Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

111111111

DEFECT LIABILITY Manyofyou will recall the decision propertywas in the condition
PROVISIONS of Justice Young in the matter of contemplated by the parties at the
Sterling Estates Development time of entering the contract,
Colin Biggers & Paisley Corporation Pty Limited v Malouf namely ready for occupation, the
court held that the defect was not a
This involved a sale 'offthe plan' of
significant defect or 'special fault' as
a home unit at Camperdown. The
defined and that the defect was not
vendorsought completion but the
required to be rectified prior to
purchaser refused to complete as
completion. The defect was not held
there was an alleged 'special fault'
by the court to be one which would
in that the floor in the lounge room
preclude the pu rchaser from
area was uneven.
substantially occupying the unit if it
The vendor did not accept that the was not repaired priorto
unevenness of the lounge room completion. Even though there
floor constituted a special fault, would be inconvenience in rectifying
issued a notice to complete and, the defect after completion, the
when the purchaser did not settle at undertaking of this work would not
the end of the time frame set out in substantially interfere with the
the notice, purported to terminate occupation of the unit by the
the contract. purchaser or his tenant.
At first instance, Justice Young Developers should give
concluded that the unevenness of consideration, when contemplating
the floor fell within the definition of whether or not a resale contract
'special fault' in the contract as it contains a defect liability provision,
required urgent attention and as to what defects the pu rchaser
constituted a special danger: can insist be attended to before
settlement and thosewhich should
However, on appeal, the three
await rectification during the
judges of the Court of Appeal
unanimously overturned this normal 90 or 180 days defect
finding. rectification period. Perhaps
developers cou ld give consideration
The court held the following to be to the provision merely stipulating
relevant: that only significant defects need to
(a) to rectify the defect wou ld be rectified before completion, with
require moving furniture, uplifting significant defects being defined as
the carpet and levelling the any defects identified by council as
unevenness. This would only take a requiring attention forthe purpose
few days and would not be unduly of issuing an occupation certificate.
inconvenient to the occupier of the This would then fit in neatly with the
unit; recent amendment to the
Conveyancing Actwhich only
(b) council had issued an occupation
requires a purchaserto settle, in
certificate in respect of the unit; and
respect to an off-the-plan
(c) the vendor had obtained purchase, 14 days after a copy of an
independent advice that the unit occupation certificate has been
development had been completed given to the purchaser:
to a satisfactory standard and that
each of the units did not contain
This article was previously
defects which were deemed to be
published in Colin Biggers &
significant and requiring immediate
Paisley's Property Update
attention.
[December/January-2003/2004).
Looking at these facts, and Reprinted with permission.
acknowledging that there was an
implied term that the purchaser
would not have to settle until the

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #95 MARCH/APRIL 2004 27

You might also like