2.00 14.00 28.00
85.25 Rft
First floor
NW Dress Room 2.00 7.38 14.75
Cut Out 2.00 50.00 100.00
114.75 Rft
H39NT ONYEX
Ground floor
Pooja 1.00 8.00 4.00 32.00
Sheela Shankar room 1.00 6.00 2.00 12.00
44.00 Sft
I PAINTING WORKS
I01 Plastic Emulsion
Stilt floor
Walls(3885.01+(140.31-(80.06-27'6")) 1.00 3,937.57 3,937.57
Ceiling 1.00 2,146.95 2,146.95
6,084.52 Sft
Ground floor
Walls 1.00 2,847.16 2,847.16
Ceiling 1.00 1,688.35 1,688.35
4,535.51 Sft
First floor
Walls 1.00 3,455.69 3,455.69
Ceiling 1.00 1,323.26 1,323.26
4,778.95 Sft
Terrace floor
Walls(715.71+60.31) 1.00 776.02 776.02
Ceiling 1.00 169.06 169.06
945.08 Sft
Terrace Floor
For wood works
D1 1.00 3.25 1.00 7.00 22.75 Sft
For Windows
W3 4.00 5.00 1.50 4.50 135.00
W5 2.00 3.00 1.50 4.50 40.50
W6 1.00 2.00 1.50 4.50 13.50
KW 1.00 3.00 1.50 4.50 20.25
V1 1.00 3.00 1.50 2.00 9.00
218.25
Total 696.00
Ground floor
For Doors
ED/W 1.00 5.00 2.50 7.00 87.50
PD 1.00 4.00 2.50 7.00 70.00
D1 2.00 3.25 2.50 7.00 113.75
D3 2.00 2.75 2.50 7.00 96.25
367.50
For Windows
W1 1.00 8.00 1.50 6.00 72.00
W2 1.00 6.00 1.50 6.00 54.00
W5 2.00 3.00 1.50 4.50 40.50
KW 1.00 3.00 1.50 4.50 20.25
V 1.00 5.00 1.50 2.00 15.00
V2 1.00 2.00 1.50 4.50 13.50
215.25
Total 582.75
First floor
For Doors
D1 2.00 3.25 2.50 7.00 113.75
D3 2.00 2.75 2.50 7.00 96.25
Sunroom Door 1.00 6.00 2.50 7.00 105.00
210.00
For Windows
W1 2.00 8.00 1.50 6.00 144.00
W4 1.00 3.00 1.50 6.00 27.00
W5 4.00 3.00 1.50 4.50 81.00
V 2.00 5.00 1.50 2.00 30.00
282.00
Total 492.00
Terrace floor
For Doors
D1 1.00 3.25 1.50 7.00 34.13
Terrace Floor
Elevation Wall (15'3"+3'0") 1.00 18.25 4.83 88.20 Sft
471.45
I06NT Inside Wall Texture
Stair case south wall (10'6"+10'6"+9'0") 1.00 14.50 30.00 435.00 Sft
J MISCELLANEOUS
J04 Stone Slab over Drains 1.00 40.00 5.00 200.00 Sft
J14 Granite Cutting for Wash basin Counter 3.00 3.00 Nos
K M.S. / S.S. WORKS (without Basic material cost but including Painting)
K01 M.S. Gate
Stilt floor
Parking Gate 1.00 20.88 7.50 156.56
Small Gate 1.00 4.00 7.50 30.00
186.56 Sft
K02 S.S. Staircase Railing
Stilt floor
External Staircase(5'4"+12'0"+9'4.5"+12'9"+3') 1.00 42.46 3.00 127.37 Sft
GLASS WORKS
1 Shower partition 3.00 3.00 Nos
2 Design Glass for railings
3 Laminated Glass for Sky light
Elliptical Skylight 1.00 101.60 101.60 Sft
Sun room Skylight 1.00 16.33 10.50 171.47 Sft
Staircase Skylight 1.00 7.58 2.42 18.33 Sft
4 Structural Glazing
5 Laminated Glass
Glass Floor 1.00 7.33 4.67 34.22 Sft
Infront Of pooja 1.00 4.00 4.00 16.00 Sft
Entrance Door pargola Top 1.00 14.08 3.50 49.29 Sft
Utility Top 1.00 25.58 3.00 76.73 Sft
Parking Pargola 1.00 24.13 3.50 84.44 Sft
Utility NW Top 1.00 2.25 2.50 5.63 Sft
Garden East wall 4.00 1.50 4.00 24.00 Sft
Glass For sliding Gate 10.00 4.83 1.50 72.50 Sft
Glass For small Gate 1.00 3.00 1.25 3.75 Sft
Buch Glass 4.00 0.67 6.00 16.01 Sft
Glass Blocks 9.00 9.00 Nos
P DEMOLITION WORKS
P04 R.C.C Work Demolition
P04D R.C.C Column Concrete
Terrace floor
Short Column 2.00 0.75 1.50 0.50 1.13 Cft
H FLOORING
ITALIAN MARBLE
H01 Italian marble for Flooring
Stilt floor
Passage Infront Of lift 1.00 4.00 5.50
Lift Sill 1.00 3.00 0.75
Ground floor
Lift Sill 1.00 3.00 0.75
Foyer,Dining & Kitchen 1.00 567.50
Living 1.00 18.00 17.00
Between Kitcken Columns 1.00 10.75 0.83
Sheela Shankar Dress Area 1.00 6.71 6.88
Pooja Flooring 1.00 9.00 9.00
Deduction
Kitchen Cabinets(1'9"+8'4.5") 1.00 10.13 1.75
First floor
Family & Study 1.00 18.00 36.75
Pinakini Dress Area 1.00 6.71 8.63
Chinmay Dress Area 1.00 7.38 9.46
B/w Study & Sunroom 1.00 7.63 0.75
Lift Sill 1.00 3.00 0.75
Demolished(Sun room Sliding door Sill) 1.00 6.00 0.75
Deduction
Cut Out 1.00 221.66
Chinmay Wardrobe(9'0"+7'4.5") 1.00 16.38 1.75
Ground Floor
Living(18'0"+17'0")*2 1.00 70.00
Foyer,Dining & Kitchen 1.00 80.17
Kitchen
North side(2'0"+2'0"+2'0") 1.00 6.00
South side(5'+1'3"+5') & (3'+1'3"+5') 1.00 20.50
East side 1.00 11.75
Infront of pooja 1.00 16.00
First floor
Family & Study 1.00 95.00
Chinmay Dress Area(5.7.5"+7.3"+1'9") 1.00 14.63
Chinmay Dress area west side(6"+4'1.5") 1.00 4.63
Ground floor
Foyer, Staircase & Dining(51'6"+9"+9"+3'4.5"-(3'3"+3'0")) 1.00 50.13
Living(18'0"+17'0") 1.00 35.00
First floor
Family 1.00 57.75
Lift,Passage &
study(2'0"+9"+1'3"+9"+4'4.5"+2'+7'3"+9") 1.00 19.13
Chinmay Dress area west side(6"+4'1.5") 1.00 4.63
First floor
NW Dress Room 1.00 7.38
Cut Out 1.00 50.00
First floor
NW Dress Room 2.00 7.38
Cut Out 2.00 50.00
First Floor
NW Toilet 1.00 6.00 9.00
SW Toilet 1.00 86.85
First Floor
NW Toilet (6'0"+9'0")*2 1.00 30.00
SW Toilet 1.00 40.50
Deductions
D3 2.00 2.75
V 2.00 5.00
KW 1.00 3.00
Ground floor
Balcony Wall Cladding
Horizontal(4'0"+4'4.5"+2'7"+3"+5'11") 2.00 17.13
Vertical 1.00 9.00
Main Door 1.00 19.00
Powder Room Flush Tank Top 1.00 2.25
SW Room Toilet Flush Tank Top 1.00 6.25
Shelf (2'0"+1'0")*2 1.00 6.00
Toilet Door Patti (2'9"+7'0"+7'0") 2.00 16.75
Utility Door(3'3"+7'0"+7'0") 1.00 17.25
First floor
SW room Toilet Flush Tank Top 1.00 6.25
Shelf (2'0"+1'0")*2 2.00 6.00
Toilet Door Patti (2'9"+7'0")*2 2.00 19.50
Windows Patti (5'0"+2'0")*2 2.00 14.00
Sunroom Platforms
South side 1.00 14.75
East side 1.00 10.00
Ground floor
Kitchen Platform
North & West(6'6"+3'4.5") 1.00 9.88 2.25
East 1.00 11.75 2.00
Brekfast table top 1.00 10.75 1.25
Brekfast table sides 1.00 11.75
South 2.00 5.00 1.25
First floor
Sun room Door Sill 1.00 6.00 0.75
Ground floor
Balcony Wall Cladding
Horizontal(4'0"+4'4.5"+2'7"+3"+5'11") 4.00 17.13
Vertical 2.00 9.00
Main Door(5'0"+7'0"+5'0") 2.00 19.00
Powder Room Flush Tank Top 2.00 2.25
SW Room Toilet Flush Tank Top 2.00 6.25
Shelf (2'0"+1'0")*2 2.00 6.00
Toilet Door Patti (2'9"+7'0"+7'0") 4.00 16.75
Utility Door(3'3"+7'0"+7'0") 4.00 17.25
First floor
SW room Toilet Flush Tank Top 1.00 6.25
Shelf (2'0"+1'0")*2 2.00 6.00
Toilet Door Patti (2'9"+7'0")*2 2.00 19.50
Windows Patti (5'0"+2'0")*2 2.00 14.00
First floor
NW Toilet 4.00 30.00
SW Toilet 4.00 40.50
Deductions
Door 6.00 2.75
TILES
H07 Vitrified tiles flooring
Stilt floor
Living,Dining & Kitchen 1.00 387.63
NE Bedroom 1.00 12.00 12.00
SE Bedroom 1.00 121.44
Pooja Flooring 1.00 4.00 4.75
Clinic 1.00 271.72
Deduction
Kitchen Cabinets(7'0"+8'3") 1.00 15.25 1.75
NE Wardrobe 1.00 12.00 1.75
SE Wardrobe 1.00 4.38 1.75
Ground floor
Kitchen Cabinets
West side(8'4.5"+1'9") 1.00 10.13 1.75
East side 1.00 11.50 2.00
Ground floor
Utility Wall 1.00 118.27
Powder Room 1.00 8.00 5.00
Ground floor
Powder Room (8'0"+5'0")*2 1.00 26.00
SW Room Toilet (6'3"+9'0")*2 1.00 30.50
Utility Wall 1.00 63.75
Utility Wall Top 1.00 14.39
Deductions
D1 1.00 3.25
Toilet Door 2.00 2.75
V 1.00 5.00
V2 1.00 2.00
H39NT ONYEX
Ground floor
Pooja 1.00 8.00 4.00
Sheela Shankar room 1.00 6.00 2.00
First floor
NW Room 1.00 13.75 13.88
SW Room 1.00 15.50 15.00
First floor
NW Room 1.00 55.25
SW Room 1.00 43.13
First floor
NW Room 1.00 3.25
SW Room 1.00 17.88
First floor
NW Room 1.00 13.00 13.88
SW Room 1.00 15.50 15.00
22.00
2.25
24.25 Sft
2.25
567.50
306.00
8.95
46.12
81.00
17.72
1,011.82 17.72
994.10 Sft
661.50
57.86
69.75
5.72
2.25
4.50
221.66
28.66
801.58 250.32
551.26 Sft
17.50 Rft
70.00
80.17
6.00
20.50
11.75
16.00
204.42 Rft
95.00
14.63
4.63
114.25 Rft
2.50 42.50
7.00 39.73
1.00 8.25
90.48 Sft
12.00
6.00
18.00 Sft
13.75 Rft
50.13
35.00
85.13 Rft
57.75
19.13
4.63
81.50 Rft
5.68 Rft
6.75
2.17
12.83
2.17
6.00
6.00
35.00
9.88
11.75
11.75
11.75
22.50
138.54 Rft
7.38
50.00
57.38 Rft
27.00
8.67
51.33
8.67
6.00
14.00
70.00
19.75
23.50
23.50
23.50
45.00
320.92 Rft
14.75
100.00
114.75 Rft
12.50 Sft
56.25 Sft
54.00
86.85
140.85 Sft
35.75
-
14.75
10.00
60.50 Sft
77.54
2.50 17.50
95.04 Sft
9.00 270.00
9.00 364.50
7.00 5.50
2.00 10.00
4.50 3.00
634.50 18.50
616.00 Sft
8.50 156.19
7.00 35.00
156.19 35.00
121.19 Sft
65.33
42.60
21.75
19.06
130.19
278.92 Sft
16.00
9.00
1.00
8.67
34.67 Sft
64.00
4.50
4.67
29.13
17.00
4.50
5.00
6.00
134.79 Rft
34.25
9.00
19.00
2.25
6.25
6.00
33.50
17.25
127.50 Rft
6.25
12.00
39.00
28.00
14.75
10.00
110.00 Rft
30.00
6.00
2.25
38.25 Sft
22.22
23.50
13.44
1.25 14.69
12.50
86.34 Sft
4.50 Sft
10.00
5.00
7.50
22.50 Sft
154.66
11.00
58.25
17.00
4.50
10.00
31.50 Rft
68.50
18.00
38.00
4.50
12.50
12.00
67.00
69.00
220.50 Rft
6.25
12.00
39.00
28.00
85.25 Rft
16.00
9.00
1.00
8.67
34.67
11.00
45.67 Rft
20.00
10.00
15.00
45.00 Sft
15.25
21.00
36.25
120.00
162.00
16.50
282.00 16.50
265.50
301.75 Rft
5.50
5.50
11.00 Rft
387.63
144.00
121.44
19.00
271.72
26.69
21.00
7.66
943.79 55.34
888.44 Sft
17.72
23.00
40.72 Sft
120.50
48.00
49.25
72.25
290.00 Rft
24.50
26.02
18.50
69.02 Sft
118.27
40.00
158.27 Sft
1,336.21
87.70
2.25
1,336.21 89.95
1,246.26 Sft
7.00 141.75
7.00 143.50
7.00 120.75
2.00 38.00
3.17 16.63
3.42 19.36
3.17 10.30
7.00 52.50
490.29 52.50
437.79 Sft
10.00 260.00
10.00 305.00
4.67 63.75
14.39
4.67 15.18
7.00 38.50
2.00 10.00
4.50 9.00
643.14 72.68
570.46 Sft
71.17
1.00 13.79
2,122.39
1.13
1,233.06
2,207.35 1,234.19
973.17 Sft
9.00
40.88
16.50
66.38 Rft
32.00 Sft
147.50 Sft
32.00
12.00
44.00 Sft
234.22 Sft
190.78
232.50
423.28 Sft
53.38 Rft
55.25
43.13
151.75 Rft
10.13 Rft
3.25
17.88
31.25 Rft
232.50
1.72
234.22 Sft
180.38
232.50
412.88 Sft
Dr. PINAKINI.K.S
ABST
C CONCRETE WORKS
C01 PCC 1:4:8
Below footing Cft 782.60 120.00 93,912.00 683.88 82,065.60
Below flooring Cft 962.17 120.00 115,460.40 699.63 83,955.60
Below Staircase Landing Cft 120.00 9.48 1,137.60
C02 RCC Footing Concrete Cft 1,854.00 210.00 389,340.00 1,526.69 320,604.90
C03 RCC Plinth Beam Cft 288.70 300.00 86,610.00 245.95 73,785.00
C04 PCC 1:3:6 Sills
Stilt floor Cft 40.31 130.00 5,240.30 8.14 1,058.20
Ground floor Cft 8.54 130.00 1,110.20 -
First floor Cft 8.25 130.00 1,072.50 -
Terrace floor Cft 40.27 130.00 5,235.10 -
C05 RCC Column Concrete
Below Stilt floor Cft 69.75 330.00 23,017.50 64.43 21,261.90 -
Above Stilt floor Cft 165.38 330.00 54,575.40 185.06 61,069.80
Ground floor Cft 165.38 330.00 54,575.40 -
First floor Cft 165.38 330.00 54,575.40 -
Terrace Floor Cft 82.69 330.00 27,287.70 -
C06 RCC Lintel Concrete
Stilt floor Cft 27.28 300.00 8,184.00 46.24 13,872.00
Ground floor Cft 24.84 300.00 7,452.00 -
First floor Cft 29.06 300.00 8,718.00 -
Terrace Floor Cft 3.75 300.00 1,125.00 -
C07 RCC Chejja, loft concrete
Stilt floor Sft 76.00 245.00 18,620.00 79.50 19,477.50
Ground floor Sft 62.00 245.00 15,190.00 -
First floor Sft 88.00 245.00 21,560.00 -
Terrace Floor Sft 16.00 245.00 3,920.00 -
C08 RCC Beam Concrete
Stilt floor Cft 289.27 305.00 88,227.35 360.53 109,961.65
Ground floor Cft 347.58 305.00 106,011.90 -
First floor Cft 313.45 305.00 95,602.25 -
Terrace Floor Cft 73.41 305.00 22,390.05 -
C09 RCC Roof Slab concrete
Stilt floor Cft 785.84 305.00 239,681.20 733.46 223,705.30
Ground floor Cft 631.65 305.00 192,653.25 -
First floor Cft 497.06 305.00 151,603.30 -
Terrace floor Cft 82.50 305.00 25,162.50 -
C10 RCC Staircase Waist Slab
Stilt floor Cft 75.17 400.00 30,068.00 19.40 7,760.00
C11 RCC Staircase Folded type -
Stilt floor Cft 800.00 37.34 29,872.00
Ground floor Cft 38.00 800.00 30,400.00 -
First floor Cft 38.00 800.00 30,400.00 -
C12 RCC Retaining wall Cft 400.00 135.00 54,000.00 -
-
2,008,980.70 635,673.00 467,914.05
-
D STEEL
Steel Reinforcement including fabrication
D01 (Basic cost=Rs.50000 /-)
Stilt floor Kgs 8,000.00 68.00 544,000.00 4,813.00 327,284.00 4,000.00 272,000.00
Ground floor Kgs 5,750.00 68.00 391,000.00 1,825.00 124,100.00
First floor Kgs 5,050.00 68.00 343,400.00 -
68.00
68.00
68.00
Terrace floor Kgs 675.00 68.00 45,900.00 -
1,324,300.00 327,284.00 396,100.00
-
E DOORS AND WINDOWS -
DOORS -
E01 Teak Wood frame with OST Flush shutter
with teak wood panneling for Main door.
-
Stilt floor Sft 28.00 2,420.00
Ground floor Sft 28.00 2,420.00 67,760.00 -
E02 Teak Wood frame withTeak wood shutter
for pooja Door - PD. -
Stilt floor Sft 28.00 2,750.00
Ground floor Sft 28.00 2,750.00 77,000.00 -
E03 Teak Wood frame with BST Flush shutter
for Room doors. -
Stilt floor Main door Sft 2,100.00
Stilt floor Sft 42.00 1,800.00 75,600.00 -
Ground floor Sft 42.00 1,800.00 75,600.00 -
First floor Sft 59.50 1,800.00 107,100.00 -
NT1 Teak Wood frame with OST Flush shutter
for Toilet, Utility & Terrace door.
Stilt floor Sft 1,750.00
Ground floor Sft 1,750.00
First floor Sft 1,750.00
Terrace Floor Sft 1,750.00
E04 Teak Wood frame with Fully Glazed Teak
wood shutter including Glass for Toilet
doors -
Stilt floor Sft 17.50 2,285.00 39,987.50 -
Ground floor Sft 35.00 2,285.00 79,975.00 -
First floor Sft 35.00 2,285.00 79,975.00 -
First floor Sliding door 2,500.00 -
E05 Sal Wood frame with commercial
waterproof Flush shutter for Servent Room
and Servent toilet doors -
Stilt floor Sft 38.50 750.00 28,875.00 -
WINDOWS -
E06 Teak wood frame with Teak wood shutter
for Windows -
Stilt floor Sft 94.50 2,100.00 198,450.00 -
Ground floor Sft 142.50 2,100.00 299,250.00 -
First floor Sft 181.50 2,100.00 381,150.00 -
E07 Sal Wood frame with Honne wood shutter
for Windows in Servent room and Servent
Toilet -
Stilt floor Sft 58.50 1,050.00 61,425.00 -
ENT1 Sliding Door
First floor Sft 3,000.00
ENT2 Pelmet Box For Sliding door Rft 2,000.00
ENT3 UPVC windows Sft 500.00
WOOD WORK ADVANCE 1,000,000.00
1,572,147.50 - -
-
F INTERIOR WORKS -
F01 Wardrobes
19 mm Century Commercial Ply, Inside
0.8mm Laminate Finish & Outside
Decorative Veneer of Rs 150/- per sft With
Mellamine Finish , Fittings all are Hetich,
Handles are below 150 Rs and Locks are
Europa.
-
Stilt floor
Below loft Sft 1,500.00 -
Above Loft Sft 900.00 -
Beam cover Sft 900.00 -
Ground floor -
Below loft Sft 80.50 1,840.00 148,120.00 -
1,400.00
Above Loft Sft 34.50 950.00 32,775.00 -
1,000.00
MDF Beam cover Sft 1,000.00
First floor -
Below loft Sft 196.35 1,840.00 361,284.00 -
1,400.00
Above Loft Sft 84.15 950.00 79,942.50 -
1,000.00 -
K M.S. / S.S. WORKS (without Basic material cost but including Painting)
K01 M.S. Gate Sft 130.00 60.00 7,800.00
K02 S.S. Staircase Railing Sft 71.06 50.00 3,553.00
K03 M.S. Covering Grill Sft 871.50 40.00 34,860.00
K04 M.S. Balcony Railing Sft 45.00 35.00 1,575.00
K05 M.S. T-angle Set 1.00 350.00 350.00
K06 M.S. Sky light covering Sft 355.00 100.00 35,500.00
K07 M.S. Ladder L.S 1.00 1,500.00 1,500.00
K08 M.S.Door Sft 42.00 60.00 2,520.00
K09 M.S.Grill Door Sft 21.00 80.00 1,680.00
K10 M.S.Frame for Structural Glazing Sft 325.00 50.00 16,250.00
KNT1 Pargola To Cover The Balcony Near
Entrance Door Sft 60.00
KNT2 Utility Covering Sft 60.00
KNT3 M.S. Staircase For Internal Staircase No 5,000.00
KNT4 M.S. Staircase In Terrace Floor No 5,000.00
KNT5 M.S. Frame For Glass Floor Sft 60.00
KNT6 Louvers For Clinic Toilet Sft 60.00
KNT7 Windows Patti Sft 30.00
KNT8 Sunroom Mesh Sft 30.00
KNT9 Compound Mesh Sft 30.00
KNT10 Sunroom Covering grill Sft 60.00
KNT11 Sump Cover No 60.00
KNT12 Cylinder Fence Sft 60.00
KNT13 Storage for generator Sft 60.00
KNT14 Shade for pressure pump Sft 60.00
KNT15 Support for Breakfast platform Sft 500.00
KNT16 Flower pot stand Sft 6,000.00
105,588.00 - -
M.S. WORKS
1 M.S. Gate Sft 130.00 400.00 52,000.00
2 S.S Staircase Railing Sft 71.06 1,000.00 71,060.00
3 M.S. Covering Grill Sft 871.50 200.00 174,300.00
4 M.S. Balcony Railing Sft 45.00 180.00 8,100.00
5 M.S. T-angle Set 1.00 5,000.00 5,000.00
6 M.S. Sky light covering Sft 355.00 300.00 106,500.00
7 M.S. Ladder L.S 1.00 8,500.00 8,500.00
8 M.S.Door Sft 42.00 380.00 15,960.00
9 M.S.Grill Door Sft 21.00 300.00 6,300.00
10 M.S.Frame for Structural Glazing Sft 325.00 200.00 65,000.00
KNT1 Pargola To Cover The Balcony Near
Entrance Door Sft
KNT2 Utility Covering Sft
KNT3 M.S. Internal Staircase No
KNT4 M.S. Staircase In Terrace Floor No
KNT5 M.S. Frame For Glass Floor Sft
KNT6 Louvers For Clinic Toilet Sft
KNT7 Windows Patti Sft
KNT8 Sunroom Mesh Sft
KNT9 Compound Mesh Sft
KNT10 Sunroom Covering grill Sft
KNT11 Sump Cover Nos
KNT12 Cylinder Fence Sft
KNT13 Storage For UPS Sft
KNT14 Shade for Pressure Pump Sft
KNT15 Support to Breakfast Platform Sft
KNT16 Flower Pot Stand Sft
S.S Staircase Railing Rft 80,000.00
Bill dt.22/04/2021 132,953.00
Bill dt.22/04/2021 331,249.00
300,000.00
512,720.00
GLASS WORKS
1 Shower partition Each 3.00 45,000.00 135,000.00
3.00 30,000.00
2 Design Glass for railings Sft 200.00 -
3 Laminated Glass for Sky light Sft 355.00 800.00 284,000.00
Elliptical Skylight Sft 900.00
Sun room Skylight Sft 800.00
Staircase Skylight Sft 800.00
4 Structural Glazing Sft 325.00 300.00 97,500.00
3 Laminated Glass
Glass Floor Sft 400.00
Infront of Pooja Sft 300.00
Entrance Door pargola Sft 300.00
Parking Pargola Sft 300.00
Utility Top Sft 300.00
Utility NW Top Sft 300.00
Garden East wall Sft 200.00
Glass For sliding Gate Sft 300.00
Glass For small Gate Sft 600.00
Buch Glass Sft 1,500.00
Glass Blocks Nos 400.00
516,500.00
KITCHEN ACCESSORIES ( Haffele Blum)
a) Tandom Box 30 Kg Nos 8.00 5,975.00 47,800.00
b) Tandom Box 65Kg with Gallery Nos 6.00 8,125.00 48,750.00
c) Spice Rack Nos 1.00 11,975.00 11,975.00
d) Dust bin holder Nos 1.00 2,875.00 2,875.00
e) Detergent holder Nos 1.00 950.00 950.00
f) Aventos Nos 4.00 14,725.00 58,900.00
Euro hardware world 344,010.00
171,250.00
3,163,440.00
P DEMOLITION WORKS
P01 SSM
Stilt floor Cft 70.00
P02 BBM 9" thk
Stilt floor Cft 70.00
Ground floor Cft 70.00
First floor Cft 70.00
Terrace floor Cft
P03 BBM 4.5" thk
Stilt floor Sft 50.00
Ground floor Sft 50.00
First floor Sft 50.00
Terrace floor Sft 50.00
P04 R.C.C Work Demolition
P04A PCC 1:3:6 Sills
Stilt floor Cft 120.00
Ground floor Cft 120.00
First floor Cft 120.00
Terrace floor Cft 120.00
P04B RCC Lintel Concrete
Stilt floor Cft 150.00
Ground floor Cft 150.00
First floor Cft 150.00
Terrace floor Cft 150.00
P04C RCC Chajja Concrete
Ground floor Cft 150.00
First floor Cft 150.00
P04D R.C.C Column Concrete
Terrace floor Cft 150.00
- - -
Q ESCALATION
Cement
1 Bill dt.04.12.19 (360.00-375.00= -15.00) Bags -15.00 40.00 -600.00
2 Bill dt.13.12.19 (360.00-375.00 = -15.00) Bags -15.00 50.00 -750.00
3 Bill dt.22.12.19 (360.00-375.00= -15.00) Bags -15.00 75.00 -1,125.00
4 Bill dt.04.01.20 (335.00-375.00= -40.00) Bags -40.00 100.00 -4,000.00
5 Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00 100.00 -1,500.00
6 Bill dt.15.02.20 (360.00-375.00= -15.00) Bags -15.00 50.00 -750.00
7 Bill dt.17.03.20 (335.00-375.00= -40.00) Bags -40.00
8 Bill dt.13.06.20 (400.00-375.00= 25.00) Bags 25.00
9 Bill dt.18.08.20 (400.00-375.00= 25.00) Bags 25.00
10 Bill dt.24.08.20 (400.00-375.00= 25.00) Bags 25.00
11 Bill dt.14.09.20 (390.00-375.00= 15.00) Bags 15.00
12 Bill dt.02.10.20 (400.00-375.00= 25.00) Bags 25.00
13 Bill dt.02.10.20 (400.00-375.00= 25.00) Bags 25.00
14 Bill dt.15.10.20 (400.00-375.00= 25.00) Bags 25.00
15 Bill dt.24.10.20 (400.00-375.00= 25.00) Bags 25.00
16 Bill dt.08.11.20 (400.02-375.00= 25.00) Bags 25.00
17 Bill dt.16.11.20 (400.00-375.00= 25.00) Bags 25.00
18 Bill dt.29.12.20 (390.00-375.00= 15.00) Bags 15.00
19 Bill dt.03.01.21 (400.00-375.00= 25.00) Bags 25.00
20 Bill dt.10.02.21 (390.00-375.00= 15.00) Bags 15.00
21 Bill dt.03.03.21 (400.00-375.00= 25.00) Bags 25.00
22 Bill dt.14.03.21 (400.00-375.00= 25.00) Bags 25.00
23 Bill dt.26.03.21 (400.00-375.00= 25.00) Bags 25.00
Steel
1 Bill dt.04.12.19 (43.01-50.00= -6.99) Kgs -6.99 3,695.00 -25,828.05
2 Bill dt.27.12.19 (46.00-50.00 = -4.00) Kgs -4.00 998.00 -3,992.00
3 Bill dt.21.01.20 (49.98-50.00 = -0.02) Kgs -0.02 470.00 -9.40
4 Bill dt.13.02.20 (47.50-50.00 = -2.50) Kgs -2.50 5,355.00 -13,387.50
5 Bill dt.24.02.20 (48.00-50.00 = -2.00) Kgs -2.00
6 Bill dt.16.05.20 (49.20-50.00 = -0.79) Kgs -0.79
7 Bill dt.01.07.20 (45.00-50.00 = -5.00) Kgs -5.00
8 Bill dt.18.07.20 (43.50-50.00) = -6.50) Kgs -6.50
9 Bill dt.25.07.20 (43.99-50.00) = -6.01) Kgs -6.01
-36,295.05 -15,646.90
S EXTRA WORKS
a) Sanction Plan Charges
b) BWSSB Prorata, Point & inspection
Charges ( Approximately ) 1.00 150,000.00 150,000.00
c)
BESCOM deposits and office expencess
for Temparory connection( Approximately) 1.00 60,000.00 60,000.00
62,000.00 1.00 62,000.00
d) BESCOM deposits and office expencess
for permanent connection( Approximately) 1.00 100,000.00 100,000.00
175,000.00
e) Bore Well Pump 100,000.00
75,000.00 1.00 75,000.00
f) Solar Water Heater (200 ltr) 60,000.00
NT1 Security Systems
Advance 50,000.00
Final payment 5,000.00
Wiring & Supervision 55,000.00
NT2 A.C System
Advance 350,000.00
Advance 100,000.00
Final payment 169,546.00
Scafolding, Masonry and Supervision 50,000.00
NT3 Solar water heater, Heat Pump, Pressure
pump and Softener 300,000.00
470,000.00 137,000.00 -
T FIXTURES & APPLIANCES (Including Labour)
a) 25 lts Geyser Nos 6.00 10,500.00 63,000.00
b) Ceiling Fans Nos 10.00 2,500.00 25,000.00
c) Tube Lights (LED) Nos 10.00 650.00 6,500.00
d) 40 W Light Nos 10.00 18.00 180.00
e) Calling Bell Nos 2.00 180.00 360.00
f) Bulkhead Fitting Nos 5.00 350.00 1,750.00
g) Electrical Chimney Nos 1.00 25,000.00 25,000.00
15,000.00
h) Hobb Nos 1.00 10,000.00 10,000.00
i) Towel Rod Nos 7.00 1,800.00 12,600.00
j) Towel Ring Nos 7.00 750.00 5,250.00
k) Soup Tray Nos 7.00 750.00 5,250.00
l) Mirror in Bathroom Nos 7.00 850.00 5,950.00
m) Corner Tray Nos 6.00 1,400.00 8,400.00
n) 1.0 H.P Water Pump & fittings Nos 1.00 12,000.00 12,000.00
o) Pelmet Rods Ls 1.00 60,000.00 60,000.00
Khaff 78,980.00
Euro Hardware World 369,000.00
241,240.00 - -
COST SUMMARY
A EARTHWORK 182,131.75 105,229.10 1,030.35
G PLASTERING 1,398,406.20 - -
H FLOORING 1,288,610.15 - -
P DEMOLITION WORKS - -
Balance payable
AKINI.K.SHANKAR RESIDENTIAL BUILDING
ABSTRACT OF PRE FINAL BILL
- - 98.28
- - -
- - -
- - 1,715.70 1,399.45
- - -
- - -
18.94 3,409.20 - 921.85
- - -
200.63 40,126.00 18.71 3,742.00 1,147.69
1,174.64 234,928.00 8.30 1,660.00 - 1,182.94
1,324.11 264,822.00 6.28 1,256.00 - 1,330.39
- 659.35 131,870.00 11.37 2,274.00 659.35
- - - -
- 504.87 60,584.40 13.34 1,600.80 1,261.62
408.42 49,010.40 - 80.05 9,606.00 - 488.47
257.25 30,870.00 31.09 3,730.80 - 288.34
163.36 19,603.20 - 163.36
283,938.40 295,692.00 271,845.60 7,616.80
- - - -
- - - -
- - - -
- 13.38 1,605.60 - 697.26
- - 143.06 17,167.20 699.63
- - - 9.48
- 18.00 3,780.00 - 1,544.69
- 12.54 3,762.00 - 258.49
- - - -
- 49.19 6,394.70 177.01 23,011.30 57.33
7.59 986.70 - 50.54 6,570.20 - 58.13
12.00 1,560.00 63.84 8,299.20 - 75.84
- 70.13 9,116.90 9.45 1,228.50 70.13
- - - -
- - - 64.43
- 28.69 9,467.70 - 213.75
169.31 55,872.30 - - - 169.31
169.31 55,872.30 - - 169.31
- 88.88 29,330.40 - 88.88
- - - -
- 12.59 3,777.00 - 58.83
28.76 8,628.00 - 1.88 564.00 - 30.64
28.22 8,466.00 3.00 900.00 - 31.22
- - - -
- - - -
- 2.00 490.00 - 81.50
60.25 14,761.25 - - - 60.25
95.25 23,336.25 - - 95.25
- 28.50 6,982.50 - 28.50
- - - -
- 40.22 12,267.10 - 400.75
354.19 108,027.95 - - - 354.19
340.69 103,910.45 - - 340.69
- 77.06 23,503.30 - 77.06
- - - -
- 11.85 3,614.25 - 745.31
631.18 192,509.90 - - - 631.18
671.90 204,929.50 - - 671.90
- 69.33 21,145.65 - 69.33
- - - -
- - - 19.40
- - - -
- - - 37.34
- - - -
- - - -
- - - 135.00
- - - -
380,786.10 398,074.50 151,570.50 41,407.00
- - - -
- - - -
- - - -
- - - 8,813.00
5,411.00 367,948.00 - - - 7,236.00
5,580.00 379,440.00 - - 5,580.00
288.00 19,584.00 - - 288.00
100.00 6,800.00 - - 100.00
-298.80 -20,318.40 - -298.80
- - - -
367,948.00 405,824.00 -20,318.40 -
- - - -
- - - -
- - - -
- - - -
- - -
- 35.00 84,700.00 - 35.00
- - - -
28.00 77,000.00 - 28.00
- 28.00 77,000.00 - 28.00
- - - -
73.50 154,350.00 - 73.50
- 42.00 75,600.00 - 42.00
- 45.50 81,900.00 - 45.50
- 45.50 81,900.00 - 45.50
- - -
56.00 98,000.00 - 56.00
- - -
- - -
22.75 39,812.50 - 22.75
- - - -
- - - -
- 38.50 87,972.50 - 38.50
- 38.50 87,972.50 - 38.50
- 42.00 105,000.00 - 42.00
- - - -
- 17.50 13,125.00 - 17.50
- - - -
- - - -
- 145.50 305,550.00 - 145.50
- 143.50 301,350.00 - 143.50
- 188.00 394,800.00 - 188.00
- - - -
- - - -
- -
42.00 126,000.00 -
12.00 24,000.00 -
351.88 175,940.00 -
1.00 1,000,000.00 -1.00 -1,000,000.00 - -
1,000,000.00 1,066,032.50 325,940.00
- - - -
- - - -
- -
- - - -
- -
113.75 170,625.00 -
34.44 30,996.00 -
12.75 11,475.00 -
- - - -
- - - -
202.50 283,500.00 -
- - - -
- -
10.13 10,130.00 -
-
- - - -
- - - -
429.25 600,950.00 -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
39.88 83,748.00 -
- - - -
13.50 17,550.00 -
- - - -
- -
- - - -
- - - -
58.44 151,944.00 -
- - - -
13.81 23,062.70 -
- - 35.75 42,900.00 -
- -
35.00 61,250.00 -
23.63 - -
- - - -
- -
- - - -
- - 46.00 92,000.00 -
- - - -
- - - -
- - 322.81 387,372.00 -
- - 104.58 94,122.00 -
1.00 700,000.00 -
1.00 300,000.00 -
60.21 108,378.00 -
43.16 21,580.00 -
33.75 42,187.50 -
141.62 127,458.00 -
15.00 13,500.00 -
133.81 26,762.00 -
- - 39.00 39,000.00 -
- - 16.00 14,400.00 -
1.00 500,000.00 -1.00 -500,000.00 1.00
1.00 200,000.00 -1.00 -200,000.00 1.00
1.00 500,000.00 -1.00 -500,000.00 1.00
- - 1,200,000.00 2,254,890.20
- - - -
- - - -
- - - -
- 4,261.18 234,364.90 61.51 3,383.05 4,261.18
- 2,333.58 128,346.90 191.63 10,539.65 2,333.58
- 2,481.15 136,463.25 191.63 10,539.65 2,481.15
- 2,182.62 120,044.10 88.20 4,851.00 2,182.62
- - - -
- 3,885.01 202,020.52 140.31 7,296.12 3,885.01
- 2,847.16 148,052.32 - 2,847.16
- 3,455.69 179,695.88 - 3,455.69
- 715.71 37,216.92 60.31 3,136.12 715.71
- - - -
- 2,146.95 118,082.25 - 2,146.95
- 1,688.35 92,859.25 - 1,688.35
- 1,323.26 72,779.30 103.63 5,699.65 1,323.26
- 169.06 9,298.30 - 169.06
- - - -
- 160.75 9,645.00 - 160.75
- 230.50 13,830.00 - 230.50
- - 1,502,698.89 45,445.24
- - - -
- - - -
- - - -
24.25 4,850.00 -
- 991.85 198,370.00 2.25 450.00 991.85
- 538.80 107,760.00 12.47 2,494.00 538.80
- - - -
17.50 2,275.00 -
- 96.17 12,502.10 108.25 14,072.50 96.17
- 109.63 14,251.90 4.63 601.90 109.63
- -
90.48 22,620.00 -
18.00 - -
- - - -
- - 234.22 4,684.40 -
- - 423.28 8,465.60 -
- - - -
- - 53.38 533.80 -
- - 157.75 1,577.50 -
- - - -
- - 10.13 101.30 -
- - 31.25 312.50 -
- - - -
- 234.22 18,737.60 - 234.22
- 412.88 33,030.40 - 412.88
- - - -
- 888.44 71,075.20 - 888.44
40.72 3,257.60 - 40.72
- - - -
- 290.00 21,750.00 - 290.00
- - - -
- 69.02 5,521.60 - 69.02
- 40.00 3,200.00 118.27 9,461.60 40.00
- - 1,246.26 99,700.80 -
- - - -
- 353.50 31,815.00 84.29 7,586.10 353.50
- 507.50 45,675.00 62.96 5,666.40 507.50
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - 278.92 39,048.80 -
- - - -
- - 34.67 3,813.70 -
- - - -
- - 56.25 6,187.50 -
- - 140.85 15,493.50 -
- -
95.04 14,256.00 -
616.00 92,400.00 -
- -
- - - -
- - - -
- - 60.50 6,655.00 -
- - - -
- - 973.17 77,853.60 -
- - - -
- - 66.38 4,978.50 -
- - - -
- - 147.50 11,800.00 -
- - - -
- - - -
- - - -
- - 38.25 3,825.00 -
- - 86.34 8,634.00 -
- - 4.50 450.00 -
- - - -
- - - -
- - - -
- - 22.50 2,250.00 -
- -
45.00 2,250.00 -
- - - -
- -
- - 82,041.70 92,086.80 -
- - - -
- - - -
- - 186.56 11,193.60 -
- - 135.00 6,750.00 -
- - 983.38 39,335.20 -
- - 70.13 2,454.55 -
- - 1.00 350.00 -
- - 275.88 27,588.00 -
- - - -
- - 45.50 2,730.00 -
- - 35.00 2,800.00 -
- - - -
- - 153.00 9,180.00 -
- - 225.71 13,542.60 -
- - 1.00 5,000.00 -
- - 1.00 5,000.00 -
- - 32.39 1,943.40 -
- - 3.58 214.80 -
- - 33.75 1,012.50 -
- - 80.00 2,400.00 -
- - 108.75 3,262.50 -
- - 245.42 14,725.20 -
- - 3.00 180.00 -
- - 15.31 918.60 -
- - 14.43 865.80 -
- - 91.87 5,512.20 -
- - 1.00 500.00 -
- - 1.00 6,000.00 -
- - - 163,458.95
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
1.00 450,000.00 - 1.00
1.00 150,000.00 -
- - 450,000.00 150,000.00 -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
1.00 100,000.00 - - 1.00
1.00 150,000.00 - 1.00
1.00 450,000.00 -
- 100,000.00 150,000.00 450,000.00
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
1.00 1,800,000.00 - 1.00
1.00 115,000.00 - 1.00
1.00 307,400.00 - 1.00
1.00 112,935.59 -
1.00 84,000.00 - 1.00
1.00 4,500.00 - 1.00
1.00 55,000.00 - 1.00
1.00 144,000.00 - 1.00
1.00 192,066.00 - 1.00
1.00 7,300.00 -
1.00 48,965.00 -
1.00 100,000.00 - 1.00
1.00 293,100.00 -
2,801,966.00 462,300.59
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- -
- -
- -
- -
- -
- -
1.00 80,000.00 -
1.00 132,953.00 -
1.00 331,249.00 -
1.00 300,000.00 -
- 844,202.00
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
1.00 200,000.00 - 1.00
1.00 370,000.00 - 1.00
- 1.00 13,452.00 -
- 1.00 87,140.00 -
- 1.00 6,732.00 -
- 1.00 100,000.00 -
570,000.00 207,324.00
- - - -
- - 3.00 135,000.00 -
- - - -
- - - -
101.60 91,440.00 -
171.47 137,176.00 -
18.33 14,664.00 -
- - - -
- -
- -
34.22 10,266.00 -
16.00 4,800.00 -
49.29 14,787.00 -
84.44 25,332.00 -
5.63 1,689.00 -
24.00 4,800.00 -
72.50 21,750.00 -
3.75 2,250.00 -
16.01 24,015.00 -
9.00 3,600.00 -
491,569.00
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - 1.00 344,010.00 -
344,010.00
3,371,966.00 2,349,405.59
- - -
- -
27.00 1,890.00 - 27.00
- - -
13.13 919.10 - 13.13
138.38 9,686.60 - 138.38
51.84 3,628.80 - 51.84
- - -
- - -
28.75 1,437.50 - 28.75
- - -
- - -
- - -
- - -
- -
7.39 886.80 - 7.39
1.69 202.80 - 1.69
- - -
- - -
- -
0.87 130.50 - 0.87
- - -
- - -
- - -
- -
0.28 42.00 - 0.28
0.28 42.00 - 0.28
- -
1.13 169.50 -
- - 18,866.10 -
- - 40.00
- - 50.00
- - 75.00
- - 100.00
- - 100.00
- - 50.00
50.00 -2,000.00 - - 50.00
100.00 2,500.00 - - 100.00
50.00 1,250.00 - 50.00
25.00 625.00 - 25.00
50.00 750.00 - 50.00
50.00 1,250.00 - 50.00
50.00 1,250.00 - 50.00
50.00 1,250.00 - 50.00
50.00 1,250.00 - 50.00
50.00 1,250.00 - 50.00
100.00 2,500.00 - 100.00
50.00 750.00 - 50.00
50.00 1,250.00 - 50.00
50.00 750.00 - 50.00
50.00 1,250.00 - 50.00
50.00 1,250.00 -
50.00 1,250.00 -
- -
- -
- - 3,695.00
- - 998.00
- - 470.00
- - 5,355.00
181.00 -362.00 - - 181.00
5,230.00 -4,131.70 - - 5,230.00
288.00 -1,440.00 - - 288.00
5,580.00 -36,270.00 - - 5,580.00
100.00 -601.00 - - 100.00
-6,493.70 -35,811.00 15,375.00 2,500.00
1.00 150,000.00 -
- -
1.00
- -
1.00 175,000.00 -
- -
1.00
- -
- -
1.00 50,000.00 - 1.00
1.00 5,000.00 -
1.00 55,000.00 -
- -
1.00 350,000.00 - 1.00
1.00 100,000.00 - 1.00
1.00 169,546.00 -
1.00 50,000.00 -
1.00 300,000.00 -
- - 500,000.00 904,546.00
-
- -
12.00 7,800.00 -
10.00 180.00 -
2.00 360.00 -
5.00 1,750.00 -
- -
- -
- -
6.00 10,800.00 -
6.00 4,500.00 -
6.00 4,500.00 -
3.00 2,550.00 -
3.00 4,200.00 -
2.00 24,000.00 -
1.00 60,000.00 -
1.00 78,980.00 -
1.00 369,000.00 -
- - - 568,620.00
- - 1,715.70 1,399.45
-
283,938.40 295,692.00 271,845.60 7,616.80
-
380,786.10 398,074.50 151,570.50 41,407.00
-
367,948.00 405,824.00 -20,318.40 -
-
- 1,000,000.00 1,066,032.50 325,940.00
- - 1,200,000.00 2,254,890.20
- - 1,502,698.89 45,445.24
- - 708,694.50 622,474.50
- - 200,000.00 719,733.22
- - 82,041.70 92,086.80
- - - 163,458.95
- - 450,000.00 150,000.00
- - 3,371,966.00 2,349,405.59
- - 590,000.00 475,000.00
- - 18,866.10 -
- - 500,000.00 904,546.00
- - - 568,620.00
5,198.51 77,977.65
5,984.55 29,922.75
98.28 1,474.20
- -
- -
109,374.60
- -
- -
921.85 165,933.00
- -
1,166.40 233,280.00
1,182.94 236,588.00
1,330.39 266,078.00
670.72 134,144.00
- -
1,274.96 152,995.20
488.47 58,616.40
288.34 34,600.80
163.36 19,603.20
1,301,838.60
- -
- -
- -
697.26 83,671.20
842.69 101,122.80
9.48 1,137.60
1,544.69 324,384.90
258.49 77,547.00
- -
234.34 30,464.20
58.13 7,556.90
75.84 9,859.20
79.58 10,345.40
- -
64.43 21,261.90
213.75 70,537.50
169.31 55,872.30
169.31 55,872.30
88.88 29,330.40
- -
58.83 17,649.00
30.64 9,192.00
31.22 9,366.00
- -
- -
81.50 19,967.50
60.25 14,761.25
95.25 23,336.25
28.50 6,982.50
- -
400.75 122,228.75
354.19 108,027.95
340.69 103,910.45
77.06 23,503.30
- -
745.31 227,319.55
631.18 192,509.90
671.90 204,929.50
69.33 21,145.65
- -
19.40 7,760.00
- -
37.34 29,872.00
- -
- -
135.00 54,000.00
- -
2,075,425.15
- -
- -
- -
8,813.00 599,284.00
7,236.00 492,048.00
5,580.00 379,440.00
288.00 19,584.00
100.00 6,800.00
-298.80 -20,318.40
- -
1,476,837.60
- -
- -
- -
- -
- -
35.00 84,700.00
- -
28.00 77,000.00
28.00 77,000.00
- -
73.50 154,350.00
42.00 75,600.00
45.50 81,900.00
45.50 81,900.00
- -
56.00 98,000.00
- -
- -
22.75 39,812.50
- -
- -
38.50 87,972.50
38.50 87,972.50
42.00 105,000.00
- -
17.50 13,125.00
- -
- -
145.50 305,550.00
143.50 301,350.00
188.00 394,800.00
- -
- -
- -
42.00 126,000.00
12.00 24,000.00
351.88 175,940.00
- -
2,391,972.50
- -
- -
- -
- -
- -
113.75 170,625.00
34.44 30,996.00
12.75 11,475.00
- -
- -
202.50 283,500.00
- -
- -
10.13 10,130.00
- -
- -
- -
429.25 600,950.00
- -
- -
- -
- -
- -
- -
39.88 83,748.00
- -
13.50 17,550.00
- -
- -
- -
- -
58.44 151,944.00
- -
13.81 23,062.70
35.75 42,900.00
35.00 61,250.00
23.63 -
- -
- -
- -
46.00 92,000.00
- -
- -
322.81 387,372.00
104.58 94,122.00
1.00 700,000.00
1.00 300,000.00
60.21 108,378.00
43.16 21,580.00
33.75 42,187.50
141.62 127,458.00
15.00 13,500.00
133.81 26,762.00
39.00 39,000.00
16.00 14,400.00
- -
- -
- -
3,454,890.20
- -
- -
- -
4,322.69 237,747.95
2,525.21 138,886.55
2,672.78 147,002.90
2,270.82 124,895.10
- -
4,025.32 209,316.64
2,847.16 148,052.32
3,455.69 179,695.88
776.02 40,353.04
- -
2,146.95 118,082.25
1,688.35 92,859.25
1,426.89 78,478.95
169.06 9,298.30
- -
160.75 9,645.00
230.50 13,830.00
1,548,144.13
- -
- -
- -
24.25 4,850.00
994.10 198,820.00
551.27 110,254.00
- -
17.50 2,275.00
204.42 26,574.60
114.26 14,853.80
- -
90.48 22,620.00
18.00 -
- -
234.22 4,684.40
423.28 8,465.60
- -
53.38 533.80
157.75 1,577.50
- -
10.13 101.30
31.25 312.50
- -
234.22 18,737.60
412.88 33,030.40
- -
888.44 71,075.20
40.72 3,257.60
- -
290.00 21,750.00
- -
69.02 5,521.60
158.27 12,661.60
1,246.26 99,700.80
- -
437.79 39,401.10
570.46 51,341.40
- -
- -
- -
- -
- -
- -
- -
- -
278.92 39,048.80
- -
34.67 3,813.70
- -
56.25 6,187.50
140.85 15,493.50
- -
95.04 14,256.00
616.00 92,400.00
- -
- -
- -
60.50 6,655.00
- -
973.17 77,853.60
- -
66.38 4,978.50
- -
147.50 11,800.00
- -
- -
- -
38.25 3,825.00
86.34 8,634.00
4.50 450.00
- -
- -
- -
22.50 2,250.00
- -
45.00 2,250.00
121.19 18,178.50
- -
- -
13.75 1,375.00
85.13 8,513.00
81.50 8,150.00
- -
- -
45.67 2,283.50
- -
- -
301.75 30,175.00
5.68 284.00
4.00 600.00
- -
1,453.76 123,569.60
- -
134.79 6,739.50
127.50 6,375.00
110.00 5,500.00
- -
31.50 1,575.00
220.50 11,025.00
85.25 4,262.50
- -
158.13 15,813.00
57.38 5,738.00
- -
320.92 32,092.00
114.75 11,475.00
44.00 22,000.00
12.50 -
40.00 -
13,507.87 1,331,169.00
- -
- -
- -
6,084.52 158,197.52
4,535.51 117,923.26
4,778.95 124,252.70
945.08 24,572.08
- -
4,322.69 103,744.56 16,254.17 16,254.17 26.00 422,608.42
2,333.58 56,005.92
2,481.15 59,547.60 11,258.53 11,258.53 24.00 270,204.72
2,182.62 52,382.88
- -
145.50 3,201.00
143.50 3,157.00
188.00 4,136.00
22.75 500.50
- -
696.00 62,640.00
582.75 52,447.50
492.00 44,280.00
34.13 3,071.70
471.46 23,573.00
435.00 26,100.00
- -
919,733.22
- -
17,187.50 171,875.00
2,400.00 24,000.00
- -
13.84 1,107.20
90.26 7,220.80
104.59 8,367.20
- -
200.00 30,000.00
322.68 58,082.40
493.67 9,873.40
229.25 6,877.50
- -
10.00 3,500.00
- -
3.00 1,800.00
1.00 300.00
2.00 2,000.00
2.00 30,000.00
1.00 15,000.00
- -
- -
- 370,003.50
- -
- -
186.56 11,193.60
135.00 6,750.00
983.38 39,335.20
70.13 2,454.55
1.00 350.00
275.88 27,588.00
- -
45.50 2,730.00
35.00 2,800.00
- -
153.00 9,180.00
225.71 13,542.60
1.00 5,000.00
1.00 5,000.00
32.39 1,943.40
3.58 214.80
33.75 1,012.50
80.00 2,400.00
108.75 3,262.50
245.42 14,725.20
3.00 180.00
15.31 918.60
14.43 865.80
91.87 5,512.20
1.00 500.00
1.00 6,000.00
163,458.95
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
1.00 450,000.00
1.00 150,000.00
- 600,000.00
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
1.00 100,000.00
1.00 150,000.00
1.00 450,000.00
700,000.00
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
1.00 1,800,000.00
1.00 115,000.00
1.00 307,400.00
1.00 112,935.59
1.00 84,000.00
1.00 4,500.00
1.00 55,000.00
1.00 144,000.00
1.00 192,066.00
1.00 7,300.00
1.00 48,965.00
1.00 100,000.00
1.00 293,100.00
3,264,266.59
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
1.00 80,000.00
1.00 132,953.00
1.00 331,249.00
1.00 300,000.00
844,202.00
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
1.00 200,000.00
1.00 370,000.00
1.00 13,452.00
1.00 87,140.00
1.00 6,732.00
1.00 100,000.00
777,324.00
- -
-
3.00 90,000.00
- -
- -
101.60 91,440.00
171.47 137,176.00
18.33 14,664.00
- -
- -
34.22 13,688.00
16.00 4,800.00
49.29 14,787.00
84.44 25,332.00
5.63 1,689.00
76.73 23,019.00
24.00 4,800.00
72.50 21,750.00
3.75 2,250.00
16.01 24,015.00
9.00 3,600.00
473,010.00
- -
- -
- -
- -
- -
- -
- -
1.00 344,010.00
344,010.00
5,702,812.59
1.00 300,000.00
1.00 290,000.00
1.00 250,000.00
1.00 125,000.00
1.00 100,000.00
1,065,000.00
- -
- -
27.00 1,890.00
- -
13.13 919.10
138.38 9,686.60
51.84 3,628.80
- -
- -
28.75 1,437.50
- -
- -
- -
- -
- -
7.39 886.80
1.69 202.80
- -
- -
- -
0.87 130.50
- -
- -
- -
- -
0.28 42.00
0.28 42.00
- -
1.13 169.50
18,866.10
40.00 -600.00
50.00 -750.00
75.00 -1,125.00
100.00 -4,000.00
100.00 -1,500.00
50.00 -750.00
50.00 -2,000.00
100.00 2,500.00
50.00 1,250.00
25.00 625.00
50.00 750.00
50.00 1,250.00
50.00 1,250.00
50.00 1,250.00
50.00 1,250.00
50.00 1,250.00
100.00 2,500.00
50.00 750.00
50.00 1,250.00
50.00 750.00
50.00 1,250.00
50.00 1,250.00
50.00 1,250.00
- -
- -
3,695.00 -25,828.05
998.00 -3,992.00
470.00 -9.40
5,355.00 -13,387.50
181.00 -362.00
5,230.00 -4,131.70
288.00 -1,440.00
5,580.00 -36,270.00
100.00 -601.00
-76,371.65
1.00 150,000.00
- -
1.00 62,000.00
- -
1.00 175,000.00
- -
1.00 75,000.00
- -
- -
1.00 50,000.00
1.00 5,000.00
1.00 55,000.00
- -
1.00 350,000.00
1.00 100,000.00
1.00 169,546.00
1.00 50,000.00
1.00 300,000.00
1,541,546.00
- -
12.00 7,800.00
10.00 180.00
2.00 360.00
5.00 1,750.00
- -
- -
- -
6.00 10,800.00
6.00 4,500.00
6.00 4,500.00
3.00 2,550.00
3.00 4,200.00
2.00 24,000.00
1.00 60,000.00
1.00 78,980.00
1.00 369,000.00
568,620.00
109,374.60 72,757.15
-
1,301,838.60 66,563.40
-
2,075,425.15 -66,444.45
-
1,476,837.60 -152,537.60
-
2,391,972.50 -819,825.00
-
3,454,890.20 -1,498,237.70
-
1,548,144.13 -149,737.93
-
1,331,169.00 -42,558.85
-
919,733.22 -146,287.07
-
370,003.50 168,236.50
-
163,458.95 -57,870.95
-
600,000.00 -161,357.00
-
700,000.00 -230,885.00
-
5,702,812.59 -2,539,372.59
-
1,065,000.00 35,000.00
-
18,866.10 -18,866.10
-
-76,371.65 76,371.65
-
1,541,546.00 -1,071,546.00
-
568,620.00 -327,380.00
25,263,320.49 -6,863,977.54
22,412,856.83
2,850,463.66
Dr.PINAKINI.K.SHANKAR PAYMENT DETAILS
Advance
07.11.2019 39 100,000.00 Poovaiah
07.11.2019 40 100,000.00 Poovaiah
07.11.2019 41 100,000.00 S.V.G Eng works
07.11.2019 42 100,000.00 R.M.C
07.11.2019 43 100,000.00 R.M.C
07.11.2019 500,000.00 Cash
30.09.2019 25,000.00 Advance
27.11.2019 38,950.00 Bescom Temp deposit
11.01.2020 500,000.00 Cash
11.01.2020 77 500,000.00 Rakshith
11.01.2020 79 50,000.00 Poovaiah
11.01.2020 80 50,000.00 Poovaiah
11.01.2020 81 200,000.00 Vijayalakshmi
09.02.2020 1,000,000.00 Cash
22.02.2020 82 166,250.00 R.M.C
14.05.2020 100,000.00 Poovaiah
14.05.2020 100,000.00 Self cheque
26.05.2020 49 139,200.00 RMC
26.05.2020 50 100,000.00 Nanda kumar
26.05.2020 51 300,000.00 Bildo_Craft
26.05.2020 52 531,000.00 Shankar enterprises
26.05.2020 53 400,000.00 Rakshith
28.07.2020 57 144,000.00 Self cheque (RMC)
28.07.2020 58 200,000.00 Bildo_Craft
28.07.2020 59 256,000.00 Self cheque
28.07.2020 76 500,000.00 Rakshith
09.09.2020 73 200,000.00 Self cheque
07.10.2020 75 200,000.00 Self cheque
21.10.2020 78 200,000.00 Self cheque
17.11.2020 85 700,000.00 Vijayalakshmi
17.11.2020 79 300,000.00 Self cheque
17.11.2020 21 100,000.00 Plastering
17.11.2020 22 150,000.00 Kumar UPVC Windows
02.12.2020 86 200,000.00 Cheque
02.12.2020 150,000.00 Cash
30.12.2020 105 500,000.00 Self Cheque
15.01.2021 86 300,000.00 Anaga Elevators
15.01.2021 87 50,000.00 Nakshatra Technologies
15.01.2021 88 50,000.00 Shyam Dhani Painter
15.01.2021 89 200,000.00 Rakshith
10.02.2021 200,000.00 Cash
10.02.2021 94 300,000.00 Cheque
06.03.2021 93 200,000.00 Self cheque
06.03.2021 96 300,000.00 Rakshith
06.03.2021 97 290,000.00 Anaga Elevators
06.03.2021 98 195,000.00 Shankar enterprises
10.03.2021 106 67,000.00 Maya Bandar Doors Ltd
10.03.2021 108 300,000.00 Euro Veneers World
10.03.2021 109 350,000.00 Air Design System
10.03.2021 500,000.00 Cash
21.03.2021 16,000.00 Refund From HMG
29.03.2021 95 200,000.00 Dhanalaxmi
29.03.2021 96 100,000.00 Paramesh N
29.03.2021 98 200,000.00 Rakshith
29.03.2021 250,000.00 Cash
17.04.2021 518 25,000.00 Cheque
17.04.2021 520 100,000.00 Cheque
17.04.2021 522 50,000.00 Cheque
17.04.2021 523 25,000.00 Cheque
21.04.2021 525 100,000.00 Cheque
27.04.2021 200,000.00 Vijayalakshmi
27.04.2021 200,000.00 Nanda kumar
27.04.2021 200,000.00 Rakshith
18.05.2021 529 100,000.00 Cheque
18.05.2021 530 100,000.00 Cheque
18.05.2021 100,000.00 Online Transfer Nandakumar
18.05.2021 100,000.00 Online Transfer Rakshith
26.05.2021 531 50,000.00 Selvam
26.05.2021 533 50,000.00 Shyam
26.05.2021 534 50,000.00 Selvam
01.06.2021 386 50,000.00
02.06.2021 387 200,000.00 Euro World
02.06.2021 388 50,000.00
02.06.2021 389 25,000.00 Selvaraj
02.06.2021 390 25,000.00 Santhosh
14.06.2021 100 340,000.00
14.06.2021 101 100,000.00
14.06.2021 102 100,000.00
14.06.2021 103 100,000.00
28.06.2021 104 100,000.00
28.06.2021 106 300,000.00
28.06.2021 107 100,000.00
28.06.2021 108 200,000.00 Renerga Power Systems pvt ltd
09.07.2021 110 250,000.00 Anaga Elevators
09.07.2021 111 100,000.00
09.07.2021 112 100,000.00
09.07.2021 113 50,000.00
09.07.2021 114 50,000.00
09.07.2021 115 50,000.00
09.07.2021 116 25,000.00
09.07.2021 117 25,000.00
10.07.2021 65,676.00 BESCOM DD
02.08.2021 118 148,562.00 Shankar Enterprises
12.08.2021 119 100,000.00
13.08.2021 120 200,000.00
13.08.2021 121 200,000.00
19.08.2021 122 98,884.00 BWSSB DD (Self)
29.09.2021 125 150,000.00 Mana Upvc Windows & Doors ltd
11.10.2021 126 300,000.00 Self
18,121,522.00
TOTAL 22,412,856.83
532 Bounced Cheque