Payment Schemes

RELEASING OF PAYMENT as per


PERIOD PROGRESS BILLING % CASH FLOW ORIGINAL CASH FLOW CASH FLOW VARIANCE
NEW CONTRACT
Equivalent Accumulative
Accomplishment as
% of the Entire Project as per the New Accumulative Cash Regular Cash Accumulative
per the New % Equivalent Amount Amount
excluding "EXCLUDED Contract Flow Flow Cash Flow
Contract
ITEMS"

TOTAL CONTRACT AMOUNT 4,575,858.94 6,485,000.00

Downpayment at Old Contract 1,945,500.00 1,945,500.00

Accumulative Work Progress%


30.00% 1,945,500.00 1,945,500.00 1,945,500.00 3,891,000.00
to Date

DOWNPAYMENT 45.00% 2,059,136.52 2,059,136.52 4,004,636.52 3,891,000.00

PROG BILLING 1 42.86% 60.00% 40.00% 1,830,343.58 1,830,343.58 5,834,980.10 1,945,500.00 5,836,500.00 (1,519.90)

PROG BILLING 2

PROG BILLING 3 42.86% 90.00% 10.00% 457,585.89 457,585.89 6,292,565.99 - 5,836,500.00 456,065.99

AT COMPLETION 14.29% 100.00% - -

RETENTION 5.00% 228,792.95 228,792.95 6,521,358.94 648,500.00 6,485,000.00 36,358.94

TOTAL 100.00% 100.00% 4,575,858.94 6,521,358.94 4,539,500.00


Payment Schemes

RELEASING OF PAYMENT as per NEW ORIGINAL CASH FLOW/ BANK


PERIOD PROGRESS BILLING % CASH FLOW
CONTRACT RELEASES
Equivalent Accumulative
Accomplishment as
% of the Entire Project as per the New Accumulative Cash Accumulative
per the New % Equivalent Amount Bank Releases
excluding "EXCLUDED Contract Flow BANk Releases
Contract
ITEMS"

TOTAL CONTRACT AMOUNT 4,575,858.94 6,485,000.00

Downpayment at Old Contract 1,945,500.00 1,945,500.00

Accumulative Work Progress%


30.00% 1,945,500.00 1,945,500.00 1,945,500.00 3,891,000.00
to Date

DOWNPAYMENT 45.00% 2,059,136.52 2,059,136.52 4,004,636.52 3,891,000.00

PROG BILLING 1 42.86% 60.00% 20.00% 915,171.79 915,171.79 4,919,808.31 1,945,500.00 5,836,500.00

PROG BILLING 2 21.43% 75.00% 20.00% 915,171.79 915,171.79 5,834,980.10 5,836,500.00

PROG BILLING 3 21.43% 90.00% 10.00% 457,585.89 457,585.89 6,292,565.99 - 5,836,500.00

AT COMPLETION 14.29% 100.00% - -

RETENTION 5.00% 228,792.95 228,792.95 6,521,358.94 648,500.00 6,485,000.00

TOTAL 100.00% 100.00% 4,575,858.94 6,521,358.94 6,485,000.00

DOWNPAYMENT 45.00% 2,059,136.52 2,059,136.52 4004636.523

PROG BILLING 1 42.86% 60.00% 20.00% 915,171.79 915,171.79 4919808.311

PROG BILLING 2 21.43% 75.00% 20.00% 915,171.79 915,171.79 5834980.099

PROG BILLING 3 21.43% 90.00% 10.00% 457,585.89 457,585.89 6292565.993

AT COMPLETION 14.29% 100.00% - -

RETENTION 5.00% 228,792.95 228,792.95 6521358.94

TOTAL 100.00% 100.00% 4,575,858.94 6,521,358.94

DP 45.00% Downpayment
60% project completion 20.00% Progress Billing
75% project completion 20.00% Progress Billing
90% project completion 10.00% Progress Billing
Retention 5% Project Completion
TOTAL CONTRACT AMOUNT 4,575,858.94

45% Downpayment 2,059,136.52


at 60% overall project completion 915,171.79
at 75% overall project completion 915,171.79
at 90% overall project completion 457,585.89
at 100% overall project completion 457,585.89

TOTAL CONTRACT AMOUNT 4,575,858.94

45% Downpayment 2,059,136.52


at 60% overall project completion 1,601,550.63
at 90% overall project completion 686,378.84
at 100% overall project completion 228,792.95
20% Progress Billing
20% Progress Billing
10% Progress Billing
5% Progress Billing/ Retention

35% Progress Billing


15% Progress Billing
5% Progress Billing/ Retention
Payment Schemes

RELEASING OF PAYMENT as per NEW ORIGINAL CASH FLOW/ BANK


PERIOD PROGRESS BILLING % CASH FLOW
CONTRACT RELEASES
Equivalent Accumulative
Accomplishment as
% of the Entire Project as per the New Accumulative Cash Accumulative
per the New % Equivalent Amount Bank Releases
excluding "EXCLUDED Contract Flow BANk Releases
Contract
ITEMS"

TOTAL CONTRACT AMOUNT 4,575,858.94 6,485,000.00

Downpayment at Old Contract 1,945,500.00 1,945,500.00

Accumulative Work Progress%


30.00% 1,945,500.00 1,945,500.00 1,945,500.00 3,891,000.00
to Date

DOWNPAYMENT 45.00% 2,059,136.52 2,059,136.52 4,004,636.52 3,891,000.00

PROG BILLING 1 42.86% 60.00% 35.00% 1,601,550.63 1,601,550.63 5,606,187.15 1,945,500.00 5,836,500.00

PROG BILLING 2 42.86% 90.00% 15.00% 686,378.84 686,378.84 6,292,565.99 - 5,836,500.00

AT COMPLETION 14.29% 100.00% - -

RETENTION 5.00% 228,792.95 228,792.95 6,521,358.94 648,500.00 6,485,000.00

TOTAL 100.00% 100.00% 4,575,858.94 6,521,358.94 6,485,000.00

DOWNPAYMENT 45.00% 2,059,136.52 2,059,136.52 4004636.523

PROG BILLING 1 42.86% 60.00% 20.00% 915,171.79 915,171.79 4919808.311

PROG BILLING 2 21.43% 75.00% 20.00% 915,171.79 915,171.79 5834980.099

PROG BILLING 3 21.43% 90.00% 10.00% 457,585.89 457,585.89 6292565.993

AT COMPLETION 14.29% 100.00% - -

RETENTION 5.00% 228,792.95 228,792.95 6521358.94

TOTAL 100.00% 100.00% 4,575,858.94 6,521,358.94

DP 45.00% Downpayment
60% project completion 20.00% Progress Billing
75% project completion 20.00% Progress Billing
90% project completion 10.00% Progress Billing
Retention 5% Project Completion